Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural
Electrification
Implemented by UNIDO
![Page 2: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/2.jpg)
Project objective
To promote renewable energy (biomass) based on mini-grid as an alternative to diesel based energy generation systems in Nigeria
![Page 3: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/3.jpg)
Project outcomes
• Preparatory works completed for facilitating replication in the identified potential sites
• Acceptance by stakeholders on the technical and financial viability of selected site for setting up the biomass based mini-grid for rural electrification
• Conducive financing and policy environment for promoting investments in rural mini-grids in place
• Capacity of local planners, institutions and experts for RE based mini-grid enhanced
![Page 4: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/4.jpg)
Outcome 1: Preparatory works completed forfacilitating replication
in the identified potential sites
• Project inception workshop organized• Project Steering Committee (PSC) inaugurated• Project Management Unit (PMU) established• National Project Manager recruited• Detailed Engineering studies, TOR for EPC
contract prepared
![Page 5: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/5.jpg)
Outcome 2: Acceptance by stakeholders on the technical and financial
viability of selected site for setting up the biomass based mini-grid for rural electrification
• Full-scale feasibility study with business plan conducted • Investment forum organized• Project stakeholders/financiers identified and organized with established Board• Project stakeholders agreement developed and endorsed by project owners• Project stakeholders exposed to biomass technology through trainings and study
tours• Project bid documents prepared and launched• Bidders have been selected and evaluated• Preferred bidder selected for the Engineering, Procurement and Construction (EPC)• EPC Contract signed• Project equity finance determined and agreed by project owners• Project debt finance being processed under the Power and Aviation Intervention
Fund (PAIF)
![Page 6: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/6.jpg)
Outcome 3: Conducive financing and policy environment for promoting investments in rural mini-
grids in place
• Consultation and arrangements ongoing with Energy Commission of Nigeria (ECN) and the National Electricity Regulatory Commission (NERC) for the review of policies and documents
![Page 7: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/7.jpg)
Outcome 4: Capacity of local planners, institutions
and experts for RE based mini-grid enhanced
• Training of staff of project owners on Renewable Energy Technologies (RETs) conducted
• Capacity building for key project stakeholders planned and awaiting approval by Federal Ministry of Finance for implementation
![Page 8: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/8.jpg)
Project budget
• GEF: 2,681,800USD• Co-financing: 11,935,00USD
![Page 9: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/9.jpg)
Enabling Activities to Review and Update the National Implementation Plan for the Stockholm Convention on Persistent
Organic Pollutants (POPs)
Implemented by UNIDO
![Page 10: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/10.jpg)
Project objectives
• Update and review the National Implementation Plan (NIP), have it endorsed and submitted to the Stockholm Convention Conference of Parties (COP); and
• Enable participating stakeholders to manage the additional POPs with newly developed technical skills, expertise and awareness
![Page 11: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/11.jpg)
Project components
• Coordination mechanism and awareness raising
• Inventories of new POPs and NIP review• National capacities assessment and priority
setting for management of new POPs• NIP formulation, endorsement and submission• Monitoring and evaluation
![Page 12: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/12.jpg)
Project partners and budget• Federal Ministry of Environment• Federal Ministry of Finance (FMF) • Federal Ministry of Health (FMoH) • Federal Ministry of Agriculture and Rural Development (FMA&RD) • Nigeria Customs Service (NCS) • National Planning Commission (NPC) • PHCN now Transmission Company of Nigeria (TCN) • Basel Convention Regional Coordinating Centre (BCRCC) • The Academia
• Project budget: $225,016
![Page 13: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/13.jpg)
Project progress
• Steering committee to be inaugurated in April 2014
• NIP inventory training to take place in May 2014
![Page 14: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/14.jpg)
Scaling up Small Hydro Power (SHP) in Nigeria
Implemented by UNIDO
![Page 15: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/15.jpg)
The project
• Project objectivePromote investment in Renewable Energy Technologies
(RETs)
• Expected focal area outcome: Investments in RETs increased
• Expected focal area output: 5.9MW RE capacity Installed
• Project Implementation Cost: 23,267,917.72USD
![Page 16: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/16.jpg)
Project components
• Human and institutional capacity building• Upgrading the capacity for local fabrication of
SHP turbines and control systems in Nigeria• Promoting investment in SHP sector• M&E and knowledge management
![Page 17: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/17.jpg)
Lessons of experience
Completed sites• WAYA Dam, Bauchi State
Capacity: 2x75kW
• Ezioha – Mgbowo, Enugu State
Capacity: 35 kW
• Kakara Tea Factory, Taraba State
Capacity: 2x200kW
• Local fabrication of SHP turbines and control systems
![Page 18: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/18.jpg)
Lessons of experience (cont’d)
Ongoing sites
• Amoke, Benue State
Capacity: 3x40 kW
• Ikeji-Ile, Osun StateCapacity: 2x35kW
• OOPL Complex, Ogun State
Capacity: 15 kW and 2 kW
![Page 19: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/19.jpg)
Progress made
• CEO endorsement document ready• Working on the co-financing letters from
partners
![Page 20: Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO](https://reader036.vdocument.in/reader036/viewer/2022082816/56649d145503460f949e8977/html5/thumbnails/20.jpg)
Project partners
• Federal Ministry of Environment• Federal Ministry of Power• Federal Ministry of Water Resources• Energy Commission of Nigeria• Bank of Industry• State Governments• Private Investor