Miller Heights Outfall Rehabilitation Project 2014

TRANSCRIPT

Page 1: Miller Heights Outfall Rehabilitation Project 2014

A Fairfax County, VA, publication

Department of Public Works and Environmental Services

Working for You!

Miller Heights Outfall Rehabilitation ProjectContract No. CN14125112Project No. SD-000031-068Task Order No. 10Providence District

August 25, 2014

Page 2: Miller Heights Outfall Rehabilitation Project 2014

Miller Heights Outfall Rehabilitation Project

Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch

Page 3: Miller Heights Outfall Rehabilitation Project 2014

Project DetailsMiller Heights Outfall Rehabilitation Project

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Description:

The Miller Heights Outfall Rehabilitation project was substantially completed on August 7, 2014, on time and within the budget. The project consists of stabilization of over 250 feet of eroded channel located near the intersection of Miller Road and Miller Heights Road. The goals of the outfall project were to address public safety concerns, stabilize a deeply eroded channel by using natural stream channel design, and provide enhanced water quality.

Project Overview:• Constructed a plunge pool below the existing culvert.• Utilizing a natural stream channel design method, six (6) single step rock cross vanes and four (4)

rock weirs were installed to allow a gradual change in the channel elevation and provided additional water quality benefits.

• Restored the site with seed mix, trees will be planted at the end of Sept. 2014. • Water quality benefits obtained include 34 (lbs./yr.) total phosphorus, 124 (lbs./yr.) total nitrogen,

and 64,820 (lbs./yr.) total suspended solids.

Project Team:• Stormwater and Planning Division – Fred Wilkins• Utilities Design and Construction Division - Yousef Rayyan• Utilities Design and Construction Division - Bharat Khanal

Page 4: Miller Heights Outfall Rehabilitation Project 2014

Miller Heights Outfall Rehabilitation Project

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Providence District, VA, Tax Map #47-1

Project Site Location

Page 5: Miller Heights Outfall Rehabilitation Project 2014

Miller Heights Outfall Rehabilitation Project

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Pre-Existing Conditions

Severely Eroded Channel Banks

Page 6: Miller Heights Outfall Rehabilitation Project 2014

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Miller Height Outfall Rehabilitation Project

Post Construction

Cross Vane and Step Weir Rock StructuresChannel Banks were Stabilized by Coir Matting and Seed Mix

Page 7: Miller Heights Outfall Rehabilitation Project 2014

Miller Heights Outfall Rehabilitation Project

Pre-Existing Conditions of the Plunge Pool Location

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Page 8: Miller Heights Outfall Rehabilitation Project 2014

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Miller Heights Outfall Rehabilitation Project Post Construction-Plunge Pool and Step Weir

Plunge Pool Armored Channel with Reinforced Bed Mix

Page 9: Miller Heights Outfall Rehabilitation Project 2014

Miller Height Outfall Rehabilitation Project Post-Construction

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Page 10: Miller Heights Outfall Rehabilitation Project 2014

Before After

Miller Heights Outfall Rehabilitation Project

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Page 11: Miller Heights Outfall Rehabilitation Project 2014

Additional Information

For additional Information, please call

www.fairfaxcounty.gov/dpwes

Ben Boxer, Public Information Officer703-324-5880, TTY 711

Ben. Ben Boxer, Public Information Officer703-324-5880, TTY 711

Ben. Ben Boxer, Public Information Officer703-324-5880, TTY 711

[email protected]

Irene Haske, Public Information Officer703-324-5500, TTY [email protected]

Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch