mice construction project in the us

23
MICE CONSTRUCTION PROJECT in the US Alan Bross Fermilab May 7, 2013

Upload: artan

Post on 25-Feb-2016

46 views

Category:

Documents


0 download

DESCRIPTION

MICE CONSTRUCTION PROJECT in the US. Alan Bross Fermilab May 7 , 2013. Outline. Project Team Scope of Effort Execution Plan Phase I & II Deliverables Some historical context Schedule details Critical Dates L2 Management Team Organizational Implementation Moving Forward Conclusion. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MICE CONSTRUCTION PROJECT in the US

MICE CONSTRUCTION PROJECTin the US

Alan BrossFermilab

May 7, 2013

Page 2: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 2

Outline• Project Team• Scope of Effort• Execution Plan

– Phase I & II Deliverables• Some historical context

– Schedule details– Critical Dates– L2 Management Team– Organizational Implementation Moving Forward

• Conclusion

Page 3: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 3

L2 Management Team• Magnet Fabrication

– Spectrometer solenoids and Coupling Coils

• RF Fabrication– 201 MHz cavities & components– Vacuum vessels

• Detector– Trackers

• Trackers to be integrated with SS when they arrive at RAL

– Cerenkov• Magnetic shielding

– Partial return yoke• US component integration

– US liaison for installation and commissioning

• Likely stationed at RAL

• + LiH absorbers (Fermilab)

Page 4: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 4

Scope of Effort• Detectors (Complete)

– Two fiber trackers with readout & cryogenics– Two Cherenkov detectors

• Absorbers– LiH Disk (complete)– LiH Wedges

• Two superconducting spectrometer solenoids• Two large-aperture (1.5m), 2.5T SC solenoids, Coupling Coil Magnet

(CCM)– CCM Prototype will be used in MuCool Test Area – Two needed for MICE Step VI

• RF System– Eight 201 MHz cavities with tuners and vacuum vessels

• Integrated with CCM– RF power components (through NSF MRI)

• Commercial products

• Magnetic Analysis and stray-field mitigation– Design and engineering of partial return yoke

Page 5: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 5

Deliverables StepIV: Fiber Trackers

Page 6: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 6

Deliverables Step IV: LiH• Deliverables

– Detector components (Complete)– Absorbers: LiH disks (complete) and wedges

• In process of establishing a CRADA with STFC which will allow us to ship the LiH to RAL (through Y12)– Since 6Li enriched, considered nuclear material

Page 7: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 7

Step IV Deliverables: SS

• Cryogenically the magnet now operates to spec– Approximately 3 W heat

load (=original calc.)– Total cooling capacity »

6.5 W• SS2 - Vetted• SS1 nearing completion• Ship

– SS2 in July ‘13– SS1 in Sept. ‘13

Page 8: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 8

Step IV Deliverables: Magnetic shielding

• Analysis to determine if partial yoke can contain stray fields in the hall so that there are no effects on any equipment– YES

• Engineering design of yoke– Conceptual design

complete• Performance looks

excellent– Full design work initiated

Shield sections: 100mm [4”] thickBacking plates: 50mm [2”] thick(front & back at vertical joint)

15” x 50 lb/ft S-beams. Bolted into floor, 100 mm away from wall

Floor template for pre-drilling holes

Page 9: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 9

Step IV Deliverables: MICE 201 MHz Production Cavity Test

•Production component system test–Fixturing–Integration/assembly–Tuner control testing–Vacuum and alignment

Ports, supportsand tuners

Fall 2013

Page 10: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 10

Step IV Deliverable: Prototype Coupling Coil Magnet (MuCool)

• The first Coupling Coil Magnets (CCM) is considered a prototype and will be used in the MuCool program, but will test MICE hardware– Cold mass produced at Qi Huan Co (Beijing) & prepped at LBNL

• First complete, 3 more to be fabricated. All SC in hand– New test facility (Solenoid Test Facility) complete

• ORC and commissioning starting in 2 weeks– Cryostat fabrication at LBNL– Final assembly

• At Fermilab with Technical Division (detailed plan under development)

Page 11: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 11

MICE RFCClite Test in MTA

Page 12: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 12

Step VI deliverables: MICE Coupling Coil Magnets with integrated RF (RFCC)

• The MICE cooling channel requires two Coupling Coils– Plan to build 3 windings– 2 Cryostats – Four vacuum vessels– Hold two RF cavities each

• Eight 201 MHz cavities– Complete save for EP

• RF power couplers, tuners, etc.

Page 13: MICE CONSTRUCTION PROJECT in the US

Resource Loaded Schedule

Page 14: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 14

Major Milestones

SS#2 Ready to Ship – July `13

CCM Prototype Tested and ready to move to the MuCool Test Area (MTA) for Testing with RF in the RFCC_Lite Configuration – April `15

SS#1 Ready to Ship – Sept `13

RFCC#1 Ready to Ship – Sept `16

RFCC#2 Ready to Ship – Nov `17

US FY13 FY14 FY15 FY16 FY17 FY18

Does not include contingency

Page 15: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 15

Step IV: Spectrometer Solenoids

Page 16: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 16

Step VI: RF

Page 17: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 17

Step VI: RFCC

RFCC-Lite

Page 18: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 18

Magnetic Mitigation

Page 19: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 19

US Risk Register I

Page 20: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 20

US Risk Register II

Page 21: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 21

0

1,000

2,000

3,000

4,000

5,000

6,000

FY13 FY14 FY15 FY16 FY17 FY18 FY19

then

-FY

$K

US MICE WBS 5 Production Costs (13-05-01)

with <contingency> = 39%

without contingency

$ 4 M/yr limit w/contingencystretchout adds another 1.9%

Now Add Contingency and Stretch

13-05-02-MAP-WBS5-Only.mpp

Almost achieves FY18 completion – BUT…

23,918 K$

17,716 K$

24,383 K$

Sums of then-FY K$

Page 22: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 22

Under These Assumptions…

Note: no approved NSF Funding for Ops & Exp beyond FY13DOE Operations & Experimental support still under development

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21

then

-FY

$K

US MICE Funding Profile

NSF MICE Ops & Exp Support- proposed profile

DOE MICE Operations andExperiment Support

1/2 MICE R&D RISK(distributed flat in FY12 $K)

MICE Construction +Production Contingency

Page 23: MICE CONSTRUCTION PROJECT in the US

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013) 23

Conclusions

• We now have a complete RLS for the US-MICE construction project– Some more work to be done– Contingency and risk included and we have

shown impact on MICE schedule given US funding constraints

• US carries majority of the technical risk– We will know much more in 4-5 months

• Expect both spectrometer solenoids to be complete• Testing of first CCM cold mass complete• Begin testing of MICE production cavity in MTA