method statement fo method statement for precast boundary wall worksr precast boundary wall works

Upload: cprelator

Post on 14-Feb-2018

265 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/23/2019 Method Statement fo Method Statement for Precast Boundary Wall Worksr Precast Boundary Wall Works

    1/5

    1. Title

    Method Statement for Precast Boundary Wall Works

    2. Purpose and scope

    The aim of this method statement is to describe the process and sequence oferection of precast elements for the boundary wall in this project.

    3. Work procedure

    1.General

    o Erection process shall conform to the requirements of project

    specification and or relevant standard.

    o Precast concrete element will be transported to site after the

    approval by in-house QA/QC staff.

    o On site survey shall be carried out for all site dimensions, axes

    locations, and to meet project requirements.

    2. Preparation of Civil Works

    o Earthwork shall be carried out as per required level.

    o Compaction, testing and blinding shall be done before starting

    erection.

    o Main grid line and benchmark will be marked by surveyor.

    o Site access road for the movement and parking of mobile cranes and

    trailers will be ensured at site before starting of erection.

    o Backfilling after completion of erection of boundary wall shall be

    made after installationof precast elements.

    Stage 1 After erecting of footing and columns.

    Stage 2 After erecting of first boundary wall panel.

    o Erection of Footing

    Footings for columns shall be transported on the bed trailers

    where they are properly tied with chains and latches.

    Lifting anchors and sleeves openings are provided in thefootings in proper locations as per design requirements for safe and

    easy handling and erecting purposes.

    Footing shall be received at site painted with one primer coat

    of water proofing bitumen followed by two finishing coats of water

    proofing bitumen.

  • 7/23/2019 Method Statement fo Method Statement for Precast Boundary Wall Worksr Precast Boundary Wall Works

    2/5

    Precast Footing

    o

    o Footing shall either be installed in its location at site using mobile

    crane of adequate capacity.

    o Individual markings for footings shall be made by the surveyor.

    o Blinding shall be cleaned and the water proofing bitumen shall be

    applied before erecting any precast footing.

    o Footing shall be leveled prior to receive column and four line (axis of

    column) to be marked on the foundation to specify the locations of thecolumn face.

    o Backfilling around the footing shall be done as per

    approved method statement of backfilling works.

    o Erection of Precast Column

    o Column shall be provided with 1 anchor on hole on top for handling

    and for erection purposes.

  • 7/23/2019 Method Statement fo Method Statement for Precast Boundary Wall Worksr Precast Boundary Wall Works

    3/5

    Precast Column

    o Column shall be transported on flat-bed trailers secured to the trailer

    with the help of latching chains or belt.

    o Precast column shall be unloaded by mobile crane of adequate

    capacity.

    o Then column shall be tilted with crane and lifted vertically in order to

    bring it to its exact location onto the footing.

    o Column shall be aligned at tail end to match the axis.

    o Wooden wedges shall be fixed at the sides between the face of the

    neck column and the inner face of the footing to keep the column in

    place without tilting or displacing.

  • 7/23/2019 Method Statement fo Method Statement for Precast Boundary Wall Worksr Precast Boundary Wall Works

    4/5

    o Verticality of the column shall be checked with the help of line and

    other instruments and any deviation shall be adjusted prior to grouting.

    o The bottom of the column shall be grouted in the footing with

    approved grouting material.

    o Erection of Precast Wall

    o Precast walls shall be transported on flat-bed trailers with double A

    frame secured with bed of trailer by chain and latches. The precast

    elements shall be secured with frame by the help of latching belts.

    o Precast wall shall be provided with lifting anchor or hook as per

    drawing for easy and safe handling and erecting purposes.

    o Precast wall is unloaded from the trailer by mobile crane of adequate

    capacity.

    o Precast wall then shall be placed on proper storage racks or taken

    directly for erection.

    o Precast shall be installed in its exact location between two columns

    and shall ensure the stability of the wall and prevent it from tilting or

    displacing.

    o Inspection Request would then be submitted for checking and

    approval of the Engineer.

    4. Safety

    1.All works shall comply with safety procedure or instruction set out in project

    safety plan and Municipality rules and regulations.

  • 7/23/2019 Method Statement fo Method Statement for Precast Boundary Wall Worksr Precast Boundary Wall Works

    5/5

    2. Know the safe working load of the hoisting equipment and hardware before

    use. Never exceed the Safe Working Load (SWL).

    3.Know the height and size of the precast element before rigging for lifting.

    4.Always inspect the rigging element prior to every use.

    5. Never wrap the hoist line around the load.

    6.Always use taglines with the precast element while lifting to keep the load

    steady.

    7.Always check the stability of the load before lifting.

    8. Check for any over head power lines.

    9.Make sure that the rigging elements are correct and safe to use for the

    intended load.

    10.Never use damaged slings, blocks, hooks for lifting, all damaged lifting

    gears to be returned to the store for repair or replacement.11.Basic PPE to worn by all staff and laborers.

    12.Trained operator and banks man will be engaged to control or operate

    heavy equipmentmachine.

    5. Equipments and tools

    1.Mobile crane

    2.Flat trailers

    3. Shovel and JCB for excavation

    4.Plate compactors5.Web sling

    6. Grinders and drill machines

    7.Hammers

    8.Plastic chem for leveling

    9.Total Station for survey

    6. Materials and references

    1.Hollow core panels

    2. Grouting material3.Approved drawing

    4. Specification