mice project status

27
1 paul drumm; 19-09-2005; FAC-PR MICE Project Status Funding Agency Committee 19 th September 2005

Upload: jackson-lambert

Post on 03-Jan-2016

68 views

Category:

Documents


0 download

DESCRIPTION

MICE Project Status. Funding Agency Committee 19 th September 2005. MICE project: Build MICE Install MICE Operate MICE PM=Coordinating: design activities interfaces construction safety resources schedule risks. MICE Project Structures. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MICE Project Status

1paul drumm; 19-09-2005; FAC-PR

MICE Project Status

Funding Agency Committee

19th September 2005

Page 2: MICE Project Status

paul drumm; September ‘05; FAC 2

MICE project:

Build MICE

Install MICE

Operate MICE

PM=Coordinating: design activitiesinterfaces constructionsafetyresourcesschedulerisks

Page 3: MICE Project Status

paul drumm; September ‘05; FAC 3

MICE Project Structures

– MICE Collaboration Board – collaboration chair– MICE Executive Board – spokesman– MICE Technical Board – project manager

• Tech Spec & Change Control• Technical Coordination

– WBS/OBS » Task Managers» Engineering integration & monitoring» Engineering installation» Safety

• MICE Schedule• MICE Risk Management• MICE(UK) fund & schedule management

Page 4: MICE Project Status

paul drumm; September ‘05; FAC 4

MICE Project Tasks

• WBS + visualisation as a set of Gantt charts– Expresses task break down & interrelationships– Critical Path– Milestone definitions– Resource (People Cash) allocation &

responsibilities– Schedule– Responsive – change controlled

• Proposed by TB• Agreed at EB

Page 5: MICE Project Status

paul drumm; September ‘05; FAC 5

WBS• 1 MICE• 1.1 MICE Integration (Drumm/RAL)

1.1.1 Mice Experiment (Drumm+TechBoard)1.1.2 Mice Into Experimental Hall (RAL/UK)1.1.3 Experimental Integration Overview (Oxford/UK)

• 1.2 Muon Beam Line and Infrastructure (Drumm/RAL)1.2.1 Muon Beam Line (RAL)1.2.2 Cryogenic Infrastructure (RAL)1.2.3 Hydrogen System Infrastructure (RAL)1.2.4 Civil Engineering (RAL)1.2.5 Plant and Services (RAL)1.2.6 Interlocks and Safety (RAL)1.2.7 MICE Support Infrastructure (RAL)1.2.8 ISIS-MICE Controls Interface (RAL)1.2.9 Vacuum Systems (RAL)

• 1.3 MICE Cooling Modules (Zisman/LBNL)1.3.1 Absorber and Focus Coil Module (Oxford/UK)1.3.2 Cavity and Coupling Coil Module (LBNL/US)1.3.3 RF Power Systems (DL/UK)1.3.4 Magnet Power Supplies (LBNL/US)1.3.5 Installation and Integration (LBNL/US)

• 1.4 Detectors, Tracker Solenoid and Measurement (Bross/FNAL)1.4.1 ToF (EU)1.4.2 Up Stream Cherenkov (UMO/US)1.4.3 Down Stream Cherenkov (EU)1.4.4 Tracker Module (IC/UK)1.4.5 µCAL(EU)1.4.6 Data Acquisition (Vacant)1.4.7 Analysis and Simulation Software (Torun)

• 1.5 Slow Controls - Instrumentation & Monitoring (Blondel)1.5.X Physics List (MAC)1.5.Y Controls Coordination (DL/UK)

• 1.6 Management (Drumm/RAL)

wro

ng

Page 6: MICE Project Status

paul drumm; September ‘05; FAC 6

task

activity

resource

integration

cavity

vacuum

absorber

UK US JpcEu

instrumentation

Page 7: MICE Project Status

paul drumm; September ‘05; FAC 7

Review roadmap

CreateWorking group

Develop Design Concept

Review

Engineer

Review

Operate

Monitoring

Video conferences

Collaboration meetings

Technical Board

TB

Control

AuditTB

Video conferences

Collaboration meetings

Technical Board

RAL

RAL

Page 8: MICE Project Status

paul drumm; September ‘05; FAC 8

Schedule Overview

Nee

ds c

orre

ctio

n

Fun

ding

Li

mite

d

Page 9: MICE Project Status

paul drumm; September ‘05; FAC 9

Integration

• Ties together– Resources– Design Activities– Oversight

Page 10: MICE Project Status

paul drumm; September ‘05; FAC 10

Beam Line

• Beam Line– Target on the ISIS synchrotron – Optics: capture; decay; matched beam into the

MICE channel • Beam elements from ISIS• New power supplies

• Decay solenoid from PSI• cryogenic system expensive

Page 11: MICE Project Status

paul drumm; September ‘05; FAC 11

Location

MICE:1 Hz800 MeV~0.1 µA

ISIS:50 Hz800 MeV300 µA

Page 12: MICE Project Status

paul drumm; September ‘05; FAC 12

MICE Hall

Page 13: MICE Project Status

paul drumm; September ‘05; FAC 13

Infrastructure

• Shielding• Electricity• Water• Alignment• RF Power Systems*

– Reuse of equipment (ex LBNL ex CERN)

• Hydrogen delivery system*– Critical safety issue

* Funded for prototyping to reduce downstream schedule risks

Page 14: MICE Project Status

paul drumm; September ‘05; FAC 14

Cooling Channel:AFC

• SC Coils surrounding liquid hydrogen cell– Complex engineering

task– Critical safety issue– 20 l each absorber– Explosive : 17% - 56%– Flammable : 4% - 75%– Ignition: 20mJ in air– Gas. Density: 6% of air– Liq. Density: 7% of

water– Expansion ratio 800:1– Particular problem of

pumping– Oxygen plates out on

cold surfaces & cannot be detected

LH2

Vac-I

Vac-IIcold

warmO2 Un-detectable

O2 detectable

Page 15: MICE Project Status

paul drumm; September ‘05; FAC 15

Absorber System

Page 16: MICE Project Status

paul drumm; September ‘05; FAC 16

Cooling Channel:RF-CC

0.38 mm thick, 420 mm dia.201 MHz

MUCOOL R&D

Curved Be windows

R&D Issue: High MV/m in a strong Bfield

Page 17: MICE Project Status

paul drumm; September ‘05; FAC 17

Cooling Channel: RF-Power

4 MW Power systems

Two high power amplifiers and drivers ex LBNL

Two high power amplifiers ex CERNdrivers ex CERN/LBNL

New LLRF system

Deliver 8MW into 8 cavitiesorDeliver 2MW into 4 cavities

Page 18: MICE Project Status

paul drumm; September ‘05; FAC 18

Cooling Channel:I&I

Module Integration: Module-to-module MICE to floor MICE to servicesAbstract: Forces Engineering Standards QA/QC

Interfaces & Integration

Page 19: MICE Project Status

paul drumm; September ‘05; FAC 19

Instrumentation: Particle Identification

• Conventional particle detection applied to accelerator diagnostics– Particle identification– Impure beam – protons, , , e

• Time-of-flight• Cherenkov• Calorimeter

– Momentum & emittance measurement• Spectrometer: Tracking in a magnetic field

Page 20: MICE Project Status

paul drumm; September ‘05; FAC 20

Instrumentation: Spectrometer Solenoid

• Critical path item

• US responsibility– Cash flow limited

construction

GanttBaseline:

End ’07End ’08

Resource limited

Page 21: MICE Project Status

paul drumm; September ‘05; FAC 21

Instrumentation:Spectrometer Tracker

pattern recognition –systematic errorsevaluated with cosmic rays – stringent tests in B field planned

Scintillating fibre tracking detector

MICE trackerSpectrometer

Page 22: MICE Project Status

paul drumm; September ‘05; FAC 22

Instrumentation: I&I

Interfaces & Integration

Page 23: MICE Project Status

paul drumm; September ‘05; FAC 23

Safety Issues

• General engineering issues– Working at height– Heavy objects– Confined spaces

• More specific risks– Cryogenic fluids– High Voltage– Magnetic fields – RF fields & Xrays– Ionising & non-ionising radiation– Liquid hydrogen

• Uniform approach safety first• Processes & tools in place• RAL Confidence in MICE is important for success

Page 24: MICE Project Status

paul drumm; September ‘05; FAC 24

Critical Path - Significant Milestones

• Delivery of Decay Solenoid Cryogenics

• ISIS Shutdown 2006/7

• Completion of beam line

• Delivery of completed tracker detector

• Delivery of PID instrumentation

• Delivery of 1st spectrometer solenoid

Page 25: MICE Project Status

paul drumm; September ‘05; FAC 25

Risk

• Delivery of items in phase 1– Cost overrun (always a risk)– Schedule slippage (¨)

• Still dependent on successful funding bids– INFN particularly– Be, Nl, CH

• Contingency plan:– Re-evaluate minimum needs to characterise the beam– Re-alignment of activities to meet these needs

Page 26: MICE Project Status

paul drumm; September ‘05; FAC 26

Risk

• Delivery of items in phase 2– Contingent on successful delivery of phase 1– Same cost & schedule risks

• US delivery cash limited– Cavities, coupling coils

• Again dependent on as yet unfunded bids (e.g.)– UK: absorbers, cavity– CH: coupling coil

Page 27: MICE Project Status

paul drumm; September ‘05; FAC 27

Summary