method statement for pvc conduit installation in concrete slab.pdf
TRANSCRIPT
9/7/2014 Method Statement For PVC Conduit Installation In Concrete Slab
http://www.methodstatementhq.com/method-statement-for-pvc-conduit-installation-in-concrete-slab.html 1/4
H o m e Disclaimer Project HSE Plan Construction Method Statements
Method Statement Template Inspection Checklists Request A Method Statement
Project Execution Plan Customer Support Download Method Statements
Method Statement Free Download
RSS
You are here: Home » Method Statements » Const ruct ion Method Statements » Elect rical Method Statements »
Method Statement For PVC Conduit Installat ion In Concrete Slab
Method Statement For PVC Conduit Installation In Concrete Slab
Tweet
Method Statement For PVC
Conduit Installation In Concrete
Slab
Tools Required
Following tools should be arranged before starting
the job.
Dia (20 & 25 ) mm pipe Bender
Mini Hacksaw Frame with Blades
Choke Lime Powder with sufficient length of Thread
500gm Hammer
Measuring Tape
End Cutter ( Kalwa )
PVC Conduit Installation Procedure
Ensure that the civil people have finished ply/post tension work on the slab.
Arrange the approved shop drawings for the area of installation.
Mark first the wall location for lower floor in slab as per latest Architecture layout so that it will
be easy to locate the drops for switch, thermostat and any other drops required for electrical
system.
Mark the opening size in Electrical Room and Telephone room as per approved electrical
drawing.
Mark the Electrical points on the slab as per approved Electrical Layout and fix proper shape
and size of the Circular Box with the help of nail/mess in case of plywood slab and provide steel
bar chairs for fixing the box in case of post tension slab.
November 5, 2012 | webmaster
Valme concretepipes
valme.it
Design, production and direct sale
of high quality concrete pipes
SPECIAL RECENT POSTS
Installation of Marble and Granite
Tiles on floor, stairs, walls and
counters
April 4th, 2014
This m ethod statem ent covers the
detailed procedure to be followed for
Supply & Installation of [...]
Method Of Statement For Installation
of wires and cables - Wiring
March 29th, 2014
Below is the list of equipm ent / Tools
required for installation of wires and cables,
which cab be u[...]
Method Statement For Installation &
Testing of SMATV System
March 21st, 2014
Below are the steps or m ethod statem ent
for installation & testing of SMATV System in
a project.[...]
Sanitary Ware Installation Method
Statement
March 20th, 2014
Installation of sanitary ware can be done
step wise as per m entioned procedure or
m ethod statem ent b[...]
Plastering Works Method Statement
March 20th, 2014
Below are the equipm ent involved in
Plaster works that should be arranged
before starting the plaste[...]
Method Statement for Internal Painting
Works
March 20th, 2014
Below is the procedure for doing the
painting works for internal painting. This safe
work m ethod sta[...]
Chiller installation method statement
March 17th, 2014
Below is a standard operating procedure
which can be used a a m ethod statem ent
for installation of c[...]
How To Do Installation of Suspended
False Ceilings
March 14th, 2014
0 Email Share
9/7/2014 Method Statement For PVC Conduit Installation In Concrete Slab
http://www.methodstatementhq.com/method-statement-for-pvc-conduit-installation-in-concrete-slab.html 2/4
« Method Statem ent For Drainage Piping PVC uPVC Underground Above Ground
Method Statem ent For GI Box And GI/PVC Conduit Installation In The Wall »
Just after completing the first layer of steel, start pvc conduiting work with different sizes of
conduit based on electrical system requirements and as per drawings. Always loop the two way
switches with 20 mm conduit as the number of wires will be more and only switch drop pipe will
not be sufficient for pulling all these wires.
Try to avoid the overlapping of conduits and keep some distance between the conduits for low
current and power/Lights.
Just after completing the work tight the conduits with binding wire and mark the circuit
numbers. identification for the raised pipe in slab for upper slab to be done for power, TV and
telephone systems and closing the mouth of pipe with the help of masking tape .
The site Engineer/Foreman should check the proper size of conduit and circular box, opening
size in both Electrical and Telephone room and be sure the work is completed as per approved
Electrical shop drawing.
Before the concrete pouring the PVC conduit installation to be inspected and approved by
consultant/client/contractor.
During concrete pouring, keep electricians for taking care of conduit to avoid any damage by
others or dislocation of joints.
LIKE US ON FACEBOOK
Filed under Elect rical Method Statements | Tags: Elect rical Method Statements, method, Method Statement For PVC
Conduit Installat ion In Concrete Slab, MST For Conduit ing Work, of
contact
Crushing Plant China
Manufacturer of MiningEquipment China!
Comments are closed.
Equipm ent Required For Installation of
Suspended Ceilings Leveling Instrum ents
Line dory C[...]
Transformer testing & commissioning
method statement
March 14th, 2014
Below is a standard m ethod statem ent
which can be used as learning purpose and
to prepare further pr[...]
METHOD STATEMENT FOR
INSTALLATION, TESTING AND
COMMISSIONING OF UPS
March 14th, 2014
1.0. PURPOSE: The purpose of this m ethod
statem ent defines the procedure to be
followed for Insta[...]
CATEGORIES
BMS
Cem ent & Clinker Testing
Civil Engineering
Civil Method Statem ents
Concrete Testing
Construction Method Statem ents
Drainage Pipes Installation
Duct Works
Electrical
Electrical Method Statem ents
Fire Suppression System
Health & Safety
HVAC Checklists
HVAC Maintenance
HVAC Method Statem ents
ISO 9001
Method Statem ent Tem plate
Method Statem ents
Piping Method Statem ents
Piping Works
Plum bing Method Statem ents
Pressure Testing
Project HSE Plan
Pum p Installation
Quality Assurance
Quality Managem ent
Risk
Risk Assessm ent
Risk Managem ent
Sam ple Form s & Form ats
Tem plates
Testing & Com m issioning
Water Supply Piping
Welding Risk
What Is Hazard?
What Is Risk?
Working At Height
9/7/2014 Method Statement For PVC Conduit Installation In Concrete Slab
http://www.methodstatementhq.com/method-statement-for-pvc-conduit-installation-in-concrete-slab.html 3/4
TAGS
& Access Control System Accessories AC Duct ing
Method Statement ac duct installat ion ACMaintenance Acoust ic Lining blank performablank proforma bms system BMS TestingProcedure Building Management SystemBuilding Management System BMS control
measures Electrical Method Statement forhazard hvac HVAC Method Statements
installat ion Installation of GI Conduits &
Accessories method Method
Of Statement Method
Statement met hod
st at ement for Inst allat ion Met hodSt at ement Templat e MST MST For BMS
of pipe flushing pressure pumps risk RiskAssessment safe work method sample
check list sample checksheet Sample
Format Electrical statement swms
template test Testing & CommissioningTesting & Commissioning MethodStatement water
DOWNLOAD METHOD STATEMENTS
Download BMS Installation Method Statem ent
Download Chilled Water Pipes Installation &
Testing Method Statem ent
Download Method Statem ent For INSTALLATION
HYDRO TESTING & FLUSHING OF FIRE FIGHTING
PIPING SYSTEM INCLUDING SPRINKLERS
Download Method Statem ent For CENTRAL
BATTERY SYSTEM INSTALLATION
Download Method Statem ent For Fire Alarm
System
Download Method Statem ent For Flushing Of
Chilled Water Piping
Download Method Statem ent For Installation Of
Packaged Units
Download Method Statem ent For Installation Of
Split Units & Risk Assessm ent
Download Method Statem ent For Installation Of
Transform ers
Download Project HSE Plan With All Form s
Hom e
Privacy Policy
Disclaim er
Hom e
Privacy Policy
Disclaim er
9/7/2014 Method Statement For PVC Conduit Installation In Concrete Slab
http://www.methodstatementhq.com/method-statement-for-pvc-conduit-installation-in-concrete-slab.html 4/4
Copyright © 2014 Method Statement Free Download | zBorder Theme powered by WordPress