metro red line segment 2boardarchives.metro.net/items/1998/03_march/10.pdf · metro red line...
TRANSCRIPT
-
e Train is Coming
LA CMT A
CONSTRUCTION UPDATE
MARCH 23, 1998
METRO RED LINE
SEGMENT 2
ROLL YWOOD EXTENSION
-
PROJECT STATUS
. 93. % CONSTRUCTION PROGRESS
TWENTY - FO UR (24) WEEKS BEHIND SCHEDULE
iJ.b" REVENUE OPERATION:
- Goal of December 1998
- Forecast June 1999
. $1.475 BILLION OF $1.641 BILLION EXPENDEDTO DATE
. $1.574 BILLION COMMITTED
-
Contract B241 Vermont/Beverly Station
Fin an cial:
$42.8 Million Paid to Date$48.0 Million Forecast at Completion
Progress: 960/0 Complete
. Street restoration
. Interior station finishes: metalceilings and artwork
. Station equipment testing over 50010complete
Issue:Impact of rockwork installation oncontract completion
Installation of entrance escalatorsbegan
-
Contract B252 Vermont/Santa Monica Station
Financial:$52.6 Million Paid to Date$58.6 Million Forecast at Completion
Progress: 98.2 % Complete. Plaza restoration work
. Station equipment testingapproached completion
. Interior wall/floor tile and metalceilings installation
Issue:. Late installation of escalator
equipment is impacting stationfinish work
Station platform level
-
Contract B261 Vermont/Sunset StationFinancial:$43.6 Million Paid to Date$52.0 Million Forecast at Completion
Progress: 880/0 CompleteEntrance and appendages concreting
. Installation of platform ceilingpanels and electrical/mechanicalequipment
. Street deck removed
Issues:Assessment of the damage toelectrical equipment caused byflooding in station
. Overall construction progress
Vermont A venue street deckremoval was completed
-
Contract B271 Hollywood/Western Station
Financial:$39.1 Million Paid to Date$46.1 Million Forecast at Completion
Progress: 960/0 Complete. Station equipment testing over 50%
complete
. Station wall and floor tile installationapproached completion
Issues:. Issuance of landscaping design
change
. Street restoration change notice
Red car replica artwork wasinstalled
-
Contract B281 Hollywood Vine StationFinancial:$49.1 Million Paid to Date$59.1 Million Forecast at Completion
Progress: 970/0 Complete
. Installation of terrazzo and starson Hollywood Boulevard
. Interior ceiling system, wall tile andfilm reel artwork installation
. Station equipment testing over85% complete
. Bus/auto plaza construction
Restoration of stars on Hollywood Blvd.continued
-
Contract B620 AUTOMATIC TRAIN CONTROL
Financial:$18.0 Million Paid to Date$22.9 Million Forecast at Completion
Progress: 89% Complete
. Fiber optic cable installation completed
. Installation of train control equipmentand cables continued in tunnels andstations
Train control equipment installationcontinued in the tunnels
-
CRITICAL PATHS
FIRE AND EMERGENCY MANAGEMENT SYSTEM
(B646) CONTRACT ISSUES
WATER DAMAGED EQUIPMENT AT
VERMONT/SUNSET STATION (B261)
AUTOMATIC TRAIN CONTROL EQUIPMENT
INSTALLATION AND TESTING (B260)
VERMONT/SUNSET STATION KAISER
ENTRANCE (B263)
-
Ii LA CMT ACONSTRUCTION UPDATEMarch 23 , 1998
... ... ... ... .... ... ... ... ... ....
METRO RED liNESEGMENT 3
NORTH HOllYWOOD EXTENSION
-
METRO RED liNENORTH HOllYWOOD EXTENSION
22MAY98 .
!;O"~"
,.,.
c"o!;~IO~'AR .
!;~"
cv.AL
~ ,.,..,
,,",000 ~~ ~""
~"
\.\."i ocv.",,0 "
~ ~o"~'"'.e
14 JAN 98
27 FEe 97
'\
~\I"~,,\lC
" !;~
0' !;""f~
s', ~~~
. \1110-
"';
22 MAY 98. .. ,,\III'
. !;!;
"CC~
.'"'.e Ii.
" '"
23 DEC 97
fI
. .
41.'NOI/r
..
J! 4 C !.IN/IISJ!4f:rCI:Ss I:I/S4
j'
. s CI/Js'jfry Sr
'1 0111:1/4 r/ON
14 JAN 98
Tunnel Access
lZZ2 Shaft
3377
23 DEe 97
- SEG.
' r-J.
'""V
+- o
HOLLYWOODHIGHLANDSTATION
(:;
Tunnel through station COJ"
Skid the tunnel machinethrough the excavated station
February 27 , 1998
PROJECTSTATUS58010 COMPLETE
May 2000 ROD
WITHIN BUDGET OF $1.
BilliON- $1 BilliON
COMMITTED
$740* MilliONEXPENDED
* Estimated
-
CO30 HOll YWOOD
HIGHLANDSTATION
78% complete
$62.5M incurred
$81 M forecast at completion
PROGRESS
. completed main entrance interior and
exterior walls and columns at
mezzanine level
. completed entrance elevator upper
ancillary landing
. completed stairs 6 & 7
ISSUESmitigation schedule for work deleted
and delays
I:J
-
CO30
HOLL YWOODHIGHLANDSTATION
mezzaninelevel concrete
-
CO31TUNNELS
UNIVERSAL
HOll YWOOD
760/0 complete$124M million incurred
$175.3M forecast at completion
PROGRESS. AR and AL arch concrete underway
south of La Brea
. AR invert concrete north of track room550/0 complete
ISSUESDiffering site condition claim -Reach
. Tunnel concreting and track levelexcavation delays
-
EWJCO311
TUNNELS -UNIVERSAL
HOLLYWOOD
HOPE & RebarbetweenHollywood/Highland & La Brea
-
CO321UNIVERSAL
CITYSTATION
75% complete
$43M incurred
$68. 1 M forecast at completion
PROGRESSplaced structural concrete in lower
exterior walls lifts 13-
placed backfill material over BRS
and station roof lifts 3-
continued to install finish items in
highbay area
ISSUESunit price quantity overruns
systems/facility coordination
-
CO321
UNIVERSALCITY STATION
Columns inCrossover
t'f