method of works install main suspending lever 23april2013
TRANSCRIPT
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
1/41
PT CEMARA SEMITAMA
RIGGING PLAN FOR LIFTINGMain Suspending Lever& Steam Drum
at Steel Structure Boiler 2x110 MWTeluk Balikpapan Kalimantan Timur
DOCUMENT NO: CS-C 1003-RD-PROC-001
Prepared by Review by Approved by Distribution
Hendra GunawanRigging Engineer
Hajarat Ts PurbaSMR
Lambok FirdausSITE MANAGER
Master : SDCC
Origin : Client
Copies : CONST. DEPT
Rev. No. BRIEF OF REVISION
Effective Date:
23-April-2013
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
2/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
2 of 41
REVISI:
0
TABLE OF CONTENT1 GENERAL ...................................................................................................................... 3
2 PURPOSE ..................................................................................................................... 3
3 GENERAL NOTE ........................................................................................................... 3
4 RESPONSIBILITY .......................................................................................................... 4
5 BASIC REQUIREMENT ................................................................................................. 4
6 PREPARATION WORK .................................................................................................. 5
7 MAIN SUSPENDING LEVER ERECTION SEQUENCE ................................................. 5
8 LIFTING EQUIPMENT .................................................................................................. 35
9 LIFTING STUDY ........................................................................................................... 37
10 BACK FILL AREA FOR CRANE ACCESS ............................................................... 39
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
3/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
3 of 41
REVISI:
0
1 GENERAL
This procedure provides information for the erection of Main Suspending Leverat Steel Structure Boiler 2x110 MW Teluk Balikpapan Kalimantan TimurProject.
2 PURPOSE
This Procedure is to make sure that all people involve in the erection, assemblyand welding of Main Suspending Lever activity understand and familiar to dothe work with quality control system for getting quality result as per client
specification and requirement, drawing, standard and code.
3 GENERAL NOTE
3.1 InspectionAs per the works required inspection, carry out inspection under attendance ofSuperintendent / Engineer and as surreally record is result.
3.2 Safety
3.2.1 A safety officer presents all times Safety Briefing.3.2.2 Job Safety Analysis (JSA) must be carried out for all crane lifts and all other
tasks that have potential risk to personnel of equipment.
3.2.3 Install scaffolding where necessary to install bolt in each beam and memberconnection.
3.2.4 Pre lift study before any lifting activity.3.2.5 Lift briefing and Safety briefing before any lift; assign responsibility to all
personnel involved. (Signalman, Rigger to crane driver, etc.)3.2.6 Ensure all equipment required for installation is on hand and in position
before lift i.e. Chain blocks, Lever blocks, Podgy, Drifts, Hammer, Spanners.Etc.
3.2.7 Tag lines must be used to control lift.3.2.8 Ground conditions must be ready before activities.
3.2.9 Set up safety rope around lifting area of Main Suspending Lever area and putnotice board entered KEEP OFF EXCEPT PERSONEL CONCERNED.
3.2.10Lifting equipment should be in certification and tagged.3.2.11Crane and other machinery shall be inspected and certified.3.3 Lifting
All conditions adapted to the lifting procedure. Prior to commencement of liftingworks, assuredly carry out check of lifting equipment.
3.4 Assembly and erectionMain Suspending Levers assembly and erection are in accordance with themanuals and drawings.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
4/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
4 of 41
REVISI:
0
4 RESPONSIBILITY
4.1 Chief ConstructionResponsible for the overall planning, coordination and control of erectionwork.
4.2 Field EngineerResponsible for field erection work implementation and maintaining acceptablequality standard.
4.3 Field Superintendent and SupervisorResponsible for the actual performance of the erection crew and examine the
actual progress of work to ensure that it fit the drawing, specifications andstandards.
4.4 Quality Control EngineerResponsible for monitor and inspect the erection activities to ensure it is beingdone in compliance with procedure, ITP (Inspection and Test Plant), drawing,Project specification and other reference standard document and procedures.
4.5 SupporterActivitiesThese activities will support by Material Control, Quality Control, WeldingSection, and others section related with these activities.
5 BASIC REQUIREMENT
5.1 Schedule and PlanningMaster schedule is usually provided by Adhi Karya. The detailed schedule isprepared by Cemara Semitama according to his planning which is based onAdhi Karyas master schedule. The milestone and the critical path can beidentified which require proper planning. The sequence of erection activitiesand the resources required is included in the planning.
5.2 Erection Drawing and Erection ManualErection drawing and manual usually provided by Vendor. The Field Engineerand Superintendent shall check all drawings intended for Main SuspendingLever Erection. All the information required is completed and all drawings shall
be of latest revision.5.3 Packing ListPacking List shall be provided by Vendor. This included all the listing ofmaterials, equipment and parts that are supplied.The Packing List should indicate the quantity of the material and equipmentsupplied and its specification as described in the erection drawing. This will alsoindicate the size and the total weight of the component and the method ofstorage. Also the packing number and material coding is very essential.
5.4 Storage Area and WarehouseUpon a thorough check on the drawing and the packing list, the quantity ofmaterials and equipment is already known, including the method of storing, the
size of the storage area and the warehouse can be identifies.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
5/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
5 of 41
REVISI:
0
5.5 ResourcesIdentification of resources is integral part of planning and scheduling is the mostessential part of the basic requirement in undertaking Steel Structure Boiler2x110 MW Teluk Balikpapan Kalimantan Timur Project in particular and in alljobs in general. Resources means, the materials, labour and equipment neededto perform Steel Structure Boiler 2x110 MW Teluk Balikpapan KalimantanTimur Project.
6 PREPARATION WORK
6.1 Checking of Main Suspending Lever Erection Drawings
This has to be done by the Chief Construction, Field Engineer, Superintendentand Supervisor to determine the correct resources needed to perform the job.
6.2 Checking of Client Supplied Material and EquipmentChecking and inspection of the materials and equipment including the spareparts is to be done by the material control. He will make sure that all materials,equipment and spare parts received from Adhi Karya, conform to the quantityand the specifications started in the packing list or shipping.
6.3 Checking of Erection Materials, Equipment, Tools and MachineryIn the early stage of planning, these resources had been already identified. Theschedule of mobilization ason planed schedule made by the Chief Constructionand Engineer.
6.4 Checking of LabourLabour requirement for every stage of erection job is prepared by the ChiefEngineer and his erection team, which is in accordance to their planning.
7 MAIN SUSPENDING LEVER ERECTION SEQUENCE
It is assumed in this procedure that before starting the erection of the MainSuspending Lever, the supporting structure were already erected and checkedby others and clearance to proceed with the Main Suspending Lever Systemerection had been obtained.The following sequences are for reference only. During actual field assembly,
refer to lifting procedure and erection drawing (Rigging plan).
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
6/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
6 of 41
REVISI:
0
Figure 1
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
7/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
7 of 41
REVISI:
0
Figure 2
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
8/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
8 of 41
REVISI:
0
Figure 3
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
9/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
9 of 41
REVISI:
0
Figure 4
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
10/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
10 of 41
REVISI:
0
Figure 5
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
11/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
11 of 41
REVISI:
0
Figure 6
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.3. HB G1(K1-K2) Elevation +40920.4. HB G1(K1-K2) Elevation +50000.5. HB G5(K1-K2) Elevation +40920.6. HB G5(K1-K2) Elevation +50000.
Step 01:1a. Install MAIN SUSPENDING LEVER 1
K1 (G2-G4) - 16033.5 Kg.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
12/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
12 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
13/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
13 of 41
REVISI:
0
Figure 7
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.3. HB G1(K1-K2) Elevation +40920.4. HB G1(K1-K2) Elevation +50000.5. HB G5(K1-K2) Elevation +40920.4. HB G5(K1-K2) Elevation +50000.
Step 01:1. Install MAIN SUSPENDING LEVER 1
K1 (G2-G4) - 16033.5 Kg.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
14/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
14 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
15/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
15 of 41
REVISI:
0
Figure 8
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.3. HB G1(K1-K2) Elevation +40920.4. HB G1(K1-K2) Elevation +50000.5. HB G5(K1-K2) Elevation +40920.4. HB G5(K1-K2) Elevation +50000.
Step:2. Install HB K1(G1G2) & K1(G4G5)
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
16/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
16 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
17/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
17 of 41
REVISI:
0
Figure 9
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.3. HB G1(K1-K2) Elevation +40920.4. HB G1(K1-K2) Elevation +50000.5. HB G5(K1-K2) Elevation +40920.4. HB G5(K1-K2) Elevation +50000.
Step:3a. Install MAIN SUSPENDING LEVER 1
K2 (G2-G4) - 39094.0 Kg.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
18/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
18 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
19/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
19 of 41
REVISI:
0
Figure 10
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.3. HB G1(K1-K2) Elevation +40920.4. HB G1(K1-K2) Elevation +50000.5. HB G5(K1-K2) Elevation +40920.6. HB G5(K1-K2) Elevation +50000.
Step:4. Install HB G2 (K1-K2) Elevation +53000.5. Install HB G4 (K4-K5) Elevation +53000.6. Install HB G1 (K1-K2) Elevation +40920 & +53000.7. Install HB G5 (K4-K5) Elevation +40920 & +53000.8. Install HB K2 (G1-G2) & HB K2 (G4-G5) Elevation +53000.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
20/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
20 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
21/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
21 of 41
REVISI:
0
Figure 11
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.
Step:
9a. Install MAIN SUSPENDING LEVER 1K3 (G2-G4) - 34212.0 Kg
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
22/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
22 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
23/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
23 of 41
REVISI:
0
Figure 12
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.
Step:9b. Install MAIN SUSPENDING LEVER 1
K3 (G2-G4) - 34212.0 Kg
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
24/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
24 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
25/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
25 of 41
REVISI:
0
Figure 13
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.
Step:10. Install HB G2 (K2-K3) Elevation +53000.11. Install HB G4 (K2-K3) Elevation +53000.
12. Install HB G1 (K2-K3) Elevation +50000.13. Install HB G5 (K2-K3) Elevation +50000.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
26/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
26 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
27/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
27 of 41
REVISI:
0
Figure 14
HOLD:1. Column K4G1, K4G5 tier 3, 4 & 5.2. Column K4G2, K4G3 & K4G4 tier 5.
LIFTING STEAM DRUMAfter Install MAIN SUSPENDING LEVER 1K3 (G2-G4) - 34212.0 Kg
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
28/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
28 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
29/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
29 of 41
REVISI:
0
Figure 15
Step:16. Install Column K4G1, K4G5 tier 3, 4 & 5.17. Install Column K4G2, K4G3 & K4G4 tier 5.18. Install HB G1 (K3-K4) Elevation +30320 & +40920.19. Install HB G5 (K3-K4) Elevation +30320 & +40920.20. Install VB K1(G3-G4) Elevation +40920.21. Install VB K1(G3-G2) Elevation +40920.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
30/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
30 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
31/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
31 of 41
REVISI:
0
Figure 16
Step:22. Install MAIN SUSPENDING LEVER 1
K4 (G2-G4) - 10769.5 Kg
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
32/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
32 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
33/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
33 of 41
REVISI:
0
Figure 17
Step:23. Install HB G2 (K3-K4) Elevation +53000.24. Install HB G4 (K3-K4) Elevation +53000.25. Install HB G1 (K3-K4) Elevation +50000.26. Install HB G5 (K3-K4) Elevation +50000.27. Install HB K4 (G1-G2) Elevation +53000.28. Install HB K4 (G4-G5) Elevation +53000.
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
34/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
34 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
35/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
35 of 41
REVISI:
0
8 LIFTING EQUIPMENT8.1 Crawler Crane Capacities 150 ton Main Boom
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
36/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
36 of 41
REVISI:
0
8.2 Crawler Crane Capacities 150 ton Main Boom + Jib
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
37/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
37 of 41
REVISI:
0
9 LIFTING STUDY
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
38/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
38 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
39/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
39 of 41
REVISI:
0
10 BACK FILL AREA FOR CRANE ACCESS
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
40/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
40 of 41
REVISI:
0
-
8/22/2019 Method of Works Install Main Suspending Lever 23April2013
41/41
PT. CEMARA SEMITAMAMethod of Works Installing For Lifting
Main Suspending Lever
Document No :CS-C 1003-RD-PROC-001
Date :
23/April/2013
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
41 of 41
REVISI:
0