METHOD STATEMENT Title : Work Method Statement for Damp Proof Membrane (DPM) Application Reference : 1.0 OBJECTIVE The proposal has been prepared to meet the Project Quality Assurance Plan of the Main Contractor for Damp Proof Membrane (DPM). 2.0 SCOPE The scope of this document is to define and establish a work method for Damp Proof Membrane (DPM) application work for “MEMBINA DAN MENYIAPKAN BANGUNAN PUSAT ISLAM SERTA LAIN-LAIN KERJA BERKAITAN DI UNIVERSITI SAINS ISLAM MALAYSIA, BANDAR BARU NILAI, NEGERI SEMBILAN DARUL KHUSUS”. 3.0 REFERENCES 3.1 Manufacturer’s product data 3.2 Undertaking letter by manufacturer’s 4.0 DEFINITION A damp-proof membrane (DPM) is a membrane material applied to prevent moisture transmission. A common example is polyethylene sheeting laid under a concrete slab to prevent the concrete from gaining moisture through capillary action. Polythene or polyethylene sheet is commonly used as a damp-proof membrane with oversight concrete for all but severe conditions of dampness. 5.0 RESPONSIBILITIES Page 1 of 3

Upload: suhaila-namaku

Post on 20-Nov-2015

882 views

Category:

Documents


67 download

DESCRIPTION

method statement

TRANSCRIPT

Technical Submittal

METHOD STATEMENT

Title : Work Method Statement for Damp Proof Membrane (DPM) Application

Reference :

1.0 OBJECTIVEThe proposal has been prepared to meet the Project Quality Assurance Plan of the Main Contractor for Damp Proof Membrane (DPM).

2.0 SCOPEThe scope of this document is to define and establish a work method for Damp Proof Membrane (DPM) application work for MEMBINA DAN MENYIAPKAN BANGUNAN PUSAT ISLAM SERTA LAIN-LAIN KERJA BERKAITAN DI UNIVERSITI SAINS ISLAM MALAYSIA, BANDAR BARU NILAI, NEGERI SEMBILAN DARUL KHUSUS.

3.0 REFERENCES3.1 Manufacturers product data3.2 Undertaking letter by manufacturers

4.0 DEFINITION Adamp-proof membrane(DPM) is amembranematerial applied to prevent moisture transmission. A common example is polyethylene sheeting laid under a concrete slab to prevent the concrete from gaining moisture through capillary action. Polythene or polyethylene sheet is commonly used as a damp-proof membrane with oversight concrete for all but severe conditions of dampness.

5.0 RESPONSIBILITIES5.1 Project manager5.2 Site Supervisor5.3 Resident Architect

6.0 HANDLING AND STORAGE OF MATERIAL6.1 Loading/unloading of the material shall be done by using either forklift or by hand to avoid any damage to the material.

7.0 TOOLS, EQUIPMENT AND PLANT7.1 N/A

8.0 WORK SEQUENCE FLOW8.1 Area to be cleaned and prepared8.2 Area to be lay with DPM is identified as per approved drawing8.3 Measured area to be installed with DPM at site8.4 DPM is cut as per measured area8.5 Overlapped between each sheet is 400mm.8.6 No damage of DPM while laying activity taken place.9.0 QUALITY PLAN9.1 Inspection form shall be submitted to the consultant to witness the inspection by site supervisor9.2 For all non-conformity, the necessary rectification work and re-inspection shall be performed, until the remedial work performed satisfactorily.9.3 QA/QC department shall ensure that materials are in good working conditions and fit for use. Any defects of materials shall be removed.9.4 All materials use for the work must comply to the standard and specification.

10.0 SAFETY PLAN 10.1 All operators to wear full PPE (Personal Protective Equipment) with the additional equipment.

11.0 ATTACHMENTAttachment 1 Manufacturers product dataAttachment 2 Undertaking letter by manufacturersAttachment 3 Inspection Checklist for Damp Proof Membrane WorkPage 1 of 2