minimizing quarrying costs by correct shotrock fragmentation and
DESCRIPTION
quarryTRANSCRIPT
Minimizing Quarrying Costs by Correct Shotrock Fragmentation and In-pit Crushing
Oct. 2006, Rev A
Jarmo Eloranta
© Metso
Contents
• Quarry process in general
• Comparison of different shotrock fragmentations
• Comparison of different crushing methods
• Conclusions
• Enclosures
2
© Metso
Challenge in Quarry Development
Distance
$/to
nWhat about the
hauling distance?
‘real’ optimum
Source: Technical University Trondheim, Norway
3
© Metso
Quarry ProcessStationary Crushers
4
© Metso
Quarry ProcessMobile Crusher(s)
Mobile primary crushing
All crushers mobile
5
© Metso
Crushing & ScreeningDrilling
Blasting
Loading
Hauling
6
Example of Quarry Cost distribution
© Metso
Approach Based on Two Phases
• Comparison of different shotrock
fragmentations, including:
- drilling and blasting
- boulder handling
- loading
- hauling
- crushing (traditional stationary)
• Comparison of different crushing
methods, including:
- stationary
- inpit, semimobile
- inpit, fully mobile
Optimum
drilling and
blasting
Optimum
crushing
Cost
Effective
Quarry
Practise
7
Comparison of Different Shotrock Fragmentations
© Metso
MAIN DATA Case 1 Case 2 Case 3 Case 4 Case 5
Drillig: Nr.of units Drilling pattern (m2)
3 9
4
6,4
5
5,8
6
4,5
8
3,3
Blasting: Specific charge (kg/m3) K50 (mm), L
0,53 410
0,76 290
0,9 250
1,15 200
1,56 150
Number of operators 18-22
Loading by excavators Bucket size (m3) Nr.of units
12
2-7 depending on blast configuration (or bigger buckets)
Hauling by trucks: Pay-load (t) Distance (km) Nr.of units
50 2
8-10 depending on blast configuration
Crushing: Primary crusher type Nr.of primary units Nr.of sec.&tertary units
Nordberg C160 jaw
2 5
General Drillability & blastability Work index (kWh/t) Drill hole dia (mm) Bench height (m) Explosive Interest rate (%) / Quarry life (y) Fuel price ($/liter) / Energy ($/kWh) Wages ($/hour)
45 / 0,7
15 89 10
Anfo 10 / 20 0,5 / 0,1
17
All together more than 50 different cases were analysed
Comparison of different shotrock fragmentations
Starting Point: Stationary Three-stage Plant with a Capacity of 1600t/h. Final Product 0-20mm
9
© Metso
Drillhole Diameter (‘’)
20,000
40,000
60,000
80,000
100,000
120,000
20,000
10,000
30,000
40,000
50,000
Top Hammer(Pneumatic & Hydraulic)
Down-the-Hole(Pneumatic)
Rotary(Roller bits)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Co
mp
ressiv
e S
tre
ng
th, U
CS
(p
si)
Ro
tary
Pu
ll-d
ow
n W
eig
ht (lb
)
Rotary(Drag bits)
Comparison of different shotrock fragmentations
Source: Metso Minerals & Tamrock studies
10
General Selection of Drilling Method
© Metso
0,00
0,10
0,20
0,30
0,40
0,50
0,000,100,200,300,400,500,600,700,800,901,001,101,201,301,401,50
64 89 115
Co
sts
[USD
/t]
Tota
l co
sts
[USD
/t]
Drillhole diameter [mm]
Impact of drillhole diameter to drilling and blasting costs
K50 = 250, drillability = medium, blastability = good
Blasting
Drilling
Drilling
Blasting
Comparison of different shotrock fragmentations
Source: Metso Minerals & Tamrock studies
11
Impact of drillhole diameter to drilling and blasting costs
© Metso
Hole Diameter
(mm )
Dri
ll &
Bla
st (
US
D /
ton
)
Blasting
Drilling
Cost1.pre/A.
Lislerud
Hole Diameter
(mm )
Qu
anti
ty p
er t
on
Boulder
count
% Fines in
shotrock
Micro-crack
damage of
fragments
Fragment
elongation
ratio
Fines in feed
Comparison of different shotrock fragmentations
Source: Metso Minerals & Tamrock studies
12
Impact of Drillhole Diameter
© Metso
Boulder Handling
Sort boulders from muck pile
Downsize the boulders
Minimize boulder count using tighter drill
patterns or reduced uncharged height
Comparison of different shotrock fragmentations
13
© Metso
Example of Direct Costs Caused by Boulders.Customer case, breakage before loading
0
10
20
30
40
50
60
0 0,05 0,1 0,15 0,2 0,25 0,3
nu
mb
er
of
bo
uld
ers
/h
$/tonnes
Hammering Costs ($/tonnes)
Comparison of different shotrock fragmentations
14
© Metso
Key Issue
• Removal of bolder
breakage outside
process
• -> improved plant
utilization
Comparison of different shotrock fragmentations
15
© Metso
K50 definition
Comparison of different shotrock fragmentations
16
Impact of Blast Distribution on Loading Costs
© Metso
Loading Operations; Examples
Auxiliary machines required
for quarry floor cleanup after
blasting for loaders with poor
mobility
Tight muckpile
(poor diggability)
due to
insufficient heave
and throw
Typical toe
problem requiring
auxiliary hyd.
excavator work
and/or use of
secondary
blasting
Comparison of different shotrock fragmentations
Source: Metso Minerals & Tamrock studies
17
© Metso
Optimum Shotrock Profiles for Loading Operations
Shotrock throw onto old
floor
New floor
(poor loadability)
Hmax dependent on loader
size and type for optimum
loading capacity
conditions
Hmax
Hmax
Front Shovels Wheel Loaders
High productivity Low productivity
Minimal cleanup area Muckpile too tight
Safe for operator Muckpile too high
Dangerous for operator
Front Shovels Wheel Loaders
Moderate productivity High productivity
Large cleanup area Muckpile is loose
Safe for operator Safe for operator
Comparison of different shotrock fragmentations
Source: Metso Minerals & Tamrock studies
18
© Metso
And Feeding by Excavator
Comparison of different shotrock fragmentations
Cat
recommendations
19
© Metso
Comparison of different shotrock fragmentations
20
Impact of Blast Distribution on Hauling Costs with Dumbers
© Metso
Why Coarser Blast Distribution Impacts on Loading and Hauling Costs?
• Material is more difficult to load due to:
- more likely toe problems
- bigger boulders
• Scope of equipment changes due to more difficult and/or longer cycle
times
• With respect to the equipment there is
- more wear
- more maintenance
Comparison of different shotrock fragmentations
21
© Metso
Results
Case K50 (mm)
Case 1 410
Case 2 290
Case 3 250
Case 4 200
Case 5 150
K50 is 50%
point of fraction
distribution
Comparison of different shotrock fragmentations
22
Case 1 Case 2 Case 3 Case 4 Case 50
1
2
3
4
Co
sts
[U
SD
/pro
du
ce
d t
on
]
Hauling
Loading
Hammering
Crushing
Blasting
Drilling
Total costs / produced ton
© Metso
Conclusions of Shotrock Fragmentation
• From the total product cost point of view, there is an optimum shotrock
fragmentation. In the case study, the optimum was k50 ~ 250 mm.
• The crushing cost share is almost unchanged with different K50 values
because the blast impacts only on primary crushing
• Even smaller drillhole diameters than used here (89mm) can be
economical, because:
- Smaller drillhole diameters produce fewer fines. In many cases this
is considered waste
- There are fewer boulders to be handled
- There are fewer micro cracks in the blasted rock, due to more ‘gentle
blasting’. In many cases, this generates better final aggregate quality
• Boulder management is important
Comparison of different shotrock fragmentations
23
Comparison of Different Crushing Methods
© Metso
Starting Points for Crushing Method Comparisons
Comparison of different crushing methods
• k50=250mm is being used as shotrock fragmentation
• The following quarrying methods are under comparison:
- stationary:
• Material is transported by dump trucks into crushing plants
- inpit, semimobile
• material is transported by dump trucks into the semimobile primary jaw crusher, and from there by conveyors to the secondary & tertiary crushing plants
- inpit, fully mobile
• primary crushing done at a quarry face with a highly mobile track mounted jaw crusher, and taken from there by conveyors into the secondary and tertiary crushing plants. No dump trucks are used.
25
© Metso
Stationary CrushersPrimary crusher cannot normally be moved
Comparison of different crushing methods
26
Typical distance 2km
© Metso
Semimobile Inpit CrushingPrimary crusher can be moved but only on a non-frequent basis.
Comparison of different crushing methods
27
© Metso
In-pit Fully Mobile CrushingPrimary crusher is track mounted, compact and movable within 5-10 minutes.
Comparison of different crushing methods
28
© Metso
In-pit Fully Mobile CrushingMovable and steerable Lokolink conveyor system is a key component
Comparison of different crushing methods
29
© Metso
Truck Transport Versus Conveyor Belt
Comparison of different crushing methods
30
Horizontal Hauling
USD/t
0,00
0,50
1,00
1,50
2,00
2,50
0,5
0,5
1,0
0,5
2,0
0,5
3,0
0,5
4,0
0,5
5,0
0,5
0,5
1
1,0
1
2,0
1
3,0
1
4,0
1
5,0
1
0,5
5
1,0
5
2,0
5
3,0
5
4,0
5
5,0
5
0,5
10
1,0
10
2,0
10
3,0
10
4,0
10
5,0
10
L (km) &
Capacity (million t/y)
US
D/t
Belt; Cost per ton
Truck; Cost per ton
Cost comparison between conveyor belt transport and dump truck haulage hauling
distance and annual capacity.
© Metso
Truck Transport Versus Conveyor Belt
Cost comparison between conveyor belt transport and dump truck haulage as a function
of vertical hauling distance and annual capacity given a haulage length to height ratio of 8 : 1.
Comparison of different crushing methods
31
H= 50/ 100/ 150/ 200 ( r at i o t o t r uck haul i ng met er s : 1 t o 8) Vertical Hauling
USD/t
0,00
0,20
0,40
0,60
0,80
1,00
1,20
1,40
50
0,5
100
0,5
150
0,5
200
0,5
50
1
100
1
150
1
200
1
50
5
100
5
150
5
200
5
50
10
100
10
150
10
200
10
H (m) &
Capacity (million t/y)
US
D/t
Belt; Cost per ton
Truck; Cost per ton
© Metso
Stationary plant Semimobile primary plant Fully mobile in-pit primary plant
Primary crusher type Size Number of units
Fixed Jaw C160
2
Semimobile Jaw C140
2
Track mounted Jaw C125
2
Loaders, excavators: Bucket size (m3) Number of units
12 2
5,5 3
5,5 2
Dump trucks: Size (t) Number of units Haulage distance (km)
50 8 2
35 7 1
- - -
Conveyor length (km) - 1 4
Number of operators 20 20 11
Secondary & tertiary crushers and screens *)
Secondaries: 2 * Nordberg OC 1560 Tertiaries: 3 * Nordberg HP500
Seven Screens: 10-20m2
Other variables As in previous drilling & blasting example
*) = K10 in Hong-Kong
Comparison of different crushing methods
Starting Point: Three Different Plant Configurations with a Capacity of 1600t/h. Final Product 0-20mm
32
© Metso
Results
Difference between stationary and fully mobile is about 25%.
Comparison of different crushing methods
33
Stationary Semimobile Fully mobile0
0,5
1
1,5
2
2,5
3
3,5
Co
sts
[U
SD
/pro
du
ce
d t
on
]
Hauling
Loading
Hammering
Crushing
Blasting
Drilling
Total costs / produced ton
K50 = 250mm, Feed rate 1600t/h
© Metso
Another Example
Comparison of different crushing methods
Sta
tio
nary
pri
ma
ry
cru
sh
er
Mo
bile
pri
ma
ry
cru
sh
er
34
Case 6a: K50=410
Case 7a: K50=290
Case 8a: K50=250
Case 10a: K50=200
Case 11a: K50=150
Case 16a: K50=410
Case 17a: K50=290
Case 18a: K50=250
Case 19a: K50=200
Case 20a: K50=150
0 0,5 1 1,5 2 2,5 3 3,5 4
Costs [USD/produced ton]
Drilling Blasting Crushing Hammering Loading Hauling
Total 2
Total costs / produced tonSpreadsheet lines 141 - 146
© Metso
Tools Available
0,00
1,00
2,00
DT-system LT-system
$/t
on
Total Cost vs. work category
Utilities
Crushing
Haulage
0,00
0,50
1,00
1,50
DT-system LT-system
$/t
on
Total Cost vs. cost category
Capital
MaintenanEnergy
This is not a case of…
• Increasing the powder factor to increase plant throughput
• Opt(blast) +…+ Opt(crush) Max($$$)
It is…
The development of a
quarrying and processing
strategy which minimizes the
overall cost per tonne treated
and maximizes company profit.
Opt(blast +…+
crush&screen) =
Max($$$)
1) Process Integration and
Optimization (PIO) Services
2) Calculation & simulation tools
35
© Metso
Conclusions for Quarry Development
• From the total product cost point of view, there is an optimum shotrock fragmentation.
• Oversize boulder frequency has a significant impact on capacity and cost.
• A smaller drillhole diameter produces fewer fines. In many cases, this is considered waste.
• The crushing cost share is almost unchanged with different K50 values when the crushing method is the same. The optimum selection is dependent on:
- Rock type due to abrasion - ‘Case-specific factors’ like the life of the
quarry, investment possibilities etc.
• Whole quarry process optimization instead of the suboptimization of individual components
• Inpit crushing can generate remarkable benefits
Work continues …
36
© Metso
Enclosures
• Operational targets for a typical aggregate producer
• K50 feed sizes
• Example: Norwegian case
37
© Metso
Operational Targets for a Typical Aggregate Producer
Shotrock fragmentation
Product cost curve
Product price curve
versus product quality
USD / tonne
Opt.
Return
38
© Metso
K50 Feed Sizes
K410
K290
K250
K200
K150
%
100
80
60
40
20
0
Return
39
© Metso
Example: Norwegian Case
Rock type Anorthosite
Explosive Slurrit 50-10
Blast size ~50 000 tonnes
0 - 300
mm
32 - 70
mm
0 - 32 mmweigh
t
weigh
t
shotrock
70
Hole diameter (mm)
80 90 110100 120
35
30
20
25
40
Pe
rce
nta
ge
of
0 -
32
mm
Ø76
Ø89
Ø102
Ø114
Large SUB’
from prior
bench level
ReturnSource: Metso Minerals & Tamrock studies
40
© Metso
Basic Selection of Loading Equipment
Source: Cat presentations
41
© Metso
Guidelines to choose loading tools for primary Nordberg LT’s
BACKHOE
EXCAVATOR
FACE
SHOVEL
WHEEL
LOADER
CONTROL OF
OVERSIZEVery good Good Mediocre
FEED
CONSISTENCYVery good Very good Mediocre
DIGABILITY Very good Very good Good
REACH 5..10 m 5..10 m 50...100 m
Can be considered
with fine blast where
bigger capacity
justifies bigger
machine
GENERAL
COMMENT
In normal blast
provides the lowest
cost per tonne
Provides the
possibility to mix
feed from different
parts of the face
SIZE vs CAPACITY
Size is selected
according to the
capacity requirement
Oversize machine is
needed to be able to
reach to the feed
hopper
Size is selected acc.
to the capacity and
distance
42