![Page 1: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/1.jpg)
METRO Gold Line BRTCBAC Meeting
August 23, 2018
1
![Page 2: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/2.jpg)
Today’s Topics
• Introductions• Corridor Management Committee Update• Public Engagement Update• History of Alignment• Project Scope Discussions• Upcoming CBAC Meetings
2
![Page 3: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/3.jpg)
3
CBAC Co-Chairs Attending First CMC Meeting
• CBAC Co-Chairs Appointed in July– Darrell Paulsen, Community Representative– Steve Morris, Business Representative
• Both Co-Chairs are members of the Gold Line CMC• Attended August 2 CMC Meeting
July 26 CBAC MeetingCBAC Co-Chairs
![Page 4: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/4.jpg)
Public Engagement Update
4
![Page 5: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/5.jpg)
5
Stakeholder Engagement Update
• Open Houses • Two corridor-wide events to review design updates and
options
July 17 and 18 Open Houses
![Page 6: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/6.jpg)
6
Stakeholder Engagement Update
• Neighborhood Meetings• Three locations where input
is needed on design options:
• Mounds vs. Maria Station Location
• Hudson Road between Etna and White Bear; mixed traffic vs. dedicated guideway
• White Bear Avenue Station Location
July 31 Neighborhood Meeting
![Page 7: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/7.jpg)
7
Stakeholder Engagement Update
• Door Knocking • Two neighborhoods where input
is needed on design options• One-on-One Meetings
• With various stakeholders along the corridor
• Community Events• Throughout the corridor
Flyer Translation into Hmong Language
July 31 East Metro Garage Open House
![Page 8: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/8.jpg)
History of Alignment
8
![Page 9: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/9.jpg)
9
Alternatives Analysis 2010-2013
• Many options were considered and ultimately eight alternatives were analyzed
![Page 10: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/10.jpg)
10
Environmental Scoping 2013-2016
• Same route was considered for bus rapid transit and light rail transit service
![Page 11: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/11.jpg)
11
Locally Preferred Alternative 2016
![Page 12: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/12.jpg)
12
Project Development 2017-2019
![Page 13: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/13.jpg)
Project Scope in Environmental
Assessment
13
![Page 14: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/14.jpg)
GBRT Goals and Objectives
Improve Mobility (Ridership & Travel Time)
Cost-Effective & Economically Viable
Support Economic Development
Protect the Natural Environment
Preserve & Protect Quality of Life
Tier 1 goals must be considered first
![Page 15: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/15.jpg)
Gold Line Committee Structure
Issue Resolution
Teams (IRTs)
Technical Advisory
Committee (TAC)
Community and
Business Advisory
Committee (CBAC)
Corridor Management Committee
(CMC)Counties Metropolitan
Council
![Page 16: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/16.jpg)
Gold Line Scope Refinement Process
Community Planning
Station Area Planning
Environmental Assessment
Scope
Local Scope
Gold Line Project Scope
16
Ongoing
2017-2018
2018
2018-2019
2019
![Page 17: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/17.jpg)
17
Scope Refinement Tasks• July
– Reviewed scope currently included in the Environmental Assessment
• August – Discuss stakeholder feedback and areas along route where
options exist• Fall/Winter
– Review updated project costs at 15% design• 2019
– Review 30% Design, Cost Estimate, and Funding
![Page 18: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/18.jpg)
18
Discussion Outline• Consider all information presented to date • Participate in the conversation• Allow time for others to speak• Be open to all ideas and comments• Consensus is not required
![Page 19: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/19.jpg)
Percent Dedicated Guideway
19
![Page 20: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/20.jpg)
20
BRT as a Premium Service• What makes the Gold Line a premiere service?
– BRT is like LRT• Distinctive station architecture and design• Station amenities like real time signage• Uniquely branded buses• Regular all-day reliable service• Direct connection to METRO system• Exclusive lanes
![Page 21: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/21.jpg)
21
Types of Guideway
Mixed Traffic
Center RunningSide Running
Curbside Running
![Page 22: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/22.jpg)
22
Gold Line BRT Mixed Traffic
• Where is mixed traffic proposed an why?Location Reason
Sections of downtown Right of Way constraints
Kellogg Bridge Planned replacement of bridge is not part of GBRT Project
Maria Ave Option (not preferred option)
Right of Way constraints
Hudson from White Bear to Etna
Low ADT means it operates like dedicated guideway, avoids impact to vegetation and neighborhood character
Tanners Lake Right of Way constraints and environmental impacts to lake
4th Street Planned replacement of bridge is not part of GBRT Project. Bridge width is constraint.
Bielenberg/Tamarack Nature Preserve
Right of Way constraints and environmental impacts to nature preserve.
![Page 23: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/23.jpg)
23
Gold Line BRT Mixed Traffic
![Page 24: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/24.jpg)
24
Mixed Traffic versus Dedicated Guideway• Federal Transit Administration requires at least 50%
dedicated• LPA route is 78% dedicated• Amount of dedicated lanes could be less depending
on options selected
CBAC Discussion
![Page 25: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/25.jpg)
Mounds Blvd/Maria Ave Station Location
25
![Page 26: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/26.jpg)
26
Mounds Boulevard Station Option
![Page 27: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/27.jpg)
27
Mounds Boulevard Station Option
![Page 28: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/28.jpg)
28
Mounds Boulevard Station Option
![Page 29: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/29.jpg)
29
Maria Avenue Station Option
![Page 30: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/30.jpg)
30
Maria Avenue Station Option
![Page 31: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/31.jpg)
31
Maria Avenue Station Option
![Page 32: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/32.jpg)
Mounds Blvd Maria AveBRT operations Preserves two-lane
dedicated guidewayMixed-traffic: lower level of BRT service
Property impacts No impacts No impactsNoise wall Requires noise wall
reconstructionNo impacts
I-94 impacts Changes to I-94 offramp and Mounds Blvd required
No impacts
Location Station further from neighborhood center
Station closer to neighborhood center
City policy Adopted in city’s Station Area Plan
Not in city policy
Cost Included in current $420M estimate
$4M cost savings over Mounds
32
Mounds Blvd/Maria Ave Station Location
![Page 33: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/33.jpg)
• Technical Advisory Committee (TAC) prefers Mounds Blvd option– Pending review of
• Americans with Disabilities Act (ADA) concerns• Final technical review by Minnesota Department of
Transportation
CBAC Discussion
33
Mounds Blvd/Maria Ave Station Location
![Page 34: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/34.jpg)
Hudson Road Mixed Traffic/Dedicated Guideway
34
![Page 35: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/35.jpg)
35
Hudson Rd Mixed Traffic Option
![Page 36: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/36.jpg)
36
Hudson Rd Dedicated Guideway Option
![Page 37: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/37.jpg)
37
Hudson Rd
![Page 38: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/38.jpg)
38
Hudson Rd Mixed Traffic Option
![Page 39: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/39.jpg)
39
Hudson Rd Dedicated Guideway Option
![Page 40: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/40.jpg)
Mixed Traffic Dedicated GuidewayPedestrian bridge No impacts Impacts Hazelwood bridgeNoise wall Minimal impacts Impacts wall full length of
HudsonProperty impacts Reduced property / boulevard
impacts by 8’Impacts properties / boulevard 8’ more
Parking Maintains on-street parking Eliminates on-street parkingHudson Rd No change: remains two-way One lane westboundBRT operations Operates as if dedicated
(existing 200 cars/day traffic volumes)
Highest level of operations
Neighborhood character
Limited impacts Potential for perceived impacts
Grace Lutheran Church
No impacts Impacts driveway
Cost $7.5M cost savings over dedicated guideway
Included in current $420M estimate
40
Hudson Rd Mixed Traffic / Dedicated Guideway Option
![Page 41: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/41.jpg)
• Technical Advisory Committee (TAC) has not indicated a preference
CBAC Discussion
41
Hudson Rd Mixed Traffic/Dedicated Guideway Option
![Page 42: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/42.jpg)
White Bear Avenue Station Location
42
![Page 43: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/43.jpg)
43
Van Dyke Station Option
![Page 44: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/44.jpg)
44
Van Dyke Station Option
![Page 45: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/45.jpg)
45
Hazel Station Option
![Page 46: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/46.jpg)
46
Hazel Station Option
![Page 47: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/47.jpg)
Van Dyke St Hazel StNeighborhood access
Closer to White Bear Ave businesses
Closer to high-density housing and potential redevelopment sites
Property impacts Property impacts to provide station access
No impacts
Visibility Station may be obstructed by buildings
Greater visibility
Station spacing Further from Sun Ray Station
Closer to Sun Ray Station
Cost Included in current $420M cost estimate
$400K increase over Van Dyke
Bike-ped links No improvements planned for Van Dyke
Hazel designated as future minor bikeway
City policy Adopted in city’s Station Area Plan
Not currently in city policy
47
White Bear Avenue Station Location
![Page 48: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/48.jpg)
• Technical Advisory Committee (TAC) has not indicated a preference
• Station area planning process lead by the counties prefers Hazel
CBAC Discussion
48
White Bear Avenue Station Location
![Page 49: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/49.jpg)
Upcoming CBAC Meetings
49
![Page 50: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/50.jpg)
• Next CBAC meeting will be a bus tour• Hold Tuesday September 25 from 10 am to 2 pm for tour
– Meet up location and exact times forthcoming
50
September CBAC Meeting
![Page 51: METRO Gold Line Project Update...Aug 23, 2018 · 3 CBAC Co-Chairs Attending First CMC Meeting • CBAC Co-Chairs Appointed in July – Darrell Paulsen, Community Representative –](https://reader035.vdocument.in/reader035/viewer/2022081618/60a454a9bc5428140e07308f/html5/thumbnails/51.jpg)
For more information:www.metrotransit.org/gold-line-project
51