minos far detector installation & commissioning
DESCRIPTION
MINOS Far Detector Installation & Commissioning. Jeff Nelson MNHEP DoE Visit September, 2002. Outline. Plane assembly Status & experience Projection methodology Projected schedule Issues & costs Safety Detector operation Live time & data collected. The detector in August…. - PowerPoint PPT PresentationTRANSCRIPT
NUMI
MINOS
MINOS Far Detector Installation & Commissioning
Jeff Nelson
MNHEP DoE Visit
September, 2002
NUMI
MINOS
DoE Review12/02Page 2
Outline
• Plane assembly>Status & experience>Projection methodology>Projected schedule>Issues & costs>Safety
• Detector operation >Live time & data collected
NUMI
MINOS
DoE Review12/02Page 3
The detector in August…
NUMI
MINOS
DoE Review12/02Page 4
Assembly & Commissioning
• SM1 Completed in July
> Met commissioning
milestone on July 26th
• 354 of 484 planes
installed
> 73% completed, 3.9 kton
• 348 planes commissioned
• All commissioned planes
are collecting calibration
& cosmic ray data
NUMI
MINOS
DoE Review12/02Page 5
Installation Schedule
• We have averaged 6.2 planes per week since installation reached full efficiency in Nov. 01
• Currently 4 days behind working schedule> Amall drop off in rate associated
with a few factors including• Workers now have vacation time • Some attrition in staffing
• Plots shows> Current FNAL working schedule> Actual installation schedule> Projected completion schedule
• Differences described in following slides
Plane Installation vs Working Schedule
0%
20%
40%
60%
80%
100%
120%
140%
160%
7/16
/200
1
8/27
/200
1
10/8
/200
1
11/1
9/20
01
12/3
1/20
01
2/11
/200
2
3/25
/200
2
5/6/
2002
6/17
/200
2
7/29
/200
2
9/9/
2002
10/2
1/20
02
12/2
/200
2
1/13
/200
3
2/24
/200
3
4/7/
2003
5/19
/200
3
Working Schedule (100% = 6.4 pln/wk)
Installation Rate
NUMI
MINOS
DoE Review12/02Page 6
Installation Extrapolation Data
• History of MINOS installation hours & plane
installation in 2 week periods
• Some drop in hours work due to crew having
accumulated vacation in their first year of
employment
> About a 10% effect
• Fit shows what a worker
accounts for roughly
0.25 planes/week
> No drop off in efficiency
for reasonable staffing levels
> Some expected a levels below 14 FTE
Installation and Staffing per Pay Period
10
12
14
16
18
20
22
24
26
11/0
4/01
12/0
4/01
01/0
4/02
02/0
4/02
03/0
4/02
04/0
4/02
05/0
4/02
06/0
4/02
07/0
4/02
08/0
4/02
09/0
4/02
10/0
4/02
11/0
4/02
Pay Period (2 Weeks)
FTE
6
8
10
12
14
16
18
Pla
nes
Inst
alle
d
MINOS crew FTE
planes erected
fte/crew
60%
65%
70%
75%
80%
85%
90%
95%
100%
Nov-
01
De
c-0
1
Jan
-02
Feb
-02
Mar-
02
Ap
r-0
2
May-0
2
Jun
-02
Jul-
02
Au
g-0
2
Se
p-0
2
Oct
-02
Nov-
02
pay period
FTE
/Cre
w
[MIN
OS
hou
rs/c
rew
/80
hou
rs]
NUMI
MINOS
DoE Review12/02Page 7
Staff & Future Projections
• Job Market in northern Minnesota> Down turn in iron mining in early 2001 > We were able to hire some very experienced millwrights & operators
for the installation crew> Steel mills are hiring again > We have lost one staff per month
each of the last 4 months• We are starting to replace these
workers to maintain the current efficiency> The projections show what happened
if we replace one of the current losses & all further losses
> This is our current plan• Adding new crew has safety, quality
& efficiency implications during training period> Particularly an issue for materials handling> Costs are about $1k per new employee> We do not take this lightly
NUMI
MINOS
DoE Review12/02Page 8
Costs & Schedule Implications
• The amount of work is the same and there are no changes in efficiency> There are no significant costs for WBS 2.4 associated
with install schedule adjustments
• The only cost implications are to on-project operations costs> 2nd shift charges for DNR hoistman and on-call
electricians> Physicist shift leader travel> Staffing for receiving at surface building> All 3 amounts to $5k per week of slip
• Now projecting a 6 week change in completion date
NUMI
MINOS
DoE Review12/02Page 9
Safety at Soudan
• Major activities>Continued monthly & annual outside inspections of
equipment and facilities>Materials handling procedure review >Field mapping, signage, & training
• Monthly joint safety meetings continued throughout the period>Back safety >Annual fire safety refresher>Annual operators certification >Cryogenic safety>Site safety update>Rescue team exercises
NUMI
MINOS
DoE Review12/02Page 10
Safety at Soudan
• We have had 4 safety reports at Soudan since the last review>1 lost days incident
• Most serious was a herniated disk while moving steel plates at the assembly workstation
>5 safety reports • 3 near misses
• 2 no list time accident
• Incident rates for project>A reportable incidence rate of 3.1
@ (per 200,000 hours worked, for crew + physicist)
>A lost time incidence rate of 2.5 @
>A lost days incidence rate of 0.5 @
NUMI
MINOS
DoE Review12/02Page 11
Detector operations
• Since the summer we have been collecting data for calibration and cosmic rays
• We have also been working to increase the live time
• Addressing potential hardware impediments>HV monitoring improved and
hardware swaps>Optimizing automatic recovery
hardware/software
• Have made good progress since early spring in increasing live time
0%
10%
20%
30%
40%
50%
60%
70%
80%
Feb-0
2
Mar-
02
Apr-
02
May-0
2
Jun-0
2
Jul-02
Aug-0
2
Sep-0
2
Oct-
02
Nov-0
2
Dec-0
2
Liv
eti
me
-0.20.40.60.81.01.21.41.61.8
Kto
n-m
onth
s (fi
d)
Livetime Exposure
NUMI
MINOS
DoE Review12/02Page 12
Slides in Hand
NUMI
MINOS
DoE Review12/02Page 13
Physicists & Installation
• A total of 900 physicist weeks or 18 physicist years at Soudan on installation tasks
• No safety incidents involving physicists at Soudan!
0
2
4
6
8
10
12
14
16
18
20
A-0
1M
-01
J-01
J-01
A-0
1S
-01
O-0
1N
-01
D-0
1J-
02F
-02
M-0
2A
-02
M-0
2J-
02J-
02A
-02
S-0
2O
-02
N-0
2D
-02
J-03
F-0
3M
-03
A-0
3M
-03
J-03
J-03
A-0
3
Shifters + expertPSL + L2
Monthly averages
Today
NUMI
MINOS
DoE Review12/02Page 14
Laboratory Staff Organization
Lab SupervisorBill Miller
Asst Lab SupervisorSafety OfficerJerry Meier
Crew BossWork station 1Brian Anderson
Crew BossMaterials HandlingSurface Building
Jack Zorman
Materials HandlerSurface Building
WelderDave Bjorgo
Materials HandlerSurface Building
Marvin Jonas
WelderWork Station 1
Dan Marolt
Steel/Scin. AssemblerWork Station 1
Jim Berg
Steel/Scin. AssemblerWork Station 1
Fred Povhe
WelderWork Station 2Tom Poderzay
Steel/Scin. AssemblerWork Station 2
SurveyorDan Harp
Administrative AideEileen Amos
Electronics TechDave Saranen
Steel/Scin. AssemblerWork Station 2
SurveyorBrian LaFrenier
Steel/Scin. AssemblerModule SorterDon Carlson
Day Shift Organization Chart
CDMS ConstructionSupervisorJim Beaty
JanitorNancy Jamnick
Lead Crew BossLab MaintenanceWork Station 2
Curt Lerol
Lab SupervisorBill Miller
Asst Lab SupervisorSafety OfficerJerry Meier
Lead Crew BossAfternoon ShiftBruce Farkas
Materials HandlingSurface Building
Equipment OperatorMike Novack
Materials HandlerSurface Building
Equipment OperatorRyan Martin
Materials HandlerSurface BuildingRandy Johnson
Crew BossWelder
Doug Wiermaa
Materials HandlerPlane Assembler
Gregg Benson
Materials HandlerPlane Assembler
Mike Raj
Plane AssemblerWelder
George Brown
Materials HandlerPlane Assembler
Mike Muhvich
Afternoon Shift Organization Chart