Midland Main Line Electrification programme
23
Electrification of the Midland Main Line has resume d under plans announced as part of Sir Peter Hendy’ s work to reset Network Rail’s upgrade programme. Work on electrifying the Midland Main Li ne, the vital long-distance corridor that serves th e UK’s industrial heartland, will continue alongside the line-speed and capacity improvement w orks that were already in hand.
Electrification of the line north of Bedford to Ket tering and Corby is scheduled to be completed by 20 19, and the line north of Kettering to Leicester, Derby/Nottingham and Sheffield by 2023.
Outputs
The Midland Main line Electrification Programme known as the MMLe is split into two key output dates, the first running from 2014-2019 (known as CP5) and the second, 2019-2023 (CP6). There are a number of sub projects running under the main MMLe programme which are delivering various improvements in the Leicestershire area. Each sub project has dependencies with each other to enable the full ES001- Midland Main Line electrification programme to be achieved
A number of interfaces and assumptions link to thes e programmes and their sub projects will affect Lei cestershire.
ES001A- Leicester Capacity
The proposed 4 tracking between Syston and Wigston is located under sub project ES001A- Leicester Capacity which can be found on page 27 of Network Rails enhancements delivery plan . The project seeks to deliver a number of capacity enhancements along the Midland Main Line corridor including grade separation (a potential fly under) at MML Wigston junction, new 4 track provision between Wigston and Leicester to enable the separation of the up and down fast and slow lines. This in turn will allow for a new slow line platform to be installed at Leicester Station and new up and slow lines between Humberstone Road and Syston Junction. These works will also look at improved capacity in the Syston area, details of which are yet to be detailed and confirmed. These works are linked with the
EM001- long distance high speed services train leng thening project ; the removal of trackside vegetation removal will be carried out / signalling changes / new footbridges and platform extensions will be undertaken along the length of the route with phase 1 being from Bedford to Market Harborough from 2019 and phase 2 -Loughborough to Sheffield from 2023. These works are linked with
PJIF funded ES003K- Market Harborough- line speed i mprovements ; this sub project seeks to deliver realignment of the track through Market Harborough, station alterations and associated infrastructure changes to improve line speeds and passenger journeys. Critical Interdependencies include the Little Bowden level crossing closure with diversion of the existing right of way over a new footbridge.
Each project will be considered “under development” up to the single option stage known as Grip 3. Until this stage is reached, uncertainty over scope and timescales for delivery is likely, all sub projects being determined both in delivery and budget by the completion of any dependant sub projects, although not mutually inclusive.
The Hendy Enhancements delivery plan update can be viewed by following the link h&ps://www.networkrail.co.uk/Hendy-review
POST HENDY REVIEW—UPDATE
The Hendy Enhancements delivery plan update (Jan 20 16)
24
RED = Proposed line of new track
Green Dashed– exis�ng track Lines to be removed
Pink = Proposed car park
Green—Network Rail land ownership
Rockingham road
Road bridge
Gt Bowden Road
To st Marys Road / Town Centre
To A6 Harborough bypass
Li"le Bowden
To Great Bowden
NORTH
Riverside
Riverside industrial
estate
Poten$al access
loca$on (A)
Poten$al access
loca$on (B)
Poten$al access
loca$on (C)
Gores Lane
Ke
"e
rin
g R
oa
d
MARKET HARBOROUGH LINE SPEED IMPROVEMENTS
HARBOROUGH STATION
Exis$ng sta$on
access
HARBOROUGH
TRAIN STATION
This plan is not to scale and is for iden�fica�on purposes only
A
A
Improved sta$on facili$es and enhanced car park with improved access
Removal of engineering sidings
Longer pla0orms
Staged construc$on
25
Great Bowden Village
— Proposed Bridge and rail track works
Sta�on ID: SPC53/28F Sta�on road overbridge
Proposal : reconstruct
Bridge ID: SPC3/28D Main Street overbridge
Proposal : reconstruct
Bridge ID: SPC3/28E Footbridge /
PROW A49 Proposal : reconstruct
Exis�ng rail line to be removed
New track line
New track line
Exis�ng rail line
to be removed
Li"le Bowden rd
Sta$on Road
Ber
ry c
lose
The Green
Langton Road
Main Street
To B6047
Great Bowden
NORTH
PROPOSALS
Works to: Station road bridge, Footbridge & Main Street bridge
Line side vegetation clearance.
New track alignment through Pony Paddock (terminating ex-isting lease as NR land)
Likely to have minor change to Public Rights of Way (permanent diversion order to be submitted)
SUBJECT TO ALTERATION
This plan is not to scale and is for iden�fica�on purposes only
26
Great Bowden Village
— Proposed Bridge and rail track works on Network R ail owned paddock land off Langton Road
Main Street
Dismantled railway line
Langton Road
Proposed new track line
Proposal : Not known at this �me
Paddocks land requiring planning
permission
Bridge ID: SPC3/28C foot / road bridge UB-
Langton Road with right of way
Bridge ID: SPC3/28B Skew Bridge
Bridge ID: SPC3/28A underbridge
Proposal : Not known at this �me NORTH
This plan is not to scale and is for iden�fica�on purposes only
Change of use to operational railway (Pony Paddocks)
27
Great Bowden Village
— Proposed Bridge and rail track works on Network R ail owned paddock land off Langton Road 2
A6 Harborough
Bypass to
Kibworth
Dismantled railway line
Langton Road
Proposed new track line Change of use to opera$onal
railway
Bridge ID: SPC3/28A - CHATERS CATTLE
BRIDGE with PROW BOAT A47
PROPOSAL: reconstruct
Proposal : Not known at this �me
NORTH
This plan is not to scale and is for iden�fica�on purposes only
Langton Road
Bridge ID: SPC3/28 A6 Harborough Bypass
PROPOSAL: Raise parapets only
A6 Harborough Bypass to
Market Harborough
To Great
Bowden
To Thorpe
Langton
Exis$ng track line 28
Overview plan
Harborough Council:
Environmental screening to inform decision on Environmental Impact Assessment
Car Park planning application
Prior approval of new station & footbridge
Change of use to operational railway (Pony Paddock)
Part 8 notification for permitted development
Listed building consent
Leicestershire County Council
Diversion order for Public Rights of Way (temp & permanent)
Highway authority:
Highway approval for new station access route
Change to bridges
29
Name of structure
Structure Class
ELR IDPost code
Highways Authority
Planning Authority
Description of Structure
Liability / Property Issues
Consents Proposal
Under Hill Bridge
Footbridge SPC5
49 LE127LP Leicestershire County Council
Charnwood Borough Council
Lattice two span skewed footbridge
NR owned & maintained for public footpath rights.
N/A Reconstruction to 5100mm
Humble Lane Bridge
Overbridge SPC5
44 LE74US Leicestershire County Council
Charnwood Borough Council
Approach arches and two span steel flat deck
NR owned & maintained for public highway rights.
N/A Reconstruction to 5175mm
Syston Road Overbridge SPC5
43 LE74UZ Leicestershire County Council
Charnwood Borough Council
Two span wrought Iron deck
NR owned & maintained for public highway rights.
N/A Reconstruction to 5175mm
Meadow Lane
OverbridgeSPC
578 LE111LE Leicestershire
County Council
Charnwood Borough Council
Two brick arch & New concrete deck
NR owned & maintained for public highway rights.
N/A
Jack existing flat deck and reconstruct central Arch with a flat deck to match jacked structure, side arch to remain.
Barkby Thorpe Lane
Overbridge SPC5
29 LE48GT Leicestershire County Council
Charnwood Borough Council
Two span concrete flat deck
NR owned & maintained for public highway rights.
N/A Reconstruction to 5175mm
Barkby Lane Overbridge SPC5
30 LE72BA Leicestershire County Council
Charnwood Borough Council
Two span concrete flat deck
NR owned & maintained for public highway rights.
N/A Reconstruction to 5175mm
Nottingham Road A60
Overbridge SPC5
75LE111H
WLeicestershire County Council
Charnwood Borough Council
Brick arch & New concrete deck
NR owned & maintained for public highway rights.
N/AJack existing flat deck and reconstruct arch with a flat deck to match jacked structure.
Chaters OverbridgeSPC
328
LE167HS
Leicestershire County Council
Harborough District Council
Three span brick arch
NR owned & maintained for a Byway Open to All Traffic BOAT
N/A Reconstruction to 5100mm
Grammar School Bridge
Overbridge SPC3
18 LE89JB Leicestershire County Council
Harborough District Council
Three span brick arch
NR owned & maintained for public footpath rights.
Conservation Area
Reconstruction with flat deck to 5175mm
Taylors Lodge
Overbridge SPC3
3LE182Q
TLeicestershire County Council
Oadby and Wigston Borough Council
Single span deckNR owned & maintained for private vehicular rights.
N/A Jack existing structure to 5175mm
Update on Bridge enhancements (phase 1)
The following bridges were previously identified and committed in the Midland Mainline Electrification programme as
requiring enhancement works. Following the unpausing of the electrification and Hendy review in September 2015, Network rail is currently in the progress of replanning the programme and as yet has not yet been able to provide LCC with a new programme timetable for the delivery of these phase 1 works. Other bridges in Leicestershire were also identified as requiring works but as they remain uncommitted .
30
Location of bridges and junctions affected by the Midland Main Line Electrification programme
North of Leicester
WIGSTON
FLY UNDER
KEY
Blue Circle— Bridges iden�fied in the MMLe
programme as requiring works
Dashed orange
circles Syston Junc�ons and sta�on
Wigston Junc�on and Wigston
Fly under loca�on
Dashed orange Length of track involved in the
Leicestershire capacity project
Bridge iden�fica�on
Blue wording Commi&ed works phase 1
Black wording uncommi&ed works
not iden�fied
(Iden�fied in Leicester Capacity)
(Iden�fied in Leicester Capacity ES001A)
(Iden�fied in
Leicester Capacity)
31
Location of bridges and junctions affected by the Midland Main Line Electrification programme
North of Leicester
KEY
Blue Circle— Bridges iden�fied in the MMLe
Phase 1 programme as requiring works
Dashed orange CroD sidings
circles
orange oval Market Harborough line speed
improvements project
Yellow line Track works outside of county
south of Leicestershire to be
completed in key output 1
2014-2019
Bridge iden�fica�on
Blue wording Commi&ed works phase 1
Black wording uncommi&ed works
CROFT SIDINGS
not iden�fied
Iden�fied in
Leicester Capacity
Iden�fied in
MHLSI (ES001A)
32