MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

Upload: johnathan-terry

Post on 26-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 1Georgia State University - Confidential

MGS 3100

Business Analysis

Statistical Quality Control

Oct 17, 2011

Page 2: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 2Georgia State University - Confidential

Agenda

Process Capability

Six SigmaOverview

Page 3: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 3Georgia State University - Confidential

Statistical Process Control

• Statistical Process Control (SPC) is a statistical procedure using control charts to see if any part of a production process is not functioning properly and could cause poor quality.

• In Total Quality Management (TQM) employees use SPC to see if their process is in control – working properly. By continually monitoring the production process and making improvements, the employee contributes to the TQM goal of continuous improvement and few or no defects.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Page 4: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 4Georgia State University - Confidential

Quality Measures – Attributes & Variables

• An attribute is a product characteristics such as color, surface texture, cleanliness, or perhaps smell or taste. Attributes can be evaluated quickly with a discrete response such as good or bad, acceptable or not, yes or no. An attribute measure evaluation is sometimes referred to as a qualitative classification, since the response is not measured.

• A variable measure is a product characteristics that is measured on a continuous scale such as length, weight, temperature, or time. For example, the amount of liquid detergent in a plastic container can be measured to see if it conforms to the company’s product specifications.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Page 5: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 5Georgia State University - Confidential

Control Charts

• Control Charts have historically been used to monitor the quality of manufacturing process. SPC is just as useful for monitoring quality in services. The difference is the nature of the “defect” being measured and monitored. Using Motorola’s definition – a failure to meet customer requirements in any product or service.

• Control Charts are graphs that visually show if a sample is within statistical control limits. The control limits are the upper and lower bands of a control chart. They have two basic purposes, to establish the control limits for a process and then to monitor the process to indicate when it is out of control. All control charts look alike, with a line through the center of a graph that indicates the process average and lines above and below the center line that represent the upper and lower limits of the process.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Page 6: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 6Georgia State University - Confidential

Control Charts for Attributes

• The quality measures used in attribute control charts are discrete values reflecting a simple decision criterion such as good or bad. A p-chart uses the proportion of defective items in a sample as the sample statistics; a c-chart uses the actual number of defects per item in a sample.

p-charts• Although a p-chart employs a discrete attribute measure (i.e. number of

defective items) and thus is not continuous, it is assumed that as the sample size gets larger, the normal distribution can be used to approximate the distribution of the proportion defective.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Z

Page 7: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 7Georgia State University - Confidential

Control Charts for Attributes~ p-chart

• The p-formula – the sample proportion defective; an estimate of the process average

• The standard deviation of the sample proportion

• To calculate control limits for the p-chart:

• z = the number of standard deviations from the process average. In the control limit formulas for p-charts (and other control charts), z is occasionally equal to 2.00 but most frequently is 3.00. A z value of 2.00 corresponds to an overall normal probability of 95 percent and z = 3.00 corresponds to a normal probability of 99.74 percent.

Z

δp =

Z

Total defectives Total sample observations

n

n

k = the number of samples

n = the sample size

Page 8: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 8Georgia State University - Confidential

Control Charts for Attributes~ p-chart (Example)

• Please read Example 1 on page 337.

• The Western Jeans company produces denim jeans. The company wants to establishes p-chart to monitor the production process and maintain high quality. Western believes that approx. 99.74 percent of the variability in the production process (z = 3.00) is random and thus should be within control limits, whereas 0.26 percent of the process variability is not random and suggests that the process is out of control.

• The company has taken 20 samples (one per day for 20-days), each containing 100 pairs of jeans (n=100), and inspected them for defects. The total number of defectives are 200.

• Find the control limits.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Z

Page 9: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 9Georgia State University - Confidential

Control Charts for Attributes~ c-chart

• A c-chart is used when it is not possible to compute a production defective and the actual number of defects must be used. For example, when automobiles are inspected, the number of blemishes (i.e. defects) in the paint job can be counted for each car, but a proportion cannot be computed, since the total number of possible blemishes is not known.

• The standard deviation

• To calculate control limits for the p-chart:

• Please read Example 2 on page 340.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Z

Z

δc =

f = the total number of defects / total number of samples

Page 10: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 10Georgia State University - Confidential

Control Charts for Attributes~ c-chart (Example)

• Please read Example 2 on page 340.

• The Ritz Hotel believes that approximately 99% of the defects (corresponding to 3-sigma limits) are caused by natural, random variations in the housekeeping and room maintenance service, with 1% caused by nonrandom variability. They want to construct a c-chart to monitor the housekeeping service.

• 15 inspections samples are selected by the hotel. An inspection sample includes 12 rooms and the total number of defects is 190.

• Find the control limits.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Z

Page 11: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 11Georgia State University - Confidential

Control Charts for Variables~ R-chart

• Variable control charts are for continuous variables that can be measured, such as weight or volume. Two commonly used variable control charts are the range chart (R-chart) and the mean chart (x-bar chart).

R-chart• In an R-chart, the range is the difference between the smallest and largest

values in a sample. This range reflects the process variability instead of the tendency toward a mean value.

• R is the range of each samplek is the number of samples.

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Z

                                  

Upper control limit                       

Lower control limit                      

Page 12: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 12Georgia State University - Confidential

Control Charts for Variables~ R-chart (Example)

• Please read Example 3 on page 343.

• In the production process for a particular slip-ring bearing the employees have taken 10 samples (during 10-day period) of 5 slip-ring bearings (n=5). Please define the control limits for R-chart. The individual observations from each sample are shown as follows:

Z

Sample k 1 2 3 4 5 R

1 5.02 5.01 4.94 4.99 4.96 4.98 0.08

2 5.01 5.03 5.07 4.95 4.96 5.00 0.12

3 4.99 5.00 4.93 4.92 4.99 4.97 0.08

4 5.03 4.91 5.01 4.98 4.89 4.96 0.14

5 4.95 4.92 5.03 5.05 5.01 4.99 0.13

6 4.97 5.06 5.06 4.96 5.03 5.02 0.10

7 5.05 5.01 5.10 4.96 4.99 5.02 0.14

8 5.09 5.10 5.00 4.99 5.08 5.05 0.11

9 5.14 5.10 4.99 5.08 5.09 5.08 0.15

10 5.01 4.98 5.08 5.07 4.99 5.03 0.10

sum 50.11 1.15

average 0.115

R

Page 13: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 13Georgia State University - Confidential

Control Charts for Variables~ x-bar chart

• For an x-bar chart, the mean of each sample is computed and plotted on the chart; the points are sample means. The samples tend to be small, usually around 4 or 5.

n is the sample size (or number of observations)

k is the number of samples

Source: Selected Chapters on Business Analysis – Ch15 Statistical Process Control

Z

                                  

Upper control limit                       

Lower control limit                      

Page 14: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 14Georgia State University - Confidential

Control Charts for Variables~ x-bar chart (Example)

• Please read Example 4 on page 345.

• Use the data from Example 3 and define the control limits for x-bar chart.

Z

Page 15: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 15Georgia State University - Confidential

Control Charts for Variables~ Tabular values for X-bar and R charts (Given)

Sample Size n A2 D3 D4

2 1.880 0 3.268

3 1.023 0 2.574

4 0.729 0 2.282

5 0.577 0 2.114

6 0.483 0 2.004

7 0.419 0.076 1.924

8 0.373 0.136 1.864

9 0.337 0.184 1.816

10 0.308 0.223 1.777

11 0.285 0.256 1.744

12 0.266 0.283 1.717

13 0.249 0.307 1.693

14 0.235 0.328 1.672

15 0.223 0.347 1.653

Page 16: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 16Georgia State University - Confidential

Control Charts for Variables~ Tabular values for X-bar and R charts (Given)

Sample Size n A2 D3 D4

16 0.212 0.363 1.637

17 0.203 0.378 1.622

18 0.194 0.391 1.608

19 0.187 0.403 1.597

20 0.180 0.415 1.585

21 0.173 0.425 1.575

22 0.167 0.434 1.566

23 0.162 0.443 1.557

24 0.157 0.451 1.548

25 0.153 0.459 1.541

Page 17: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 17Georgia State University - Confidential

Agenda

OverviewProcess Capability

Six Sigma

Page 18: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 18Georgia State University - Confidential

Process Capability

Process Capability – A measure of how “capable” the process is to meet customer requirements; compares process limits to tolerance limits. There are three main elements associated with process capability – process variability (the natural range of variation of the process), the process center (mean), and the design specifications.

Process limits (The “Voice of the Process” or The “Voice of the Data”) - based on natural (common cause) variation

Tolerance limits (The “Voice of the Customer”) – customer requirements

Page 19: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 19Georgia State University - Confidential

Process Capability

• Variation that is inherent in a production process itself is called common variation.

common variation

specification

(1)

specification

common variation

(3)

specification

common variation

(2)

specification

common variation

(4)

Page 20: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 20Georgia State University - Confidential

Process Capability Ratio

• One measure of the capability of a process to meet design specifications is the process capability ratio (Cp). It is defined as the ratio of the range of the design specifications (the tolerance range) to the range of process variation, which for most firms is typically ±3δ or 6δ

• If Cp is less than 1.0, the process range is greater than the tolerance range, and the process is not capable of producing within the design specifications all the time. If Cp equals 1.0, the tolerance range and the process range are virtually the same. If Cp is greater than 1.0, the tolerance range is greater than the process range.

• Companies would logically desire a Cp equal to 1.0 or greater, since this would indicate that the process is capable of meeting specifications.

Page 21: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 21Georgia State University - Confidential

Process Capability Ratio (Example)

• Please read Example 6 on page 354.

• The XYZ Snack Food Company packages potato chips in bags. The net weight of the chips in each bag is designed to be 9.0 oz, with a tolerance of +/- 0.5 oz. The packaging process results in bags with an average net weight of 8.80 oz and a standard deviation of 0.12 oz. The company wants to determine if the process is capable of meeting design specifications.

Page 22: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 22Georgia State University - Confidential

Process Capability Index

• The Process Capability Index (Cpk) differs from the Cp in that it indicates if the process mean has shifted away from the design target, and in which direction it has shifted – that is, if it is off center.

• If the Cpk index is greater than 1.00 then the process is capable of meeting design specifications. If Cpk is less than 1.00 then the process mean has moved closer to one of the upper or lower design specifications, and it will generate defects. When Cpk equals Cp, this indicates that the process mean is centered on the design (nominal) target.

• Please read Example 7 on page 354.

where• x-bar is the mean of the process

• sigma is the standard deviation of the process

• UTL is the customer’s upper tolerance limit (specification)

• and LTL is the customer’s lower tolerance limit

3

X-UTLor

3

LTLXmin=Cpk

Page 23: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 23Georgia State University - Confidential

Interpreting the Process Capability Index

Cpk < 1 Not Capable

Cpk > 1 Capable at 3

Cpk > 1.33 Capable at 4

Cpk > 1.67 Capable at 5

Cpk > 2 Capable at 6

Page 24: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 24Georgia State University - Confidential

Process Capability Index (Example)

• A process has a mean of 45.5 and a standard deviation of 0.9. The product has a specification of 45.0 ± 3.0. Find the Cpk .

Page 25: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 25Georgia State University - Confidential

Process Capability Index (Example)

= min { (45.5 – 42.0)/3(0.9) or (48.0-45.5)/3(0.9) }

= min { (3.5/2.7) or (2.5/2.7) }

= min { 1.30 or 0.93 } = 0.93 (Not capable!)

However, by adjusting the mean, the process can become capable.

3

X-UTLor

3

LTLXmin=Cpk

Page 26: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 26Georgia State University - Confidential

Agenda

Process Capability

Six SigmaOverview

Page 27: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 27Georgia State University - Confidential

What is Six Sigma?

• A goal of near perfection in meeting customer requirements

• A sweeping culture change effort to position a company for greater customer satisfaction, profitability and competitiveness

• A comprehensive and flexible system for achieving, sustaining and maximizing business success; uniquely driven by close understanding of customer needs, disciplined use of facts, data, and statistical analysis, and diligent attention to managing, improving and reinventing business processes

• Source: The Six Sigma Way by Pande, Neuman and Cavanagh

Page 28: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 28Georgia State University - Confidential

Six Sigma Quality

• The objective of Six Sigma quality is 3.4 defects per million opportunities!

Degree of Shift in Mean Quality Level (# Defects per Million Opportunities)

(Number of Standard Deviations) 3 Sigma 4 Sigma 5 Sigma 6 Sigma

0.0 2700 63 0.57 0.002

0.5 6440 236 3.4 0.019

1.0 22832 1350 32 0.019

1.5 66803 6200 233 3.4

2.0 158,700 22800 1300 32

Page 29: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 29Georgia State University - Confidential

Is Six Sigma Realistic?

·

1

11

21

31

41

3 4 5 6 7

10

1

100

1K

10K

100K

765432

1

11

21

31

41

3 4 5 6 7

10

1

100

1K

10K

100K

765432

1

11

21

31

41

3 4 5 6 7

10

1

100

1K

10K

100K

765432

(66810 ppm)

IRS – Tax Advice (phone-in)

Best in Class

(3.4 ppm)

(0.43 ppm)

·(233 ppm)

AverageCompany

Purchased MaterialLot Reject Rate

Air Line Baggage Handling

Wire Transfers

Journal VouchersOrder Write-up

Payroll Processing

Doctor Prescription WritingRestaurant Bills

·······

Defe

cts

Per

Million O

pport

unit

ies

(DPM

O)

SIGMA

Page 30: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 30Georgia State University - Confidential

Six Sigma Improvement MethodsDMAIC vs. DMADV

Define

Measure

Analyze

Design

Validate

Improve

Control

Continuous Improvement Reengineering

Page 31: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 31Georgia State University - Confidential

Six Sigma DMAIC Process- Define

• Define: Define who your customers are, and what their requirements are for your products and services – Their expectations. Define your team goals, project boundaries, what you will focus on and what you won’t. Define the process you are striving to improve by mapping the process.

Measure

Control

Define

Analyze

Improve

Page 32: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 32Georgia State University - Confidential

Six Sigma DMAIC Process- Measure

• Measure: Eliminate guesswork and assumptions about what customers need and expect and how well processes are working. Collect data from many sources to determine speed in responding to customer requests, defect types and how frequently they occur, client feedback on how processes fit their needs, how clients rate us over time, etc. The data collection may suggest Charter revision.

Measure

Control

Define

Analyze

Improve

Page 33: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 33Georgia State University - Confidential

Six Sigma DMAIC Process- Analyze

• Analyze: Grounded in the context of the customer and competitive environment, analyze is used to organize data and look for process problems and opportunities. This step helps to identify gaps between current and goal performance, prioritize opportunities to improve, identify sources of variation and root causes of problems in the process.

Measure

Control

Define

Analyze

Improve

Page 34: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 34Georgia State University - Confidential

Six Sigma DMAIC Process- Improve

• Improve: Generate both obvious and creative solutions to fix and prevent problems. Finding creative solutions by correcting root causes requires innovation, technology and discipline.

Measure

Control

Define

Analyze

Improve

Page 35: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 35Georgia State University - Confidential

Six Sigma DMADV Process- Design

• Design: Develop detailed design for new process. Determine and evaluate enabling elements. Create control and testing plan for new design. Use tools such as simulation, benchmarking, DOE, Quality Function Deployment (QFD), FMECA analysis, and cost/benefit analysis.

Measure

Validate

Define

Analyze

Design

Page 36: MGS3100_05.ppt/Oct 17, 2011/Page 1 Georgia State University - Confidential MGS 3100 Business Analysis Statistical Quality Control Oct 17, 2011

MGS3100_05.ppt/Oct 17, 2011/Page 36Georgia State University - Confidential

Six Sigma DMADV Process- Validate

• Validate: Test detailed design with a pilot implementation. If successful, develop and execute a full-scale implementation. Tools in this step include: planning tools, flowcharts/other process management techniques, and work documentation.

Measure

Validate

Define

Analyze

Design