minimizing quarrying costs by correct shotrock fragmentation and

42
Minimizing Quarrying Costs by Correct Shotrock Fragmentation and In-pit Crushing Oct. 2006, Rev A Jarmo Eloranta

Upload: salimaliomar2000

Post on 23-Oct-2015

41 views

Category:

Documents


0 download

DESCRIPTION

quarry

TRANSCRIPT

Page 1: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

Minimizing Quarrying Costs by Correct Shotrock Fragmentation and In-pit Crushing

Oct. 2006, Rev A

Jarmo Eloranta

Page 2: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Contents

• Quarry process in general

• Comparison of different shotrock fragmentations

• Comparison of different crushing methods

• Conclusions

• Enclosures

2

Page 3: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Challenge in Quarry Development

Distance

$/to

nWhat about the

hauling distance?

‘real’ optimum

Source: Technical University Trondheim, Norway

3

Page 4: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Quarry ProcessStationary Crushers

4

Page 5: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Quarry ProcessMobile Crusher(s)

Mobile primary crushing

All crushers mobile

5

Page 6: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Crushing & ScreeningDrilling

Blasting

Loading

Hauling

6

Example of Quarry Cost distribution

Page 7: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Approach Based on Two Phases

• Comparison of different shotrock

fragmentations, including:

- drilling and blasting

- boulder handling

- loading

- hauling

- crushing (traditional stationary)

• Comparison of different crushing

methods, including:

- stationary

- inpit, semimobile

- inpit, fully mobile

Optimum

drilling and

blasting

Optimum

crushing

Cost

Effective

Quarry

Practise

7

Page 8: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

Comparison of Different Shotrock Fragmentations

Page 9: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

MAIN DATA Case 1 Case 2 Case 3 Case 4 Case 5

Drillig: Nr.of units Drilling pattern (m2)

3 9

4

6,4

5

5,8

6

4,5

8

3,3

Blasting: Specific charge (kg/m3) K50 (mm), L

0,53 410

0,76 290

0,9 250

1,15 200

1,56 150

Number of operators 18-22

Loading by excavators Bucket size (m3) Nr.of units

12

2-7 depending on blast configuration (or bigger buckets)

Hauling by trucks: Pay-load (t) Distance (km) Nr.of units

50 2

8-10 depending on blast configuration

Crushing: Primary crusher type Nr.of primary units Nr.of sec.&tertary units

Nordberg C160 jaw

2 5

General Drillability & blastability Work index (kWh/t) Drill hole dia (mm) Bench height (m) Explosive Interest rate (%) / Quarry life (y) Fuel price ($/liter) / Energy ($/kWh) Wages ($/hour)

45 / 0,7

15 89 10

Anfo 10 / 20 0,5 / 0,1

17

All together more than 50 different cases were analysed

Comparison of different shotrock fragmentations

Starting Point: Stationary Three-stage Plant with a Capacity of 1600t/h. Final Product 0-20mm

9

Page 10: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Drillhole Diameter (‘’)

20,000

40,000

60,000

80,000

100,000

120,000

20,000

10,000

30,000

40,000

50,000

Top Hammer(Pneumatic & Hydraulic)

Down-the-Hole(Pneumatic)

Rotary(Roller bits)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Co

mp

ressiv

e S

tre

ng

th, U

CS

(p

si)

Ro

tary

Pu

ll-d

ow

n W

eig

ht (lb

)

Rotary(Drag bits)

Comparison of different shotrock fragmentations

Source: Metso Minerals & Tamrock studies

10

General Selection of Drilling Method

Page 11: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

0,00

0,10

0,20

0,30

0,40

0,50

0,000,100,200,300,400,500,600,700,800,901,001,101,201,301,401,50

64 89 115

Co

sts

[USD

/t]

Tota

l co

sts

[USD

/t]

Drillhole diameter [mm]

Impact of drillhole diameter to drilling and blasting costs

K50 = 250, drillability = medium, blastability = good

Blasting

Drilling

Drilling

Blasting

Comparison of different shotrock fragmentations

Source: Metso Minerals & Tamrock studies

11

Impact of drillhole diameter to drilling and blasting costs

Page 12: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Hole Diameter

(mm )

Dri

ll &

Bla

st (

US

D /

ton

)

Blasting

Drilling

Cost1.pre/A.

Lislerud

Hole Diameter

(mm )

Qu

anti

ty p

er t

on

Boulder

count

% Fines in

shotrock

Micro-crack

damage of

fragments

Fragment

elongation

ratio

Fines in feed

Comparison of different shotrock fragmentations

Source: Metso Minerals & Tamrock studies

12

Impact of Drillhole Diameter

Page 13: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Boulder Handling

Sort boulders from muck pile

Downsize the boulders

Minimize boulder count using tighter drill

patterns or reduced uncharged height

Comparison of different shotrock fragmentations

13

Page 14: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Example of Direct Costs Caused by Boulders.Customer case, breakage before loading

0

10

20

30

40

50

60

0 0,05 0,1 0,15 0,2 0,25 0,3

nu

mb

er

of

bo

uld

ers

/h

$/tonnes

Hammering Costs ($/tonnes)

Comparison of different shotrock fragmentations

14

Page 15: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Key Issue

• Removal of bolder

breakage outside

process

• -> improved plant

utilization

Comparison of different shotrock fragmentations

15

Page 16: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

K50 definition

Comparison of different shotrock fragmentations

16

Impact of Blast Distribution on Loading Costs

Page 17: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Loading Operations; Examples

Auxiliary machines required

for quarry floor cleanup after

blasting for loaders with poor

mobility

Tight muckpile

(poor diggability)

due to

insufficient heave

and throw

Typical toe

problem requiring

auxiliary hyd.

excavator work

and/or use of

secondary

blasting

Comparison of different shotrock fragmentations

Source: Metso Minerals & Tamrock studies

17

Page 18: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Optimum Shotrock Profiles for Loading Operations

Shotrock throw onto old

floor

New floor

(poor loadability)

Hmax dependent on loader

size and type for optimum

loading capacity

conditions

Hmax

Hmax

Front Shovels Wheel Loaders

High productivity Low productivity

Minimal cleanup area Muckpile too tight

Safe for operator Muckpile too high

Dangerous for operator

Front Shovels Wheel Loaders

Moderate productivity High productivity

Large cleanup area Muckpile is loose

Safe for operator Safe for operator

Comparison of different shotrock fragmentations

Source: Metso Minerals & Tamrock studies

18

Page 19: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

And Feeding by Excavator

Comparison of different shotrock fragmentations

Cat

recommendations

19

Page 20: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Comparison of different shotrock fragmentations

20

Impact of Blast Distribution on Hauling Costs with Dumbers

Page 21: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Why Coarser Blast Distribution Impacts on Loading and Hauling Costs?

• Material is more difficult to load due to:

- more likely toe problems

- bigger boulders

• Scope of equipment changes due to more difficult and/or longer cycle

times

• With respect to the equipment there is

- more wear

- more maintenance

Comparison of different shotrock fragmentations

21

Page 22: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Results

Case K50 (mm)

Case 1 410

Case 2 290

Case 3 250

Case 4 200

Case 5 150

K50 is 50%

point of fraction

distribution

Comparison of different shotrock fragmentations

22

Case 1 Case 2 Case 3 Case 4 Case 50

1

2

3

4

Co

sts

[U

SD

/pro

du

ce

d t

on

]

Hauling

Loading

Hammering

Crushing

Blasting

Drilling

Total costs / produced ton

Page 23: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Conclusions of Shotrock Fragmentation

• From the total product cost point of view, there is an optimum shotrock

fragmentation. In the case study, the optimum was k50 ~ 250 mm.

• The crushing cost share is almost unchanged with different K50 values

because the blast impacts only on primary crushing

• Even smaller drillhole diameters than used here (89mm) can be

economical, because:

- Smaller drillhole diameters produce fewer fines. In many cases this

is considered waste

- There are fewer boulders to be handled

- There are fewer micro cracks in the blasted rock, due to more ‘gentle

blasting’. In many cases, this generates better final aggregate quality

• Boulder management is important

Comparison of different shotrock fragmentations

23

Page 24: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

Comparison of Different Crushing Methods

Page 25: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Starting Points for Crushing Method Comparisons

Comparison of different crushing methods

• k50=250mm is being used as shotrock fragmentation

• The following quarrying methods are under comparison:

- stationary:

• Material is transported by dump trucks into crushing plants

- inpit, semimobile

• material is transported by dump trucks into the semimobile primary jaw crusher, and from there by conveyors to the secondary & tertiary crushing plants

- inpit, fully mobile

• primary crushing done at a quarry face with a highly mobile track mounted jaw crusher, and taken from there by conveyors into the secondary and tertiary crushing plants. No dump trucks are used.

25

Page 26: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Stationary CrushersPrimary crusher cannot normally be moved

Comparison of different crushing methods

26

Typical distance 2km

Page 27: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Semimobile Inpit CrushingPrimary crusher can be moved but only on a non-frequent basis.

Comparison of different crushing methods

27

Page 28: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

In-pit Fully Mobile CrushingPrimary crusher is track mounted, compact and movable within 5-10 minutes.

Comparison of different crushing methods

28

Page 29: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

In-pit Fully Mobile CrushingMovable and steerable Lokolink conveyor system is a key component

Comparison of different crushing methods

29

Page 30: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Truck Transport Versus Conveyor Belt

Comparison of different crushing methods

30

Horizontal Hauling

USD/t

0,00

0,50

1,00

1,50

2,00

2,50

0,5

0,5

1,0

0,5

2,0

0,5

3,0

0,5

4,0

0,5

5,0

0,5

0,5

1

1,0

1

2,0

1

3,0

1

4,0

1

5,0

1

0,5

5

1,0

5

2,0

5

3,0

5

4,0

5

5,0

5

0,5

10

1,0

10

2,0

10

3,0

10

4,0

10

5,0

10

L (km) &

Capacity (million t/y)

US

D/t

Belt; Cost per ton

Truck; Cost per ton

Cost comparison between conveyor belt transport and dump truck haulage hauling

distance and annual capacity.

Page 31: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Truck Transport Versus Conveyor Belt

Cost comparison between conveyor belt transport and dump truck haulage as a function

of vertical hauling distance and annual capacity given a haulage length to height ratio of 8 : 1.

Comparison of different crushing methods

31

H= 50/ 100/ 150/ 200 ( r at i o t o t r uck haul i ng met er s : 1 t o 8) Vertical Hauling

USD/t

0,00

0,20

0,40

0,60

0,80

1,00

1,20

1,40

50

0,5

100

0,5

150

0,5

200

0,5

50

1

100

1

150

1

200

1

50

5

100

5

150

5

200

5

50

10

100

10

150

10

200

10

H (m) &

Capacity (million t/y)

US

D/t

Belt; Cost per ton

Truck; Cost per ton

Page 32: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Stationary plant Semimobile primary plant Fully mobile in-pit primary plant

Primary crusher type Size Number of units

Fixed Jaw C160

2

Semimobile Jaw C140

2

Track mounted Jaw C125

2

Loaders, excavators: Bucket size (m3) Number of units

12 2

5,5 3

5,5 2

Dump trucks: Size (t) Number of units Haulage distance (km)

50 8 2

35 7 1

- - -

Conveyor length (km) - 1 4

Number of operators 20 20 11

Secondary & tertiary crushers and screens *)

Secondaries: 2 * Nordberg OC 1560 Tertiaries: 3 * Nordberg HP500

Seven Screens: 10-20m2

Other variables As in previous drilling & blasting example

*) = K10 in Hong-Kong

Comparison of different crushing methods

Starting Point: Three Different Plant Configurations with a Capacity of 1600t/h. Final Product 0-20mm

32

Page 33: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Results

Difference between stationary and fully mobile is about 25%.

Comparison of different crushing methods

33

Stationary Semimobile Fully mobile0

0,5

1

1,5

2

2,5

3

3,5

Co

sts

[U

SD

/pro

du

ce

d t

on

]

Hauling

Loading

Hammering

Crushing

Blasting

Drilling

Total costs / produced ton

K50 = 250mm, Feed rate 1600t/h

Page 34: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Another Example

Comparison of different crushing methods

Sta

tio

nary

pri

ma

ry

cru

sh

er

Mo

bile

pri

ma

ry

cru

sh

er

34

Case 6a: K50=410

Case 7a: K50=290

Case 8a: K50=250

Case 10a: K50=200

Case 11a: K50=150

Case 16a: K50=410

Case 17a: K50=290

Case 18a: K50=250

Case 19a: K50=200

Case 20a: K50=150

0 0,5 1 1,5 2 2,5 3 3,5 4

Costs [USD/produced ton]

Drilling Blasting Crushing Hammering Loading Hauling

Total 2

Total costs / produced tonSpreadsheet lines 141 - 146

Page 35: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Tools Available

0,00

1,00

2,00

DT-system LT-system

$/t

on

Total Cost vs. work category

Utilities

Crushing

Haulage

0,00

0,50

1,00

1,50

DT-system LT-system

$/t

on

Total Cost vs. cost category

Capital

MaintenanEnergy

This is not a case of…

• Increasing the powder factor to increase plant throughput

• Opt(blast) +…+ Opt(crush) Max($$$)

It is…

The development of a

quarrying and processing

strategy which minimizes the

overall cost per tonne treated

and maximizes company profit.

Opt(blast +…+

crush&screen) =

Max($$$)

1) Process Integration and

Optimization (PIO) Services

2) Calculation & simulation tools

35

Page 36: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Conclusions for Quarry Development

• From the total product cost point of view, there is an optimum shotrock fragmentation.

• Oversize boulder frequency has a significant impact on capacity and cost.

• A smaller drillhole diameter produces fewer fines. In many cases, this is considered waste.

• The crushing cost share is almost unchanged with different K50 values when the crushing method is the same. The optimum selection is dependent on:

- Rock type due to abrasion - ‘Case-specific factors’ like the life of the

quarry, investment possibilities etc.

• Whole quarry process optimization instead of the suboptimization of individual components

• Inpit crushing can generate remarkable benefits

Work continues …

36

Page 37: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Enclosures

• Operational targets for a typical aggregate producer

• K50 feed sizes

• Example: Norwegian case

37

Page 38: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Operational Targets for a Typical Aggregate Producer

Shotrock fragmentation

Product cost curve

Product price curve

versus product quality

USD / tonne

Opt.

Return

38

Page 39: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

K50 Feed Sizes

K410

K290

K250

K200

K150

%

100

80

60

40

20

0

Return

39

Page 40: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Example: Norwegian Case

Rock type Anorthosite

Explosive Slurrit 50-10

Blast size ~50 000 tonnes

0 - 300

mm

32 - 70

mm

0 - 32 mmweigh

t

weigh

t

shotrock

70

Hole diameter (mm)

80 90 110100 120

35

30

20

25

40

Pe

rce

nta

ge

of

0 -

32

mm

Ø76

Ø89

Ø102

Ø114

Large SUB’

from prior

bench level

ReturnSource: Metso Minerals & Tamrock studies

40

Page 41: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Basic Selection of Loading Equipment

Source: Cat presentations

41

Page 42: Minimizing Quarrying Costs by Correct Shotrock Fragmentation And

© Metso

Guidelines to choose loading tools for primary Nordberg LT’s

BACKHOE

EXCAVATOR

FACE

SHOVEL

WHEEL

LOADER

CONTROL OF

OVERSIZEVery good Good Mediocre

FEED

CONSISTENCYVery good Very good Mediocre

DIGABILITY Very good Very good Good

REACH 5..10 m 5..10 m 50...100 m

Can be considered

with fine blast where

bigger capacity

justifies bigger

machine

GENERAL

COMMENT

In normal blast

provides the lowest

cost per tonne

Provides the

possibility to mix

feed from different

parts of the face

SIZE vs CAPACITY

Size is selected

according to the

capacity requirement

Oversize machine is

needed to be able to

reach to the feed

hopper

Size is selected acc.

to the capacity and

distance

42