Reception/Transmission Test: USAP 2003-2004 Field Season Matthew Lazzara AMRC/SSEC University of Wisconsin-Madison Mike Comberiate NASA Goddard Space Flight Center Pat Smith/NSF

Upload: kalb

Post on 15-Jan-2016

17 views

Category:

Documents


0 download

DESCRIPTION

MGS Reception/Transmission Test: USAP 2003-2004 Field Season. Matthew Lazzara AMRC/SSEC University of Wisconsin-Madison Mike Comberiate NASA Goddard Space Flight Center. Pat Smith/NSF. Project Objectives: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

MGS Reception/Transmission Test:USAP 2003-2004 Field Season

Matthew Lazzara

AMRC/SSEC

University of Wisconsin-Madison

Mike Comberiate

 NASA Goddard Space Flight Center

Pat Smith/NSF

Page 2: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

Project Objectives:• Test the reception of Aqua and/or Terra satellite direct

broadcast data (sample passes) with the MGS• Process the data on station into scientifically usable data• Transmit the results and other derived products back to the

United States via the TDRSS/MTRS link with MGS

Pat Smith/NSF

Page 3: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

Objectives:• What it takes to

accomplish this in terms of software, infrastructure, personnel, etc.

• The timing to do these tasks

• Identify any problems or obstacles to this process

Software:• IMAPP• RT-STPS

Page 4: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

New Capabilities for MGS• The following new capabilities have been demonstrated but are

not yet operational• MGS can now receive EOS Direct Broadcasts

- Terra realtime (MODIS)- Aqua realtime (MODIS, AIRS, etc)- Available on McMurdo LAN for IMAPP to process

• Can receive EOS-Aqua playbacks at 150Mbps- Contains same data over an orbit.

• Can now return extremely large files to CONUS

- One-way link to White Sands

- Mail tapes to end user

- Next day as scheduled in advance

• Operational capabilities may require more resources

Page 5: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

TDRS

White Sands Complex (WSC)

A. Fortin 03/01/04

TSI Frame Sync DQM 150Mbps RAID-Linux red hat with Timesys Kernel-For remote scheduling either 1)API using ports 5001 and 5002 2)API using ports 6001 and 6002 for NASA file transfer demonstration-Raid may also contain Science products,such as EOS Direct Broadcast movies-Data transfer via MTRS using internal s/w of RAID and/or via NASA custom “file transfer”

MTRS Laptops-Win2000-Control/status only of MTRS RF equipment

10-meter MGS

X Band RF equipment

Closed IONetNSF LANLTO-200 Robotic Tape Library

Closed IONet

Clock

Data

NSF McMurdo LAN

200GB Tapes get shipped to Alaska SARand/or sent via TDRS to WSC. Also available to local MCM users if needed.

MTRS2 RFEquipment

Control/Status

TSI Frame Sync DQM 150Mbps RAID-VxWorks/Unix-For remote scheduling either 1)https GUI 2)API using ports 5001 and 5002 3)API using ports 6001 and 6002 for NASA file transfer demonstration

Internet

-McMurdo generated data products-remote scheduling via TSI software or NASA file transfer software

Tapes shipped to Alaska SAR or otherswith LTO tape drives

NSFFW

To Internet

Science Data or Telemetry DataDATA OUTPUTS ONLYECL/TTL CLOCK/DATA

SCSI

SCSI

- Interface to Science Users in MCMIs this EOS Data Processing Workstation- This computer is on MCM LAN- For security, user at McMurdomust use tape drive to retrieve/sendany data to MGS RAID

MGS FY04RAID to RAIDtransfers

External Site

LTO-200 Robotic Tape Library

LTO-200 Tape DriveSCSI

Page 6: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

Direct Broadcast from EOS• MGS now has the capability to receive the realtime,

direct broadcast telemetry from EOS Terra or EOS Aqua

• Key driver was to enable improved weather forecasting– MODIS/AIRS vertical Water Vapor profiles

– Can easily meet the timeliness requirements for forecasting

• Data is recorded from the RAID onto Tapes– Tapes are walked over to a computer on the Internet

– Data is converted to Level 0 and ready for processing by IMAPP software on-site in McMurdo

• Limited by availability of the single aperture

Page 7: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

High Volume Data Return to CONUS• Intended to enable data products generated in

McMurdo to get to end users in CONUS– Polar Stereographic Movies (NSF and NASA users)– Also works for any spacecraft telemetry (NASA missions)

• TDRS is available for next day data returns– Extremely high volume files are possible (125Mbps)– Telemetry Files or Data Files– Data received at White Sands (WSC) is taped and tapes

mailed to end user– Alternate DVD-RW option in the works for ~4GB files– Eventual https access from WSC for lower volume files

Page 8: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

LTO-200 Tape LibrarySCSI

MGS RAID

Detailed RAID to RAID Communications

Closed IONet

FirewallWSC RAID

SCSI

LTO-200 Tape Library

A. Fortin 03/01/04

TDRS

MTRS2 RFEquipment

WSC RFEquipment

Clock

Data

Science Data or Telemetry DataDATA OUTPUTS ONLYECL/TTL CLOCK/DATA

Clock

Data

Science Data or Telemetry DataDATA OUTPUTS ONLYECL/TTL CLOCK/DATA

SPTR LAN (Internet)

TCP Server (port 6001)

TCP Client (port 6001)

TCP connection for acknowledgements to MGS RAID, to maintain file transfers

RF connection for sending file data to WSC RAID

-FTP Server for science access to data (https access eventually)-https server for access to scheduling software

Page 9: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

MGS FY04 - New Capabilities Summary -MGS RAID has been activated and will be incorporated into the MGS automation.-RAID enables 150Mbps data capture from EOS-EOS direct broadcast collection is possible but limited by 10-m antenna availability.-Data returns to CONUS at 125Mbps are working via TDRS.

- TDRSS not interested in meeting timeliness requirements but “next day” is okay-NASA engineering effort now focused on RAID install at WSC and “Demonstration Mode” of RAID to RAID data transfers (via MTRS) from MGS to WSC.

-MGS RAID must remain on Closed for MGS automation operations.-We put WSC RAID on the Internet?

-Internet WSC RAID requires no waiver for RAID to RAID comms.-WSC RAID is always listening for the MGS RAID to start a connection-TCP comms between RAIDs is for acknowledgements only of data through the TDRS link.-Eventually will set up an https log-in for end users to access data on WSC Drive electronically, but that is constrained to low volume data files. -A Tape mailing operation is underway for the very high volume data files

-RAIDs cannot perform a transfer of data when MGS RAID is receiving X-band pass.-RAID will have software to allow remote scheduling.-RAID will perform two types of transfers

-Telemetry transfers (raw data only, can use existing software on RAIDs)-File transfers (allows any type of file for transfer, NASA built software)

-NASA operates the demonstration until NASA decides to turn over to operations.

Comberiate 3/1/04

Page 10: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

Potential Upgrades if Funded

• Add a Data-Stripping capability in MCM– Send low volume data to CONUS via Internet– Send bulk data to CONUS via TDRS next day

• Add Second Aperture (fully automated)– Recommend a X/S/L Receive-only 12-ft system– Remove single point failure– Increase number of supports per day

• Electronic access to WSC by end users– Better connectivity is a function of need

Page 11: MGS Reception/Transmission Test: USAP 2003-2004 Field Season

Results and Considerations

• Succeeded in getting the telemetry data with MGS

• Problems with preprocessing data & networking

• Didn’t finish the full end to end test – but learned some key issues…

These and other issues can be dealt with.

• MGS network connected to the McMurdo LAN

• Improved computing (AMRC) for handling IMAPP processing & shear large volume of data

• Need to handle data flow back to the US:– TDRSS/MTRS time (24x7?)– Internet (Commercial or

Internet 2?) connection from Windsands/Goddard to end users (NCAR, Wisconsin, etc.)