milestones of the estlink2 cable project
DESCRIPTION
Milestones of the Estlink2 cable project. Timo Partanen Energy Market Authority [email protected]. Estlink2, recent development. Investment decision May 20th, 2010 Fingrid / Elering share 50/50 Capacity 650 MW Total investment cost 320 million € Commissioning early 2014 - PowerPoint PPT PresentationTRANSCRIPT
![Page 2: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/2.jpg)
Estlink2, recent development
• Investment decision May 20th, 2010• Fingrid / Elering share 50/50• Capacity 650 MW• Total investment cost 320 million €• Commissioning early 2014• Preconditions:
– 100 million € investment subsidy from EU– Positive development on the Estonian power market
![Page 3: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/3.jpg)
Recent development in the Estonian power market
• Nord Pool Spot opened new Estlink –price area early April.
• Fingrid and Elering rented 250MW capacity from the owners of present Estlink-cable for NPS.
• Total present capacity of Estlink is 350 MW.• Elspot-procurement in Estonia exceeds 20 %.• Almost all of the available Elspot / Estlink- capacity
has been used. • Finnish and Estonian prices have differed 80% of
hours, so new capacity is desperately needed.
![Page 4: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/4.jpg)
Estlink and Estlink2
![Page 5: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/5.jpg)
Estlink2 interconnection cross section
![Page 6: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/6.jpg)
Estlink2 Project schedule
![Page 7: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/7.jpg)
Estlink2 Key project milestones
• Seabed survey report done in December 2009• Starting of PQ procedures for the cable and
converter suppliers in December 2009• Environmental studies and permit applications done
in February 2010• Final investment decision in May 2010• Inquiry documents ready for the cable and
converter in May 2010• Signing of the cable and converter contracts in
December 2010
![Page 8: Milestones of the Estlink2 cable project](https://reader036.vdocument.in/reader036/viewer/2022062423/56814e2f550346895dbb93d8/html5/thumbnails/8.jpg)
Thank you for your attention!