methods of dewatering
TRANSCRIPT
![Page 1: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/1.jpg)
.
![Page 2: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/2.jpg)
A Seminar presentation
on
Methods of Dewatering
On Construction SiteBy
Gaikwad A. A.
Guide: Ms. Pujari P.D..
![Page 3: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/3.jpg)
CONTENTS
Introduction
Lesson Objective
Purpose of Dewatering
Factors controlling Selection
Methods of Dewatering
Conclusion
.
![Page 4: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/4.jpg)
Introduction
4
GWT
Deep Foundation
Lowering WT
Definition
If Overlooked??
![Page 5: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/5.jpg)
Lesson Objective
5
To know the concept of Dewatering
To know Importance of Dewatering
To know various Methods of Dewatering
![Page 6: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/6.jpg)
6
Purpose of Dewatering
During construction stage:-
dry excavation
proceed efficiently
Reduce lateral loads
Improve characteristics of foundation materials
Increase stability of slopes and side-hill fills
Prevent piping and frost heaving in pavements
![Page 7: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/7.jpg)
77
Purpose of Dewatering
Post construction stage :-
Reduce uplift pressures on bottom slabs
Reduce lateral pressures on retaining structures
Control embankment seepage in all dams
Purpose of Dewatering
![Page 8: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/8.jpg)
Factors Controlling Selection
Nature and Permeability of Ground
Geologic conditions of soil
Extent of area to be Dewatered
Depth of Water table below ground level
Amount by which it has to be lowered
Proposed methods of excavation and ground support
Proximity of existing structure
8
![Page 9: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/9.jpg)
9
Soil Permeability
Coefficient(k)(cm/sec)
Relative Permeability
Coarse gravel Exceeds 10^-1 High
Clean sand 10^-1 to 10^-3 Medium
Dirty sand 10^-3 to 10^-5 Low
Silt 10^-5 to 10^-7 Very low
Clay Less than 10^-7 Impervious
Permeability of Soil
![Page 10: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/10.jpg)
10
![Page 11: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/11.jpg)
Methods of Dewatering
Surface water control
Sump pumping
Wellpoint systems with suction pumps.
Ejector system
Ground freezing
Deep (bored) wells with pumps.
11
![Page 12: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/12.jpg)
1.Sump Pumping
12
![Page 13: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/13.jpg)
13
1.Sump Pumping
What is Sump?
Slope
Pump
Fines
Lined
![Page 14: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/14.jpg)
14
![Page 15: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/15.jpg)
15
Widely used method
Most economical method for installation and maintenance
Can be applied for most soil and rock conditions
Most appropriate where boulders or massive obstructions
j are met with in the ground
Advantages of Open Sump and Ditches
![Page 16: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/16.jpg)
1616
Due to more flow of GW towards excavation risk of
collapse of sides occurs.
In open or timbered excavations there is risk of
instability of the base due to seepage towards pumping
sump.
Note:- Greatest depth to which the water table can be
lowered by this method is about 8 m below the pump.
Disadvantages of Open Sump and Ditches
![Page 17: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/17.jpg)
2.Wellpoint System
17
Fig. Cross section of a typical well-point system
![Page 18: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/18.jpg)
18
2.Wellpoint System
Perforated Well
Material
Sandy
Foot – Orifice
Series of Closely Placed
Dimension
Spacing
Construction steps
![Page 19: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/19.jpg)
1919
2.Wellpoint System
19
Well point arrangement
![Page 20: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/20.jpg)
20
Well point System(Spacing)
soil spacing
Silty sand 1.5-2.0
Sandy gravel 1.0-1.5
Fine to coarse gravel 0.5-1.0
![Page 21: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/21.jpg)
21
Single Stage Well-point system
21
![Page 22: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/22.jpg)
22
Multi - Stage Well Point System
22
![Page 23: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/23.jpg)
2323
Multi - Stage Well Point System
23
![Page 24: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/24.jpg)
24
Installation is very rapid
Requires reasonably simple and less costly equipment
Water is filtered hence not carries soil particles.
There is less danger of subsidence of the surrounding
gj ground than with open-sump pumping
Advantages of Well point System
![Page 25: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/25.jpg)
2525
A lowering of about 6 m is possible, beyond which
excessive air required, resulting in the loss of pumping
efficiency.
If large gravel, stiff clay or soil containing boulders is
available then it is not possible to install well points.
Disadvantages of Well point System
![Page 26: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/26.jpg)
3.Eductor Well
26
Pump
![Page 27: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/27.jpg)
27
3.Eductor Well
Vacuum / Ejector
Control pore pressure
Fine soil
Extract GW , Generate vacuum
Drainage system
Working
![Page 28: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/28.jpg)
28
![Page 29: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/29.jpg)
29
They are flexible in level and layout
Stable in operation
Able to run dry without damage
Not limited by depth. Also effective to greater depths
Best in low-yielding wells
Energy intensive
Venturi in base of well creates vacuum
Advantages of Eductor Well
![Page 30: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/30.jpg)
3030
4.Ground Freezing
Figure – Formation of frozen earth barrier in different soils
![Page 31: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/31.jpg)
31
![Page 32: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/32.jpg)
32
Pipes prior to freezing
Following initiation of freeze
Closure of frozen earth wall
Complete frozen earth wall
![Page 33: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/33.jpg)
33
5.Deep Well
![Page 34: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/34.jpg)
34
5.Deep WellGreater than 8m
Pump
Size
Perforated as well as Imperforated pipe - Material
Suitability
Artesian water
Chance of settlement
Pumping capacity (3000 to 60,000 gallons/min)
![Page 35: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/35.jpg)
35
Summery of dewatering methods
Method Suitability
Sump pumping Gravel or well graded sandy gravel, partially cemented
material , porous rock formation etc
Well point systems Sandy soil
Drawdown limit 15 ft
Ejector system Fine sand condition
Dewater up to depth of 100 ft
Ground freezing groundwater cutoff, stabilization of earth for tunnel
excavation,
arrest landslides and to stabilize mineshafts
Deep (bored) wells Artesian water
Pumping capacity (3000 to 60,000 gallons/min)
Dewater up to depth of 300 ft
![Page 36: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/36.jpg)
36
![Page 37: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/37.jpg)
Books: DEWATERING AND GROUNDWATER
CONTROL(HQ.DEPARTMENTS OF ARMY, AIR
FORCE, NAVY WASHINGTON)
Construction Dewatering and Ground
Freezing (University of Washington)
![Page 38: Methods of Dewatering](https://reader030.vdocument.in/reader030/viewer/2022020106/55a6921c1a28ab604d8b4696/html5/thumbnails/38.jpg)