minimizing interference between top tension risers for tension … · 2020. 5. 21. · dril-quip,...
TRANSCRIPT
MINIMIZING INTERFERENCE BETWEEN TOP TENSION RISERS FOR TENSION LEG PLATFORMS
Ryan Koska 2H Offshore Engineering Pty. Ltd.
Perth, WA, Australia
Jim Kaculi Dril-Quip, Inc.
Houston, TX, USA
Mike Campbell 2H Offshore Inc.
Houston, TX, USA
Darren Mills Dril-Quip, Inc.
Houston, TX, USA
ABSTRACT Interference between TTRs is a key design challenge. For
spars, this is typically mitigated by having a large spacing
between wellheads, thus increasing the distance between risers
along the water depth. However, due to lower TTR tensioner
stroke limits combined with larger vessel offsets, the feasibility
of spacing out the wellheads for TTRs on a TLP is limited. The
result is TTRs that are closer together through depth and
therefore more likely to contact each other in extreme current
conditions.
This paper presents the approach used to minimize the
interference between the top tension risers on TLPs. Specific
topics include considering current profiles with varying
directions through the water depth, adjusting the top tension of
the risers, and utilizing low-drag vortex-induced vibration
(VIV) suppression strakes. The relative effect of each of these
topics is also discussed.
INTRODUCTION Top tension risers on TLPs are typically within close
proximity to each other, as shown by the example wellbay and
nominal seafloor layout in Figure 1. Typical center-to-center
spacing between adjacent wellbays is 5-6m and the minimum
nominal spacing between adjacent wellheads is usually less than
10m. The proximity of risers, combined with stroke and vessel
payload limitations makes mitigating potential interference
between risers challenging.
In recent years, there has been a trend to include drilling
capabilities to production vessels. This allows the operator to
bring production online with a few pre-drilled wells and then
drill and complete the rest of the field using the production
vessel. The revenue from the initial production help the
operator start to recover the up-front capital costs more quickly
and eliminating the need for a separate drilling vessel reduces
the overall cost to develop the field. However, this can further
complicate riser interference by adding a drilling riser with a
different diameter and top tension factor from the production
risers.
In addition, at the detailed design phase of projects, the hull
design, resulting payload limitations and deck heights and
stroke limits are often fixed. This limits the ability to optimize
the riser configurations to improve riser to riser interference.
Figure 1 – Example Wellbay and Seafloor Layout
Proceedings of the ASME 2013 32nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013
June 9-14, 2013, Nantes, France
OMAE2013-11182
1 Copyright © 2013 by ASMELearn more at www.2hoffshore.com
TOP TENSIONED RISER DESCRIPTION Typical configurations of the production and drilling risers
are shown in Figure 2. The production risers on TLP are usually
dry tree systems and the drilling riser are high pressure systems
with a surface BOP.
Production risers on TLPs typically have a steel outer
diameter of 12-16 inches (304.8–406.4mm) with 1-3 inches
(25.4-76.2mm) of external insulation. For this paper, an outer
diameter of 14 inches (355.6mm) with 2 inch (50.8mm) thick
external insulation is considered. VIV suppression strakes are
typically present on the majority of the riser length. The most
common strake drag coefficient is 1.6, leading to increased riser
deflections under current loading and therefore, increased
likelihood of clashing between risers.
Drilling risers on production vessels can have the same
pipe size as the production riser or can be full size risers with
outer diameters of about 21 inches (508mm). Buoyancy
modules can be used in order to reduce the tension requirements
for the riser. For this paper, a full size 20 inch diameter riser is
considered with buoyancy modules present on about half of the
riser’s length. The buoyancy modules have an outer diameter of
46 inches (1.17m). Most of the remaining riser length has VIV
suppression strakes, as shown in Figure 2. The large diameter of
the buoyancy modules, combined with the presence of strakes
on the rest of the riser can lead to high drag loading on the riser,
thus increasing the probability of interference between it and
adjacent production risers.
Figure 2 – Example TLP Production and Drilling Riser
Configurations
CURRENT LOADING Currents in the regions in which TLP are either already
present or are currently being design can be quite onerous, with
the 100 year surface current speeds ranging from 2.1 to 2.7
knots (1.1 to 1.4 m/s). Example 100 year current profiles are
shown in Figure 3.
0
100
200
300
400
500
600
700
800
900
1,000
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6
Ele
va
tio
n a
bo
ve
Mu
dli
ne
(m
)
Current Speed (m/s)
100 YEAR EXTREME CURRENT PROFILES1000m Water Depth, Locations with TLPs
Gulf of Mexico Australia (North West Shelf) Brazil
Figure 3 – Example 100 Year Extreme Current Profiles
INTERFERENCE ANALYSIS APPROACH
Interference analysis is conducted using the non-linear,
time-domain analysis software FLEXCOM, [1]. Wake effects
are implemented in FLEXCOM using the wake theory
developed by Huse, [2], in accordance with API RP 2RD, [3].
The wake from the upstream riser reduces the current velocity
acting on the downstream riser, as shown in Figure 4. The
reduced velocity decreases the deflection of the downstream
riser, therefore increasing the likelihood of interference between
the risers.
Both risers are susceptible to VIV excitation due to the fact
that neither is fully straked. VIV fatigue analysis is conducted
for both risers in order to determine the drag amplification due
to VIV. In order to remain conservative, the VIV drag
amplification is applied to the upstream riser, but not to the
downstream riser.
Static analysis with the vessel offset and current loading is
used to evaluate each of the selected riser pairs and
environmental loading directions. The minimum riser clearance
is extracted for each load case in order to determine if clashing
between risers occurs. Contact between risers is typically not
2 Copyright © 2013 by ASMELearn more at www.2hoffshore.com
allowed for operating and extreme environments. Depending on
operator requirements, contact between risers can be allowed
during survival conditions. As per API RP 2RD, contact can
only be allowed provided that subsequent analysis shows that
the contact does not threaten the integrity of either riser, [3].
Figure 4 – Wake Profile Behind and Cylinder in Stationary
Flow, [2]
RISER INTERFERENCE CHALLENGES
A number of factors contribute to the potential for clashing
between adjacent risers. These include items such as the
presence of VIV suppression strakes, riser splay limitations and
vessel payload capacity.
Riser Splay Limitations An effective method of mitigating interference between top
tension risers is to increase the spacing of the wellheads. This
increases the distance between adjacent risers through the water
column and reduces the likelihood of clashing. However, there
are several consequences of increasing wellhead spacing that
must be considered.
By increasing the wellhead spacing, the riser splay, which
is the lateral distance between the wellhead and wellbay, must
also increase. This results in higher bending moments in the
tieback connector at the base of the riser for vessel offsets
opposite to the riser direction of splay (i.e. - a far offset). The
riser splay, and therefore the wellhead spacing, must be small
enough so that the tieback connector bending moment capacity
is kept within acceptable limits during extreme storm events.
Another consequence of increasing the riser splay is that
the riser stroke also increases. An example of this is shown in
Figure 5. For a 120m TLP offset away from the direction of
riser splay with associated set-down, the riser stroke due to
vessel offset alone increases from 31 inches (0.79m) to 52
inches (1.32m) with an increase in splay from 6.5m to 13.5m.
The total riser stroke range is increased due to environmental
loading, dynamic vessel response, tidal variations, thermal and
pressure loading from internal fluids, and changes in weight due
to variation in contents. These factors can add several feet to the
overall stroke range of the riser. TLP tensioners typically have a
stroke capacity of less than 10 feet (3m), making stroke a key
design parameter. The riser splay, and therefore the wellhead
spacing, must be small enough so that the tensioner stroke range
is not exceeded.
0
10
20
30
40
50
60
0 2 4 6 8 10 12 14
Ris
er
Str
ok
e (
in)
Riser Splay (m)
PRODUCTION TTR STROKE VS SPLAYNo Environmental Loading; 120m TLP Offset; 6.0m TLP Setdown
Figure 5 – Riser Stroke vs. Splay
Vessel Payload Limitations The riser deflections due to current loading, and therefore
the likelihood of interference between risers, can be reduced by
increasing the riser top tension, as shown in Figure 6. However,
due to the potential for a large number of risers combined with
the limited payload capacity of TLPs, there is typically little
margin for increasing the tension in the risers. This is
particularly the case during the detailed design phase of work,
when the vessel payload capacity is essentially fixed.
0
100
200
300
400
500
600
700
800
900
1,000
1,100
1,200
1,300
-2 0 2 4 6 8 10 12 14
Ele
va
tio
n a
bo
ve
Mu
dli
ne
(m
)
Lateral Riser Deflection (m)
EFFECT OF TOP TENSION ON RISER DEFLECTION100 Year Current, No Vessel Offset or Wave Loading
TTF = 1.7 TTF=2.0 TTF=2.4 Figure 6 – Riser Deflection for Range of Top Tension
Factors
3 Copyright © 2013 by ASMELearn more at www.2hoffshore.com
INTERFERENCE MITIGATION METHODS FOR TLPS Several mitigation methods can be utilized TLP TTRs in
order to overcome the challenges presented above and achieve
acceptable riser clearance. These methods include considering
the change in current direction through depth, the use of low
drag VIV suppression strakes, and optimizing the tension of the
risers.
Consideration of Current Direction through Depth In order to be conservative, interference analysis is often
conducted considering unidirectional current profiles. This
maximizes the wake effects on the downstream riser, therefore
increasing the likelihood of interference between the risers.
However, current profiles typically have variations in
direction through depth. Considering directionality of the
current profiles through depth can reduce any unnecessary
conservatism of the interference analysis. The portion of the
current profile out of the plane of the two risers reduces the
length of the downstream riser that is in the wake field of the
upstream riser, therefore reducing the probability of
interference. An example of riser clashing that is mitigated by
considering multidirectional currents is shown in Figure 7 and
Figure 8.
This approach to reduce conservatism can be utilized
provided that sufficient current measurements have been taken
in order to determine the predominant current directions
through depth. An example of this would be a location that has
a predominant surface current direction due to ocean circulation
and a different principal bottom current direction due to
bathymetric characteristics, such as an escarpment. Variations in
the current direction, both at the surface and through depth
should be accounted for in order to ensure that the most onerous
case is captured.
Figure 7 – Example of Riser Clashing with Unidirectional
Current Profile
Figure 8 – Example of Riser Clearance Achieved using
Multidirectional Current Profile
4 Copyright © 2013 by ASMELearn more at www.2hoffshore.com
Utilizing Low Drag VIV Suppression Strakes The most common drag coefficient for the VIV suppression
strakes used on the production and drilling risers is 1.6.
However, vendor published test data is available showing that
strakes can be manufactured that have a drag coefficient of
about 1.4 while maintaining VIV suppression efficiency of
greater than 90%. The selection of low-drag strakes for use on
the production riser supported by available test data allows for
the use of a reduced drag coefficient in the interference
analysis.
The effect of strake drag coefficient on production riser
deflections with 100 year current loading with no vessel offset
is shown in Figure 9. Deflections for the riser without strakes
are also shown for comparison. Utilizing low drag strakes
reduces the maximum deflection of the riser from 14m to
12.5m. Low drag strakes can be specified in addition to the
consideration of multi-directional current profiles to greatly
improve clearance between adjacent risers of the same type and
top tension.
The use of low drag strakes can have a negative effect on
first and second order fatigue due to the reduced hydrodynamic
damping acting on the riser. Higher levels of vessel motions are
allowed to propagate along the riser’s length, resulting in more
fatigue loading. Analysis should be conducted to confirm that
the riser has adequate fatigue performance with low drag
strakes.
0
100
200
300
400
500
600
700
800
900
1,000
1,100
1,200
1,300
-2 0 2 4 6 8 10 12 14 16
Ele
va
tio
n a
bo
ve
Mu
dli
ne
(m
)
Lateral Riser Deflection (m)
EFFECT OF STRAKE DRAG COEFFICIENT ON RISER DEFLECTION
100 Year Current, No Vessel Offset or Wave Loading
No Strakes Strake Cd = 1.4 Strake Cd = 1.6
Figure 9 – Riser Deflections for Range of Commercially
Available Strake Drag Coefficients
Optimizing Drilling Riser Top Tension Unlike the production riser, the majority of the drilling riser
is unstraked. This causes lower deflections for the drilling riser
for the same current loading and leads to interference when the
production riser is upstream of the drilling riser. Therefore,
larger drilling riser deflections are required in order to mitigate
interference with the production risers. It is generally
undesirable to add strakes to the buoyant joints on the drilling
riser as this increases the complexity and time required for riser
installation and retrieval.
In order to increase the deflection of the drilling riser and
mitigate interference with the production risers, the top tension
factor, defined as the top tension applied divided by the weight
of the riser, is reduced from 1.75 to about 1.5. This reduction in
top tension effectively mitigates the interference when the
production riser is upstream, while keeping the drilling riser
deflection low enough so that clearance is maintained when the
production riser is downstream. An example of the interference
between production and drilling risers being mitigated by
reducing the drilling riser tension is shown in Figure 10.
Reducing the riser top tension typically results in a
reduction in fatigue lives, particularly due to VIV. Analysis
should be conducted to confirm adequate fatigue performance
with the reduced tension.
Figure 10 – Example of Interference between Production
and Drilling Riser Mitigated by Reducing Drilling Riser
Top Tension
Drilling Riser TTF = 1.75
Drilling Riser TTF = 1.5
5 Copyright © 2013 by ASMELearn more at www.2hoffshore.com
CONCLUSIONS Due to the close spacing between risers as well as limited
vessel payload and riser stroke capacities, interference between
risers is a key design challenge for top tension risers on tension
leg platforms. Addressing riser interference to a detailed level
as early as possible, preferably during FEED, is recommended
as changes to riser tension or stroke limits can be made during
this phase.
Three mitigation techniques can be utilized in order to
minimize the potential for clashing between the production and
drilling risers on TLPs. These mitigation methods include
considering multi-directional currents through depth, utilizing
low drag strakes on the production risers and optimizing the top
tension of the drilling riser. Using one or more of these methods
in combination can successfully mitigate interference between
top tension risers on a TLP.
NOMENCLATURE TLP Tension Leg Platform
TTF Top Tension Factor
TTR Top Tension Riser
VIV Vortex Induced Vibration
REFERENCES
[1] Marine Computational Services (MCS) –
“FLEXCOM-3D Three-Dimensional Nonlinear Time
Domain Offshore Analysis Software.” Version 7.9.4,
2009
[2] Huse, E., “Experimental Investigation of Deep Sea
Riser Interaction,” Paper No. 8070, Offshore
Technology Conference, Houston, May 1996.
[3] American Petroleum Institute (API), “Design of
Risers for Floating Production Systems (FPSs) and
Tension-Leg Platforms (TLPs)”, API Recommended
Practice 2 RD, First Edition, June 1998, Reaffirmed
May 2006.
6 Copyright © 2013 by ASMELearn more at www.2hoffshore.com