michael fadelle, energy development programme for dominica, 5-2012

43
Michael A. Fadelle Coordinator Renewable Energy Programme May 2012

Upload: detlef-loy

Post on 18-Apr-2015

29 views

Category:

Documents


2 download

DESCRIPTION

Presentation at conference SIDS E4ALL in Barbados, May 2012

TRANSCRIPT

Page 1: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Michael A. Fadelle

Coordinator

Renewable Energy Programme

May 2012

Page 4: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Introduction Dominica:

Known as "The Nature Island of the

Caribbean" due to its abundant plant and

animal life, extensive park system, volcanic

peaks, lava craters, the largest boiling lake in

the world, waterfalls, rivers, and lakes.

Blessed with abundant resources and

significant potential for economic and social

development.

Has a population of approximately 71,000.

Size island is about 750 square kilometres.

Dominica faces significant challenges

regarding it’s development.

4 5/8/2012

Page 5: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Introduction continued

Economy is predominantly agriculturally based: - high level of dependence on bananas;

Dominica’s economy has suffered due to market access problems.

Increasing dependence on tourism (nature/eco-tourism) and services (financial; ICT).

Dominica requires reliable and cost-effective types of infrastructure, and especially in energy.

Electricity and transport sectors represent considerable challenges for Dominica.

5 5/8/2012

Page 6: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Introduction continued Dominica has no natural petroleum

resources.

Small size of the market, therefore

high cost of fuel and electricity.

Further, the reliability and efficiency

of the current electricity distribution

system and public transportation is

extremely limited.

Dominica possesses considerable

natural resources to provide for its

energy security with a combination of

renewable energy technologies –

hydro, wind, solar, biomass,

geothermal – and improved energy

efficiency.

6 5/8/2012

Page 7: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Introduction continued

Use of clean renewable energy and energy efficiency technologies will enhance the

tourism sector. Dominica is the Nature Island of the Caribbean!!

These technologies will also benefit agriculture, industry, commerce, government and residents.

Dominica’s Medium Term Economic Strategy states that major investments in electricity generation and distribution are necessary to facilitate the requirements for the further diversification of the economy.

Dominica can demonstrate the viability of sustainable energy systems to other nations.

7 5/8/2012

Page 8: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Electricity Services Currently, diesel generators fuelled by

imported oil (70%) and hydropower plants

(30%) generate Dominica’s electric power.

There are two operating diesel plants (Fond

Cole and Portsmouth) – 16.03 MW

Three hydropower facilities (Laudat,

Trafalgar and Padu) – 6.42 MW

Total: 22.45 MW

Thermal generation has grown modestly.

Recent addition of 3 medium speed

generator for addition 4.2MW at the Fond

Cole power station.

Cost of electricity in Dominica has risen

significantly in recent years and are subject

to world oil prices. 8 5/8/2012

Page 9: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Electricity

Services

continued

Residential customers pay approx. EC$0.70/kWh (US$0.26) for the first 50kWh and EC$0.81/kWh (US$0.30) for additional kWh.

Fuel surcharge is calculated monthly and added as a per cost to the total consumption.

Dominica’s electricity tariffs is among the highest in the Eastern Caribbean - a source of concern and protest among many residents.

Slow economic growth resulted in a very slow growth in peak electricity demand.

9 5/8/2012

Page 10: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Electricity

Services continued

Customer base for electricity services comprises domestic, commercial, hotel, industrial, lighting and street lighting.

Dominica Electricity Services Ltd. (DOMLEC) is the only licenced provider of electricity.

DOMLEC is owned by US firm WRB (51%). The Dominica Social Security owns 20%. Local corporate and private citizens own the remaining 29%.

10 5/8/2012

Page 11: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy Supply through the Years

11

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

Generating Plant kW Installed Capacity - DOMLEC

- Hydro 7,600 7,600 7,600 7,600 7,600 7,600 7,600 7,600 7,600 7,600 7,600 7,600 7,600

- Diesel 10,036 10,036 11,090 11,090 12,840 12,840 12,840 13,590 14,440 15,890 15,890 17,170 17,170

Total 17,636 17,636 18,690 18,690 20,440 20,440 20,440 21,190 22,040 23,490 23,490 24,770 24,770

5/8/2012

Page 12: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy Supply through the Years

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

Production (MWh) Gross Generation

Hydro 36,226 33,841 33,670 32,410 31,590 27,036 35,929 28,523 33,736 27,876 27,797 21,885

20,554

Diesel 23,867 31,942 36,630 42,226 45,925 53,929 44,203 48,404 45,493 55,779 57,619 64,497

66,944

Total 60,093 65,783 70,300 74,636 77,515 80,965 80,132 76,927 79,229 83,655 85,416 86,382

87,498

12 5/8/2012

Page 13: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy Supply through the Years

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

Sales of Electricity by Sector (MWh)

Domestic 24,968 26,721 28,716 30,023 30,872 31,772 32,856 32,942 33,062 33,492 34,176 33,732

34,051

Commercial 11,655 13,435 14,767 15,503 16,052 17,068 22,758 21,669 24,017 24,993 26,469 28,788

30,278

Hotel 1,792 1,757 2,312 3,244 3,154 4,026 2,839 2,473 2,704 2,649 2,439 2,002

6,004

Industrial 2,686 2,326 4,348 4,553 4,420 2,801 4,607 4,354 5,508 5,504 5,357 5,600

2,028

Lighting 6,566 7,054 6,110 6,202 6,409 7,127 9 2 1 1 - 1

-

Street Lighting 914 1,000 1,041 1,069 1,098 1,120 1,125 1,295 1,127 1,150 1,130 1,298

1,325

Total 48,581 52,293 57,294 60,594 62,005 63,914 64,194 62,735 66,419 67,789 69,571 71,421

73,686

% change 7.64 9.56 5.76 2.33 3.08 0.44 - 2.27 5.87 2.06 2.63 2.66

3.17

13 5/8/2012

Page 14: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

14

-

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000 Domestic

Commercial

Hotel

Industrial

Lighting

StreetLighting

Energy Supply through the Years Electricity Sales by Sector and Year: 1996-2008

5/8/2012

Page 15: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy Supply through the Years Electricity Sales by Sector’s Piece of the Pie in 2008

15

Domestic 46%

Commercial 41%

Hotel 8%

Industrial 3%

Lighting 0%

Street Lighting 2%

5/8/2012

Page 16: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy Supply through the Years

Peak Demand (kW)

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

10,130 11,390 12,348 13,010 12,966

13,866 13,043

12,923 13,190 14,368 14,467 14,501

14,663

Growth

(%) - 12.44 8.41 5.36 - 0.34

6.94 - 5.94 - 0.92 2.07 8.93 0.69 0.24

1.12

16 5/8/2012

Page 17: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy Supply through the Years Peak Demand

17

-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

5/8/2012

Page 19: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Energy and Transportation

The transportation sector is a

concern for Dominica in terms of

sustainable energy use:

Unregulated bus routes;

Low-efficiency used car

imports.

High fuel consuming

vehicles;

19 5/8/2012

Page 20: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme The Government of Dominica has embarked

on a programme to explore and develop Dominica’s geothermal resources, primarily to generate clean and lower cost electricity.

Dominica embarked on a European Union funded 1.5 million Euro geothermal resource exploration project, “Preparation of a Geothermal based Cross-Border Electrical Connection in the Caribbean”.

The project is co-funded by the AFD and the FFEM with an additional €4.5million, the EIB for €1.1 million for a submarine interconnection study.

The Government of Dominica contributed in excess of €5 million.

20 5/8/2012

Page 21: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme Project is to determine whether the geothermal

resource in Dominica is technically suitable for

generating electricity.

Can lead to underwater electrical transmission

and interconnection to supply neighbouring

islands of Guadeloupe and Martinique with 40-

50 MW of electricity each.

The project required exploratory drilling to

characterize the resource, particularly pressure,

temperature, and mineral content, and to

determine the feasibility and long term viability

of the investment required.

21 5/8/2012

Page 22: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme

Government established PMU to manage the implementation of the project.

All required staff was in place at September 2010.

PMU responsible to Minister for Public Works, ENERGY and Ports

PMU budget is approximately 450,000 euros for the first three years.

22 5/8/2012

Page 23: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development programme The progress of this EU project depended on

the results of initial surface investigations at the Wotten Waven Geothermal Resource area.

Tests were conducted under a Transnational Partnership Agreement between Dominica, Guadeloupe, and Martinique, and ADEME and BRGM partly funded under the EU’s INTERREG IIIB (Caribbean Space) programme.

This "Géothermie Caraïbe" project was the preliminary phase of the more comprehensive EU funded initiative in Dominica.

Cost was approximately €1.1m.

Activities were conducted by consultants and technical staff of the CFG (French Geothermal Company) of the BRGM.

23 5/8/2012

Page 24: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development programme The INTERREG phase focused on key points

which will ensure the success of the project from a technical, administrative and legal point of view.

This project had four (4) main objectives:-

To validate the information in the OAS studies carried out in 2005;

To make a preliminary analysis of the environmental impact of the proposed project;

To make a preliminary analysis of the legal and institutional framework of the project; and

To revise and update the economic assessment of the project.

Report and results of the investigations under the INTERREG IIIB phase submitted and presented at a conference of the Partners in December 2009.

24 5/8/2012

Page 25: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development programme

The EU/AFD/EIB/GoD funded project is divided into two (2) principal Activities.

Activity I will deal with the final characterization of the Geothermal Power Production potential that will specify the power production areas, undertake an investment prospectus for the proposed development, and undertake test drilling in those specific areas.

Activity II will support the establishment of the PMU and provide TA in respect of policy, environment, regulation, communication and public relations, and monitoring. Will include advice on PPA with existing and potential electricity distributor.

25 5/8/2012

Page 26: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme Project intends to sell at least 40-50 MW of

electricity each to Guadeloupe and Martinique.

Up to 20 MW will be reserved for the Dominican market.

Total investment required for 120 MW plant estimated at US$450M to US$500M.

Plan to start with small geothermal power plant of 5-10MW for local market. – will help to test and evaluate the resource and the reservoir.

Production can begin by the year 2014.

Project can reduce the cost of electricity from US$0.27/KWh to US$0.06-0.10/KWh, before fuel surcharge… (Geothermal Power plant will require practically NO fuel …)

26 5/8/2012

Page 27: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project Drilling contract signed with Iceland Drilling Co. in April

2011 to drill three test or exploratory wells.

Sites were selected based on results of OAS and Interreg IIIB funded studies, and with support from technical advisors.

Government/PMU secured sites.

EIA for test drilling conducted by French firm - Caraibes Environnement – based in Guadeloupe - funded by ADEME.

EIA approved. Results found to be favourable.

Drilling and Well Testing supervisors contracted – Geothermal Resource Group (US firm).

Well testing contractor selected – Iceland GeoSurvey (ISOR) of Iceland.

Drilling works started in December 2011.

The wells were drilled utilizing the Wire-line Coring mining technique. A level area of approximately 3000 square meters was prepared for the drilling rig and related equipment to carry out the drilling and testing activities.

27 5/8/2012

Page 28: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

Well Locations

Well Site 1: Trafalgar/Wotten Waven

Well Site 2: Laudat - Adjacent to the Aerial Tram Rain Forest facility

Well Site 3: Laudat - Close to Domlec’s Balancing Tank

28 5/8/2012

Page 29: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project Contractors

Drilling Contractor: Iceland Drilling Company (IDC)

•Original Contract Sum: (exclusive of VAT (15%): 3,976,702.00 Euros

Well Testing Contractor: Iceland GeoSurvey (ISOR)

•Contract Sum: 461,146 Euros

Drilling Supervisor: Geothermal Resource Group (GRG)

•Contract Sum: 426,394.34 Euros

Site Preparation Contractor: Offshore Civil & Marine Inc.

Lot One XCD$ 715,672.60

Lot Two XCD$ 1,197,935.74

Lot Three XCD$ 986,216.71

Key Timelines

November 20, 2011: Shipment with drilling rig and related equipment arrived in Dominica;

December 4, 2011: Drilling rig taken to site;

December 5, 2011: Official commencement ceremony of the drilling of exploratory geothermal wells;

December 15, 2011: Drilling rig up was completed;

December 16, 2011: Exploratory drilling commenced.

29 5/8/2012

Page 30: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

First Well Drilled – Site 2

o Drilling started on December 16, 2011

o Drilling completed on January 28, 2012

o Final depth of well: 1469 metres

o Depth of 4 ½” slotted liner: 1337m

o Highest temperature logged: 241 degrees Celsius

o Highest Pressure logged: 82 Bars (1190 psi)

o Number of days drilling: 41

o Total Number of work days: 65

o Date of flow test: March 9th and 10th 2012

Results of Flow Test Total flow estimated at 6.4 – 6.6 kg/s with 4.9-5.1l/s

liquid flow and 1.5kg/s of steam

Enthalpy 940-980kJ/kg

Fluctuating gas concentrations between 34 and 63 wt%

Dominant gas is CO2 (93.6 to 96.2 vol%)

30

5/8/2012

Page 31: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

Second Well Drilled – Site 3

Commencement date of WW-3: February 15, 2012

Completion date of WW-3: March 14, 2012

Final depth of well WW-3: 1613 meters

Depth of 4 ½” slotted liner: 1605m

Highest temperature logged: 245 degrees Celsius

Highest Pressure logged: 98 Bars (1421 psi)

Number of days drilling: 29

Total Number of work days: 40

Date of flow test: April 17, 2012

Preliminary results of flow test

Total flow estimated at 22 kg/s

Well thermal output equivalent to 3.5MW

31 5/8/2012

Page 32: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

Third Well Drilled – Site 1 o Commencement date of WW-1: March 28,

2012 o Completion date of WW-1: April 27, 2012 o Total depth: 1200m o Depth of 4 ½” slotted liner: 1200m o Highest temperature logged: 180 degrees

Celsius o Maximum pressure logged: 108 Bars

(1566psi) o Total number of days drilling: 31 o Total number of work days: 42 Preliminary results suggest that Well 1 is very permeable, and it has the potential to be a very good well for geothermal energy. The projected date for opening up and flowing the well is the week of June 10, 2012. By that time the well would have had sufficient time to recover thermally and allow for a good flow test.

Final Results and Reports of the exploratory drilling are expected by

September 2012.

32 5/8/2012

Page 33: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

Government is very satisfied with preliminary results of the test wells

drilled

33 5/8/2012

Page 34: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

Next phase will involve:

Evaluation of test drilling results.

Deciding on the approach for:

o Power Plant development:– small plant for domestic market, and large plant for export market;

o Project ownership/corporate structure;

o Nature and extent of Government’s participation and involvement;

Complete/finalize feasibility for small (10MW) power plant;

Undertake feasibility studies of submarine electrical interconnection between Martinique, Guadeloupe and Dominica;

34 5/8/2012

Page 35: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Geothermal Project

Results of flow tests will allow for

the creation of a model of the

geothermal field (including the

geothermal reservoir), and to

identify the location of the power

plant, production and reinjection

wells, and allow for the sustainable

exploitation of the geothermal

resource.

35 5/8/2012

Page 36: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme

Dominica is also moving speedily to: Do further review the Electricity Supply

Act (ESA) of 2006;- CREDP/GTZ/CSEP (OAS)

Prepare Regulations for the ESA; - CREDP/GTZ

Enact Geothermal Resources Development Bill; - supported by the World Bank Geothermal Resources Development Bill

drafted.

Planning and Environmental Regulations for Renewable Energy drafted.

BOTH documents submitted for review and vetting by the Attorney General’s chambers.

Articulate its National Energy Policy and Road Map (support from the OAS); and

Prepare a Sustainable Energy Plan; - CARICOM, the OAS, and the GTZ.

36 5/8/2012

Page 37: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme Goals of the Sustainable Energy Plan

The Energy Policy and Sustainable Energy Plan:

Lays out a strategy by which the energy production and use in Dominica may be transformed, becoming more economically and environmentally sustainable, while enhancing the electricity generation mix.

Ensure the existence of adequate energy supplies at affordable rates to sustain economic development, while meeting current and projected power demand.

Provide for stable, reliable, and affordable electricity supplies for all customers.

Lower the price of electricity for consumers.

37 5/8/2012

Page 38: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme Goals of the Sustainable Energy Plan continued...

Enhance the security of energy supply and use for all sectors of the economy.

Allow reasonable incomes for businesses engaged in the local energy sector.

Attract international investment where appropriate – tourism; manufacturing; agro-processing...

Promote energy efficiency and conservation at all levels of the economy in order to achieve optimum economic use of renewable and non-renewable sources of energy.

38 5/8/2012

Page 39: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme Goals of the Sustainable Energy Plan continued...

Protect the local and global environment by

maximizing the use of renewable-energy and

energy-efficiency alternatives where viable. This is especially relevant in Dominica as much of the renewable energy generation may take place in nature preserves or rain forest areas. It is essential that this be done in a manner that does not threaten biodiversity, forestation levels, and other environmental aspects.

Promote the generation of income through energy

exports produced from indigenous energy sources

(esp. geothermal resources).

39 5/8/2012

Page 40: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Current Energy Development Programme Other Initiatives

Other planned and proposed initiatives include:

Undertake supplementary electricity generating plant of 15 MW with financial assistance from the Gov’t of Venezuela as a short term energy security measure, and to safeguard against power failure.

Preparing an Electricity System Development Study and Electricity Generation Plan for the country;

Studies to identify sites for NEW hydro power plants around the island;

Geothermal Resource assessment in the north of Dominica;

Undertake Energy Audit of Gov’t facilities and street lights;

Encourage use of solar hot water systems in homes and hotel sector;

40 5/8/2012

Page 42: Michael Fadelle, Energy Development Programme for DOMINICA, 5-2012

Outstanding Matters

1. Approval and implementation of National Energy Policy.

2. Finalize and approve, and implement Sustainable Energy Plan –

important component is the Energy Efficiency programme for

Dominica.

3. Need for a comprehensive strategy and approach to implementing

host of Technical Assistance activities and programmes for both RE

and EE, in the context of sustainable development.

4. Need for TA to review and validate project and renewable energy

resource evaluation reports.

5. Need for TA to undertake electricity system generation study and

generation plan - USTDA considering similar support to DOMLEC.

6. TA to undertake Energy Audit of Government facilities and street

lights.

7. Energy Efficiency audits in tourism/hotel sector including cost

reduction measures including use of solar power – hot water and AC

refrigeration.

8. Capacity development in RE technologies.

42 5/8/2012