minnesota power - umn ccaps · 2015-09-15 · minnesota power system upgrades for phase angle...
TRANSCRIPT
Minnesota Power System Upgrades for Phase Angle Regulating Transformers
September 6, 2015
Ken Sletten & Benjamin Fameree
30 West Superior Street
Duluth, MN 55802
(Ken 218-355-3456) (Ben 218-355-2907)
[email protected] [email protected]
Table of Contents
I. Introduction……………………………………………………………………………….. 1
II. Planning and Overview…………………………………………………………………... 1
III. Phase 1 – Background ………………………………………………………………….... 2
IV. Phase 1 – Execution and Commissioning……………………………………………….. 2
V. Phase 1 – Lessons Learned and Summary……………………………………………… 3
VI. Phase 2 – Background……………………………………………………………………. 4
VII. Phase 2 – Execution and Commissioning……………………………………………….. 4
VIII. Phase 2 – Lessons Learned and Summary……………………………………………… 5
IX. Conclusion………………………………………………………………………………… 5
X. Resources………………………………………………………………………………….. 6
XI. Appendix…………………………………………………………………………………... 7-15
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 1
1. http://www.reinhausen.com/ Motor Drive TAPMOTION® ED flyer 2. http://www.ifallscoldtesting.com/
Introduction
Minnesota Power (MP) and Ontario Hydro share a 115kV interconnection transmission line from
International Falls substation to Fort Francis substation respectively. Due to the large phase regulation
difference that can take place both daily and seasonally, an unusual configuration of phase angle
regulating transformers (PAR) was installed at the International Falls substation and put into service in
1995. Two Siemens (150MVA) PAR transformers were installed in series; their internal design housed a
delta exciting winding and series quadrature legs with Reinhausen tap changers. Their design allows the
series units to operate with a +/- 70 degree phase shift allowing a combined range of 140 degree phase
shifting capability at full load rating. Each PAR transformer had four individual motor drives split on
each side of the transformer labeled the source and load terminal. All eight motor drives were replaced in
2013, a difficult task with an outage window of one week per transformer. Due to the aging existing
control system, a new replacement system was undertaken in 2014. A high need for monitoring
capability was stressed for this project as past tap changing errors had created headaches with no ability to
remotely diagnose issues. A field visit was needed each time. As error time increased, coupled with a
remote site location for our personnel, remote monitoring and diagnostic analysis was needed for the new
controller system. A Reinhausen controller system was installed in December 2014. The importance of
this line allows Minnesota Power energy transactions with Ontario Hydro that allow the diversity of fuel
and load between the power systems grids, a great economic benefit for both parties. A twelve day
outage was requested; a daunting task of installing new wires in sub-zero temperatures was required to
ensure the system was fully operational. The combined effort of contracted engineering, internal
planning, and a great effort on the part of our technicians and field crew along with Reinhausen support
personnel, allowed the controller replacement project to be completed in the allotted outage time.
Planning and Overview
With the original 10 & 11 PAR transformers installed in 1995 including the original Reinhausen motor
drives and VANSCO controller system, the approximately 20 year old system was due for an upgrade.
With the complexity on both the engineering and technician installation, the project was split into two
phases. Phase 1 was to be executed in 2013 and would consist of upgrading all eight motor drives for
both 10 & 11 PAR transformers with new Reinhausen TAPMOTION® ED 1 motor drives. Phase 2 was
to be executed in 2014 and would consist of upgrading the controller system with new Reinhausen
TAPCON® 260 controllers. Each project had unique challenges and obstacles to overcome and will be
highlighted separately with respect to the chronological timeline of the project. International Falls
substation is located in International Falls, MN and located on the Minnesota, Ontario border (see
Appendix – Figure 1). International Falls, MN is known nationally as “The Ice Box of the Nation” 2 this
northern climate location makes for an ideal condition for extreme cold weather testing in the United
States. International Fall’s substation is located 160 miles north of MP’s main Herbert Service Center
(HSC) in Duluth, MN and 100 miles north of MP’s branch service center located in Eveleth, MN. With
the remote and cold location, careful planning was taken to ensure all material, tools, food and overnight
accommodations where provided to all personal for both phases of the projects. Overtime was expected
and a “can do” and “must finish” attitude was planned by all personal.
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 2
Phase 1 – Background
Each transformer’s motor drive had numerous issues that started to affect the overall reliability and
operation of the transformer. Aged mechanical drive shafts along with deteriorating cam shafts and
failing contacts became progressively worse from 2008 to 2013. A project team was assembled in
January of 2013 and an initial budget of 1.4 million was approved by upper management for the
replacement and installation for all eight motor drives to be replaced in the fall of 2013. With only one tie
line between Minnesota Power and Ontario Hydro, careful planning was needed for coordinating outage
requirements for construction. Winter provided the best off peak loading time for outage coordination.
Each transformer was given a one week outage split by a one week gap. With the amount of unwiring,
disassembling, and installation of all four motor drives on each transformer, the weekends were planned
as flow over days. With the original motor drives installed and commissioned by Reinhausen, it was
decided to contract the bulk of the work to Reinhausen technicians and have a small MP crew as added
support with the intent for oversite and training purposes on the new motor drives. Each PAR
transformer was split into two halves, load and source with each side operated by two motor drives acting
as a unit; an on load tap changer (OLTC) and advance retard switch (ARS) motor drive (see appendix –
Figure 2). The interlocking wires between OLTC and ARS motor drives would have to be completely
replaced. With phase 2 of the project to replace the controllers next year, the wiring from the control
house to each motor drive was re-used for phase 1 with the plan to replace with all new cables in phase 2.
Phase 1 – Execution and Commissioning
Plans were put in place to begin the week long outage for 11 PAR transformer September 16th – 20
th,
2013 and 10 PAR transformer the week of September 30th – October 4
th, 2013. The first week consisted
of numerous tasks for 11 PAR transformer (see appendix – Figure 3). With a late fall construction
schedule and a small control house, onsite logistical planning for an all-weather headquarters facility on
site was recommended. Two large 30 feet x 15 feet construction trailers were used to shelter all personal
on site. A total of fourteen Reinhausen personal including ten technicians, two engineering leads, and
two designers were flown in, coming as far away as Germany. A total of twelve MP personal including
six construction & maintenance (C&M) technicians, two communication technicians, two relay
technicians, and two engineers were on site the entire week. Work was broken up into two teams, five
Reinhausen technicians, two MP C&M technicians, and one MP relay technician. Each team worked on
the load and source side of 11 PAR transformer at the same time. Demolition of all four motor drives
went quickly and the construction schedule became a day ahead of schedule. Work progressed with the
installation of the OLTC motor drives onto the side of the transformer. The new drive shaft was installed
but due to the physical location of the new motor drive cabinet and permanent location of the drive shaft
gear box located at the top of the transformer, an angle was introduced with the vertical motor drive shaft
leaving the cabinet (see Appendix – Figure 4). The ARS motor drive cabinets were installed, next and
this same issue was present. The angle for the vertical drive shaft was great enough for a mid-point
coupler to be installed on the vertical shaft to relieve pressure off the shaft. The new OLTC and ARS
motor drives required a sophisticated interlocking wiring system and all new cable and conduit were
wired between the drives. Thirty interconnections were needed between each OLTC and ARS motor
drives. Control cable coming from the control house Automatic Power Flow
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 3
3. www.Reinhausen.com Dehydrating Breathers DB 200
Control (APFC) panel used for alarm and control was determined to be in good condition and re-used for
this phase of the project. The main control cabinet on each transformer housed the AC distribution feeds
for the motor drives and the cable leads from the main cabinet to the motor drives was also re-used. As
both motor drives were getting ready to be commissioned, an error was found with the drive shaft ratio.
The ARS motor drive was not able to make a full rotation to change the tap changer from position 1 to
position 2. This error was found Wednesday evening. A call was made to Germany to inquire on the
mistake, and to see if a drive shaft with the correct ratio was available at one of the Reinhausen facilities
in the United States. No spare part could be found but thanks to Reinhausen support personal, a gear box
with the correct ratio was found in Germany and arrived the next night in Minneapolis, MN. A crew was
assembled to drive from International Falls to the Minneapolis International Airport to pick up the
equipment and head straight back. Once the equipment was received and installed, a second issue was
discovered. The original thermal overload protection breakers in each new motor drive were found to be
undersized as increased heating capacity in each motor drive was needed for the cold winters.
Additionally, new MESSKO® MTraB® DB 200 3 devices were installed for both load and source OLTC
oil tanks. These devices replaced the existing conventional breather devices and had a built in
microprocessor for continuous monitoring of the vapor in the oil conservator tank. Due to the cold
climate, heaters in each unit were needed. The extra heaters in the motor drives along with the heating
circuit for the dehydrating breathers, prompted an increase in circuit protection breakers size. The nearest
warehouse with the correct breakers was Minneapolis, MN. Another team was sent on an overnight
pickup down to Minneapolis, MN to pick up the breakers and drive them back to International Falls. It
was not until Saturday morning when everything passed point to point checks and commissioning and
testing were able to begin. Luckily, all testing was finished Saturday evening and 10 PAR transformer
was put back into service. A week later, 11 PAR transformer was scheduled for it’s week outage.
Everything went well and 11 PAR was able to be placed into service on the scheduled Friday of the week.
Phase 1 – Lessons Learned and Summary
Even with all the preparation beforehand, problems arose that were not foreseen to be an issue. Incorrect
gear ratios on the motor drive shaft presented a difficult challenge that could have halted the project for
weeks if it wasn’t for Reinhausen’s support personal that determined the correct ratio, tracked down the
correct parts in Germany, and oversaw the speedy transportation for an overnight delivery through United
States customs, thus ensuring we received the parts within 24 hours. Increasing the size of the motor
protective circuit breaker in each motor drive was another issue solved. New parts were located and
quickly transported to the job site, all in part to Reinhausen support personal. Since the motor drive would
rotate half way through its 32 position rotation and would automatically rotate back to the original
position, the motor drive clutch required stiffer springs for increased friction. This would cause an
incomplete or tap change error ever time this happened. A temporary fix was installed on each motor
drive until new springs could be installed in early December 2013. The source ARS local remote switch
broke on 11 PAR transformer. Spare parts were ordered and temporary switch from 10 PAR motor drives
was used. With multiple issues arising during the motor drive replacement project, one thing was for sure,
MP and Reinhausen’s work crew were able to keep focus, work together, and finish the project as
scheduled and on time.
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 4
4. http://www.cai-engr.com/ 5. www.Reinhausen.com TAPCON 260 controllers
Phase 2 – Background
The original controller system was from VANSCO, which utilized an Allen Bradley programmable logic
controller. When the original system was commissioned in 1995, a logic controller was the only option,
as the complex power flow calculations and continuous error checking was needed. With original
engineers from the project retired, expert help was needed in order to complete phase 2 of the project.
Minnesota Power reached out to Commonwealth Associates Inc., 4 as they have used their consultants and
expertise in the past to design a phase shifter controller for another substation just a few years prior. The
complexity of the design rested on the shoulders of Commonwealth. The design for an upgrade in
sophistication was required. With the current controller system, any alarms triggered by the controller
would have to be field inspected and analyzed on site. MP could have field technicians on site within two
hours from our Eveleth service branch and many times occurring in the middle of the night and in the
cold of winter. Main engineering support was based out of the HSC in Duluth, MN for any issues with
the PAR transformers. It would require a lot of phone calls for troubleshooting with technicians remotely
to evaluate the ladder logic (see Appendix – Figure 6). The original VANSCO controller used a CRT
monitor on site to view alarms (See Appendix – Figure 7). The aging communications card in each
controller only allowed viewing access from one of the controller based systems. Each transformer is
controlled by the same controller by either the primary unit, and has a completely redundant system that
can be switched over at any time on a secondary unit. The secondary unit had a failed communication
card and diagnosis for reading alarms was through the LED light ups on the back of the system (see
Appendix – Figure 8). The control was switched over on a set schedule between primary and secondary.
When the secondary system was activated, alarms were read using the LEDs instead of the CRT monitor
and ladder logic prints were used for diagnostics along with helpful cheat sheets taped on the panel (see
Appendix – Figure 9). Usually a field visit was required from engineering when difficult issues arose
after troubleshooting. As the frequency of difficult issues increased, a three hour drive from Duluth, it
was becoming more and more prevalent a remote diagnostic system would be of more value. The digital
fault recorder DFR, originally commissioned with 10 & 11 PAR transformers back in 1995, was due also
for an upgrade for the same remote diagnostic improvements needed with the controllers. It was decided
to perform both projects at the same time as outages could be coordinated together.
Phase 2 – Executing and Commissioning
Preparation work for phase 2 began the beginning of October 2014, as according to the planned
construction schedule (see Appendix – Figure 10). A two week outage for construction and
commissioning was needed for phase two. MP planned to replace all cabling from the controller panel to
10 & 11 PAR transformer motor drives. As all existing conduit was filled, we needed to install and extend
the cable trench to both transformers. This allowed for easy access for installation and any future planned
additions for both 10 and 11 PAR transformers (see Appendix – Figure 11). Eighteen thousand feet of
new control cable was used for both DFR and controller projects. The new TAPCON® 260 4 controllers
from Reinhausen needed fully customized input output cards and software to meet and replace the
existing controllers (see Appendix – Figure 12). As the previous system had a primary and secondary
system, so the new system also had a completely redundant system for reliability reasons. A two week
outage was set for December 1st – 12
th, 2015. MP had planned to test the new software for the controllers
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 5
the week of November 17-21st at HSC. Reinhausen representatives flew from Germany to deliver and
install the new software but were delayed by 1 week, this added stress on the entire project. Thankfully,
testing of the new software went smoothly and completed the Thursday before the scheduled outage.
Shelters were constructed around each motor drive cabinet the week before the outage; they consisted of
heaters, foam insulation and a tarp for rain (see Appendix – Figure 13). On the first day of the outage,
morning temperatures reached -20 degrees Fahrenheit and crews were extra happy to have heated shelters
as they started unwiring hundreds of connections. The total amount of connects for the entire project was
under a thousand. Demolition and installation of the new controller panel went quickly and the project
was a day ahead of schedule coming into the second week of the outage. Once all wires and connections
were checked by our relay technicians, the long process of testing every function in the controllers took
place. During the commissioning and testing process, problems started to surface. Many long days of
testing and commissioning were needed the final week in order to complete phase 2 project on time (see
Appendix – Figure 14).
Phase 2 – Lessons Learned and Summary
New current transformers were installed on the motor to be recorded by the DFR. Due to the long
distance of the cables, not a strong enough signal was able to be brought back. A quick in the field fix of
double wrapping the primary connection to increase the secondary current output of the current
transformers at the motor drive was performed. We placed temperature transducers in each OLTC motor
drive cabinet to remotely monitor the inside temperature next to the motor. These transducers needed to
be externally powered and another fix in the field was performed by installing 24 volt DC power supplies
on each circuit. Originally 10 PAR and 11PAR transformers were positioned with the original crane
installation in 1994 back to back. This original placement of the transformers is in contrast to both MP’s
energy control center (EMS) and tap changer controller definitions of power flow. As defined by our
EMS, positive power flow is defined as power flow from Minnesota Power to Canada; negative power
flow is defined as power flow from Canada to Minnesota Power. Power flow defined by the designers of
the Tapcon controller originally was backwards to MP’s definition. The Reinhausen controllers were
quickly reprogrammed in the field to meet MP’s definition. The controller expects an increase positive
power or decrease negative power flow when transformer taps go in advance direction; vice versa the
controller expects an decrease positive power or increase in negative power flow when transformer taps
go in retard direction. With the transformers faced back to back correct raise and lower commands were
needed in order for the transformers to cooperate when advance or retard tap positions. With the finish of
adding the new digital fault recorder, individual alarms for each motor drive can now be viewed remotely
and can be time stamped for added troubleshooting ability.
Conclusion
Monitoring on both the DFR and controller panel has greatly improved remote troubleshooting ability.
Alarms for each motor drive are now able to be viewed remotely through the DFR. An event trigger is set
with the tripping of the motor protective switch on each motor drive. Each alarm on every motor drive is
recorded with the time stamp when activated. MP’s approach of splitting up the work into two phases,
allowed for successful individual projects. Both phases needed outside engineering expertise, planning,
equipment coordination, and a “can do” attitude from the work crew, resulting in both projects finishing
on time.
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 6
Resources
1. http://www.reinhausen.com/ Motor Drive TAPMOTION® ED flyer
2. http://www.ifallscoldtesting.com/
3. www.Reinhausen.com Dehydrating Breathers DB 200
4. http://www.cai-engr.com/
5. www.Reinhausen.com TAPCON 260 controllers
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 7
Appendix
Figure 1
Figure 2
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 9
Figure 4
Old Motors with couplers for motor drive shaft angle
New Motors still needing couplers for motor drive shaft angle
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 10
Figure 5 Installation of new motor drives
Setting new motor drive
Aligning new drive shaft
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 11
Figure 6
Figure 7
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 12
Figure 8
Figure 9
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 13
Figure 10
Figure 11
International Falls 115kV Construction Schedule - Replace 10 & 11 PST Controller Project
Date
C&M
Northern
C&M
Central Relay CI
MP
Eng CW MR Description of Work
Special
Equipment Material Notes:
Pre-Outage 1-Oct 2 2 1 Pre-Construction for Trench and Cable install Meeting at HSC
13-Oct 2 Receive Old Castle trench system
ASV to off
load pallets
Oct 13 - 24 4 Install trench system
Compactor,
ASV with
bucket
Geo-textile fabric, Pea
Rock, Sand?, Conduit,
Conduit Caps, 4/0
copper, Steel Cable
clips
Oct 22 - 24 2 Install Cable in trench Shielded Cable
Oct 20 - Nov 7 2 1 1 Install Additional DFR equipment in DFR pnl
Fuse Blocks, Tesla
4000, 5 current
modules
Prints set for Oct 10,
Receive equipment
Oct 10
Nov 10 - 14 2 Install Tapcon software
Panel delivered on
Nov 6 to HSC
Nov 17 - 26 1 1 1 1 1 Tapcon In House Testing
Ken Sletten will need
to come up with a
testing plan
Nov 10 - 21 2 1 Install additional SI board and wire up panel
19-Nov 1 1 1 1 3 1 1 Final Pre Construction Meeting (All leads) Meeting at HSC
13-Nov 2
2 construction trailers delivered and installed
with provisions. Have 2 portable john hualed
to site
Have heat, Wi-fii, and
other provisions
necessary
Nov 3 - 7
Program new TESLA for DFR and additional
TESLA used for PST motor drives
Pete Shommer (Tim
Salmonson)
Nov 17 - 28 4
Install wooden platforms for all 8 motor
drives
Install tarps and
possible heaters for
adequate working
conditions.
30-Nov
Have meeting with crew to go over details of
work for the week and to answer questions
Meeting at hotel
night before outage.
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 14
Figure 12
Figure 13
System Upgrades for Phase
Angle Regulating Transformers
September 6, 2015
P a g e | 15
Figure 14
International Falls 115kV Construction Schedule - Replace 10 & 11 PST Controller Project
December 1 2 3 4 5 WKND 8 9 10 11 12 WKND Description of Work
# of
Guys
Special
Equipment Material Notes:
OutageInstall conduit into all
motor drives 2
Re-wire Motor drives
with new cable/
terminate end into
panel 6 2 days per XFMR, 3 guys per side
Install wiring from
panel to panel inside
control house for
Controller panel 2
2
Remove exisiting DFR 2
DNP conversion for
RTU 2
RTU outage for 10 & 11TR will be for a
couple of hrs
Install new DFR 2
CT circuits 126 line, 134 line have
independent CT's, 10 & 11 Cap bank
neutral CT circuits have relaying and
726 line has watt transducers…
Commision / wire
check DFR 1
Install GPS clock and
RTU points 2
Install CT's in motor
drives / temperture
gauges 2
Commision / wiring
check on Controller pnl 2
Commision / wiring for
all new RTU points 2
install TESLA
programing changes 1
Install New BCD boards 2
Provide Added
Schematic support 1
Commision / testing
Tapcon both Pri & Sec
systems 3
Total # guys during
outage
9
?
2
2
2
1
3Reinhausen
Workforce Color CodeC&M Northern
C&M Central
Relay Technicians
Communications
MP Engineering
CommonWealth