minutes of the 432 meeting of the ... minutes of the 432th i.pdf · 1 common effluent treatment...
TRANSCRIPT
Page 1 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 1 of 49
Minutes of the 432thmeeting of the StateLevelExpertAppraisalCommittee held on 11/09/2018 at
Committee Room, GEER Foundation, Gandhinagar.
The 432thmeeting of the StateLevel ExpertAppraisalCommittee (SEAC) was held on
11thSeptember2018 at Committee Room, GEER foundation, Gandhinagar. Following members
attended the meeting:
1. Dr. Dinesh Misra, Chairman, SEAC
2. Shri S. C. Srivastav, Vice Chairman, SEAC
3. Dr. V. K. Jain, Member, SEAC
4. Shri V. N. Patel, Member, SEAC
5. Shri R. J. Shah, Member, SEAC
6. Shri A. K. Mule, Member, SEAC
The agenda of TOR/Scopingcases and Appraisal was taken up. The applicants made presentations on
the activities to be carried out along with other details furnished in the Form-1, PFR, EIA-EMP reports
and other reports.
6. SIA/GJ/MIS/19756/2017 M/s. Ajrakhpur Hastkala Vikas Sangathan (CETP) Common Plot No. 1 of survey no. 694 of Paddhar-Ajrakhpur, Post: Kukma, Ta.:Bhuj, Dist.: Kutch.
Appraisal
Project / Activity No.: 7(h)
Project status: New
• PP has submitted online application vide no. SIA/GJ/MIS/19756/2017 dated 19/07/2018 for obtaining
Environmental Clearance.
• SEAC has recommended the project to SEIAA and SEIAA has issued TOR to PP vide letter dated
28/09/2017.
• Project proponent has submitted EIA Report prepared by M/s: Shivalik solid waste management Ltd,
based on the TOR issued by SEIAA, Gujarat.
• Public Hearing was conducted by Gujarat Pollution Control Board on 08/05/2018 at project site of
M/s. Ajrakhpur HastkalaVikas Sangathan (CETP) at Common Plot No. 1 of survey no. 694 of
paddhar-Ajrakhpur, kutch.
• This is a new unit proposes for Common Effluent Treatment Plant as tabulated below:
Sr. no.
Treatment Facility Capacity
1 Common Effluent Treatment Plant (CETP) 150 KLD
• The project falls under Category B of project activity 7(h) as per the schedule of EIA Notification
2006.
Page 2 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 2 of 49
• PP was called for presentation in the SEAC meeting dated 11/09/2018.
• Salient features of the project are as under:
S.
No.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores): 1.46Crores
B Total Plot area (sq. meter) 1102.5 Sq. m.(CETP covered area)
Green belt area,/Tree Plantation area (sq. meter) 277 Sq. m.
C Employment generation During construction Phase: 6 persons
During Operational Phase: 4 persons
D Water
i
Source of Water Supply
(GIDC Bore well, Surface water, Tanker supply etc.)
Tankers
Status of permission from the concern authority.
ii Water consumption (KLD)
Category KLD
(A) Domestic 2
(B) Gardening --
(C) Industrial
Process --
Washing --
Boiler --
Cooling --
Others 3
Industrial Total 3
Total (A + B + C) 5
1) Total water requirement for the project:5 KLD
2) Quantity to be recycle: 3 KLD
3) Total fresh water requirement:2 KLD
iii Waste water generation (KLD)
Category Waste water KLD Remarks
(A) Domestic 1.6 Septic tank/ Soak pits
(B) Industrial
Process --
Washing --
Boiler --
Page 3 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 3 of 49
Cooling --
Others --
Total Industrial
waste water
--
Total [A + B] 1.6
-
iv Treatment facility within premises with capacity
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc..
1 Coarse Screen � 60 deg. Inclined to horizon � Made of PP flats of 6 x 30
mm. � Spacing 20 mm center to
center of the bars. � Size: 500 mm X 700 mm
01 Nos.
2 Bar Screen � 60 deg. Inclined to horizon � Made of PP flats of 6 x 30
mm. � Spacing 20 mm center to
center of the bars. � Covered with 10 size SS 304
mesh folding type � Size: 500 mm X 700 mm
01 Nos.
3. Effluent Withdrawal Pump
� Type: Centrifugal, non-clog � Flow rate: 15 m3 /hr � H.P.: 3.0
(1w+1s)=2 Nos.
4. Reaction Tank-1 � Size 2.0M x 1.0M x 1.5 M
01 No.
5. Reaction Tank-2 � Size 4.0M x 1.0M x 1.5 M
01 No.
6. Tube Settler � Dimension ø 4.0 m x 4.0 m height
02 No.
Civil items
S.No
ITEMS PARTICULARS QTY.
1 Equalization Tank-1
� Size: 4 M X 4 M X 3 M (SWD: 01 No
2. Equalization Tank-2
� Size: 7 M X 6 M X 6 M (SWD: 01 No
3. Storage Tank � Size: 6.0M X 4.0M X 3.0M 01 No
4. Sludge Sump � Size: 3.0 M X 3.0 M X 3.5M 01 No
5. Lab, Panel & Office Rooms
� Size: 5.0 M X 4.0 M X 5.5 M 01 No
6. Sludge Drying Beds
� Size: 5 M X 4 M X 1M
01 No
7. Foundation � For tube settlers 01 Lot
Electro-mechanical items
S.No. ITEMS PARTICULARS QTY.
Page 4 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 4 of 49
7. MBBR Cum Aeration Tank
� Size: 7.0M X 3.0M X 4.5 M 01 No.
8. Sludge (Screw) Pump
� Type: Screw pump � Flow rate: 5000 Ltr / hr. � HP: 3.0
01 No.
9. Blower � Type: Twin lobe type � Flow rate: 200 M3/hr � HP: 5.0/ 7.5
2 Nos.
10. Sec. Clarifier � Dimension: ø 4.5 m x 4.0 m height
01 No.
11. Sludge Recycling Pump
� Type: Centrifugal, non-clog type
� Flow rate: 7.5 M3/Hr � H.P.: 2.0
02 Nos.
12. Dosing Tanks � Agitator cum dosing tanks � Size: 2.0m x 1.0 m x 1.0 m
02 Nos.
13. Dosing Pumps � Type: Plunger/Diaphragm � HP: 0.5
4 Nos.
14. Lime Dosing Pump
� Type : Centrifugal � Flow rate : 1000-1500 LPH � Motor H.P. : 1.0
01 No.
15. Filtration Pump � Type centrifugal pumps. � Capacity: 15 M3 /Hr
(1w+1s)=2 Nos.
16. Multigrade Filter (Mgf)
� Dimension: Ø 1.0 X 2.2 M 01 No.
17. Iron Filter (Ir)
� Dimension: Ø 1.2 X 2.2 M 01 No.
19. Filter Press � Plate and frame type � Size = 600 mm x 600 mm
01 No.
20. D.G. Set � 10 KVA
01 No.
21. D.G. Diesel Storage Tank
� MOC: MS 01 No.
22. Lab Equipment Chemicals glassware’s & instrument for testing pH, BOD, COD, TDS & Total suspended solids etc
01 Lot.
23. INSTRUMENTATION
Level Controller
� Type : Fixed, � MOC : SS-316, � SIZE : 6 mm Rod
3 Sets
Electro-Magnetic Flow meter
� MOC : SS-316 flange mounted � Flow rate: 20 M3 /Hr � Dia : 40 mm � Make : Rose mount � With digital display LCD type � Instantaneous & Integral Flow meter
1 No
pH probe 1Nos
Pressure gauges
� Dia 4” dial � Make : H Guru/ waree � 0-5 Kg
6 Nos
Page 5 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 5 of 49
v Mode of Disposal & Final meeting point
Domestic: Septic Tanks
Industrial: The treated waste water proposed to be stored in overhead tank shall be supplied
for its use by member units for washing & flushing purpose.
Vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , Name of
CF
NA
Membership of Common facility (CF)
NA
Vii Reuse/Recycle details (KLD)
The treated waste water proposed to be stored in overhead tank shall be supplied for its use by
member units for washing purpose. Excess treated waste water shall be used for development
and maintenance of Green belt.
E Air
i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
S.
No.
Source of
emission
With Capacity
Stack
Height (meter)
Type of
Fuel
Quantity of
Fuel
MT/Day
Air Pollution
Control
Measures
(APCM)
Type of
emissions
i.e. Air
Pollutants
1
Proposed DG
set of capacity
10 KVA
As per CPCB
Norms <30 mts. Diesal
Depend upon
usage as
standby
Stack with
appropriate
ht.
PM,CO
Nox +HC
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.): NA
-
iii Fugitive emission details with its mitigation measures.As below:
During Construction Phase: Dust will be generated and control by water sprinkling
F Hazardous waste
(as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules
2016.
I S.
no.
Type/Name of
Hazardous
waste
Source of
generation
Category and
Schedule as
per HW Rules.
Quantity
(MT/Annum
)
Disposal Method
1 Chemical
Sludge
Physico-
chemical
treatment
35.5 37.5 kg/day TSDF site
Page 6 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 6 of 49
2 Bio Sludge Biological
treatment
4.5 kg/day To be used as
manure
3 Used oil DG Set 5.1 Depending
upon usage
Registered
recycler & for
lubrication
ii Membership details of TSDF, CHWIF etc.
M/s SaurashtraEnviro Projects Pvt. Ltd, which
is located in Kutch District may be the suitable
place for sludge disposal. A MoU for disposal
of waste will be done prior to start of operation
phase.
Iii Details of Non-Hazardous waste & its disposal
(MSW and others)
Non-Hazardous waste shall be disposed as per
MSW rules.
G Solvent management, VOC emissions etc.
NA
ii VOC emission sources and its mitigation measures
NA
• During the meeting dated 11/09/2018, technical presentation made by project proponent.
• Salient features of the project submitted by PP are as mentioned above.
Observation:
• This proposal is for new CETP at proposed location.
• Total water consumption for CETP operation will be 5 KLD. The treated wastewater from CETP will
be stored in overhead tank and shall be supplied to member units for washing purpose Stand-by D.G.
Set is proposed and diesel will be used as fuel.There will be no process gas emission.
• Hazardous waste management will be as per the HW Rules 2016.
• Proposed CETP is for the treatment of waste water generated from 49 no.s of small & tiny textile
processing units who are engaged in this activity and are clustered around Ajrakhpur which is
popularly known as ‘Ajrakhpur Block Printing Cluster’.
• The proposed CETP is located within the cluster area. The effluent discharge from the participating
units will be taken to the CETP site through 150 mm dia. PVC Pipe, already laid down. The distance
from the nearest unit is 40 meters and 350 meters length is used to take the effluent from furthest
unit.
• This CETP will receive waste water generated from the small textile units. The treated waste water
proposed to be stored in overhead tank shall be supplied for its use by member units for washing
purpose.
• Online monitoring system in line with Central Pollution Control Board (CPCB) guidelines shall be
Page 7 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 7 of 49
installed to monitor flow and TDS.
• The baseline environmental quality has been assessed for various components of the environment
viz. air, noise, water, biological and socioeconomic aspect. The baseline environmental study has
been conducted for the study area of 10 km radial distance from project site for the period Mid-
September 2017 to Mid-December 2017. Ambient Air Quality monitoring was carried out for PM10,
PM2.5, SO2, NOx, C6H6, O3 and CO at eight locations, including the project site. Values conform to
the prescribed standards for Ambient Air Quality. The incremental Ground Level Concentration (GLC)
has been computed using AIRMOD. The resultant concentrations are within the NAAQS. The
modelling study proved that the air emissions from the proposed plant would not affect the ambient
air quality of the region in any significant manner. The ambient air quality around the proposed
project site will remain within the National Ambient Air Quality Standards (NAAQS).
• All the ground water parameter is well within permissible limit.
• Risk assessment including prediction of the worst-case scenario and maximum credible accident
scenarios has been carried out. The detail proposed safeguard measures including On-Site / Off-Site
Emergency Plan has been covered in the RA report.
• Public hearing was conducted at project site dated: 08/05/2018. The major points were discussed
during public hearing is water scarcity.
Discussions & Conclusion:
• Committee noted that the water source is existing bore well. However, they have not taken any
permission from CGWA. Upon asking, PP inform that they will apply to CGWA for ground water
withdrawal and till then they will fulfill their water requirement through tankers from paddhar gram
Panchayatborewell.
• PP has proposed to use excess treated waste water for development and maintenance of Green belt
which was not accepted by the Committee and asked to reuse treated waste water completely within
member units except utilization for green belt & plantation. PP agreed for the same. PP has
submitted characteristics of the combined effluent & treated waste water. CETP inlet norms are also
submitted by PP.
• PP has proposed primary, secondary and tertiary treatment units for treatment of waste water.
• PP has submitted legal undertaking regarding they will not allow any chemical units as a member of
this CETP.
• Committee deliberated on area break up of proposed site, CER, CETP inlet and outlet norms etc.
After deliberation, it was unanimously decided to recommend to SEIAA for grant of
EnvironmentalClearance (EC).
7. SIA/GJ/IND2/19513/2017 M/s. Black Rose Industries Limited
Plot No. 675, Notified GIDC Industrial Estate,
Appraisal
Page 8 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 8 of 49
Jhagadia, Dist – Bharuch, Gujarat, India.
Project / Activity No.: 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/MIS/19513/2017 dated 19/07/2018 for obtaining
Environmental Clearance.
• SEAC has recommended the project to SEIAA and SEIAA has issued TOR to PP vide letter dated
28/09/2017.
• Project proponent has submitted EIA Report prepared by Siddhi Green Excellence Pvt. Ltd.,
Ankleshwarbased on the TOR issued by SEIAA.
• This is an existing unit engaged in Synthetic Organic Chemicals and now proposes for expansion as
tabulated below:
Sr. No.
Name of Products
Existing quantity
Proposed quantity
Total after EC
expansion End Use CAS No. Remarks
MT / Month
1 Acrylamide Aqueous Solution (50%)
1666.66 -- 1666.66 Acrylamide
Polymers etc. 79-06-1 No change
2 Polyacrylamides (Powder)
-- 833.33 833.33
Water treatment,
oilfield chemicals etc.
25987-30-8, 25085-02-3, 69418-26-4, 9003-05-8
New Products
3 Polyacrylamides (Liquid)
-- 3333.33 3333.33 Water
treatment, binders etc.
25987-30-8, 25085-02-3, 33882-67-6, 26100-47-0
4 Polycarboxylates -- 416.67 416.67 Textiles, Paints
etc. 9003-01-4
5 N-Methylol Acrylamide
-- 166.67 166.67 Adhesives, etc. 924-42-5
Total 1666.66 4750.00 6416.66
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 11/09/2018.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores): Proposed: 60 Crores (For expansion only)
(1) Capital cost for EMS (Environmental Management System): 65.2 lakh (2) Recurring cost towards the environmental protection measures: 90 lakh per Annum.
B Total Plot area ( sq. meter) Existing: 34075 Sq.m Proposed: 00 Sq. m. Total: 34075 Sq. m.
Green belt area,/Tree Plantation area ( sq. meter)
Existing: 12540 Sq.m Proposed: 00 Sq.m
Page 9 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 9 of 49
Total: 12540 Sq.m
C Employment generation
1. Direct Existing: 32 nos. company employees + 3 nos. on contract basis Proposed Additional: 45 nos. company employees + 5 nos. contract basis Total After Proposed Expansion: 77 nos. company employees and 8 nos. contract workers
2. Indirect
D Water
i
Source of Water Supply(GIDC Bore well, Surface water, Tanker supply r etc...)
GIDC
Status of permission from the concern authority.
As per CTO, Industrial = 93.5 KL/day Domestic = 7.5 KL/day
Letter from GIDC for supply of additional quantity of water required for expansion is received.
ii Water consumption (KLD)
Type In KL / day Existing GIDC water
consumption granted as
per CTO
Actual additional water
requirement for expansion
Total water requirement
after expansion
1 2 3
(i) Domestic
: 7.500 0.000 7.500
(ii) Industrial
: (a)Process Plant
: 35.660 181.500 217.160
(b) Boiler : 6.380 193.000 199.380
(c) Cooling : 46.500 155.000 201.500
(d) Washing : 1.250 2.000 3.250
(g) Gardening : 16.275 19.900 36.175
Domestic : 7.500 0.000 7.500
Industrial : 106.065 551.400 657.465
Total : 113.565 551.400 664.965
Recycle water for Industrial 10.750 195.000 205.750
Recycle water for Gardening 1.815 4.900 6.715
Total GIDC Water Requirement 101.000 351.500 452.500
1) Total water requirement for the project: 664.965 KLD
2) Quantity to be recycle: Steam condensate recycle- 185.5 KLD to be returned to boiler, RO
permeate- 20.25 KLD to be used for process, washing and utility makeup, MEE condensate water- 6.715 KLD to be used for green belt development and / or utility makeup.
3) Total fresh water requirement: 452.500 KLD
iii Waste water generation (KLD)
Wastewater generation (KLD)
Existing As per CTO
Additional after
expansion
Total after proposed expansion
Disposal Method
Page 10 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 10 of 49
(i) Domestic
: 7.0 0.0 7.0 To Soak pit via Septic tank
(ii) Industrial
: (a) Processing
: 1.5 2.5 4 To ETP (Primary and secondary treatment) and
then to RO (b) Boiler : 0.85 12 12.85
(c) Cooling : 3.5 5 8.5 To RO & MEE plant
(d) Washing : 1.25 0.5 1.75
DOMESTIC : 7.0 0.0 7.0 To Soak pit via Septic tank
INDUSTRIAL : 7.1 20.0 27.1
20.25 (treated effluent from RO & MEE plant for recycling to process), 6.715 (MEE condensate recycling to gardening), 0.135 (MEE sludge to TSDF site)
TOTAL 14.1 20.0 34.1
iv Treatment facility within premises with capacity(ETP,MEE, STP etc).
ETP Capacity (Existing)= 5 KLD MEE Capacity (Existing)= 28.8 m3/day RO capacity (Existing)= 7.2 m3/day
v Mode of Disposal & Final meeting point
Domestic: Disposed off through soak pit via septic tank
Industrial: Unit is ZERO liquid Discharge. 20.25 (treated effluent from RO & MEE plant for recycling to process), 6.715 (MEE condensate recycling to gardening), 0.135 (MEE sludge to TSDF site)
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , name of CF
---
Membership of Common facility (CF) --- vii Reuse/Recycle details (KLD) Refer point no. D (ii) & (iii)
E Air [Existing & Proposed] i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Sr. No.
Stack PCB ID/
Stack Attached to
Capacity/ Remarks
Fuel used & rate of consumption
Air Pollution Control
Measures (APCM)
Stack Height
in meter (From G.L.)
Parameter
s
Permissibl
e Limit
s
Unit
As per Existing CTO
1 (Existi
ng)
54563-Baby
Boiler*
Baby Boiler-I (Cap: 0.4 TPH) & Baby Boiler-II standby ((Cap:
0.4 TPH)
H.S.D (400
Lit/Day)
Adequate Stack
Height with SMF
30 PM SO2
NOX
150
100 50
mg/ Nm
3
ppm ppm
2 (Existi
ng)
90941- D.G. set**
D.G Set (380 KVA)
H.S.D (100
Lit/Day)
Adequate Stack
Height with SMF
9
Page 11 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 11 of 49
Proposed additional
3 (New)
Boilers x 2 nos.
Boilers x 2 nos. (Capacity of Boiler no.1- 2500 kg/hr-.
& Boiler no.2 - 5000 kg/hr)
imported coal –
22 MT/day
Multi Cyclone
Separator, Bag Filter and Water Scrubber to each boiler
30
(common stack)
PM SO2
NOX
150
100 50
mg/ Nm
3
ppm ppm
4 (New)
D.G. Set
D.G. Set (500 KVA)
HSD – 900
lit/day
Adequate Stack
Height with SMF
11
*After proposed Expansion existing small industrial non IBR boiler will be stand by. ** D.G. sets are and shall be used as stand-by power only during power failure.
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.) [Existing & Proposed]
There is no process emission from existing manufacturing process and there shall be no process emissions from proposed new products also. However, as the process involves use of organic nitrogen compounds, as an additional measure towards controlling traces of Hydrocarbons and ammonia during process, it is proposed to install a water scrubber attached to all reactor vents at new production plant. Proposed process stacks
Stack No.
Stack PCB ID / Stack
Attached to
Name of Process / Plant
Air Pollution Control System
Height (m)
Air Emission
Pollutant Permissible
Limit
1 (New)
Reaction Vessels
Production plant -
new
Water Scrubber
15 HC
traces NH3
20 mg/Nm3
175 mg/Nm3
Scrubbing solution shall be sent to ETP for treatment and recycle by RO and MEE. iii Fugitive emission details with its mitigation measures.
[Existing & Proposed]..As below
Page 12 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 12 of 49
Sr. No.
Probable sources
Proposed Control measures
1 Pump glands and seals
All process pumps handling HAP chemicals with low V.Ps will be seal less, ensuring no emissions.
2 Emissions from Bulk Storage Tanks during storage, loading and unloading
Storage tanks storing acrylonitrile and acrylic acid are provided with Breather valve assembly. Set pressure of breather valves is kept above the vapor pressures of stored material to avoid fugitive emission. Tank Pressure equalization shall be applied wherever required Closed transfer system will be provided.
3 During reactions All reactors shall be closed and provided with condenser with required utility. Temperature and pressure conditions shall be stringently controlled as per the process requirement and optimized with low temperature and vacuum conditions wherever feasible.
4 Release from Sampling Lines
Shall be carried out using a closed loop sampling system.
5 Valves, Flanges, plugs and instrument connections
Welded pipes to be used wherever feasible Suitable gasket material to be used Suitable gland packing to be used in valves Periodic inspection and maintenance of pipes and pipe fittings
6 Emissions during filtration process
Closed filtration system to be provided. Workers shall be provided PPEs as per requirement.
7 Drum filling machinery
Closed transfer systems shall be adopted, workers shall be provided PPEs, minimum manual operations
8 Warehouse storing drums and bags
Spillages shall be strictly prevented, proper handling equipment. Roof top ventilators Spill control procedures and equipment shall be provided
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.[Existing & Proposed]
i
Sr. No.
Type of Waste
Source of
Generation
Sch.
Category
(As per Sched
ule Rules-2016)
Quantity MT Per Annum
Facility Mode of
Treatment & Disposal
Existing
Proposed
Total
1
Empty barrels/containers/liners/bags with hazardous
chemicals/wastes
Raw material containers/ Bags
I 33.1 2.01 603.99 606.0
0
Collection, Decontamin
ation, Disposal, Reuse,
Storage, Transportati
on
Disposal by send It to authorized decontamination facility/recycler or
reuse or send back to supplier
Page 13 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 13 of 49
2
Waste Polyacrylam
ide
From producti
on of Polyacrylamides Liquides
& powder
I 34.2 40.1
5 319.85
360.00
Co-processing, Collection, Disposal,
Treatment, Storage,
Transportation
Send it to TSDF of BEIL, Ankleshwar Send for co-processing to RSPL
3
Spent ion exchange
resin containing
toxic metals
DM plant
I 35.2 0.50 5.50 6.00
Collection, Disposal,
Treatment, Storage,
Transportation
Disposal by send it to TSDF of BEIL, Ankleshwar
4
Sludge from ETP
From ETP
I 35.3 0.73
1.10
1.83
Collection, Storage,
Treatment, Transportation, Disposal
Disposal by sent it to TSDF site of M/s. BEIL, Ankleshwar.
5 Sludge from
MEE From MEE
I 35.3 12.7
8 352.23
365.00
Collection, Storage,
Treatment, Transportation, Disposal
Disposal by sent it to TSDF site of M/s. BEIL, Ankleshwar.
6
Spent Carbon or
filter medium
From production of Polyacrylamides Liquides&powde r
I 36.2 71.1
8 84.83 156
Co-processing, Collection,
Incineration, Disposal, Storage,
Transportation
Disposal by incineration in common incinerator of BEIL, Ankleshwar , send it for co-processing to RSPL
7 Used or spent oil
Machinery
I 5.1 1.10 10.905 12.00
Collection, Disposal, Reuse,
Storage, Transportati
on
Disposal by Reuse in plant & machinery as lubricant or sell it to authorized re-refiners/recycler.
Non Hazardous Waste Generation
Sr. No.
Type of Was
te
Category (As Per
Sc)-2016
Quantity (MT/Annum) Source of Generatio
n
Mode of Treatment & Disposal
As per Existing CTO
EC applied for Additional
Qty
Total After EC expansio
n
1 Ash --- --- 1210 1210 From coal combustio
n
To be sold to brick Manufacturers or manufacturers of Cement articles or products
ii Membership details of TSDF, CHWIF etc.
Unit has obtained Letter of acceptance from M/s. Bharuch Enviro Infrastructure Ltd.
Page 14 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 14 of 49
(BEIL) for accepting landfill waste at their TSDF and incinerable waste at CHWIF site at Ankleshwar. Unit is having MoU with M/s. Recycle Solutions Pvt. Ltd., Panoli unit for sending spent carbon and polymer waste for co-processing. Letter of acceptance for additional quantities is also obtained from RSPL
iii Details of Non-Hazardous waste & its disposal (MSW and others)
Fly ash: 1210 MT/Annum shall be sold to brick manufacturers and manufacturers of Cement articles or products
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents.
Solvent Recovery - No solvent is used at site and proposed expansion also doesn’t involve any solvents.
ii VOC emission sources and its mitigation measures Refer point no. E (iii)
• During the meeting dated 11/09/2018, technical presentation made by project proponent.
• At present unit is engaged in manufacturing of organic products for which they have obtained EC
&CC&A from the concern authorities. The proposal is for expansion by addition of new Synthetic
Organic Chemicals.
• Salient features of the project submitted by PP are as mentioned above.
Observation:
• This proposal is for expansion of existing unit and for now proposes a new synthetic organic chemical
product. The earlier unit hasgot EC in 2012 and amended in 2016. Unit has gotCC&A for existing
unit. Copy of EC, EC amendment, CC&A, compliance reports of all is submitted. PP ensured that
there are no court cases pending and no public complaints against the project.
• Total water consumption will be 664.965 KLD. Total wastewater generation will be 27.1 KLD.4 KLD
out of process wastewater and washing will be treated in ETP. Treated water from ETP, cooling and
washing will be goes through RO followed by MEE. The unit will maintain complete ZLD.
• Imported Coal will be used as fuel for proposed boilers.
• Adequate APCM will be provided for proposed process gas emission.
• Hazardous waste management will be adequately provided.
• The baseline environmental quality has been assessed for various components of the environment
viz. air, noise, water, biological and socioeconomic aspect. The baseline environmental study has
been conducted for the study area of 10 km radial distance from project site for the period October
2017 to December 2017. Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2,
NOx, C6H6, NH3, CO and VOC at ten locations, including the project site. Values conform to the
prescribed standards for Ambient Air Quality. The incremental Ground Level Concentration (GLC)
has been computed using AIRMOD. The resultant concentrations are within the NAAQS. The
Page 15 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 15 of 49
modelling study proved that the air emissions from the proposed plant would not affect the ambient
air quality of the region in any significant manner. The ambient air quality around the proposed
project site will remain within the National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident
scenarios has been carried out. The detail proposed safeguard measures including On-Site / Off-Site
Emergency Plan has been covered in the RA report.
Discussions & Conclusion:
• The Certified Compliance Report (CCR) is submitted by RO and it was discussed in detail. PP has
submitted compliance status with respect to non-compliance of CCR which was found satisfactory.
• Committee deliberated on product profile and its use, wastewater management, safety measures.
• Committee asked PP for management of Hazardous waste as per the HW Rules 2016.
• EMP, SCR & CER was discussed in details.
After deliberation, it was unanimously decided to recommend to SEIAA for grant of Environmental
Clearance (EC).
8. SIA/GJ/IND2/28507/2017 M/s. Robin Dyes and Intermediates Pvt. Ltd. Plot No. 810/2, GIDC Estate, Sachin, Ta. Chorasi, Dist: Surat – 394 221, Gujarat
EC Amendment
Project / Activity No.: 5(f)
Project status: Amendment of EC
• SEIAA, Gujarat has accorded Environment Clearance to M/s. Robin Dyes and Intermediates Pvt. Ltd.
vide letter no. SEIAA/GUJ/EC/5(f)/460/2017 Dated: 29/04/2017
• Now, project proponent (PP) has applied online vide proposal no. SIA/GJ/IND2/28507/2017dated
18/07/2018 for Amendment in EC.
• The existing product profile is as per existing EC as tabulated below:
Sr. No.
Name of the Products
CAS no. /CI no.
Existing Quantity
MT/Month
Total Proposed Quantity
MT/Month
End-use of products
1 G-Salt 118-32-1 7.5 35 Dyes
2 R-Salt 148-75-4 -- 15 Dyes
3 Amido G-Acid 86-65-7 -- 35 Dyes
4 K-Acid 118-03-6 -- 30 Dyes
Total 7.5 115
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 11/09/2018.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project
Page 16 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 16 of 49
(Rs. in Crores): Existing: 2.0Crores Proposed: 2.0 Crores Total: 4.0 Crores
1. Capital cost for EMS (Environmental Management System):1.0 Crores
2. Recurring cost towards the environmental protection measures: 1.5 Crores per Annum.
B Total Plot area ( sq. meter) Existing: 4842.3 Sq. m. Proposed: 00 Total: 4842.3 Sq. m.
Green belt area,/Tree Plantation area ( sq. meter) Existing: 00 Proposed: 1600 Sq. m. Total: 1600 Sq. m.
C Employment generation
1. Direct 15
2. Indirect 20
Total 35
D Water
i
Source of Water Supply(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Water Supply
Status of permission from the concern authority.
Company is obtained the permission for water supply from GIDC
ii Water consumption (KLD)
Category
Existing Water Consumption KLD
Total Proposed Water Consumption KLD
(A) Domestic 2.00 4.00
(B) Gardening 0.0 4.00
(C) Industrial
Process 2.00 12.0
Washing 0.00 1.00
Boiler 2.00 5.00 Cooling 0.50 10.00
Others 00 0.3
Industrial Total 4.5 28.3
Total (A + B + C) 6.5 36.3
1) Total water requirement for the project: 41.0 KLD
2) Quantity to be recycle: 0.0 KLD
3) Total fresh water requirement:41.0 KLD
iii Waste water generation (KLD)
-
Category Existing Waste water generation KLD
Total Proposed Waste water generation KLD
(A) Domestic 2.00 4.00 (B) Industrial
Process 2 10
Page 17 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 17 of 49
Washing 00 1
Boiler 00 0.5
Cooling 0.5 0.5 Others 0.25
Total Industrial waste water 2.5 12.75
-
iv Treatment facility with capacity (ETP, CETP, MEE, STP, Spray Dryer etc).
ETP – 10 KL/Day (2 Nos.)
v Mode of Disposal & Final meeting point
Domestic: 4.0 KL/Day
Industrial: 12.75 KL/Day Proposed Total: 6.114 KL/Day (As per EC Amendment) -> Primary treated effluent conforming to CETP inlet norms will be sent to CETP of Ms. GECL for further treatment and disposal. Proposed Total: 6.636 KL/Day (As per EC Amendment) -> Primary treated effluent conforming to CETP inlet norms will be sent to Common MEE facility of Ms. GECL for further treatment and disposal.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , name of CF
Common facility – CETP and Common MEE
Membership of Common facility (CF) CETP – GECL/18-19/11 dated: 06/06/2018
vii Reuse/Recycle details (KLD) 0.00
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Existing:
SR. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 Baby Boiler 30
Agrowaste
2 MT/Month
SPM SO2 Nox
Adequate Stack Height/MCS
2 TFH (200 U)
30 Adequate Stack Height/MCS
3 D. G. Set - Stand By (Capacity: 125
KVA ) 11 LDO 100 Lit/Hr
SPM SO2 NOx
Adequate Stack Height
Additional
SR. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 *Thermopack (600 U)
30
Agrowaste 60
MT/Month
SPM SO2 Nox
Cyclone Separator
2 Hot Air Generator
30 Cyclone
Separator
Page 18 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 18 of 49
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.)
Existing:
Sr. no.
Source of emission
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures (APCM)
1 Reactor - 1 SO2< 40 mg/Nm3
15.0 Two Stage Alkali
Scrubber
2 Reactor - 2 SO2< 40 mg/Nm3
12.0 Two Stage Alkali
Scrubber
-
iii Fugitive emission details with its mitigation measures. As below:
During operation stage, leakage through valves/pumps, leakage and emission from open drum containing chemicals, open feeding, storage tanks, etc. will be major sources of fugitive emissions and VOCs. Excess use of solvent/s may also results fugitive emission from the process vessels.
• Solid raw material charging will be done through closed system.
• Entire process will be carried out in the closed reactors with proper maintenance of pressure
and temperature.
• Close feeding system will be provided for centrifuges. Centrifuge and filtrate tank vents will be
connected to vent chillers.
• Fugitive emission over reactors, formulation areas, centrifuges, chemical loading, transfer
area, will be collected through hoods and ducts by induced draft and controlled by
scrubber/dust collector.
• Emphasis will be given to solvent management/solvent loss prevention.
• Control by having proper scrubbing system.
• Condenser to trap VOC.
• Enclosures to chemical storage area, collection of emission from loading of raw materials in
particular solvents through hoods and ducts by induced draft, and control by scrubber/dust
collector to be ensured.
• Nitrogen blanketing will be provided, besides special care needs to be taken for control in
respect of odorous chemicals.
• Proper maintenance schedule will be adhered to avoid emissions through flange joints, pump
seals etc.
• Minimum number of flanges, joints and valves in pipelines.
• Proper gland packing will be maintained for pumps and valves and to the extent possible
pumps with mechanical seal.
• All Flange joints of the pipe lines which carry solvents will be covered with flange guards.
• All rotating equipments like pumps will be installed with mechanical seals to arrest any sort of
Page 19 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 19 of 49
emissions.
• A regular preventive maintenance schedule will be in place to replace or rectify all gaskets
and joints etc. as a part of ISO systems to ensure no fugitive emissions take place.
• Periodic monitoring of work area will be carried out to check the fugitive emission.
• Solvent tank vents will be connected to vent chillers.
• Stand by pumps will be provided on all scrubbers. Besides, scrubbers are equipped with on-
line pH meter with hooter system for better operational control.
• Regular inspection of floating roof seals and proper preventive maintenance of roofs and
seals for tanks.
• Adequate ventilation will be provided.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.
i
Sr. no.
Type of Hazardous waste
Source of generation
Category and Schedule as per HW Rules.
Existing Quantity (MT/Annum)
Total Proposed Quantity (MT/Annum)
Disposal Method
1 ETP Sludge ETP SCH-I/35.3
120 120 Collection, Storage Transportation and disposal at GPCB approved TSDF site.
2 MEE Salt MEE SCH-I/35.3
36 00
3 Gypsum ETP SCH-I/26.1
500 500
4 Discarded Drums/bags
Raw Material
Storage& Handling
SCH-I/33.1
9.72 9.72 Decontaminate and
Reuse/ Sell to Scrap Vendor
5 Used / Spent Oil
Plant and Machineries
SCH-I/5.1 0.36 0.36 Collection, storage and used as lubricant within the premises / sell to MoEF approved Recycler/
Reprocessors
6 Dil. Sulfuric Acid
Process SCH-I/26.3
3420 3420 Collection, Storage and sell to end user who is having Rules -9 Permission.
Quantity of discarded containers must be in MT/Annum.
ii Membership details of TSDF, CHWIF etc.
Company has membership of TSDF/CHWIF
ii Details of Non-Hazardous waste & its disposal (MSW and others)
There is no generating the non-hazardous waste.
G Solvent management& VOC emissions etc.
i Details of Solvent recovery (As per respective ToR) Company will not use the solvent to
Page 20 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 20 of 49
Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
manufacturing dye intermediates.
ii VOC emission sources and its mitigation measures
Company will not use the solvent to manufacturing dye intermediates.
• During the meeting dated 11/09/2018, technical presentation made by project proponent.
• Salient features of the project submitted by PP are as mentioned above.
Observation:
• Total water consumption will be 41 KLD. Total Industrial wastewater generation will be 12.75
KLD.After amendment 6.114 KLD will be treated by primary treatment and sent to CETP as per the
existing EC condition and remaining 6.636 KLD will be treated by primary treatment and sent to
common MEE of GECL-Sachin.
• Agro waste will be used as fuel for Additional thermo pack and hot air generator.
• MEE will be removed from EC and hence, the MEE salt will be NIL.
• PP has proposed to amend EC conditions as below:
Sr. no.
Condition no. in which changes proposed.
As per EC As per proposed amendment
Justification
1 A.2 (Point No. 16)
Concentrated stream wastewater shall be subjected to MEE (500 Liter/hour) & centrifuge within the factory premises.
Company has obtained the permission to send the treated neutralized effluent into Common MEE facility, M/s. GECL, Sachin for concentrated wastewater. So now Company proposes Effluent treatment Plant (Primary treatment) to neutralize the effluent then neutralized effluent will send the treated neutralized effluent into Common MEE facility, M/s. GECL, Sachin.
Operation cost of own MEE is higher than common MEE.
2 A.2 (Point No. 17)
In case of waste water treated with in house MEE, Condensate (5 KL/Day) will be reused for process and fresh water requirement shall not exceed 35 KL/Day in that case.
Company has obtained the permission to send the treated neutralized effluent into Common MEE facility, M/s. GECL, Sachin for concentrated wastewater. So now Company proposes Effluent treatment Plant (Primary treatment) to neutralize the effluent then neutralized effluent will send the treated
Operation cost of own MEE is higher than common MEE.
Page 21 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 21 of 49
neutralized effluent into Common MEE facility, M/s. GECL, Sachin.
Discussions & Conclusion:
• Committee deliberated that existing CETP discharge will be continue as per existing EC and
additional quantity will be sent to common MEE instead of in-house MEE.
After deliberation, it was unanimously decided to consider the project for further consideration only
after satisfactory submission of the following:
1. Treatability and feasibility of the treated wastewater to be discharged to the common MEE.
2. Compliance status of Common MEE facility of M/s: GECL, Sachin w.r.t. existing environmental
conditions. Details of total capacity, spare capacity, compliance of written instructions issued by
GPCB etc. shall be incorporated in compliance report.
9. SIA/GJ/IND2/22382/2017 M/s. CHITANYA LIFE SCIENCE PVT. LTD. Plot No. D2/CH/215, GIDC Industrial Estate, Dahej-2, Tal: Vagra, Dist: Bharuch-392130
EC Amendment
Project / Activity No.: 5(f)
Project status: Amendment of EC
• SEIAA, Gujarat has accorded Environment Clearance to M/s. CHITANYA LIFE SCIENCE PVT.
LTD.vide letter no. SEIAA/GUJ/EC/5(f)/234/2017 Dated: 24/04/2017
• Now, project proponent has applied online vide proposal no. SIA/GJ/IND2/22382/2017dated
18/07/2018 for Amendment in EC.
• The existing product profile is as per existing EC as tabulated below:
Sr. No.
Name of the Products
CAS no. /CI no.
Quantity MT/Month
End-use of products
1 Oxyclozanide 2247- 92-1
150
Treatment and control of gastrointestinal and lung worm
infections in domestic animals like Cattle, Sheep and Goats
2 Pyroxicam 36322- 90-4 Used in veterinary medicine to treat certain neoplasias expressing
cyclooxygenase (COX) receptors, such as bladder, colon and
prostatecancers
3 Tizanidine 64461- 82-1 Used as a muscle relaxant
4 PiperazineHexahydrate
142-63- 2 Anthelmintic
5 Piperazine Citrate 41372- 10-5 Pharma
6 PiperazineAdipate 41372- 10-5 Pharma
7 PiperazineDihydrochloride
110-85- 0 Pharma
8 PiperazinePhosphate
-- Pharma
9 Povidone Iodine 25655- 41-8 Topical antiseptic and anti-infective
Page 22 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 22 of 49
10 Potassium Citrate 6100- 05-6 Alkalinizing agent and antiurolithic
11 Potassium Iodide 7681 -11-0 10 Antifungal, Expectorant and Iodinesupplement
12 Sodium Iodide 7681- 82-5 Expectorant and Iodine supplement
13 Carvedilol 72956- 09-03 0.1 Medicine
14 Olanzapine -- 0.4 Medicine
15 Ondansetron Hydrochloride
99614-01-4 Medicine
16 Pregabaline 148553 -50-8 Medicine
17 Amlodipine Besylate
111470 -99-6 Medicine
18 Glimipride 93479- 97-1 1.0 19 Lacidipine 103890 -78-4 Medicine
20 Venlafaxin Hydrochloride
99300- 78-4 Medicine
21 Losarton Potassium
124750 -99-8 Medicine
22 Lidocaine Hydrochloride
73-78-9 Medicine
23 Glibenclamide 10238- 21-8 7.5 Medicine 24 Niclosamide 50-65-7 Medicine
25 Metaxalone 1665- 48-1 Medicine 26 Benzarone 1477- 19-6 Medicine
27 Benzbromarone 3562- 84-3 Medicine
28 Ethenzamide 2869- 83-2 Medicine 29 Aceclofenac 89796- 99-6 Medicine
30 Pentaprazole Sodium
138786 -67-1 Medicine
Total 169.0
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 11/09/2018.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project (Rs. in Crores): 4.5Crores
1. Capital cost for EMS (Environmental Management System):1.0 Crores
2. Recurring cost towards the environmental protection measures: 1.5 Crores per Annum.
B Total Plot area ( sq. meter) 4842.3 Sq. m. Green belt area,/Tree Plantation area ( sq. meter) 1600 Sq. m.
C Employment generation
1. Direct 12
2. Indirect 25
Total 37
D Water
i
Source of Water Supply(GIDC Bore well, Surface water, Tanker supply etc...)
GIDC Water Supply
Status of permission from the concern authority.
Company is obtained the permission for water supply from GIDC
Page 23 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 23 of 49
ii Water consumption (KLD)
Category
Water Consumption KLD
(A) Domestic 2.00
(B) Gardening 3.00
(C) Industrial
Process 22.50 Washing 2.00
Boiler 5.00 Cooling 6.50
Others Industrial Total 36.00
Total (A + B + C) 41.00
1) Total water requirement for the project: 41.0 KLD
2) Quantity to be recycle: 0.0 KLD
3) Total fresh water requirement:41.0 KLD
iii Waste water generation (KLD)
-
Category KLD
(A) Domestic 1.50
(B) Industrial
Process 18.5
Washing 1.50
Boiler 0.50
Cooling 1.00
Others
Total Industrial waste water 21.50
-
iv Treatment facility with capacity (ETP, CETP, MEE, STP, Spray Dryer etc).
ETP – 25 KL/Day MEE – 20 KL/Day
v Mode of Disposal & Final meeting point Domestic: 1.5 KL/Day
Industrial: 21.50 KL/Day
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , name of CF
Common facility – CETP
Membership of Common facility (CF) CETP vii Reuse/Recycle details (KLD) 0.00
E Air
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
-
SR. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
1 Steam Boiler (3.0TPH)
Common Stack-20
Natural Gas/Agro waste
650SCM/Day/2.0M
T/Day
SPM SO2 Nox
Adequate Stack Height/MCS
Page 24 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 24 of 49
2 Thermic Fluid Heater(1.0 Lac Kcal/Hr.)
Natural Gas/Agro waste
600SCM/Day/1.5 MT/Day
Adequate Stack Height/MCS
3 D.G. Set(50 KVA, Standby) 9 Diesel 10 Lit/Hr
SPM SO2 Nox
Adequate Stack Height
-
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.) -
Sr. no.
Source of emission
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures (APCM)
1 Reactor - 1 HCl
SO2 12.0
WaterScrubber Followed by Alkali Scrubber
2 Reactor - 2 NH3 12.0 Two Stage Water
Scrubber
- iii Fugitive emission details with its mitigation measures.
As below:
During operation stage, leakage through valves/pumps, leakage and emission from open drum containing chemicals, open feeding, storage tanks, etc. will be major sources of fugitive emissions and VOCs. Excess use of solvent/s may also results fugitive emission from the process vessels.
• Solid raw material charging will be done through closed system.
• Entire process will be carried out in the closed reactors with proper maintenance of pressure
and temperature.
• Close feeding system will be provided for centrifuges. Centrifuge and filtrate tank vents will
be connected to vent chillers.
• Fugitive emission over reactors, formulation areas, centrifuges, chemical loading, transfer
area, will be collected through hoods and ducts by induced draft and controlled by
scrubber/dust collector.
• Emphasis will be given to solvent management/solvent loss prevention.
• Control by having proper scrubbing system.
• Condenser to trap VOC.
• Enclosures to chemical storage area, collection of emission from loading of raw materials in
particular solvents through hoods and ducts by induced draft, and control by scrubber/dust
collector to be ensured.
• Nitrogen blanketing will be provided, besides special care needs to be taken for control in
respect of odorous chemicals.
• Proper maintenance schedule will be adhered to avoid emissions through flange joints, pump
seals etc.
• Minimum number of flanges, joints and valves in pipelines.
Page 25 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 25 of 49
• Proper gland packing will be maintained for pumps and valves and to the extent possible
pumps with mechanical seal.
• All Flange joints of the pipe lines which carry solvents will be covered with flange guards.
• All rotating equipments like pumps will be installed with mechanical seals to arrest any sort of
emissions.
• A regular preventive maintenance schedule will be in place to replace or rectify all gaskets
and joints etc. as a part of ISO systems to ensure no fugitive emissions take place.
• Periodic monitoring of work area will be carried out to check the fugitive emission.
• Solvent tank vents will be connected to vent chillers.
• Stand by pumps will be provided on all scrubbers. Besides, scrubbers are equipped with on-
line pH meter with hooter system for better operational control.
• Regular inspection of floating roof seals and proper preventive maintenance of roofs and
seals for tanks.
• Adequate ventilation will be provided.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.
i
Sr. no.
Type of Hazardous waste
Source of generation
Category and Schedule as per HW Rules.
Quantity (MT/Annum)
Disposal Method
1 ETP Sludge ETP 35.3 24 Collection, Storage Transportation and disposal at GPCB approved TSDF site.
2 MEE Salt MEE 35.3 187.2
3 Inorganic Process
Waste
Process 28.1 142.5
4 Spent Carbon
Process 28.2 32.4 Collection, Storage Transportation and disposal at Cement industries for Co-Processing or CHWIF
site.
5 Organic process waste
Process 28.1 3
6 Distillation Residue
Distillation 20.3 351
7 Spent Solvent
Process 28.5 7420 Collection, Storage and Reuse within premises/sell to end user who is having Rules -9 Permission.
8 Discarded Drums/bags
Raw Material
Storage & Handling
33.1 9 Decontaminate and
Reuse/ Sell to Scrap Vendor
9 Used / Spent Oil
Plant and Machineries
5.1 0.6 Collection, storage and used as lubricant within the premises / sell to MoEF approved Recycler/Reprocessors
Page 26 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 26 of 49
10
Sodium Bisulphite
Process & Scrubber
28.1 1620 Collection, Storage and sell to end user who is having Rules -9 Permission.
11 Phthalyl Hydrazine
Process 28.1 6
12 Liquor Ammonia (20%)
Process & Scrubber
28.1 630
ii Membership details of TSDF, CHWIF etc.
Company has membership of TSDF/CHWIF
ii Details of Non-Hazardous waste & its disposal(MSW and others)
There is no generating the non-hazardous waste.
G Solvent management& VOC emissions etc.
i Details of Solvent recovery (As per respective ToR) Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents
• All the solvents shall be directly distilled from product mixes and; if required shall be purified in packed column with the help of reflux and therefore there is no generation of any distillation residue from the solvent distillation.
• The solvent distillation system shall be designed so as to achieve minimum 95% recovery of solvent.
• Pure solvent, crude solvent and distilled (recovered) solvent shall be stored only in storage tanks and we shall not be using drums at any stage in the Solvent Management System.
• Wherever required, the solvents shall be directly pumped into day tanks from the storage tanks and shall be charged into the reactors without involving any manual handling.
• All the pumps shall be mechanical seal type to avoid any leakage of solvent.
• All necessary fire fighting systems shall be provided with alarm system. Flame proof wiring and flame proof electrical accessories shall be provided to avoid any mishap.
• All the storage tank and day tank shall be connected to a vent system through cooling water and chilled brine condensers to prevent loss of solvents in the atmosphere.
• All the distillation column vents will be also connected to cooling water/chilled brine condensers for maximum possible recovery of the solvents.
All the vents will be connected to a common carbon Adsorber for removing traces of solvent from vent gases
ii VOC emission sources and its mitigation measures
Volatile Organic Content Measures: To prevent losses of these solvents in atmosphere, following infrastructure shall be used in addition to LDAR program • Leak Free Pumps for transfer of solvents • MSW Gaskets in solvent pipelines to prevent leakage from flanges
Page 27 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 27 of 49
• Minimum number of flanges, joints and valves in pipelines. • To eliminate chances of leakages from glands of pumps, mechanical seal will be provided at all solvent pumps. • All the rotating equipments like pumps will be installed with Mechanical Seals to arrest any sort of emissions. • Condenser and scrubber post Reactor with cooling arrangement • Enclosures to chemical storage area, collection of emission from loading of raw materials in particular solvents through hoods and ducts by induced draft, and control by scrubber / dust collector to be ensured. • In case the small spillage or leakage observed, first pour the china clay (vermiculate) on material and collect the contaminated china clay (vermiculate) and send to ETP. • If the spillage is of inflammable liquid, switch off all the power supply in the area to prevent Electric Spark. • Two condenser will install with cooling water and chilled brine to recover the solvent. • Primary Condenser HE-01: Cooling Tower water or Chilled water will be used to condense the solvents depend on the vapor pressure at its operating conditions and the non condensed vapors will be condensed in a Secondary Condenser VOC Trap Condenser HE-02: Chilled Brine at -05 0C will be used to trap any traces of Solvent which is slipped from Secondary condenser
• During the meeting dated 11/09/2018, technical presentation made by project proponent.
• Salient features of the project submitted by PP are as mentioned above.
Observation:
• Total water consumption will be 41 KLD. Total Industrial wastewater generation will be 21.5 KLD.
After amendment will be treated by effluent treatment plant followed bysolvent stripper and MEE. The
treated effluent will be discharged through GIDC pipeline into the deep Sea.
• Unit has proposed amendment in EC conditions as below:
Sr. no.
Condition no. in which changes proposed.
As per EC As per proposed amendment
Justification
1 A.2 (Point No. 15)
Final Treated effluent (30 KLD) shall be sent to RO for further treatment. RO
Company has obtained the permission to discharge the treated effluent into deep sea through GIDC pipeline,
Reuse of treated effluent is not suitable in pharma process due to
Page 28 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 28 of 49
Permeate 21.1 KLD shall be reused in industrial activities and RO reject shall be sent to MEE.
So now Company proposes Effluent treatment Plant (Primary, Secondary and tertiary treatment), Solvent Stripper and MEE to treat the effluent then treated effluent will dispose off into deep sea through GIDC pipeline after achieving GPCB norms.
contamination.
2 A.2 (Point No. 16)
Unit shall provide adequate ETP along with RO & MEE system for the treatment of industrial wastewater and to maintain Zero Liquid Discharge (ZLD).
Company has obtained the permission to discharge the treated effluent into deep sea through GIDC pipeline, So now Company proposes Effluent treatment Plant (Primary, Secondary and tertiary treatment), Solvent Stripper and MEE to treat the effluent then treated effluent will dispose off into deep sea through GIDC pipeline after achieving GPCB norms.
Reuse of treated effluent is not suitable in pharma process due to contamination.
Discussions & Conclusion:
• Committee deliberated that existing effluent will be treated in ETP followed by solvent stripper and
MEE as per existing EC and now the treated effluent will be discharge to deep Sea through GIDC
pipeline instead of recycle by RO system.
After deliberation, it was unanimously decided to consider the project for further consideration only
after satisfactory submission of the following:
1. Detailed technical justification for proposed EC amendment in mode of disposal. Revised water
balance diagram considering proposed EC amendment.
2. Adequacy report of proposed ETP to achieve discharge norms for GIDC drainage prescribed by
GPCB. Stage wise characteristic shall be incorporated.
10. SIA/GJ/THE/21296/2017 M/s. Sumeet Industries Ltd. R.S. No. 289, 291, 292 & 304, 304/Plot No.1 & 304/Plot No.2, Village: Karanj, Tehsil: Mandvi, Dist.: Surat, Gujarat
Screening & Scoping
Project / Activity No.: 1(d)
Project status: Expansion
Page 29 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 29 of 49
• This office has received an application vide their online proposal no.SIA/GJ/THE/21296/2017dated
01/01/2018 regarding grant of Terms of Reference [ToR] for preparation of EIA/EMP report.
• Project proponent (PP) has submitted Form-1, PFR and relevant details/information.
• This is an existing unit engaged in Captive Power Plant, yarn manufacturing and now proposes for
expansion for Captive Power plant as tabulated below:
• The project falls under Category B of project activity 1(d) as per the schedule of EIA Notification
2006.
• PP was called for presentation in the SEAC meeting dated 11/09/2018.
• The project proponent along with their expert / consultant M/s. M/s. Aqua Air Environmental
Engineering Pvt. Ltd., Suratattended the meeting and made presentation before the committee.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project Existing: 395.54
SR. NO.
PRODUCT EXISTING ADDIONAL TOTAL
PROPOSED END USE
1. Captive Power plant
Natural Gas Based (Stand By)K 1.0 MW X 1 Nos = 1.0 MW 1.5 MW X 1 Nos = 1.5 MW 2.0 MW X 2 Nos = 4.0 MW 2.0 MW X 1 Nos = 2.0 MW 4.3 MW X 2 Nos = 8.6 MW Furnace Oil Based (operational)K 4.8 MW X 1 Nos = 4.8 MW Total = 21.9 MW
Coal based CPP - 20.0
MW
24.8 MW (FO Based CPP – 4.8 MW + Coal based CPP – 20.0 MW). Company will discontinuous Natural gas base CPP (17.1 MW) after getting EC and CTE of Coal base CPP.
Electricity will be captive consumed.
2. PET Melt Chips 51700 MT/Year
- 51700 MT/Year 48300
MT/Year
Yarn Mfg.
3 Filament Yarn (POY & FDY)
48300 MT/Year
- Weaving Fabric
4 Menthol Products
60.0 MT/Year
-60.0 MT/Year
00 --
5 Waste Yarn 3.0 MT/Year
- 3.0 MT/Year
--
Total
100063 MT/Year & Natural gas base CPP -17.1 MW, FO
Based CPP – 4.8 MW
Coal based CPP - 20.0
MW & -60
MT/Year
100003 MT/Year & Coal based CPP - 20.0 MW, FO
Based CPP – 4.8 MW
Page 30 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 30 of 49
(Rs. in Crores):
Proposed: 72.62 Total: 468.16
B Total Plot area ( sq. meter)
Existing: 35705.22 Sq. m. Proposed: 3556.50 Sq. m. Total: 39261.72 Sq. m.
Green belt area,/Tree Plantation area ( sq. meter)
Existing: 6125 Sq. m. Proposed: 1175 Sq. M. Total: 7300 Sq. m.
C Employment generation Existing: 660 Proposed: 05 Total: 655
D Water
i
Source of Water Supply(GIDC Bore well, Surface water, Tanker supply etc...)
Bore well
Status of permission from the concern authority. Permission under process.
ii Water consumption (KLD)
Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(A) Domestic 15.0 - 15.0 (B) Gardening - 24.0 24.0
Industrial
Process - - -
Washing 7.0 - 7.0
Boiler 8.0 230.0 238.0 Cooling 93.0 157.0 250.0
Others - - - Industrial Total 108.0 387 495
Grand Total (A+B+C) 123.0 411.0 534.0
1) Total water requirement for the project: 534.0 KLD
2) Quantity to be recycle: 262.0 KLD
3) Total fresh water requirement: 272.0 KLD
iii Waste water generation (KLD)
Category Existing KLD
Proposed (Additional) KLD
Total after Expansion KLD
Remarks
(A) Domestic 8.0 - 8.0
Industrial
Process 36.0 - 36.0
Conc. Stream Allow in MEE
Washing 7.0 - 7.0 Dilute stream allow in ETP & RO.
Boiler 6.0 174.0 180.0
Cooling 41.0 4.0 45.0
Others - - -
Total Industrial waste water
90.0 178.0 268
-
Page 31 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 31 of 49
iv Treatment facility within premises with capacity [ETP (Primary, Secondary, Tertiary),MEE, Stripper, Spray Dryer, STP etc].
MEE capacity-100 KLD ETP -I (Low COD & TDS) = 142 KLD ETP-II (High TDS) = 36 KLD
v Mode of Disposal & Final meeting point Domestic: Sock pit /septic tank
Industrial: Zero Liquid Discharge
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc. , name of CF
Not Applicable
Membership of CF Not Applicable
vii Reuse/Recycle details (KLD) 262 KLD (RO permeate-182 KLD & MEE Condensate-80 KLD) will be reuse for cooling purpose.
E Air[Existing & Proposed]
i Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
-
SR. no.
Source of emission
With Capacity
Stack Height (meter)
Type of Fuel
Quantity of Fuel MT/Day
Type of emissions
i.e. Air Pollutants
Air Pollution Control Measures
(APCM)
EXISTING
1 Coal fire TFH
(7500 U) 32
Coal 33
MT/day
PM
SO2
NOx
ESP
2 Steam Boiler
(1TPH) stand by 30
MCS + Teema Cyclone Separator
3 Gas fire TFH
(4000 U) X 2 Nos. 32
Natural Gas
15,000 SM3/day
-
4
Gas Generator Sets
[1.0 MW, 1.5MW, 2.0 MW x (2 Nos.)]
Total: 6.5 MW 18
(each GG Set)
CPP
Natural Gas
17.1 MW
80,000 SM3/day
-
-
5
Gas Generator Sets
[2.0 MW, 4.3MW, 2.0 MW x (2 Nos.)]
Total: 10.6 MW
-
6 4.8 MW Power
Plant(FO BASED) 30
Furnace Oil
22 M3/day
-
PROPOSED
1
Steam Boiler (85 TPH) for Coal
Based captive Power Plant
(20 MW)
80 Coal 400
MT/Day
PM SO2 NOx
Air Pre-heater, Economizer and
Electro Static Precipitator
-Note: Gas generator sets will be discontinues after getting EC and CTE of Coal based CPP.
ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.) [Existing & Proposed]
- There is no Process Gas Emission
iii Fugitive emission details with its mitigation measures. [Existing & Proposed]WAs below:
- Minimum joints & Flange
Page 32 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 32 of 49
- Close process, Auto handling for charging material - Pumps with double mechanical seal, Proper ventilation Leak detection /checking - Regular maintenance & monitoring
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.[Existing & Proposed]
i
Sr. no
Type/Name of
Hazardous waste
Source of generatio
n
Category and
Schedule as
per HW Rules.
Quantity (MT/Annum)
Disposal Method Existing
Proposed
Total
1 ETP
Sludge ETP plant 34.3 25 12 37
Collection, storage, transportation and disposal at TSDF site M/s. BEIL, Ankleshwar
2
Discarded
Containers
Raw Material Storage
33.3 3000
No./Year
- 3000
No./Year
Collection, storage decontamination and disposal by selling to registered re-refiners.
3 Used Oil
Machineries
&equipments
5.1 5000
Liter/Year
1000 Liter/Ye
ar
6000 Liter/Ye
ar
Collection, storage, transportation and
disposal by reuse or selling to registered refiners approved by
GPCB.
4 MEE Salt MEE plant
34.3 - 12
MT/Year
12 MT/Yea
r
Collection, storage, transportation and
disposal at TSDF site M/s. BEIL, Ankleshwar
NON HAZARDOUS
1 Fly Ash - - 55
MT/Year
55 MT/Yea
r
Bricks manufacturing plant within factory premises & sell to National Highway
Authority of India (NHAI) for road construction.
ii Membership details of TSDF, CHWIF etc. TSDF BEIL
iii Details of Non-Hazardous waste & its disposal (MSW and others)
Fly Ash = 55 MT/Year Mode of Disposal: Bricks manufacturing plant within factory premises & sell to National Highway Authority of India (NHAI) for road construction.
G Solvent management, VOC emissions etc. i Types of solvents, Details of Solvent recovery, %
recovery. reuse of recovered Solvents NA
ii VOC emission sources and its mitigation measures - Minimum joints & Flange - Close process - Proper ventilation - Leak detection /checking - Regular maintenance & monitoring
Page 33 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 33 of 49
• Earlier the PP was called in SEAC Meeting dated: 08/03/2018. Technical presentation was made by
the project proponent. Technical presentation was made by the project proponent. Committee
observed that this project is for expansion in Captive Power plant, however, water balance and
management is submitted considering entire project. Committee was of the view that PP shall submit
all the details pertaining to Power plant only. Issues regarding compliance of existing unit, Coal
handling, source of water etc. have been discussed during the meeting. PP informed that they will
submit revised proposal with revised water balance and relevant details. Committee found that PP
has not covered important issues regarding impact on surrounding area due to proposed project in
proposed ToR. Looking to the poor presentation by environmental consultant, Committee defer the
proposal and decided to consider the case only after satisfactory submission of Revised
proposal with Revised Form & PFR.
• During the meeting dated 11/09/2018, technical presentation made by project proponent.
• At present unit is engaged in manufacturing of yarn and fabric products with captive power plant for
which they have obtained EC &CC&A. The proposal is for expansion by addition of new 20 MW coal
based CPP.
• Salient features of the project submitted by PP are as mentioned above.
Observation:
• This proposal is for expansion of existing unit and for now proposes a new CPP. This unit is having
validEC &CC&A for existing unit. Copy of EC, CC&A, CC&A compliance report is submitted. The
compliance of EC from regional office will be submitted during EIA. PP ensured that there are no
court cases pending and no public complaints against the project.
• Total water consumption will be 534 KLD. Total wastewater generation will be 268 KLD. Diluted
stream will be treated in ETP-1 followed by RO and concentrated stream will be evaporated in MEE.
RO permeate and MEE condensate will be reused for cooling purpose. Thus, unit will maintain
complete Zero Liquid Discharge.
• 85 TPH coal based boiler will be added for proposed CPP. Air pre heater, economizer and ESP will
be provided for the proposed boiler.
• Hazardous waste management will be adequately provided.
Discussions & Conclusion:
• Committee deliberate that EC compliance report submitted by PP was discussed, 3 points were
partially complied and 1 point is not complied. PP has committed to comply the condition.
• Committee noted that adequate Coal handling will be provided.
• EMP, SCR & CER was discussed in details.
After deliberation, it was unanimously decided to recommend to SEIAA to grant for Terms of
Reference:
1. Executive summary of the project – giving a prima facie idea of the objectives of theproposal, use of
resources, justification, etc. In addition, it should provide a compilation of EIA report including EMP
Page 34 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 34 of 49
and the post-project monitoring plan in brief.
2. Present land use pattern of the study area shall be given based on satellite imagery.
3. Geological features and geo-hydrological status of the study area.
4. Demarcationof proposed activities in lay out of the existing premises. Provision of continuous
unobstructed peripheral open path within the projectareafor unobstructed easy movement of the
emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.
5. Explore the possibilities for Air cooled condensers instead of Water cooled condensers in order to
reduce the raw water requirement.
6. Technical details of the proposedpowerplant along with details of strategyforimplementation reuse /
recycle and other cleanerproductionoptionsforreduction of wastes. Generation of waste gases and
utilization of waste heat have tobeset out.
7. Assessment of source of the water supply with adequacy of the same to meet with the
requirementsfor the project. Copy of letter of permission obtained from the concerned authority
forsupply of additional raw water for the proposed activities.
8. Action plan for complete ZLD for existing as well as proposed CPP.
9. Application wise break-up of treated effluent quantity to be recycled / reused in various applications
like cooling purpose etc.
10. Detailed water balance (including reuse-recycle, if any) along with qualitative and quantitativeanalysis
of each wastestreamtobe generated from all sources including Boilers, Cooling Towers, process,
washing etc. Details of methods to be adopted for the water conservation.
11. Details of the treatment facilities proposed for the effluent to be generated from the power plant
including existing project. Details of the ETP units including its capacity (KL/day), size of each unit,
retention time and other technical parameters and details about up-gradation in the existing ETP (if
any proposed) to take care of the wastewater to be generated from the proposed activities.
12. Characteristics of untreated and treated wastewater. A detailedeffluenttreatability study vis-à-vis the
adequacy and efficacy of the treatment facilities proposed for the wastewater tobe generated along
with adequacy and efficacy report. The characteristic on which treatability is based shall also be
stated.
13. Site-specific meteorological data including temperature, relative humidity, hourly wind speed and
directionand rainfall shall be provided.
14. Anticipated environmental impacts due to the proposed project/production may be evaluated for
significance and based on corresponding likely impacts VECs (Valued Environmental Components)
may be identified. Baseline studies may be conducted within the study area of 10 km for all the
concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to
identify mitigation measures.
15. One complete season base line ambient air quality data (except monsoon) to be given along with the
dates of monitoring. The parameters to be covered shall be in accordance with the revised National
Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring
stations should be so decided so as to take into consideration the pre-dominant downwind direction,
population zone and sensitive receptors. There should be at least one monitoring station in the
upwind direction. There should be at least one monitoring station in the pre dominant downwind
direction at a location where maximum ground level concentration is likely to occur.
16. Impact of the project on the AAQ of the area. Details of the model used and the input parameters
used for modeling should be provided. The air quality contours may be plotted on a location map
Page 35 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 35 of 49
showing the location of project site, habitation, sensitive receptors, if any. The wind roses should
also be shown on this map. Air quality modeling to be carried out considering the partial and
complete failure of the ESP.
17. Quantity of the fuel requirement, its source and transportation, storage, handling and management
along with the environmental management to beadoptedfor this. Fuel analysis to be provided
(sulphur, ash content and heavy metals including Pb, Cr, As and Hg).
18. A confirmed fuel linkage along with the supportive documents of long term supply of coal for the
project requirements should be provided.
19. Specific details of (i) Details of the utilities required (ii) Quantity and characteristics of each fuel along
with analysisreport and its source (iii) Flue gas emission ratefrom each utility (iv) Air PollutionControl
Measures proposedto each of the utility along with its adequacy.
20. Technical details of ESP proposedtobeinstalled as air pollutioncontrolsystem along with its adequacy,
details of its operational controls with DCS, system for online monitoring of the pollutants from the
stacketc. Details of provisions to be kept in ESP to ensure that in any casethe air emission does not
cross the GPCB norms including provision of standby field in the ESP, preventive maintenance,
failure / tripping control system, guaranteefrom the ESP supplier, alternative arrangements in case of
the failure / tripping of the ESP etc. ESP should be designed to achieve GPCB norms at the outlet.
21. List of all the sources of fugitive emission. Detailedplanforprevention and control of fugitive emission /
dusting at each and every stage of fuel handling including unloading / loading at port,
transportationfrom port toplant, unloading / loading / stacking / conveyance / transfer at plant etc.
Detailed specifications and schematicdiagram of water sprinkling system including number of
sprinklers to be installed, pipe diameter and nozzle diameter of the sprinklers, quantity of water to be
consumed by sprinklers etc.
22. Impact on localtransportation infrastructuredueto the project such as transportation of fuel, ash etc.
Base line status of the existing traffic, projected increase in truck traffic as a result of the project in the
present road network, impact on it due to the project activities, carrying capacity of the existing roads
and whether it is capable of handling the increased load. Arrangement for improving the infrastructure
like road etc. if any should be covered. Whether any additional infrastructure would need to be
constructed and the agency responsible for the same with time frame.
23. Details and time bound program for installation of online monitoring system in the existing as well as
proposed plants for monitoring of the pollutants from the stacks and process vents with a
softwareand an arrangement to reflect the online monitored data on the company's server, which can
be accessed by the GPCB on real time basis.
24. Provision of Continuous Ambient Air Quality Monitoring Station [CAAQMS] within premises, with an
arrangement to reflect monitored data on the company’s server, which can be accessed by the
GPCB on real time basis.
25. Details of measures proposed for the noise pollution abatement and its monitoring.
26. Details of management of the hazardous wastes tobe generated from the project stating detail of
storageareafor each type of waste, its handling, its utilization and disposal etc. How the manual
handling of the hazardous wastes will be minimized.
27. Detailed plan of ash evacuation, handling, storage and utilization should be provided. Undertaking
stating that ash pond shall not be constructed and it shall be stored in closed silos only should be
incorporated.
28. Details of seismic design aspects to be adhered to in the project.
Page 36 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 36 of 49
29. Technical details of conveyor belts and mitigation measures toensure that there will be no dust
emission from conveyor belts.
30. Details of proposed disposal of solid wastes that may generate due to spillage of materials.
31. Specific safety measures proposed at storage yard / warehouse and conveyor belts.
32. Details of firefighting system including provision for flame detectors, temperature actuated heat
detectors with alarms, automatic sprinkler system, location of fire water tanks & capacity, separate
power system for firefighting, details of qualified and trained fire personnel& their job specifications,
nearest fire station&timerequired to reach the proposed site. Submitlinediagram of the fire hydrant
network.
33. Copy of membership certificate of Common Environmental Infrastructure like TSDF, if any taken,
should be incorporated.
34. Details of 100% fly ash utilization plan as per latest fly ash Utilization. Notification of GOI along with
firm agreements / MoU with contracting parties including other usages etc. shall be submitted. The
plan shall also include disposal method / mechanism of bottom ash.
35. A detailed EMP including the protection and mitigation measures for impact on human health and
environment as well as detailed monitoring plan and environmental management shall proposed for
implementation and monitoring of EMP. The EMP should also include the concept of waste-
minimization, recycle/reuse/recover techniques, energy conservation, and natural resource
conservation. Total capital cost and recurring cost/annum earmarkedforenvironmentpollution control
measures.
36. Occupational health impacts on the workers and mitigation measures proposed to avoid the human
health hazards along with the personal protective equipment to be provided to the workers. Provision
of industrial hygienist and monitoring of the occupational injury to workers aswell as impact on the
workers. Plan forperiodicmedical checkup of the workers exposed. Details of work zone ambient air
quality monitoring plan as per Gujarat Factories Rules.
37. Risk assessment including prediction of the worst-case scenario and maximum credible accident
scenario related to fire and explosion issues due to storage and use of fuel should be carried out.
The worst-case scenario should take into account the maximum inventory of storage at site at any
point in time. The risk contours should be plotted on the plant layout map clearly showing which of
the activities would be affected in case of an accident taking place. Based on the same, proposed
safeguard measures including On-Site / Off-Site emergency plan should be provided. Measures to
guard against fire hazards including details of automatic fire detection and controlsystem&detailed
fire control plan showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump,
toxic gas detectors etc. should also be provided.
38. Provisions for water supply, fuel (kerosene or cooking gas), lighting, sanitation etc. to the construction
work force so as to avoid felling of trees/mangroves and pollution of water and the surroundings.
Details of personal protective equipments to be provided to construction workers at the site.
39. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,
manufacturing utility staff for safety related measures.
40. Public hearing shall be carried out as per the MoEFCC’s OM dated 04/04/2016. A tabular chart for
the issues raised and addressed during public hearing/consultation and commitment of the project
proponent on the same should be provided. An actionplanto address the issues raised during public
hearing and the necessary allocation of funds for the same should be provided.
41. Detailed five year greenbelt development program including annual budget, types &number of trees
Page 37 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 37 of 49
to be planted, area under green belt development [with map], budgetary outlay; along with
commitment of the management to carry out the tree plantation activities outside the premises at
appropriate places in the nearby areas and elsewhere.
42. Proposal for socio-economic development activities including community welfare program most
useful in the projectareafor the overallimprovement of the environment. Submit a detailed plan for
social corporate responsibilities, with appropriate budgetary provisions for the next five years and
activities proposed to be carried out; specific to the current demographic status of the area.
43. Plan forcompliance of the EP Rules and CREP guidelinesfor the proposedpower plant.
44. Compliance status of the existing unit with respect to various conditions given in the Environmental
Clearance and CC&A orders obtained for the existing plants.
45. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure
notices etc. served by the GPCB to the existing unit in last three years and actions taken then after
for prevention of pollution.
46. Copy of Environmental Clearance obtained for the existing project and a certified report of the status
of compliance of the conditions stipulated in the environmental clearance for the existing operation of
the project by the Regional Office of the MoEF&CC.
47. Details of fatal / non-fatal accidents, loss of life or man hours, if any, occurred in the existing unit in
last three years and measures proposed to be taken for avoiding reoccurrence of such accidents in
future.
48. Any litigation pending against the project and / or any direction / order passed by any Court of Law
against the project, if so, details thereof.
49. Does the company have a well laid down Environment Policy approved by its Board of Directors? If
so, it may be detailed in the EIA report. Does the Environment Policy prescribe for standard operating
process / procedures to bring into focus any infringement / deviation / violation of the environmental
or forest norms / conditions? If so, it may be detailed in the EIA.
50. What is the hierarchical system or administrative order of the company to deal with the environmental
issues and for ensuring compliance with the EC conditions. Details of this system may be given.
51. Does the company have a system of reporting of non-compliances / violations of environmental
norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This
reporting mechanism should be detailed in the EIA Report.
52. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be
incorporated in the EIA Report.
53. An undertaking by the Project Proponent on the ownership of the EIA report as per the MoEF&CC
OM dated 05/10/2011 and an undertaking by the Consultant regarding the prescribed TORs have
been complied with and the data submitted is factually correct as per the MoEF&CC OM dated
04/08/2009.
54. All documents to be properly referenced with index and continuous page numbering.
55. A tabular chart for the issues raised and addressed during public hearing/consultation and
commitment of the project proponent on the same should be provided. An action plan to address the
issues raised during public hearing and the necessary allocation of funds for the same should be
provided.
56. A tabular chart with index for point-wise compliance of above.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
Page 38 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 38 of 49
MoEFCC’s sector specific EIA Manual for ‘Thermal Power Plants’ shall be considered as generic TORs for
preparation of the EIA report in addition to all the relevant information as per the generic structure of EIA
given in Appendix III in the EIA Notification, 2006.
The draft EIA report shall be submitted to the Gujarat Pollution Control Board for conducting the
public consultation process as per the provisions of the EIA Notification, 2006.
The project proponent shall have to apply for Environmental clearance through online portal
http://environmentclearance.nic.in/along with final EIA report.
Validity of ToR:
• The ToRs prescribed for the project will be valid for a period of three years for submission of
EIA & EMP report. ToR will lapse after three years from the date of issue.
• The period of validity could be extended for a maximum period of one year provided an
application is made by the applicant to the Regulatory Authority, at least three months before
the expiry of valid period together with an updated Form-I, based on proper justification and
also recommendation of the SEAC.
•
11. SIA/GJ/IND2/18911/2017 M/s. JembyChem Limited. Plot No. C-1/335, 336,337, GIDC Estate, Phase-II, Vatva, Ahmedabad
Appraisal
Project / Activity No.: 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/18911/2017dated 10/11/2017 for obtaining
Environmental Clearance.
• SEAC has recommended TOR to SEIAA and SEIAA has issued TOR to PP vide letter dated
30/04/2017.
• Project proponent has submitted EIA Report prepared by M/s: SanEnvirotech Pvt. Ltd., Ahmedabad;
based on the TOR issued by SEIAA.
• This is an existing unit engaged in Synthetic Organic Chemicals and now proposes for expansion as
tabulated below:
Sr. no.
Name of the Products
CAS no. Quantity (MT/Month) End-use of the products Existing Proposed Total
1 Sulpho Tobias Acid 171570-11-9 2 23 25
2 J-Acid 87-02-5 2.528 47.472 50
3 J-Acid derivatives 12.67 87.33 100
1. N-Acetyl J-Acid 6334-97-0 2. N-Methyl J-Acid 22346-43-6
3. N-Benzoyl J-Acid 132-87-6 4. N-Phenyl J-Acid 119-40-4
4 RW-Acid (Di-J Acid) 87-03-6 10 10
5 Sulpho J- Acid 6535-70-2 10 10
6 N-Methyl Gamma Acid
6259-53-9 00 05 05
Total 17.198 182.802 200
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Page 39 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 39 of 49
• PP was called for presentation in the SEAC meeting dated 25/05/2018.
• Salient features of the project are as under:
Sr. no.
Particulars Details
A Total cost of Proposed Project
(Rs. in Crores):
Existing: 2.5 Crores Proposed: 1.5 Crores Total: 4.0 Crores
(3) Capital cost for EMS (Environmental Management System): 0.4 Crores
(4) Recurring cost towards the environmental protection measures: 0.5 Crores per Annum.
B Total Plot area ( sq. meter)
Existing: 2212.0 Sq. m. Proposed: --- Sq. m. Total: 2212.0 Sq. m.
Green belt area,/Tree Plantation area (sq. meter)
Existing: 200 Sq. m. Proposed: 415 Sq. m. Total: 615 Sq. m.
C Employment generation
3. Direct Existing: 40 Proposed: 15 Total: 55
4. Indirect Existing: Proposed: Total:
D Water
I
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply r etc...)
GIDC water supply
Status of permission from the concern authority. Permission obtained from GIDC. ii Water consumption (KLD)
Existing KLD
Proposed (Additional)
KLD
Total after Expansion
KLD
Remarks
(A) Domestic 2.5 2.5 5.0
(B) Gardening 1.0 4.0 5.0
Industrial Process 19.0 26.0 45.0
Washing 1.5 18.5 20.0 Boiler 1.0 9.0 10.0
Cooling 9.0 6.0 15.0 Others -- 5.0 5.0
Industrial Total 30.5 64.5 95.0
Grand Total (A+B+C) 34.0 71.0 105.0
1) Total water requirement for the project: 105 KLD
2) Quantity to be recycle: ---
3) Total fresh water requirement: 105 KLD
iii Waste water generation (KLD)
Category Existing KLD
Proposed (Additional)
KLD
Total after Expansion
KLD
Remarks
(A) Domestic 2.0 1.0 3.0
Page 40 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 40 of 49
Industrial
Process 16.0 52.0 68.0
Washing 15.0 5.0 20.0 Boiler 0.5 0.5 1.0
Cooling 0.5 4.5 5.0 Others (water
treatment) -- 5.0 5.0
Total Industrial waste water
32.0 67.0 99.0
Total (A+B) 34.0 68.0 102.0
- iv Treatment facility within premises with capacity [For existing and Proposed]
[In-house ETP (Primary, Secondary, Tertiary), MEE, Stripper, Spray Dryer, STP etc. ETP1 (Dilute stream): 50 m3/day having primary & tertiary treatment units.
ETP2 (Concentrated stream): 100 m3/day having primary treatment units.
v Mode of Disposal & Final meeting point
Domestic: Soak pit
Industrial: 24.0 KLD Dilute Sulphuric Acid will be sent to Novel Spent Acid Management, Vatva for reuse by actual users or for treatment; 68.0 KLD after primary treatment will be sent for common MEE/evaporator/spray dryer to avoid load on CETP; 31.0 KLD dilute effluent from washing and utilities will be treated in ETP and after achieving CETP inlet norms sent to CETP-GESCSL, Vatva for further treatment and final disposal.
vi In case of Common facility (CF) like CETP, Common Spray dryer, Common MEE etc., name of CF
CETP: GESCSL, Vatva Common MEE/evaporator/ spray dryer
• Sanand Eco Project Ltd.,Sanand
• GESCSL, Vatva
• Society for Clean Earth, Vatva
• Society for Clean and Green Environment., Naroda Novel Spent Acid Management, Vatva
Membership of Common facility (CF)
Attached as Annexure-V of EIA report.
vii Reuse/Recycle details (KLD)
--
E Air [Existing & Proposed]
I Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
Existing & Proposed
-
Sr.
no.
Source of emission
With Capacity e.g. Boiler (8
TPH)
Stack Heigh
t (mete
r)
Type of fuel
Quantity of Fuel
MT/Day
Type of emissions i.e. Air Pollutants
Air Pollution Control
Measures (APCM)
Existing
1. Steam Boiler* (0.6 TPH)
15 Bio fuel 2.0 MT/da
SPM SO2
--
Page 41 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 41 of 49
y NOx
2. Thermic Fluid Heater* (4.0 lakhs kcal/hr.)
15 Bio fuel SPM SO2 NOx
--
3. D G set (125 kVA)
11 Diesel 30 lit/hr.
Proposed scenario after expansion
1. Steam Boiler (1.0 TPH)
15 Bio fuel (Briquett
e)
4 MT/da
y
SPM SO2 NOx
Cyclone separator
2. Thermic Fluid Heater (10.0 lakhs kcal/hr.)
15 Bio fuel (Briquett
e)
6.5 MT/da
y
Multi Cyclone separator
3 D G set (125 kVA)
11 Diesel 30 lit/hr
Adequate stack height
* Existing boiler & TFH with capacity of 0.6 TPH &4.0 lakhs kcal/hr. will be dismantled after expansion and unit will install boiler of 1 TPH and TFH of 10.0 lakhs kcal/hr.
Ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.) [Existing & Proposed]
-
Sr. no.
Source of
emission
Type of emission
Stack/Vent Height (meter)
Air Pollution Control Measures (APCM)
Existing
1 Reaction Vessels
SO2<40 mg/Nm3 15 Alkali Scrubber (Ventury + Packed column)
Proposed Addition
1 Reaction Vessels
SO2<40 mg/Nm3
15 Alkali Scrubber (Ventury + Packed column)
-
Iii Fugitive emission details with its mitigation measures. As below
To control fugitive emission, following steps will be implemented:
• Entire process will be carried out in closed reactors.
• Pneumatically transfer of liquid raw material in rector.
• Raw material will be stored in the covered structure.
• Regular maintenance of valves, pipes etc.
• PPEs will be provided to the workers.
• Frequent work area monitoring will be done ensure fugitive emissions level.
• Greenbelt will be developed around the plant to arrest the fugitive emission.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016.Existing & Proposed
I
Sr.
no.
Type/Name of
Hazardous waste
Source of
generation
Category and
Schedule as
per HW Rules
Quantity (MT/Annum)
Disposal Method
Existing Propose
d
Total
1 ETP ETP 35.3 40 250 290 Sold to cement
Page 42 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 42 of 49
sludge MT/month
MT/month
MT/month
manufacturer or Disposal to TSDF site.
2 Discarded containers/ barrels/ liners
RM storage
and packaging area
33.1 12 nos./mo
nth Liner-8 kg/mont
h
30 nos./mo
nth Liner-50 kg/mont
h
42 nos./mo
nth Liner-58 kg/mont
h
Being used for packing of ETP sludge in case of excess it will be sold to approved recyclers.
3 Used Lubricating Oil
D.G. set,
machinery
5.1 200 Lt/yr.
200 Lt/yr.
400 Lt/yr.
It will be sold to approve recycler with CPCB.
4 Spent Sulphuric Acid (24%-65%)
Process 26.3 -- 1222 Kl/month
1222 Kl/mont
h
Collection, storage and partial reuse in-house and balance qty. sent to Novel spent management or actual users under Rule-9 of Haz. rules, 2016
5 Sodium Bi Sulfite (40-45%)
Process B(15) 45 Kl/month
345 Kl/month
390 Kl/mont
h
Collection, storage and reuse in-house
ii Membership details of TSDF, CHWIF etc.
TSDF-
• Ecocare Infrastructure Pvt. Ltd., Ghaspur, Dist. Surendranagar,
• Cluster EnviroPvt. Ltd., Matar, Dist. Kheda
• MauryaEnviroProject Pvt. Ltd., Jamiyatpura, Dist. Mahisagar
iii Details of Non-Hazardous waste & its disposal (MSW and others)
Existing: 6 MT/month After expansion: 18 MT/month (sold to brick manufacturer also use for land levelling, conditioning & road construction)
G Solvent management, VOC emissions etc.
i Types of solvents, Details of Solvent recovery, % recovery. reuse of recovered Solvents.
• No use of any solvent.
ii VOC emission sources and its mitigation measures
• No sources of VOC emission
• During the meeting dated 25/05/2018, technical presentation made during the meeting by project
proponent.
• Technical presentation was made by the project proponent. Committee observed that water balance,
spent acid generation and its management is not addressed properly in EIA report as well as
presentation.
After deliberation, Committee decided to consider the proposal for appraisal only after satisfactory
submission of revised EIA report with proper water balance, sound spent acid management
considering as hazardous waste, cleaner production technology, area adequacy with green belt area
etc.
Observation:
Page 43 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 43 of 49
• This is existing unit manufacturing organic chemical and now proposes for synthetic organic chemical
manufacturing plant. Unit has valid CC&A for existing unit. The CC&A Compliance was discussed in
detail. There is no court case/legal action pending against the unit.
• Committee deliberate that Total water requirement will be only 105 KLD and total wastewater
generation will be 99 KLD. 31 KLD of dilute wastewater will be treated in ETP 1 and sent to CETP. 68
KLD of concentrated stream will be treated in ETP 2 and sent to common MEE/evaporator/spray
dryer.
• 24 KLD of dilute Sulfuric acid will be sent to NOVEL.
• Biofuel will be used after expansion for steam boiler and thermic fluid heater.
• Hazardous waste management will be mentioned adequately.
• The baseline environmental quality has been assessed for various components of the environment
viz. air, noise, water, biological and socioeconomic aspect. The baseline environmental study has
been conducted for the study area of 5 km radial distance from project site for the period March 2017
to May 2017. Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NO2, and VOC
at six locations, including the project site. Values conform to the prescribed standards for Ambient Air
Quality. The incremental Ground Level Concentration (GLC) has been computed using ISCST3. The
resultant concentrations are within the NAAQS. The modelling study proved that the air emissions
from the proposed plant would not affect the ambient air quality of the region in any significant
manner. The ambient air quality around the proposed project site will remain within the National
Ambient Air Quality Standards (NAAQS). The result of water samples are within the norms
prescribed in BIS.
• Risk assessment including prediction of the worst-case scenario and maximum credible accident
scenarios has been carried out. The detail proposed safeguard measures including On-Site / Off-Site
Emergency Plan has been covered in the RA report.
Discussions & Conclusion:
• Committee deliberated that PP has submitted EIA report with proper water balance, sound spent acid
management considering hazardous waste, best technology available for waste reduction.
• Committee noted that Higher quantity of industrial wastewater generation will be due to use ofIce and
water retain with products. Main sources of industrial wastewatergeneration will be process, washing
and utilities. Entire quantity of theindustrial wastewater will be segregated.
• Unit has full-fledge ETP with capacity of 50 m3/day for dilute stream and100 m3/day for concentrated
stream. After expansion, unit will treat itseffluent in same ETP.
• Hydraulic or organic load onCETP will not increase resulted to proposed expansion. Concentrated
frommanufacturing activities willbe evaporated and only dilutestream will be sent to CETPafter
treatment. No additional discharge envisages.
Page 44 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 44 of 49
• PP has acquired a new land to provide greenbelt area.
After deliberation, it was unanimously decided to recommend to SEIAA for grant of environment
clearance.
12. SIA/GJ/IND2/18298/2017 M/s.Intersperse Industries Plot No C-1-7,67/16, Phase-I, GIDC, Vatva, Ahmedabad, Gujarat 382445
Appraisal
Project / Activity No.: 5(f)
Project status: Expansion
• PP has submitted online application vide no. SIA/GJ/IND2/20847/2017 dated 10/11/2017 for
obtaining Environmental Clearance.
• The SEAC had recommended TOR to SEIAA and SEIAA issued TOR to PP vide letter dated
29/04/2017.
• Project proponent has submitted EIA Report prepared by M/s: Green Circle Inc., Vadodara based on
the TOR issued by SEIAA.
• This is an existing unit engaged in Synthetic organic chemicals and now proposes for expansion as
tabulated below:
Sr. no.
Name of the Products CAS no. / CI no.
Quantity (MT/Month) End-use of the products Existing Proposed After
proposed
1 Para Amino Acetanilide 122-80-5 2.00 MT/Month
13.00 MT/Month
15.00 MT/Month
Dyes Drugs
2 2 Chloro PPD - 2.0 MT/Month
6.0 MT/Month
8.0 MT/Month Pigment
3 Carbazole 86-74-8 2.5 MT/Month
7.5 MT/Month
10.0 MT/Month
Pigment
4 N-Ethyl Carbazole 86-28-2 - 5.00 MT/Month
5.00 MT/Month
Pigment
5 2 Amino Di Methyl Terephthalate (ADMT)
5372-81-6 - 10.00 MT/Month
10.00 MT/Month
Pigment
6 2,5-Di Chloro PPD (2,5 DCPPD )
20103-09-7 - 5.00 MT/Month
5.00 MT/Month
Pigment
7 Meta Amino Acetanilide HCL ( MAA )
621-35-2 - 3.00 MT/Month
3.00 MT/Month
Dyes
TOTAL 6.5 MT/Month
42.5 MT/Month
49.0 MT/Month
-
• The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
• PP was called for presentation in the SEAC meeting dated 28/02/2018.
• Salient features of the project are as under::
Sr. no.
Particulars Details
Page 45 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 45 of 49
A Total cost of Proposed Project (Rs. in Crores):
Existing:Rs.1.0 Crores Proposed: Rs. 0.48 Crores Total: Rs.1.418 Crores
(1) Capital cost for EMS (Environmental Management System): Rs. 0.10Crores (2) Recurring cost towards the environmental protection measures: Rs. 0.20 Crores per
Annum. B Total Plot area
( sq. meter) Existing:2000 Proposed:- Total:2000
Green belt area,/Tree Plantation area ( sq. meter)
Existing:- Proposed:600 Total:600
C Employment generation
1. Direct Existing:10 Proposed:5 Total:15
2. Indirect Existing:15 Proposed:10 Total:25
D Water
i
Source of Water Supply (GIDC Bore well, Surface water, Tanker supply r etc...)
GIDC
Status of permission from the concern authority. GIDC Letter ii Water consumption (KL/day)
Existing KL/day
Proposed (Additional) KL/day
Total after Expansion KL/day
(A) Domestic 1.1 - 1.1
(B) Gardening - 0.4 0.4
(C) Industrial
Process 2.0 14.1 16.1 Washing 2.0 1.0 3.0
Boiler 2.0 - 2.0
Cooling 2.3 - 2.3
Others - - -
Industrial Total 8.3 15.1 23.4
Grand Total (A+B+C) 9.4 15.5 24.9
iii Waste water generation (KL/day)
Category Existing KL/Day
Proposed (Additional) KL/day
Total after Expansion KL/day
(A) Domestic 1.1 0.25 1.35
(B) Industrial
Process 1.7 13.35 15.05 Washing 2.0 1.0 3.0
Boiler - - -
Cooling 0.3 - 0.3
Others - - -
Total Industrial waste water 4.0 14.35 18.35
Page 46 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 46 of 49
iv Treatment facility within premises with capacity (ETP,MEE, STP etc).
ETP In house Capacity:20 KL/day
v Mode of Disposal & Final meeting point
Domestic: Soak Pit
Industrial Diluted: CETP,Vatva (Existing), Common Spray Drying Facility, Vatva for proposed
Vi Reuse/Recycle details (KL/day) 5 KL/day
Vii Details of rain water harvesting ETP In house &Common Effluent Treatment Plant , Vatva, Ahmedabad
E Air[Existing & Proposed]
I Flue gas emission details No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
-
SR. no.
Source of emission With Capacity e.g. Boiler (8 TPH)
Stack Height (meter)
Name of the fuel
Quantity of Fuel MT/hr& MT/Day
Type of emissions i.e. Air Pollut ants
APCM
1. Steam Boiler (1.0 Ton)
11
Fire wood /Agro waste
6.0 MT/Day
PM SO2 NO2
Multi Cyclone
2. Hot Air Generator (2 Lac Kcal)
11 LDO
500 Lit/Month
PM SO2 NO2
Multi Cyclone
3 DG set - Diesal
5 Lit/ Hr
PM SO2 NO2
-
Ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOxetc.) [Existing & Proposed]
-
Sr. no.
Source of emission
Type of emission
Stack/Vent Height (meter)
APCM Emission Standards
There are no process gas emissions.
- Iii Fugitive emission details with its mitigation measures.
[Existing & Proposed]
• Fugitive emission will due to the leakages in pump, storage container, material transferring, and packing.
Mitigation measures:
• Proper storage of raw materials, products and fuels
• Ensuring closed feeding and sampling.
• Establishing SOPs for start-up, shut down and maintenance operational procedure Regular work place and ambient air quality monitoring will be done.
F Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016. [Existing & Proposed]
I
Sr. no.
Type/ Name of
Source of generation
Category and
Quantity(MT/Annum) Disposal Method Existing Propos After
Page 47 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 47 of 49
Hazardous waste
Schedule as per HW Rules.
ed Proposed
1 ETP Waste
Treatment of Effluent
34.3 180 300 480 Collection, Storage, Transportation, Disposal at TSDF approved by the board
2
Process Waste
Filtration 26.1 79.2
280.8 360
Collection, Storage, Transportation, Disposal at TSDF approved by the board
3 Discarded Container
Packing 33.3
1.5
2.5
3.5
Collection, Storage, Decontamination, Transportation, Disposal by selling to authorized recycler or send back to supplier
4 Used Oil Machinery 5.1 - 0.5 0.5
Collection, Storage, Transportation, Disposal by selling to Registered re-refiners
ii Membership details of CETP, TSDF, CHWIF, Common MEE etc.
CETP for discharge of treated waste water, SEPPL for TSDF, Common Spray Dryer Facilities of GESCSL, Vatva
iii Details of Non-Hazardous waste & its disposal(MSW and others)
AMC collection centre
G Solvent management (If any)
i Details of Solvent recovery (As per respective ToR)
Not any
ii VOC emission sources and its mitigation measures
VOC source:
• Liquid material storage area
• Production area VOC mitigation measures
• Store VOC-containing products in air-tight containers.
• Buy products with less packaging as the printing of packaging materials generates VOCs
• Will assign a person develop and implement the VOC reduction plan.
• Utilizing natural ventilation Maintaining the good housekeeping practice.
• During the meeting dated 28/02/2018, technical presentation made during the meeting by project
proponent.
• For the above referred proposal, Consultant of the project requested to defer the proposal as project
Page 48 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 48 of 49
proponent could not come due to illness which was agreed upon.
• Committee insisted PP and consultant to be well aware of the proposal. After deliberation, it
was decided by the committee to defer the proposal in one of the upcoming SEAC meeting.
Observation:
• This is existingunit manufacturing organic chemical and now proposes for synthetic organic chemical
manufacturing plant. Unit has valid CC&A for existing unit. The CC&A Compliance was discussed in
detail. There is no court case/legal action pending against the unit.
• Total water consumption will be 24.9 KLD. Total wastewater generation will be 18.35 KLD it will be
treated in ETP. Existing 4 KLD discharge to the CETP will be continue and additional 14.35 KLD will
be sent to the common spray drying facility.
• Firewood or agrowaste will be used as fuel for boiler.
• There will be no process gas emission.
• Hazardous waste management will be adequately provided.
• The baseline environmental quality has been assessed for various components of the environment
viz. air, noise, water, biological and socioeconomic aspect. The baseline environmental study has
been conducted for the study area of 5 km radial distance from project site for the period March 2017
to June 2017. Ambient Air Quality monitoring was carried out for PM10, PM2.5, SO2, NO2, and VOC
at eight locations, including the project site. Values conform to the prescribed standards for Ambient
Air Quality. The incremental Ground Level Concentration (GLC) has been computed using AIRMOD
view. The resultant concentrations are within the NAAQS. The modelling study proved that the air
emissions from the proposed plant would not affect the ambient air quality of the region in any
significant manner. The ambient air quality around the proposed project site will remain within the
National Ambient Air Quality Standards (NAAQS).
• Risk assessment including prediction of the worst-case scenario and maximum credible accident
scenarios has been carried out.The detail proposed safeguard measures including On-Site / Off-Site
Emergency Plan has been covered in the RA report.
Discussions & Conclusion:
• The purpose of proposal was discussed. Unit has got closure in December 2017 for installation of
boiler without CTE-amendment. Then after PP has got CTE-amendment for the same.
• Committee noted that the best available technology has been used for the project.
• Committee asked PP for management of Hazardous waste as per the HW Rules 2016. Waste nickel
is generated from the mfg. process of Carbazol which is not mentioned in hazardous waste
management.
• EMP, SCR & CER was discussed in details.
Page 49 of 49
432ndmeeting of SEAC-Gujarat, Dated 11.09.2018
Page 49 of 49
After deliberation, it was unanimously decided to consider the project for further consideration only
after satisfactory submission of the following:
1. Management of waste Nickel as per the HW Rules 2016. Revised HW management shall be required
to submit.
2. Detailed outlay of Environmental Management Plan with year-wise budgetary provision including
bifurcation of each activity with provision of capital cost and recurring cost. Tree plantation activity
shall be considered precisely.
3. Details of the treatability and feasibility of waste water to be disposed of by means of spray dryer and
its impact on Environment and Human Health. Submit Adequacy of Spray Dryer.
Meeting ended with thanks to the Chair and the Members.
Minutes approved by:
1. Dr. Dinesh Misra, Chairman, SEAC
2. Shri S. C. Srivastav, Vice Chairman, SEAC
3. Dr. V. K. Jain, Member, SEAC
4. Shri V. N. Patel, Member, SEAC
5. Shri. R. J. Shah, Member, SEAC
6. Shri A. K. Mule, Member, SEAC