METRO ALGIERS LINE 1, EXTENSION "A", HAMMA-HAI EL BADR, GAAMA Facts Project Description Execution of the second section of line 1 of the underground railways in Algiers. The project comprises the execution of four underground railway stations including 4.1 km of tunnels and 16 ventilation structures. Construction started with the driving of five starting pits from which tunnel driving then started simultaneously at several locations using the New Austrian Tunnelling Method (NATM). The tunnels are driven using excavators with gunned concrete infill and inner shell executed in a second step. The tunnel is executed impermeable to press water without drainage with sealing foil and watertight concrete bottom. Three to four tunnel tubes are driven in parallel alternately from starting pits located between the stations. The stations are executed according to our special proposals whereby the building pit sheetings are integrated into the stations as such forming an integral part of the stations. At the stations Mer et Soleil and Cite Amirouche a solution with open bored pile walls was adopted, whereas the stations Jardin d´Essai and Les Fusilles are executed using diaphragm walls with cover and cut method. The stations are executed as white tanking using watertight concrete so that no sealing is required. MAIN QUANTITIES: Tunnel cross-section: 54 m² Diapgragm walls (64 cm / 80 cm): 28,000 m² Bored piles (dia. = 90 cm): 11,000 m Excavation stations / shafts: 318,000 m³ Excavation tunnels: 262,000 m³ Structural concrete: 210,000 m ³ Shotcrete: 40,000 m³ Formwork (tunnels and stations): 206,000 m² Reinforcing steel (tunnels and stations): 15.000 to City/Country Algier / Algeria Client Entreprise Métro d'Alger (EMA), Algier Architect Systra-SGTE Paris Contract Value € 197,00 Mio. Construction Period 10/2003 - 12/2006 (38 months) .

Upload: others

Post on 05-Jun-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: METRO ALGIERS LINE 1, EXTENSION A, HAMMA-HAI EL BADR, …

METRO ALGIERS LINE 1, EXTENSION "A", HAMMA-HAI EL BADR, GAAMA

Facts Project DescriptionExecution of the second section of line 1 of the underground railways in Algiers. Theproject comprises the execution of four underground railway stations including 4.1 km oftunnels and 16 ventilation structures. Construction started with the driving of five startingpits from which tunnel driving then started simultaneously at several locations using theNew Austrian Tunnelling Method (NATM). The tunnels are driven using excavators withgunned concrete infill and inner shell executed in a second step. The tunnel is executedimpermeable to press water without drainage with sealing foil and watertight concretebottom. Three to four tunnel tubes are driven in parallel alternately from starting pitslocated between the stations.The stations are executed according to our special proposals whereby the building pitsheetings are integrated into the stations as such forming an integral part of the stations. Atthe stations Mer et Soleil and Cite Amirouche a solution with open bored pile walls wasadopted, whereas the stations Jardin d´Essai and Les Fusilles are executed usingdiaphragm walls with cover and cut method.The stations are executed as white tanking using watertight concrete so that no sealing isrequired.

MAIN QUANTITIES:Tunnel cross-section: 54 m²Diapgragm walls (64 cm / 80 cm): 28,000 m²Bored piles (dia. = 90 cm): 11,000 mExcavation stations / shafts: 318,000 m³Excavation tunnels: 262,000 m³Structural concrete: 210,000 m ³Shotcrete: 40,000 m³Formwork (tunnels and stations): 206,000 m²Reinforcing steel (tunnels and stations): 15.000 to

City/Country

Algier / Algeria

Client

Entreprise Métro d'Alger (EMA), Algier

Architect

Systra-SGTE Paris

Contract Value

€ 197,00 Mio.

Construction Period

10/2003 - 12/2006 (38 months)

.