methodology and project planning str1 kawashima. methodology list down all tasks group tasks under...

13
Methodology and Project Planning STR1 Kawashima

Upload: dorothy-sharp

Post on 18-Jan-2018

230 views

Category:

Documents


0 download

DESCRIPTION

Isolation of Hydrocarbon-degrading Bacteria from Guimaras Soil Samples Soil samples from various oil-contaminated areas in Guimaras will be obtained and stored in 50 mL conical tubes at room temperature. To isolate possible hydrocarbon- degrading bacteria from each sample, a pinch of soil will be inoculated into 50 mL of liquid minimal medium (for 1 L: 0.5g KH 2 PO 4, 2.0g KNO 3, 1.0g MgSO 4 7H 2 O, g CaCl 2 2H 2 O, 0.002g FeSO 4 7H 2 O) with 50 μL of bunker oil (Petron Corporation, Philippines), and subjected to incubation while shaking at 37ºC at 225 rpm for one week. Once a visible change in turbidity is observed, an applicator stick will be dipped into the suspension culture and streak plated on Luria-Burtani (LB) agar (Pronadisa, Madrid, Spain). One streak plate will be made for each soil sample and incubated overnight at 37°C. Isolated bacterial colonies of different colonial morphologies will be picked and subcultured into separate LB agar slants.

TRANSCRIPT

Page 1: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Methodology and Project Planning

STR1 Kawashima

Page 2: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Methodology

Page 3: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Isolation of Hydrocarbon-degrading Bacteria from Guimaras Soil Samples

Soil samples from various oil-contaminated areas in Guimaras will be obtained and

stored in 50 mL conical tubes at room temperature. To isolate possible hydrocarbon-

degrading bacteria from each sample, a pinch of soil will be inoculated into 50 mL of

liquid minimal medium (for 1 L: 0.5g KH2PO4, 2.0g KNO3, 1.0g MgSO4 7H2O, 0.0012g

CaCl2•2H2O, 0.002g FeSO4•7H2O) with 50 μL of bunker oil (Petron Corporation,

Philippines), and subjected to incubation while shaking at 37ºC at 225 rpm for one

week. Once a visible change in turbidity is observed, an applicator stick will be

dipped into the suspension culture and streak plated on Luria-Burtani (LB) agar

(Pronadisa, Madrid, Spain). One streak plate will be made for each soil sample and

incubated overnight at 37°C. Isolated bacterial colonies of different colonial

morphologies will be picked and subcultured into separate LB agar slants.

Page 4: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Isolation of Hydrocarbon-degrading Bacteria from Guimaras Soil Samples

Soil samples from various oil-contaminated areas in Guimaras will be obtained and

stored in 50 mL conical tubes at room temperature. To isolate possible hydrocarbon-

degrading bacteria from each sample, a pinch of soil will be inoculated into 50 mL of

liquid minimal medium (for 1 L: 0.5g KH2PO4, 2.0g KNO3, 1.0g MgSO4 7H2O, 0.0012g

CaCl2•2H2O, 0.002g FeSO4•7H2O) with 50 μL of bunker oil (Petron Corporation,

Philippines), and subjected to incubation while shaking at 37ºC at 225 rpm for one

week. Once a visible change in turbidity is observed, an applicator stick will be

dipped into the suspension culture and streak plated on Luria-Burtani (LB) agar

(Pronadisa, Madrid, Spain). One streak plate will be made for each soil sample and

incubated overnight at 37°C. Isolated bacterial colonies of different colonial

morphologies will be picked and subcultured into separate LB agar slants.

Page 5: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Project Management

Page 6: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Project Management Tools

Page 7: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Process Flowchart

Page 8: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

GENERAL description of an activityEach activity is bounded in

a RECTANGLE

ARROWS indicate what’s next

Page 9: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Go to Trinoma

Get tickets

Buy snacks

Watch movie

Eat dinner

Go home

Gantt Chart

1 4 60

17:00 20:00 21:0016:00

Time, hours

18:00 19:00 22:00

2 3 5

current

Page 10: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Go to Trinoma

Get tickets

Buy snacks

Watch movie

Eat dinner

Go home1 4 60

17:00 20:00 21:0016:00

Time, hours

18:00 19:00 22:00

2 3 5

current

Names are in imperative form

Time increments run along the bottom, in hours/days/weeks/months

Task names take up one row

Page 11: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Go to Trinoma

Get tickets

Buy snacks

Watch movie

Eat dinner

Go home1 4 60

17:00 20:00 21:0016:00

Time, hours

18:00 19:00 22:00

2 3 5

current

Bars represent expected duration of the task

Arrows connect prerequisite tasks

Shaded bars mean finished tasks while unshaded bars are unfinished

Shading tells how complete a task is

(think percentage)

Page 12: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Go to Trinoma

Get tickets

Buy snacks

Watch movie

Eat dinner

Go home1 4 60

17:00 20:00 21:0016:00

Time, hours

18:00 19:00 22:00

2 3 5

current

This line marks the current time/date

Fully shaded bars left of the line are completed tasks

Unshaded bars right of the line are tasks

yet to be started

Unshaded bars LEFT of the line are

behind schedule

Page 13: Methodology and Project Planning STR1 Kawashima. Methodology List down all tasks Group tasks under general activities Make a process flowchart Write a

Network ChartA=1 B=2

C=1

D=2 E=1 F=1

Code Description Duration (hr)

A Go to Trinoma 1

B Get tickets 2

C Buy snacks 1

D Watch movie 2

E Eat dinner 1

F Go home 1