MINUTES OF TWENTY SECOND COORDINATION MEETING (14/07/2015)
Following issues of effective coordination for development of Mumbai were discussed on 14/07/2015 and status of work clarified as follows:-
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
1 MMRDA CR / WR
CBE
A. Proposed construction of elevated connecter between Bandra-Kurla
complex and Eastern express
highway. 1. GAD for ROB between Kurla &
Sion. 2. GAD for ROB for Chunabhatti
Railway Station.
3. GAD for ROB near Chunabhatti Railway station. In lieu of L-xing
No. 1/T.
MMRDA suggested on 23.09.2014 that proposed elevated corridor (CSTM-Panvel) may be raised at
Chunabhatti to the same level as at Kurla to
enable ROB 2 & ROB 3 at Chunabhatti to remain underneath. MRVC and Railways agreed.
MMRDA also indicated that they are not able to lower the level of the connector by 1.5 m as
requested by MRVC. This will result into keeping
the PNVL - CSTM fast corridor at level of 18 to 20 meters right from SCL Road Kurla point to EE
highway Chunabhatti point. It was requested by Central Railway to add a Road
also along with Fast corridor for effective disaster
Management. i) GAD for ROB between Kurla & Sion approved on
16.01.15. ii) Chunabhatti Station ROB GADs approved on
27.01.15. iii) Chunabhatti LC No. 1T, ROB approved on
29.01.15.
Launching scheme of all the three ROBs will be submitted by MMRDA by 15.04.15.
Case cannot be submitted to CRS without launching schemes. After this work Chunabhatti
level crossing shall be closed.
No change as on 10.3.15, 24.03.2015 & 07.04.2015. PDC of 15.04.2015 will be honored.
PDC shifted from 15.4.2015 to 6.5.2015. Consultants (M/s STUP) have submitted all the 3
launching schemes. They will be submitted by MMRDA before next meeting.
Instead of launching scheme, the revised GADs
with plate girders have been submitted on 19.5.15.
MMRDA has already revised the approved GAD and submitted to CR on 19.05.15. No reason for
revision of superstructure from already approved
trough girder to plate girder (60m span) has been submitted. Matter is being discussed with MMRDA.
It was clarified that Railways does not use
plate girders for spans >30m. Earlier
approval of through girder should only be developed.
Page 2 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
2 MMRDA CR
CBE
Mumbai -Trans Harbour sea link (MTHL) Approval of GAD’s of ROB’s over Central
Railway land from Sewri to Chirle Mainland Nhava side Drg. No.
180581/142 sheets, and 2180581/ 1 to 7
sheets.
Observations regarding span arrangement over running lines conveyed to MMRDA vide letter
dated 17.07.2014. MMRDA was to provide revised GAD of this by
07/10/14. Now target shifted to 14/10/14. Target
busted again. Again PDC fixed at 30.10.14. PDC 17/11/14.
Meeting held on 12/11/14. Crossings will be with 3 spans. Instead of 5 sets of piers it was decided to
submit GAD with 2 sets of piers.
Final GAD from MMRDA is awaited. PDC 01/01/2015. Revised PDC 20/1/15
PDC again shifted to 15.2.15 due to work to be done by M/S CES ( Consultants of MMRDA)
GAD is yet to be submitted by MMRDA. PDC – 15.4.2015. No change in above PDC on
24.03.2015 & 7.4.2015.
GAD submitted on 16.4.2015. Approval of DFC and construction will be obtained by 24.4.2015. CBE
will issue in-principle approval to submit final GAD to be signed by Division and Headquarters.
Clearance of DFC awaited by CBE. In-principle
approval to MMRDA will be given by 10.5.15 DFC approval given by Shri Prakash Mudliar.
IPA given to MMRDA on 10.5.15. Tracing of this approved GAD will be given by MMRDA
on 09.6.15. CBE: Not received from MMRDA. Tracing
being submitted on 16.6.2015.
39 CR MMRDA
DRM
Connecting the existing skywalk on west side of Ghatkopar station to the Metro
building so as to ensure seamless connectivity with railway’s 12 meters
wide FOB.
Under process.
Details given to MMRDA on 15/10/14.Consultants of MMRDA working on this.
PDC 15.11.14. Delayed to 05/12/14.
DRM BB: Proposal has to be submitted by MMRDA. The
same has not been submitted till date. Concerned officials not available on 16/12/14.
MMRDA yet to decide whether to complete this
project or not.
ITEM CLOSED.
ITEM OPENED on 10.2.15. PDC 15.4.15
No change as on 10.3.2015, 24.03.2015.
PDC of 15.04.2015 will be honored.
Page 3 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Detailed drawing submitted to DEN (HQ). PDC for approval – 30.4.2015.
Approval given with two corrections on 30.4.15. PDC for MMRDA for corrected detailed drawing –
08.5.15. Corrected drawing received on
10.5.15. Approved by DRM/BB to be given by 09.6.15.
Approval given on 16.6.2015.
89 CR MMRDA
MMRDA has carried out widening of the road between Ambernath, Vangani and
Khopoli. Due to widening, some existing
110kv Railway Transmission line towers need to be shifted.
17 transmission line towers are prone to hitting by road vehicles and cause disturbance to traction
tower supply in KYN-PUNE section affecting train
movement. Joint Survey by Railways & MMRDA officials
already done in 2014. An Estimate for shifting of these towers sent to MMRDA by BB division for
depositing the money in March 2014. Money has not been deposited by MMRDA till
date. MMRDA had apprehensions that land
required for shifting has been identified by Railways or not. They were advised that shifting
has been planned in all details. MMRDA agreed to deposit Rs.6 Crore as
asked by Railways by 09.6.15 after
verification of tower nos. at site by joint visit of S/Shri M. Patil ( MMRDA) and P.K
Kataria (Rlys) on 28.5.15.
Inspection completed. Prima facie, the inspection revealed that 15 towers need
immediate protection @ Rs. 20L -25 L per
tower and 4 towers need immediate shifting. MMRDA opined that while shifting
they should also be redesigned to take less space also.
Page 4 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
102 CR MMRDA
Permission to cross railway land for providing connectivity of Mumbai Metro
and Ghatkopar station.
1.MMRDA has constructed Metro station at Ghatkopar on CR’s land without obtaining the prior
permission from this Railway. 2.The area involved in construction of elevated
Metro Railway station at Ghatkopar is 1215 sqm
(Metro station building area 1163 sqm + Stair case are 52 sqm)
3.The total charges equivalent to 99% market value of land for the year 2014 + nominal charges
of Rs. 1000/- p.a. for 35 years including service
tax @ 12.36% worked out to Rs. 22,20,94,433/-. 4.MMRDA has paid Rs.21,25,90,840/- for Metro
station building area vide cheque no. 218628 dated 07.04.2015.
5.The charges for 52 sqm of Stairs area amounting to Rs.95,03,593/- is still
outstanding from MMRDA.
Page 5 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
5 CIDCO CR
CBE
Proposal of crossing of Navi Mumbai Metro line at Taloja station on Diva-
Panvel railway line by DFCCIL.
It is necessary to accord approval by
Railways to the Metro Station No.10,
portion of Depot approach via duct and
the pier at the edge of the railway boundary (to facilitate the NHAI span
crossing) since all these work are away from the operational area of Diva-Panvel
line and it will expedite the execution of
the Metro works held up on the Railway land.
Meeting held between CIDCO & DRM, Central Railway along with other railway officials on
18.09.2014. Central Railway & DFCC came to an Agreement on
the track layout of their respective track layout at
Taloja Station. Further item was discussed with DRM/BB,
CE/CIDCO and PCE with GM/CR on 07.10.2014. Revised drawing with relocation of RUB at location
of existing LC will be given by CIDCO by 10/10/14.
This will permit some more space for expansion to C.Rly. Meeting in GM’s Room held at 15.30 hours
on 07.10.2014. CIDCO submitted revised GAD based on the
discussions by 14/10/14. PDC for Railways and DFC 26/10/14. Rly gave feedback 22/10/14. GAD
by CIDCO to be given on 25/12/14.
Central Railway agreed that the structure of station No 10 and Depot Approach Viaduct of Navi
Mumbai Metro, located away from the operational area of Diva panel line are permitted for
construction. GM , Central Railway instructed the
concerned Railway officials to release letter by 27/11/14, to commence construction.
Central Railway confirmed that on formal submission of GAD of superstructure of NM Metro
crossing of operational Diva- Panvel line, the construction of pier of NHA3 crossing stands
approved for construction. Since this is located
away from the operational area of Diva- Panvel line and at edge of Railway Boundary.
CIDCO is requested to expedite submission of GAD of through type girder. In view of delay on part of
CIDCO designer, it was decided today that
maintenance agreement will be submitted by Railway to CIDCO 15/1/15. As soon as
agreements s executed by CIDCO, the construction of Depot, station no 10 and NH
crossing can be started.
Follow-up meeting was held by CAO(C)/ PCE with CBE/CR, and CE/CIDCO on 13.1.2015 and decided
that CIDCO will submit GAD showing vertical and Horizontal clearances pending superstructure
structural drawing in week time.
Draft Agreement submitted for legal check on
19.01.2015. After legal vetting of Agreement same will be sent to BB Divn for execution with CIDCO.
After execution of agreement and receipt of GAD permission for work will be processed.
GAD submitted to Mumbai division on 30.01.15
and is under approval. Draft Agreement has been sent to CIDCO on
23.01.15 for signature is yet to be returned duly signed. Same will be returned by 20.2.15 or
earlier. Work can start within two days, thereafter. Draft agreement is yet to be received from CIDCO.
PDC 24.2.2015.
Page 6 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
PDC shifted to 03.03.2015 on 24.02.2015 as MD /CIDCO’s approval is pending. Expected by
15.3.2015. GAD approved by Mumbai division and DFCCIL is
received in HQs on 23.02.15 and after scrutiny
GAD returned to CIDCO for following modifications:
1. Pier no.292 and 293 across existing Railway tracks have been proposed as single piers. It
would be advisable to provide at least two piers
for stability. 2. The vertical clearance over railway tracks is
13.76 m which is quite high. Further, 11.0 m height of girder will result in approx. 25m high
space unusable for Railways. The overall height can be reduced by designing semi through girder.
3. Single truss girder has been proposed for both
the tracks. Separate girders for two tracks should be planned to facilitate ease of maintenance.
PDC for CIDCO to react and sort out above issues – 15.3.2015 Clarification by CIDCO to CBE vide letter dated 17.03.15 @ pier configuration. MOD is signed on 19.03.15. Agreement signed by CIDCO & CR on 20.03.2015.
Authority to start work given during today’s
meeting (07.04.15) in writing. Permission for starting work in Rly area at 2 locations granted by
Division on 07.04.15 vide L.No. BB/W/3521/Metro
Rail/DB. 1) Pier No.P-290 next to NH4 for highway span. 2) Depot approach via duct.
Station No. 10 - Permission to construct has been granted on 21.04.15.
Preliminary presentation with CRS on 12.5.15
along with forest officers of S. No.13 No Rep as on 26.5.15.
CBE: No issue pending with CR.
CRS meeting re-planned on 27.7.15
13 CR
GoM / CIDCO
b) Land acquisition for Nerul /
Belapur-Seawoods – Uran Rly
project. (Ch: 8000 to Ch.11000)
This matter is under process with the office of
Collector, Raigad and the Forest department.
The matter is under process with the office of Collector, Raigad and the Forest Dept.
TDC Dec 2014. CIDCO is chasing actively. PDC of Dec. 14 will be
honoured.
a) CIDCO is following up with concerned Land
Acquisition Authority of GoM for Navi Mumbai / Raigad for expediting acquisition of the private
land. b) CIDCO is also following up for transfer of Forest
Land. The matter involves multiple Govt
Departments. Expected PDC will be given in next meeting.
Page 7 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
One meeting has been held by CIDCO PDC is not possible now. It will be given by 28.2.15.
Forest land will be handed over early. Private land will be treated separately on priority.
No change as on 24.03.2015, 07.04.2015 and
21.4.15. Still no PDC is possible by CIDCO. CIDCO hopes to solve the problem by 15.05.15.
No Rep as on 26.5.15.
Due to queries of Forest dept. Railway has to
justify the alignment with one letter from CIDCO.
15 CR CIDCO
GM
Acquisition of land for DFCCIL alignment through Panvel.
The issuance of MoM of the meeting held on 04th July, 2014 in presence of C.S., GoM by PS (UD-i)
office GoM is expected anytime as discussed
during Empowerment Committee meeting on 26.09.14.
Meeting called by Additional Secretary (Transport) on 28.04.15.
Re-alignment of DFC being relooked into after meeting of Additional CS, DFC and
CIDCO.
In the meeting on 28.04.15 under chairmanship of ACS(Transport)GoM – it
was decided that CIDCO will complete scrutiny of the proposal in 10 days & discuss
with DFCCIL, if there is a problem at any
location. Feedback awaited. No Rep as on 26.5.15.
CIDCO has carried out its internal study on
the issues and propose to discuss with DFCC
next week.
17
*
CR
GoM/CIDCO
CAO / C
ROB’s in lieu of 13 nos. of Level
Crossings have been sanctioned by Railway Board on cost sharing basis in
connection with DFCCIL alignment.
Sanction of State Government for sharing 50% of the cost is awaited.
6 GADs submitted to CIDCO
(One pertains to MMRDA ) (LC 9 does not pertain to CIDCO area)
(LC 6 near Bomali village needs to be
clarified whether the approach road pertains to PWD or CIDCO)
There are no guidelines regarding cost sharing. It
was decided to technically finalize the GAD drawings of these ROBs without waiting for clarity
on cost sharing.
DFCCIL to get the appropriate letter issued from Board, on cost sharing.
TDC for approval of GADs 30/10/14 (with 4 lane modification). Meeting fixed by CAO/C on
29.10.14. 3 Drawings will be approved by CIDCO by 14/11/14. Rest 3 by 31/12/14.
In the last meeting between CIDCO & C. Rly. held
on 13.11.2014, the nodal drawing of three locations LC 10, LC 20 & LC 23 were given to C.
Rly. to super impose the GAD of the ROB / RUB
Page 8 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
for checking the junction arrangement details. PDC 5/1/15. There is delay of 15 days on both
PDCs due to feedback from DFC. Progress held up for want of revised Board circular
on cost sharing.
PDC 10.3.15 for Board Circular.
Meanwhile 4 GADs submitted by CR to CIDCO
and 2 GADs submitted to MMRDA on
Sept.2013 are still pending for approval. PDC - 30.03.2015 by CIDCO.
PDC - 30.03.2015 by MMRDA for LC No. 6 &
9. No change as on 10.3.15 and 24.03.2015. Railway
to study for RUBs at maximum possible sites. PDC of 30.3.2015 will be honoured by CIDCO &
MMRDA New PDC of 22.04.2015 for MMRDA and CIDCO
fixed on 07.04.2015.
Meeting called by Additional Secretary (Transport) on 28.04.15.
All Four crossings of CIDCO will be RUBs. For remaining seven, discussions are on by
GoM.
DFCCIL:
20 LC in Maharashtra (13CR+7WR) against which ROBs/RUBs are yet to be sanctioned by State
Govt./Local bodies. Issue of cost sharing was discussed in meeting
between Ch.Secy GoM & MD/DFFCILon 28.03.15.
Ch.Secy GoM directed to submit the cost of each ROB along with location details for initiating
process of sanction by corporation/Road authority. Details of 17 ROBs costing 650.28 crores have
been submitted to Secretary (PWD) GoM on
24.04.15. (out of these 17 LCs, only One LC no. 23 pertains to CIDCO)
For remaining 3 LCs which are in CIDCO territory, option of providing ROBs/RUBs is under discussion
between CR & CIDCO.
Follow up meeting was held with ACS (Transport) on 28.04.15 & advised DFCCIL to submit GAD of
these ROBs. Accordingly GAD for 10 ROBs has been submitted on 15.05.15 in first phase.
GoM & CIDCO is requested to expedite the process for cost sharing. No Rep as on
26.5.15.
Only two GADs are pending with CIDCO. Railway to clear the feasibility of four RUBs
instead of ROBs.
Page 9 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
31 CIDCO CR
DRM
Taking over of maintenance of 14 nos. of suburban railway stations by the railways
on or before 31st March 2015. &
Finalizing the pending maintenance
agreement between Central Railway and CIDCO for the maintenance period
beyond 2008.
CR has not taken over maintenance from CIDCO as yet. As such we cannot charge w.e.f. 2008. We
will charge w.e.f 2015 after we take over. We can take over after CIDCO does one time clearance of
arrears / deficiencies and clarifies the separation
of utilities. Agreement for 2008-2015 will also have to be
signed. DRM / BB, Central Railway to be the single point
for co-ordinating and decision in the matter.
He will hold detailed meeting with CE ( Spl. Proj) / CIDCO in DRM office on 8/10/14 at 15:00 hrs.
DRM / BB held meeting on 17.10.14. Next meeting planned on 29.10.14 and site visits on 5.11.2014.
CIDCO: The maintenance agreement between CR &
CIDCO has not been formalised w.e.f. 2008.
CIDCO has already communicated the draft of the maintenance agreement in 2011-12. Now since it
is decided that Railways shall take over maintenance of the stations w.e.f. 01.04.2015, the
maintenance agreement should be finalised by
Railways considering 2008-2015. CIDCO & Railways jointly should finalize the issues
pertaining to the outstanding dues, if any, on either side, the cost of repairs to be shared & as
also the utilities sharing / separation. JUINAGAR will be taken over by Railways first. JA
grade meetings over. SA grade meetings to be
done and issue finalized by 15.3.15. New PDC -30.4.2015. Site Insp. of Juinagar Station done on 5.03.15. Letter regarding details for Shops and Stations area sent to CE (SP)CIDCO on 20.3.2015. Details awaited.
Some details of agreement done with Shopkeepers are not available with CIDCO.
It was decided on 7.04.2015 to repair the agreement in such a way that share of
maintenance charges, if not borne by shops shall be borne by CIDCO in future.
Meeting will be conducted with CE CIDCO by
Mumbai Division.
No Rep as on 26.5.15. DRM Central Railway to hold this discussions
with CIDCO. CIDCO has requested to form
JWG to resolve the issues within definite time frame.
Page 10 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
42 CIDCO CR
DRM
For re-locating the Assistant Commissioner of Police, harbour
Division’s Office at the ground level unit of the Vashi Railway Station Building
(south side), the keys of these offices
have to be handed over to CIDCO for completing the handing over process.
Currently, the keys to these premises are kept in Station Master’s office.
The said premises are in possession of Central Railway since 1992 and are being used for various
purposes. Further all the station building in Navi Mumbai will be under control of Central Railway
from 01.04.2015, so it will be appropriate that the
railways take a view on this issue. TDC: 15.10.14.
CIDCO informed that these premises should have lock up and even room for the Hon’ble Judge also.
To be discussed in 08/10/14 meeting.
CIDCO informed that these premises have lock up and room for the Hon’ble Judge. This premise has
to function as mandated. Meeting rescheduled for 17.10.2014.
Railway has planned a safety training centre for Motormen & ASMs..
Two rooms out of five are likely to be
encroached. Subject to be finalized by 15.03.2015 along with item. No.31. Linked
with Sr. No.31. New PDC – 30.4.2015.
No Rep as on 26.5.15.
48 CIDCO
CR
DRM
Due to site constraint, CIDCO requires
1200 square meter railway land (CH 77 kms) along Panvel Uran railway line near
Bhangarpada falling under village
Dapoli, Tal -Panvel for laying the storm water drain in Pushpak Nagar which is
part and parcel of Navi Mumbai International Airport Project.
DEN (LM) CSTM through letter dtd 16/5/2014
informed CIDCO that land shall be leased to CIDCO for 35 years.
CIDCO to submit its proposal to Railways as
explained in the meeting. PDC for CIDCO 30/10/14.
Submitted on 8/10/14. Copy again given on 11/11/14.
DRM BB : Proposal is under divisional approval.
XEN CIDCO to liaise with BB Division. a)Proposal for leasing of 1200 m2 land is under
divisional approval. b)Proposal for exchange of land is not received
from CIDCO. No change as on 10.3.15. CIDCO advised to
send lease proposal as per ready reckoner
rates. Proposal for transfer of land to be dealt on
normal leasing basis
No Rep as on 26.5.15.
Railways to send letter to CIDCO.
Page 11 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
49 CIDCO CR
CAO / C
The final approval for two ROBs taken up for construction at MSEB Sub-station and
Uran Station on Nerul-Uran Railway Line are awaited from Railway.
Both ROBs are under scrutiny of Design office and for some clarifications, concerned designer of that
bridge is required at design office of headquarters office of CR. Old PDC was 15/10/14. C.Rly
requested for priority.
MSEB was indicated by CIDCO as priority 1 PDC for MSEB 31/10/14.
PDC for URAN 07/11/14. Both progresses are on schedule.
Designer required again in CAO(C)‘s office for
minor clarifications. One approval of MSEB done on 24/11/14. Second consultants to visit CAO ( C )
for URAN. Design to be finalized by 15.3.15.
No change as on 10.3.15. Consultant visited on 11.3.2015.
URAN design received from Consultant on
6.04.2015. Now CAO/C will approve by 30.4.2015. Design finalized by CAO/C on 18.04.15.
For ROB of MSEB, CIDCO will give revised design because of gas pipelines. No Rep as on 26.5.15.
CIDCO examining the designs due to gas pipelines.
90 CIDCO
CR0
Civil works of Phase-I at new Seawoods
Darave Railway Station was completed in Feb’2015 & C.Rly were requested to take
necessary action towards diversion of
Rail Operations from Old station to Phase-I of New station to facilitate its
commissioning as well as taking up the construction of Phase-II.
CIDCO is yet to get the confirmation and schedule
from CR. This item may be considered on top priority to enable further works by CIDCO.
CAO/C indicated that OHE issues are pending. CIDCO wanted the diversion of
trains from old station to new station so that old station can be dismantled. This
point shall also be covered by CIDCO in their presentation on 12.5.15.
No Rep as on 26.5.15.
CIDCO requested Railways to expedite.
Page 12 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
16
*
CR MbPT/
MMRDA
CAO/C
Construction of Wadala- Kurla dedicated Goods Line (on deposit terms) is pending
for want of removal of hutments and rehabilitation. Resettlement of the
project affected persons to be done by
MMRDA / MbPT.
237 allotments done out of 1680 encroachments. 150 shifted out of 237. SPARC (NGO) coordinates.
PDC Dec ’14 - given by MMRDA but progress on ground is not commensurate.
Fresh allotments are held up due to MMRDA. New
shifting held up for wants of repairs to tenement by MMRDA. (Civil Engineering Dept).
Dy CE MbPT: Demolition of the hutments vacated by the slum dwellers and construction of the
compound wall along the safety zone is in
progress. Demolition of the huts of the PAPs who have been
allotted the tenements but not shifted from the project site is scheduled on 10.11.2014.
Fresh allotment of tenements held up for want of repairs to the tenements.
CAO/C: Work is held up. MbPT absent on
16/12/14. 445 allotments done. 220 shifted. 680 tenements
repaired. 800 tenements scrutinized. No further progress till 10.2.15.
Now the same 445 shelters are being allotted to
hutment owners of MAP-3 from Wadala end. Commercial encroachments as seen during joint
site visit, should also be planned by MbPT/MMRDA for resettlement at the earliest.
No change on 10.3.15 and 24.3.2015. 70 allotments of commercial sites also done.
Railways requested MbPT to advise MMRDA to
allotments for hutments in the vicinity of Shanmukhanand RUB as there is a long lead item
and its tender is waiting for finalization. 483 allotments done now. Shifted only 220.
600 allotted and 330 shifted as on 26.5.15. Earthwork contract awarded by Railways. Work will
start within a fortnight.
MbPT has requested for changes of alignment near
Raoli Bridge so that 400 PAPs can be saved. Sketch discussed during meeting on 26.05.2015.
Rlys to examine the proposal by 02.06.2015. Railways work on above proposal to be completed
by 22.06.15. [1024 allotted and 375 shifted as on 16.06.15]
1024 allotted and 400 shifted as on 14.07.15. Revised allotment near Ravli
Junction at Wadala to be approved by C.Rly - This will reduce the pending allotment work
of 656 encroachments to about 250.
Page 13 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
25 MbPT CR
GM
Taking over of Port Railway by C.Rly and Exchange of Haji Bunder land of
Railways with Wadala land of MbPT.
Agreement sent to MbPT on 08.09.2014. MbPT is waiting for Rani Jadhav Committee report.
C.Rly cannot introduce 12 car services on harbour line without this agreement of MbPT. Detailed
meeting with MbPT office postponed to 10/10/14
at 17:00 hrs. ROB meeting was requested by MbPT on
14/10/14, which can be held today itself. MbPT vide its letter dated 27.10.2014 has
forwarded its comments on the Central Railway’s
letter dated 08.09.2014 wherein certain terms and conditions have been stipulated for taking over
Port’s railway operations. MbPT Absent on 16/12/14.
This point added in the agenda of Port Trust meeting planned for 7/1/15.
Meeting planned for 13.1.2015. Meeting planned
for 19.1.2015. Meeting postponed again. Meeting with Shri Parmar held by GM/CR on 20.02.2015.
No change on 10.3.15 and 24.3.2015 and subsequently on 26.05.15
100 MRVC MbPT
Requirement of 240 sq.meter land from MbPT at Wadala
Extension of PF no. 4 at Wadala Road on CSTM end requires 240 sq.meter of MbPT
land which has been principally agreed by MbPT. In this regard a reminder has been
sent to CE/MbPT vide letter no.
MRVC/W/167/I/Land Acqn. dated 07.05.15
Page 14 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
101 CR MbPT
Land license fee for excess railway land of 3209.70 sqm. outstanding
from MbPT.
MbPT has not paid land license charges for 3209.70 sqm. Of land. The total outstanding
amount accumulated is Rs. 3,88,86417/- including service tax up to 31.03.15.
MbPT may pay the outstanding dues
expeditiously.
105 MbPT
CR
700-800 meters 52 Kg Rails, two 8
1/2 turn outs, 30 nos. fishplates (60Kg) and about 1000 sleepers are
required by MbPT.
PCE/CR will organize this material supply.
Page 15 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
6 MCGM CR
CBE
Carnac Road Over Bridge & Hancock ROB: - Rebuilding of Carnac Road over
bridge at KMs. 0/1-2 & Hancock Road over bridge at KMs. 2/6-7.
MCGM has agreed for dismantling of existing ROBs by Railways at their cost. Estimate for demolition
of existing bridge submitted to MCGM on 30.05.2014 but acceptance is still awaited.
Dismantling scheme of existing ROB has been
submitted on 08.08.2014. MCGM was to approve this by 5/10/14.
CAO (C) CSTM will execute the work of demolition. It was decided to process for CRS sanction
simultaneously for dismantling
MCGM submitted the GAD & TAD to Railway for approval on 14.08.2014 for the new bridges to be
constructed. GAD and TAD returned to MCGM with observation
vide letter no. W.294.Rehab.Genl. dated 20.08.2014 regarding launching.
Revised GAD and TAD was awaited from MCGM by
15/10/14. Today MCGM clarified that they need approved plan of 5th and 6th line.
MCGM was requested by Railways to delink dismantling from the new bridge in view of public
safety.
Central Railway was to give approved plan of 5th and 6th line plan by 20/10/14. Plan given on
16.10.14. PDC for MCGM 15.11.14. Scrap will be removed by Rlys a.s cost of scrap has
been subtracted from estimate. Utilities planning in interim to be detailed by MCGM
by 5/12/14.
Rs.2.6 Cr received from MCGM on 27.11.14. Utility shifting – JJ hospital pipe of 300 mm dia.
and 9 cables of BEST , 3 cables of MTNL be taken along with 900 mm. dia. pipe of MCGM pipe bridge
2M away. Abandoned pipe of 600 mm dia. to be
thrown. For shifting of utility services on pipeline bridge
needs strengthening before shifting which is being advised to Construction Dept. Pipe and cables will
be provided by user dept. of MCGM.
PDC for strengthening of pipe bridge and dismantling –
CBE: Tender for dismantling of 2 ROBs opened on
06.01.15 and under finalization with CAO/C. PDC for finalization 10.3.15. Meeting with CAO(C) & CE/Br. of MCGM held on 23.02.15 & BMC is requested to shift utilities by BMC itself & intimate date for starting dismantling. Shri A.R.Patil (9869022185) of BMC has been nominated for planning the utility shifting of Carnac ROB first. He will take up Hancock ROB after that. Meeting with CE/Br MCGM of utilities on 17.03.15. In meeting BMC, CE agreed to explore scope of diverting all utilities either by new utility bridge or by adjusting it on proposed ROB. Schematic plan is being developed by BMC in coordination with BEST, MTNL, and Hydraulic Deptt.
Page 16 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
It was decided to close the traffic on both the bridges w.e.f 15.4.2015. Necessary notices in
newspapers to be given by traffic Police of BMC. Meeting with consultant Shri S.N. Bobe of MCGM to
be held in GM’s chamber to decide the modus
operandi of accommodating the utilities on 8.04.2015 or 9.4.2015, CBE & CAO/C will be
present. A meeting with CRS will also be held before preliminary TAD is made.
CRS meeting conducted on 21.04.15 at 1500 hrs.
Demolition starts from 01.10.15 and finishes on 31.12.15 for first bridge and from 01.02.16 to
31.05.16 for the second bridge. MCGM will submit the utility shifting plans for both the bridges by
31.05.15. MCGM is planning shifting of utilities with
consultant Shri Bhobe.
MCGM on 26.5.15 indicated that they have held a meeting with all departments of utilities and not
drawn any minutes. MCGM wanted Railways to provide solution which is not possible. Details like
weight/meter and length of utilities also not given
by MCGM. Water supply and Electric supply of JJ Hospital may be jeopardized if bridge has to be
stopped and dismantled. CBE had meeting with Municipal Commissioner on
09.06.15. it has been agreed to dismantle Hancock bridge from 01.10.15 and Carnac bridge from
01.12.15.
CE(Bridge)/MCGM Shri Kori has held two meetings with concerned departments to shift the utilities. It
was requested by Railways to call CBE and CE//C/ MTP should be called by MCGM for the third
meeting.
All utilities of Hancock by Nov.15 and for
Carnac all utilities will be shifted by Jan.16. Dismantling by Railways can start on Oct 1st,
2015.
Launching of both the bridges by incremental method is being planned. 2nd
meeting to be held by CBE/ CRly with MCGM officers’ consultant on 30.7.15.
7 MCGM
CR
CBE
Currey Road ROB & Tilak ROB: -
Proposed strengthening work of Currey road and Tilak ROB at kms. 6/2-3 and
Tilak ROB at kms. 9/5-6.
Estimate amounting for Currey Road ROB
Rs.2,50,91,702/- and for Tilak ROB Rs.2,35,70,677/- vide letter No. B.W. 3512.
Estimate. ROB.Gen.DB. dated 30.06.2014 submitted to MCGM. Not received as per MCGM.
To be given again. Acceptance of estimate awaited from MCGM
TDC 22/10/14. Confirmed today, to be behind
schedule. Revised target 7.11.14.
Page 17 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Target Revised again to 26/11/14. Rs 5 Crore will be deposited by 28/11/14.
Rs 2.5 Crs received for Currey Road on 15/12. PDC for Tilak 22/12/14.
Tilak Bridge money (2.5Cr) received on 25/12/14.
Tender for strengthening of 2 ROBs is being invited. NIT will be issued by 30.1.2015.
CBE: Tender for strengthening of 2 ROBs is beings invited. NIT will be issued by 20.02.15.
CBE: NIT for strengthening of 2 ROBs will be
issued by 15.03.15. Fund deposited by MCGM for both ROBs. Tender schedule under finance vetting. Tender is being
invited by Dy.CE/C/DR. No change as on 10.3.15.
Tender schedule still under vetting of FA&CAO (Cons) as on 06.04.15.
NIT issued, Tender opening on 19.05.15.
No representative of MCGM and no
discussions on 5.5.15 MCGM advised on 26.5.15 that utilities of
Currey Road and Tilak may also be planned for shifting as during strengthening the
bridge will be lifted also and disturb the
utilities. Draft scheme of strengthening to be discussed with CRS on 30.6.2015.
Meeting with CRS to be held on for this
scheme.
8 CR
MCGM
GM
Issue of Occupation Certificate for “E”
building at Railway Officer’s Flats at
Nirmal Park, Byculla. Three Meetings already held on the issue with MCGM at
the level of GM and MCGM commissioner.
5% land for amenities was earmarked along the
station road and as BEST service station.
MCGM postponed the targets from 05/10/14 to 30/10/14. Now Railways will be forced to have a
relook on rules. Status: issue is taken up with BEST by MCGM. BEST remarks received.
Case being processed by BMC. No discussions on 10.3.15, 24.03.2015 &
07.04.2015. No representative of MCGM and no
discussions on 5.5.15 Concerned Officer of MCGM to act or
comment on GoM’s minutes dated 27.4.15 not present.
9 CR MCGM
GM
Approval of layout for proposed construction of Railway Staff Quarters on
replacement account at Gunpowder road railway colony near Dockyard station.
MCGM has submitted a comprehensive report with Ch Eng (DP) / MC. Under process with MCGM.
TDC was 30/9/14. No progress by MCGM, will be taken up after elections.
Status: Approval of layout will be issued by
30/11/14. Letter is yet to be issued. No discussions on 10.3.15, 24.03.2015 &
07.4.2015.
Page 18 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
No representative of MCGM and no discussions on 5.5.15 and 26.5.15.
27 WR
MCGM
Land Acquisition 550 sq. m at Vile Parle
(South) on BMC road in connection with
6th line work between Mumbai Central to Borivali. – Correspondences have been
made with MCGM authorities on 25.02.14, 04.04.14, 28.04.14 &
26.06.14.
Joint inspection by W.Rly and MCGM official held
on 24/9/14.
Land required is not encroaching any road. It is not infringing with any future plans. Can be
acquired by W.Rly. Detailed plan submitted on 6/10/14 to Ex. Eng /
Traffic. MCGM representative agreed to request Ex Engg
(Tfc) to expedite. On 26/11/14. MCGM has asked
WR to submit details of owners. PDC 7/1/2015. Local society members objected to survey & a
meeting fixed with MCGM on 5/1/15 but postponed. Issue resolved without meeting. Total
station survey now to be done by RITES by
5.2.2015. Survey completed on 9.2.15.Land required is now
319.sq m. Since the land is from the footpath of the BMC road, BMC is planning to widen the road
by demolishing 16 buildings for which RITES survey is done.
Discussions with Exec. Engg/Traffic Shri Patel held
with DY.CE. PDC for deciding the demolition as per DP – 28.02.2015.
WRly to approach city survey department. They will provide the name of owner, if it is private
land, BMC has no objection to handover the land
in principle as they can widen the road on the other side.
Shri Shende (9892924769)of MCGM & Shri Sanjay Tyagi of WR to approach City Survey
department jointly as they had asked for some
BMC plans. It was decided that this is BMC land. Now BMC will
advise the cost of land to Railways after clearance of DP department, so that Railways can pay.
Concerned Officer not present. Mr.Shende refused to discuss.
Next meeting planned on 19.6.15 between
DM/suburban and Dy. CE/Const.II (Shri D. Mishra).
29 WR
MCGM
Completion of approaches of ROB’s at
Jogeshwari, so that Level crossings can be closed and Oshiwara station can be
commissioned. a) Construction of Road Over Bridge in
lieu of LC 26 & 27.
b) Construction of Road over Bridge in lieu of LC 24 & 25.
MCGM will complete ROB approaches by May ’15.
Interior progress on schedule as per WRly. Approach held up on east side for 80m . Out of
500 meter due to encroachment. PDC by MCGM will be given in next meeting.
West side encroachment removed. East side
encroachers gone to court. MCGM requested to do out of court settlement for east side at the
Page 19 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
earliest. Issue resolved out of court. PDC’s stated above will be honoured. (May 2015).
No change as on 10.3.15, 24.03.2015 & 07.04.2015.
No representative of MCGM and no discussions on
5.5.15. PDC for south side approach of Jogeshwari –
31.7.15. PDC for north side approach of Jogeshwari –
31.12.15.
50
(a)
50
(b)
MCGM
CR
DRM
Widening of Nanepada Nallah from
Railway culvert to Jai Hind colony. MCGM has already paid Rs.3,43,43,524/-
towards Way Leave Charges of railway
land vide Receipt No MR 063195 dated 24/12/2013 for grant of NOC to carry out
the construction of nallah work in railway premises. Matter pertains to Divisional
Engineer (Land) C.Rly.
Widening of Nanepada Nallah
( below the track )
Item 50 to 56 given by Storm Water Department,
who is not present in the meeting. To be discussed in next meeting of 14/10/14.
The drawing has been returned with remarks on
13/10/14. Meeting held on 20.10.14. Site inspection with
MCGM planned for next week. Site inspection done on 14/11/14 with Se DEN
(South). PDC for approval by DRM – 05/12/14.
DRM BB: GAD for work under Railway Area being
finalized. BOX is not feasible. Pipe crossing will be planned
with 1.8 m dia as done in Kurla upstream. NOC also requested by MCGM, after above is settled.
Drawing approval to be done by 8/1/15. HQ PDC
25/1/15. PDC of 08.1.15 postponed to 22.1.15
HQ PDC now stands at 15.2.15. Proposal with zonal HQ (CE(G)) since 17.02.2015. Original GAD duly signed by division & proposal vetted by finance also sent to HQ on 17.02.15.
Since the money was deposited by BMC in 2013, they requested that 2013 rates to be used. Same
was agreed to. Proposal with CE(G) since 17.02.15
SWD should start the work at the earliest
Proposal duly vetted by finance being sent to Rly.Bd for post facto sanction. Work started by
MCGM. MCGM indicated that old contractor will not
do this work. New tender will be floated. PDC 30.6.15
Railway has submitted plans to MCGM using five
1.8m dia pipes vide Sr. DEN south’s letter no. BB.3512.BMC.NEW/BR/DB dated 24.12.14. PDC
for approval by MCGM 15.05.15.
Page 20 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
New tender will be floated by BMC by 30.6.15. Consultant (M/s MWH) has recommended to
MCGM, the width to be increased from 6m to 16m. Railway clarified that the C-S area of 16m x 1.5 m
(depth) BOX can be met with by multiple pipe of
1.8m dia as suggested by Railways and that this WORK HAS TO BE DONE BY RAILWAYs ONLY.
MCGM will not be permitted to do this work.
MCGM is yet to give permission for pipe pressing
instead of Box pressing as decided long ago in this meeting to facilitate Railway to plan their work.
51 MCGM CR
DRM
Work of widening of Somaiya Nallah from Vidyavihar station (east) to Tansa
pipeline is proposed to be undertaken in
the fair season starting from OCT 2014. NOC for the work is required from C.Rly
to carry out the work. Matter is being pursued with Sr Divn. Engg.(South) C.Rly
.
Photo copy of proposal given by MCGM again on 11/11/14. Site inspection planned on 21/11/14
with Sr DEN (South). Joint inspection done. DRM
will communicate way lease charges by 10/12/14. DRM BB: Existing Somaiya Nallah is 8m wide.
During Joint Inspection, MCGM requested to widen Nallah by 2m width and 7m wide service road all
along the Nallah. MCGM is requested to submit GAD incorporating this requirement. GAD was
awaited from MCGM five copies deposited again
by MCGM on 16/12/14. Revised PDC 15/1/15.
Received on 16.1.15. Hutments on this land will be decided by MCGM only for settlement, if
applicable.
Railways will not be able to spare land for service Road if it is made wider than 3 metres. GAD duly signed by BOs is under revision at OSD level. Proposal was sent to Finance for vetting of leasing amount Rs.34.61 Cr. on 12.02.15. Finance asked feasibility report from all BO which is awaited from Sr.DSTE & Sr.DOM. PDC 24.3.2015. Certificate that the hutments on the land being proposed to be transferred will be rehabilitated by
MCGM under PAP awaited. Reply of MCGM
regarding certificate is still pending.
SWD department, who has to give this certificate
was not present on 07.4.2015. Shri Vhatkar should be pursued by OSD (services).
Matter being chased with CE CWD Mr. Vhatkar, who will call for a meeting before 30.04.15.
Meeting not held by Shri Vhatkar till 5.5.15. Meeting not held by Shri Vhatkar till 26.5.15 also.
Shri Vhatkar is only discussing this point on
phone. MCGM has to finalise the R&R scheme.
Page 21 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
53 MCGM WR
Proposed work of widening and draining of V.H.Desai Nallah parallel to W.Rly
Dahisar (west) from Dahisar Sub way to
creek. NOC for the work is required from WRly
for which site visit and co-ordinations between agencies is required so that
Way Leave Charges can be paid to carry
out the work.
PDC 11/1/15. Feasibility Okayed. On 28/10 Proposal to be submitted by MCGM.
PDC 05/12/14. Letter given by WR again on
16/12. Further PDC for money deposit for MCGM – 7/1/15. Revised PDC 25/1/15.
Concerned MCGM engineer not present. Concerned MCGM engineer not present on
10.2.15. Again not present on 24.2.2015. Cost of
project to be given by MCGM so that WRly can advise the supervision charges. Mr
Khamkar(8879329216) is the concerned engineer – Not present on 10.3.15 also. To be pursued on
phone. Cost of project will be given by MCGM by
10.4.2015 after detailed soil investigation.
No change on 7.4.2015. WR to pursue with MCGM. MCGM assured that estimate will be submitted by
30.04.15. Estimate of Rs. 20 Crs submitted last week.
Railways to indicate the supervision charges.
MCGM to proceed with tendering. MCGM on 26.5.15 is revising the Rs. 20 Cr.
Estimate to include Avdhoot Nagar Nallah also. Estimate of Rs. 32.13 Crs made. Railway
clearance also required by MCGM as these Nallahs are very close to the track
60 CR
MCGM
CAO / C
Kurla Subway:
New Subway for providing East to West connectivity on Kalyan end of Kurla
station has been constructed by Railways
in Oct 2005. Subway could not be commissioned so far due to non-
completion of exit and entry works on the approaches.
CE(Bridges),MCGM vide their letter No.
Ch.E/5060/Bridges dated 31.12.2013 has confirmed that MCGM will execute the part work of
approaches which is falling in MCGM limit. On
confirmation of MCGM, CR has finalized Railway portion (East approach) tender. Railway work will
start by 03.03.2015.West approach to be done by MCGM.
Tender to be floated by MCGM after administrative approval. It was wrongly recorded by MCGM as
floated in previous meeting. PDC for MCGM for
tender schedule finalization by 30.04.2015. No change as on 10.3.15, 24.03.2015 &
07.4.2015. PDC of 30.04.2015 by MCGM will be honoured.
East approach will be done by Rlys by 15.06.15
and West approach work will start in Oct.’15 after tender invitation in first week of May ’15.
No representative of MCGM and no discussions on 5.5.15.
PDC of Oct.’15 will be honoured as indicated by MCGM on 26.5.15. Completion period is
one year.
Page 22 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
64 MCGM CR
Construction of FOB across Harbour Railway line at Govandi station near
Ankur cinema in M/East ward.
Rs. 2,00,23,139/- paid on 28.03.2013.
PDC 30/6/15. No representative of MCGM and no
discussions on 5.5.15
New PDC- 31.8.2015 by Railways.
65 MCGM
CR
Construction of FOB across Harbour
Railway line at Govandi station from Kumud Vidyalaya to Tata Nagar in
M/East ward. Rs. 2,49,79,290/- paid on 28.03.2013.
PDC 30/6/15
No representative of MCGM and no discussions on 5.5.15
New PDC- 30.11.2015 by Railways.
66 MCGM
CR
Construction of FOB across Harbour
Railway line at Mankhurd station in M/East ward.
Rs. 3,11,72,881/- paid on 28.03.2013.
PDC 31/8/15
No representative of MCGM and no discussions on 5.5.15
New PDC- 31.1.2016 by Railways.
67 MCGM CR
Construction of FOB across Harbour Railway line at Kurla from Brahmanwadi
Kurla (West) to Kurla (East) end of
platform No.9 in L ward. Rs. 1,60,000/- paid on 16.05.2000.
Rs. 1,10,00,000/- paid on 01.12.2006. Rs. 30,00,000/- paid on 22.11.2007.
Rs. 34,95,140/- paid on 25.03.2008.
Rs. 2,45,90,263/- paid on 28.03.2013. (Total .. Rs. 4.22 Crores)
PDC 30/11/15 No representative of MCGM and no
discussions on 5.5.15
PDC of 30.11.15 will be honoured by Railway.
80 CR MCGM/GoM
Permission for cutting/relocating of the
trees to facilitate construction of Wadala-Kurla Dedicated Goods Line for Mumbai
Port Trust.
166 nos. of trees are to be cut/ relocated.
The proposal for cutting of the trees was
submitted to Dy. Supdtt of Gardens, ”E” ward,
Byculla of MCGM on 25.02.2012 and thereafter the matter has been followed up a number of times.
Joint inspection of the site has been done with MCGM officials.
Permission of cutting /relocating of trees is still awaited from MCGM, although a period of 2 ½
years has already elapsed and the project of new line is held up.
Photographs to be attached by CAO/C. Reference of 25.2.12 also required.
Joint inspection done on 19.03.2015 with Garden
Supdt., Mr Hire.
Permission by Tree Authority / Garden Suptd. awaited.
No representative of MCGM and no
Page 23 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
discussions on 05.5.15 and 26.5.15.
Tree authority has been given revised photographs of tress involved and the
ground marking of proposed line on 15.6.15.
81 WR
MCGM
Providing covering on MCGM Nallah no.
64 (Krishna Nagri Nallah) of MCGM passing under platform no. 7 & 8 at
Borivali station.
MCGM is requested to take action for its immediate cleaning and providing
covering of the Nallah to avoid inconvenience to public commuting to
and from Borivali.
Western Railway to submit MAP.
MCGM indicated that NOC from adjoining society will be required which may not be true.
To be pursued with Mr. Khamkar (8879329216) –
Not present on 10.3.2015 and 7.4.2015 Under process by MCGM.
WR to pursue and send Officers to MCGM headquarters with Shri Dilip Bhoir.
Shri Bhoir ( 9987148657 ) is yet to decide whether
this Nallah will be covered or not. Drawings and details to be given by WR to
Shri Dusane. Drawing givcen by WR to Shri Dusane on
05.5.15. MCGM to arrange covering of Nallah as per above drawing.
Finally it was decided that Railway will cover
this nallah on its own cost with removable covers ( Each cover to weigh about 60 kg of
monogrammed with WR emblem)
82 CR MCGM/GoM
Permission for cutting/relocating of the
trees to facilitate construction of Pit Lines at Wadi Bunder.
Permission for cutting of 10 nos. of trees is
awaited since 31.12.2014, in connection with the work of construction of maintenance of Pit Lines at
Wadi Bunder. Inspection by officials of Dy.Supdtt of Gardens, MCGM done in Feb’15.
Reminder letter no. DR/DRG/Pit Line/WB dt.
11.03.15 sent by Dy. CE(C) Dadar. Due to delay in permission for cutting of trees, the important work
of construction of Pit Line getting delayed. Joint Meeting done with Garden Supdt. on
19.03.2015.
Permission awaited from Tree Authority. Inspection scheduled before 30.04.15 by Garden
Suptd. No representative of MCGM and no
discussions on 5.5.15 and 26.5.15. Notice issues by Tree authority. By 30.6.15,
permission to work will be awarded..
Page 24 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
84 CR
MCGM
CBE
Repairs of 14 Nos. ROB & re-building of
9 Nos. ROBs at sub-urban area on Mumbai division:
List of 14 Nos. R.O.B for repairs: 1.CSTM - PNVL (HB) – Wadala Km.9/10-11, 2. CSTM-KYN–Ghatkopar (KYN end) Km.19/18-20/1, 3. CSTM-KYN–KJRD Km.24/5-6, 4. CSTM-PNVL (HB) – Chembur-1 Km.17/6-7, 5. CSTM-PNVL(HB) – Chembur-2 Km.17/9-10, 6. CSTM – PNVL (HB) – Govandi Km. 19/2-03, 7. CSTM-KYN – GC ROB (BB end) Km.18/15-16, 8.CSTM-PNVL (HB)–Mankhurd Km. 21/2-03, 9.CSTM-KYN – Mulund Km.30/19-31/1, 10.CSTM-KYN – Tilak Hospital Km. 11/5-06, 11.CSTM-PNVL(HB)–Koliwada Km.11/12-13, 12. CSTM-PNVL(HB) – Chunabhatti Km 12/28-13/1, 13.CSTM-KYN – Curry Road Km. 6/2-3, 14. CSTM-KYN – Tilak ROB Km.9/5-6.
List of 9 Nos. ROB for re-building:
1. CSTM-KYN (Carnac) Km.0/1-2,
2. CSTM-KYN(Hancock)Km.2/16-17, 3.CSTM-KYN(Olivent)Km.3/7-8,
4.CSTM-KYN(TramByculla) Km.3/17-18,
5.CSTM-KYN(Garden)Km.4/5-7, 6.CSTM-KYN(Arthur)Km.5/5-7,
7.CSTM-KYN(Carol(CR+WR Portion) Km.7/9-10,
8.CSTM-KYN(Sion)Km.12/11-12,
9.CSTM-KYN(Nahur) Km.28/6-7
All ROB on Mumbai division have been inspected
and has been noticed that 14 Nos. of ROB have to be repaired and 9 Nos. of ROB have to be rebuild.
Repairing of 2 ROBs i.e. Tilak ROB & Curry Road
ROB, already MCGM deposited an amount of Rs.
4.85 Cr. with Railway.
Repair work of remaining of 12 Nos. of ROBs has been proposed to be carried out and ROB wise
estimate have been prepared with total cost of Rs.
1.47 Cr.
Rebuilding of 2 ROBs i.e. Hancock & Carnac are already proposed and in process.
Dismantling cost of two ROBs already deposited by
MCGM with Railway.
Remaining 7 Nos. of ROBs which have outlived their codal life and on condition basis, required to
rebuild. The estimated cost of rebuilding of these bridges is Rs.172.49 Cr.
Sanction for rebuilding of 7 ROB may be arranged by MCGM.
In this connection matter referred to Chief Engineer (Bridges) MCGM, by Divisional
Engineer/CSTM vide letter No.BB/W/3521/ROB/Genl/DB dt.26.02.2015.
Matter to be pursued with Shri Shrinivas
Addl.Mun.Comm./Eastern suburbs by OSD(services).
Meeting not held. Hoped by 12.5.15. No progress on 26.5.15.. MCGM Commissioner
should attend meeting himself or send a technical
Officer with proper authority.
Municipal Commissioner, MCGM during meeting on 09.06.15 with CBE, CAO/C has stated that commitment of funds will be communicated by 20.06.15 and work shall be carried out by Central Railway.
Page 25 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
85 CR
MCGM
CBE
Repairs to 18 Nos. Public FOB & re
building of 4 Nos. of Public FOB at suburban area of Mumbai division.
Structural audit of all Public FOBs on Mumbai
suburban area has been carried out thoroughly by the field officials of Railway.
4 Nos. of FOBs are need to be replaced on condition basis. The detail estimate cost of
Rs.10.63 Cr. already been intimated to Chief
Engineer (Bridges) MCGM on 12.1.15 & letter dt. 30.03.2015.
Remaining 18 Nos. public FOBs need repair work at cost of Rs. 5.92 Cr. conveyed to Chief Engineer
(Bridges) MCGM vide letter dt.29.1.15 & letter
dt.30.03.2015. In this connection, Municipal Commissioner, MCGM
have been advised by Chief Bridge Engineer/Central Railway vide letter
No.W.294.BR.FOB.Maintenance dt.19.1.2015. Amount yet to be deposited by MCGM.
Matter to be pursued with Shri Shrinivas Addl.Mun.Comm/ Eastern suburbs by OSD(services). Meeting not held yet. It is hoped that meeting will
be held by 12.5.15. No progress on 26.5.15. MCGM Commissioner
should attend meeting himself or send a technical Officer with proper authority.
Municipal Commissioner, MCGM during meeting on 09.06.15 with CBE, CAO/C has stated that funds will be communicated by 20.06.15 and work shall be carried out by Central Railway.
86 CR
MCGM
CE/C/MTP
Construction of ROB at Vikhroli is held
up for want of action to be taken by MCGM on the following items;
a. Construction of 60 m wide D.P. Road on East side of Vikhroli, for which an
assurance was given by MCGM to Hon’ble High Court, Mumbai’s order
dt. 10.03.2010 and 31.03.2010 in
The matter has already been referred to Municipal
Commissioner, MCGM vide this office letter No. EW/221/PL/25 dt. 24.02.2015 followed by
reminder letter dt. 02.04.2015
Approach tenders will be allotted by MCGM
30.09.15
No representative of MCGM and no
Page 26 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
PIL No. 134 of 2009. b. Relocation of Police Chowky on
Vikhroli East to maintain the existing 17 feet width of the access
road (running parallel to track) from
main Pheroj Shah Godrej Road during construction .
c. Taking up construction of the approaches of the proposed ROB by
MCGM which will facilitate launching
of girders of railway span. d. Removal of encroachments, falling
on the alignment for approaches of the ROB and D.P. Road.
discussions on 5.5.15 and on 26.5.15.
MCGM indicated that PDC may be proponed
and tender finalized by 31.7.2015.
87 CR MCGM
Currey Road – New FOB to be constructed at CSTM end.
Location of landing on west side in MCGM area to be finalized.
Since MCGM is not giving permission of any other option we should complete the work
by landing the FOB at proposed location.
91 WR MCGM
Culvert No 53 & 54 near Malad Station. Railway has proposed
widening as both sides of the Nallah have been widened
Remarks of MCGM shall be given by 15.10.15.
Estimate should be given by WR by 02.6.15.
Meeting held on 4.6.15 and it was decided to press pipes on both sides of existing culvert.
MCGM to submit plans.
92 MCGM CR
Mukhyadhyapak Nallah and Dharavi Nallah- For widening Rs. 6 Cr paid
in 2008
Central Railway to give position in next meeting.
C.Rly failed to comment this case in their
records.
MCGM requested to give details of money paid. Site visit also to be done by S/Shri
V.L.Kamble,Dy.Ch.Eng.(SWD)City, Shri Y.P. Junnarkar,A.E.(SWD)MCGM&Y.P.Singh(Rlys)
on 27.5.15 As requested by MCGM.
Inspection done on 27.5.15 and work done
is Rs. 6 Cr shown.
Page 27 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
93 MCGM
CR
Chunabhatti drain was damaged by
Railways. Railways have paid Rs.55
lakhs for upside work to MCGM.
The work has to be done by MCGM . MCGM
can complete the work and raise bills on
Railways which will be honoured.
96 MRVC MCGM
Permission for Tree cutting: a) Tree cutting at Wadala Road
b) Tree cutting at Dockyard
Road
c) Tree cutting at Reay Road
d) Tree cutting at Kings Circle
Proposal seeking permission for tree cutting with details have already been submitted to
MCGM’s Byculla Office.
97 MRVC
MCGM
Permission for geo-technical
examination is required at Dockyard Road.
For safe execution of rock cutting, MCGM’s
permission for Detailed Investigation of the rock mass, by drilling the bore hole is
required. The geo technical is t be carried out from top of the hillock which comes
under MCGM area. In this regard, a letter to Hydraulic Engineer/MCGM vide letter no
W/MRVC/167/1/BMC dated 05.02.15 has
been written.
98 MRVC
MCGM
Additional Exit/entry point in the
middle of PF no. 1 at Wadala Road.
MCGM has been approached to permit
additional exit/entry at middle of PF no. 1 on west side through their approach road to
sewage plant by shifting the gates.
Page 28 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
99 MRVC MCGM
Permission for skywalk to Rafi Ahmed Kidwai Marg and erection of
pier at Wadala Road station
Modified proposal in consultation with CE(sewage dept) was sent to
Exe.Engr(Sew.) on 03.06.15 after joint inspection of site. A reminder has also been
already sent to CE (Sewage operations) on
15.04.15.
103 MCGM
WR
Proposed ROB between Lower Parel
and Mahalaxmi Railway station connecting Dr. E. Moses Road and
N.M. Joshi Road
GAD was submitted on 21.3.11 and revised
GAD on 14.9.12. Further the compliance was again sent on 22.03.13. Western Railway
vide letter 20.2.14 informed that the said
ROB is not feasible however the matter was again discussed with CBE on 6.7.15. based
on which the GAD is under preparation
104 MCGM CR
Construction of ROB at Vidhyavihar Railway Station
Revised GAD was submitted to Railways by MCGM on 8.5.15. Railways queries dated
5.6.15 were complied on 29.6.15. The GAD
was discussed on 30.6.15. Revised GAD awaited from MCGM by 30.7.15.
Page 29 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
11 CR TMC
CAO /C
For construction of ROB at level crossing no. 29-C at diva station, consent of TMC
for sharing 50 % of the cost of the ROB and approval of the GAD are held up.
Encroachments on the approach road are the main cause of delay. TMC decided to do a survey and
come up with revised plan of action by 15.11.14. Board meeting of Dec ’14 is likely to clear this
project. None attended from TMC on 6/1/15. Even
GAD is yet to be approved by TMC. TMC not present on 20.1.15.
TMC attended on 10.2.15. Plan for new alignment submitted with CAO/C. East side landing of ROB
has been shown to be on the proposed platforms
of line No.5 & 6. To be rectified by TMC. PDC 03.03.2015.
Rough sketch made on 10/3/15 during meeting given by TMC on 10/3/15 to DRM/BB to cross
check whether proposed landing is now interfering with Railway land / Buildings. Rough sketch returned to TMC for incorporating Railways observations. TMC has been intimated that proposed alignment is interfering with railway land vide letter dated 13.03.15.
Discussed in A.S. (Transport)‘s meeting on
23.04.15. TMC will give final plan of DIVA ROB by 19.5.15
No. rep on 26.5.15
TMC wanted 3 more months to modify plans and
change the DP.
Proposal sent to General Body of TMC
59 CR TMC
CAO /C
Construction of KHAREGAON ROB in lieu of LC No. 28/C between Thane-Kalwa on
cost sharing basis (50:50) between CR &
TMC, sanctioned in the year 2012-13. Approach land is with Court receiver.
The work in Railway portion is in progress in full swing but the work on approaches is yet to be
started by TMC. This is likely to result into delay in
commissioning of the ROB and consequently in closing the LC gate.
Joint letter to be written to Court receiver. Draft by TMC given on 26/12/14. Rly will write to collector
as desired by TMC. TMC will now request court
with the help of collector. TMC absent on 6/1/15. TMC absent on 20.1.15 also. TMC attended on
10.2.15. No further progress on land issue. Copy of letter written by Railways to be given to TMC by
Secretary. Letter to collector issued on 24.02.2015. Copy given to TMC. TMC to pursue the
Page 30 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
matter with Court and Collector office. All the 3 piers in Railway area completed.
Girder fabrication started. Approaches to be made by TMC – Land under dispute.
No development. Land acquisition held up in
Collector office. Shri Malegaonkar requested to intervene.
No. rep on 26.5.15
No progress from Collector office till
16.06.15.
88 CR TMC
Approach Road to Kalva Station on west side
Only elevated Road is possible. Scheme submitted to TMC almost two months back.
Final drawing will be submitted by TMC on
19.5.15. Funds will be managed separately. No. rep on 26.5.15
TMC agreed to give the concept plan by
30.06.15.
Page 31 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
12 CR KDMC
CAO /C
ROB at level crossing no 47-B between Shahad- Ambivali station has been
completed in Railway portion but work on the approaches by KDMC is at stand
still.
Contractor of KMDC is not progressing the work. Due to problem of land acquisition. 12 out of 16
foundation works started, remaining 4 foundations, one will be started by Dec.14.
(One NRC pipeline to be shifted) work of three
foundations also started. June 15 requested as final date.
Land dispute of 2 piers will be solved by KDMC by 3/1/2015. KDMC is negotiating with a builder (Mr
Gadda) who is having one of the two POA of the
land lady. Expected PDC 31/1/15. FIR lodged by land owner. Progress to be reviewed in next
meeting. Approved GAD of 38C (Thakurli gate) submitted by KDMC on 16/12/14.
Present on 24.02.2015 and 10.3.15. KDMC has no solution but to wait for
litigation to conclude.
KDMC has started pier cap casting work.
68 KDMC
CR
Construction of 24.00 m. Wide Railway
parallel D.P. Road from Mhasoba Nagar
Thakurli to Patripool,Kalyan Benefits:-This road connects Kalyan -
Dombivli parallel to railway line reduces road length by 3.0 Km.
Useful for Railway passengers.
Railway Land required at a) Mhasoba
Nagar Thakurli East total lenght 60.00
Mt and b) Kachora Gaon total length
85.00 Mt .
Inform to KDMC by Rlys. vide L.No.
BB/W/6001/LM/KDMC-Road/THK-
KYN/449/DB dated 22/12/2014 to clarify the proposal.
Feasibility to be studied by OSD (services)
for sparing ( 60 + 85 ) x 24 sq. meters.
None present on 24.02.2015 and 10.3.15.
Proposal needs modification, feasibility of sparing additional land and cost being
worked out.
Cost will be advised to KDMC on 25.04.15. Rs.24 Cr advised to KDMC. KDMC expressed
inability to pay on 26.5.15
As per field inspection done on 30.6.15l; Railways agreed to execute land for land for
above to facilitate Govt. land acquisition by
C.Rly for 5th & 6th line.
69 KDMC
CR
15.00 Meter wide DP road near Mahila Samiti School at Thakurli East.
Railway has demanded Rs 14.07 Crs
towards lease charges of 3510 Sq.mt which comes out to be (Rs 40,095 per
Sq.mt) the rates are commercial rates.
(Draft Agreement submitted to Commissioner KDMC on 5/3/2012 for
signing is still awaited)
OSD / Services to study the ROB drawing of KDMC.
None present on 24.02.2015 and 10.3.15.
Page 32 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
It is requested to correct the lease charges as per the open land rate based
on State ready reckoner.
Proposal for flyover submitted as per commercial rates of ready reckoner.
KDMC will hold meeting with OSD(S) on 24.04.15 to decide the rates at 1100 hrs.
Alignment to be changed as suggested by
Railways. This will be signed jointly by OSD /BB and
project execution /KDMC by 30.7.15.
73 KDMC
CR/
CAO/C
ROB at Level Crossing gate no 38-C
between Thakurli and Kalyan. Detail
construction estimate is sanction by Central Railway on 20/11/2013 for Rs.
1392.7 Lakhs Since work is on cost sharing. To join this ROB to Railway
parallel road the Elevated road is
proposed and GAD is approved. It is requested to give required Railway
land without any value charges. KDMC has submitted the agreement for the
said work to Dy CE(Const) GC on Dt 25.11.2014 for approval and sign.It is
requested to accept the agreement and
execute it on Railways part so as to deposit Rs. 242.63 lakhs to Railway as
KDMC share.
(The work executed by CAO/C agreement signed &
copy of same send to KDMC on 31.12.14)
One water pipe line of KDMC on Thakurli
East is coming in the way of foundation. KDMC have to shift it early.
None present on 24.02.2015 and 10.3.15.
Revised Tenders being invited by KDMC due to no response.
No representative of KDMC & no discussions on 05.05.15.
Tender invited. To be finalized by July end.
This is a fourth call. No response received.
Still KDMC is hopeful to fix agency by 31.8.15.
76 KDMC
CR
ROB at Level Crossing NO.51-A between Ambivali and Titwala station.
KDMC has submitted GAD by vide letter No.KDMC/CE/18, 21/05/2014 to Sr. DEN
[N/E] CSTM. GAD approval requested.
(GAD approved and sent to HQ on 31.12.14) OSD BB : Remarks from HQ received on 03.02.15 & sent to KDMC on 05.03.15.
None present on 24.02.2015 and 10.3.15. KDMC has been asked to revise drawing as per HQ remarks vide letter dated 05.03.15.
PDC 07.05.15. No representative of KDMC & no discussions on
05.05.15.
Corrected GAD Submitted to CAO/C on 20.5.15. Ghatkopar Dy CE cleared the GAD. KDMC will
submit the GAD to CAO/C by 30.06.15.
Launching scheme is now being worked again with reduced span of 10m instead of
13m.
PDC – 31.7.15
Page 33 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
77 KDMC
CR
Construction of Skywalk under SATIS Kalyan East
Since Elevated booking office is included in Phase II work and which is under
tendering process it is not possible to
construct elevated booking structure immediately. Due to this work of Phase I
is prolonged. Hence it is requested to dismantle the existing booking shed and
SBI ATM to carry further foundation at
two location. KDMC is willing to construct Temporary booking office on 5.00 wide
span as done by railway on west side.
Sr No 68 to 77 to be discussed by KDMC with OSD services in a detailed meeting at 1600
hrs on 20.01.15. None present on 24.02.2015 and 10.3.15.
Tender for overhead booking office under finalizing
by KDMC. Permission to connect sky walk to FOB will
be given after acceptance letter of Booking office is issued. To be done on the same day.
No representative of KDMC & no discussions
on 05.05.15.
Acceptation letter of Booking office will be issued by 05.6.15
Shifting of indicator cables, telephone cables
to be done by C.Rly by 31.8.15.
Page 34 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
19 CR
GoM
DRM
NAGOTHANE-ROHA (160KMPH)
LAND ENCROACHMENT & Land acquisitions
GoM clarified on 23.09.14 that this encroachment
will have to be removed by Railways only. GoM will, however, provide police bandobast. To be
done after elections. Planned in next 10 days. CAO ( C) to fence & put
Cess material on the same day. Meanwhile a copy
of wrongly drawn minutes was seen. These will be cancelled and as when encroachments are
removed, track will be slewed to increase the speed.
STAY obtained by encroachers to be vacated by
CAO/C. Court has given stay order against elimination
of structure till final decision of court. Now we
will avoid the encroachments by using
different alignment. It was decided on 07.4.2015 that this work will be done under
police protection for which DC (Raigad) may be requested.
20 CR
GoM
GM
Payment of MAHAGENCO: An
outstanding of `84.34 Crs on net
demurrage and other charges is pending
with MAHAGENCO for payment to
Central Railway.
GoM is requested to offset the electricity bills of
Central Railway by the amount of agreed upon demurrage. Issue is pending for last 18 months.
GoM indicated that MAHAGENCO officers visit CS
every Thursday in 2nd half. CCM/CR to ask for slot on 20/11/14. Meeting cancelled by CS. New date
awaited. To be fixed after new set of officers settle down. Agenda for next meeting with
Transport Secretary to finalized by CAO/C.
Page 35 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
21 CR
GoM
GM
a) Return of the land taken over by
Collector, Solapur without Railway’s consent near Solapur Station. (101
crore.)
GoM has advised CR to prefer an appeal with Divl.
Commissioner, Pune in the matter. DRM/SUR advised to file an appeal.
Previous Chief Secretary had agreed to a proposal that transactions between CR and GoM shall be
debited and Credited as per the then value of land
in a Register of Running accounts. 20/11/14 fixed for Meeting with CS. Meeting
cancelled by CS. New meeting date awaited. Not present on 10.3.15.
This issue will be raised with Transport
Secretary. Meeting done on 23.4.15. This item will be
discussed in the next meeting of Addl Chief Secy Transport.
b) Allotment of Land at Pune in lieu of
land already handed over between Latur-Harangul in Latur District. (14
crore)
C) Relinquishment of land at Belapur-Shevgaon in Ahmednagar district.
(18 crore)
D) Balance payment regarding Land
handed over to PMC, Pune for widening of road. (1.29 crore)
22 CR GoM
GM
Levy of Octroi /LT to m/s IOCL for HSD oil at Miraj.
Miraj Municipality is the only authority in Maharashtra levying the tax for last 3 years. This
money has to be refunded. COS / C.Rly to press for arrears.
Not present on 10.3.15.
24 GoM
CR
CAO /C
SANCTION OF EIGHT PROJECTS:
i. WADSA–DESAIGANJ-GADCHIROLI
NEW LINE.
Hon’ble CM has written to Hon’ble MR requesting
to expedite sanction of pending projects.
i. Revised estimate of Rs 469 Cr has been checked
by PWD/Nagpur. Rs 10 Crs will be release shortly. Part estimate under sanction with
Railway Board. FLS and Geo- technical exploration has been completed.
Hon’ble CM requested Hon’ble MR to expedite
sanction of revised estimates for the project. Rs. 10 crores released on 05.02.15. SECR has revised the estimate to Rs. 403 cr not yet sanctioned by Railway Board
(GoM has cleared this project of Rs.469
crores)
Page 36 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
ii.GADCHANDUR-ADILABAD NEW LINE.
iii. PUNE-NASIK - NEW LINE.
iv. KARAD-CHIPLUN - NEW LINE.
v.MANMAD-DHULE-INDORE-NEW LINE
vi.NAGPUR-NAGBHID GAUGE CONVERSION.
vii.Ahmednagar–Beed-Parli-
ii. Survey report submitted to Rly Board on 03.05.2013 at a cost of 48.4 crs. ROR
8.35% with 50% sharing with GoM.
Status: Project not sanctioned yet.
iii. Survey report submitted to Rly Board on
12.03.2010 at projected cost of 1899.6 crs with ROR less than (-)2.84%. Revised ROR with 50%
cost sharing by GoM is 4.11%, sent to Rly Board on 28.02.12.
Status: Project not sanctioned yet.
iv. Survey Report submitted to Rly. Board on
29.01.2010 at projected cost of 928.1 crs with ROR (-) 4.37%. Revised project cost with 50%
share of GoM with ROR (-) 3.17%. KRCL is likely to do this project.
Proposal for participating in the project is under consideration of Maharashtra Maritime Board.
Project sanctioned in Budget by 20.5.15
v. Updated Report submitted to Rly Board in 2004 with revised cost of Rs. 2257 crs and ROR 9.52%.
Status: Project not sanctioned yet.
vi. Project sanctioned in 2013-14 at a cost of 401 crs. Final location survey and estimate preparation
has been started. Board have stipulated that no expenditure is to be
incurred by SECR without Boards approval.
Hon’ble MR has been requested by Hon’ble CM to expedite pending approval.
Page 37 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Vaijnath
viii.Wardha - Nanded
Another Rs.125 crore earmarked by Railways in FY
2015-16 (GoM share till 31.03.2015 – Rs. 208.75 Crs & MR share till 31.03.2015 – Rs. 276.25 Crs).
There are 31 cases of land acquisition due to
change of alignment to be reviewed by CAO/C.
GoM has released Rs. 208.75 Cr till 31.03.15 GoM has approved cost sharing for the
revised estimate of Rs. 2826 crores.
Sanction of Rly Bd is awaited.
GoM share till 31.03.2015 – Rs. 55 Crs
MR share till 31.03.2015 – Rs. 42.31 Crs
Rs 35 Crs earmarked by Railways in 2015-16. Matching funds to be arranged by
GoM.
GoM has decided to contribute 40% of
revised estimate of Rs.2500 crores. A total of 68.6 crores are the budget layout for
Beed- Parli and Wardha – Nanded.
26 WR
PS(Forest)
GoM, Collector Mumbai
Suburban, District
Collector/
Suburban, Commssioner
Konkan
Land Acquisition at 4 locations (Total
1178 sqm) i.e. Vile Parle (South) &
(North), Malad (West) and Borivali (South) in connection with 6th line work
between Mumbai Central to Borivali. – Application for Land acquisition
submitted on 15.10.2012 and 25% of
Estimated cost of land has been deposited on 18.02.14 and 14.03.14.
OSD (Rlys) has been asked to coordinate with
collector (suburban) to expedite land acquisition
cases. Action to be taken after elections. Documents
given to OSD (Rlys) on 17.10.14 Rs 48 lakhs deposited with GoM in March ’14. Sec
IV notification for land acquisition by Dec ’14.
Meeting held with DM (Suburban) on 25/11/14. DM (Sub) advised that this acquisition will be done
under new rates with fresh social impacts study to be done after WR deposits charges for the same.
Collector requested to exempt social impact study
under section 9, section 40 of new act on 6.1.2014.
Shri Malegaonkar given a copy of reference made to collector for facilitating the permission.
Not present on 10.3.15. Shri Malegaonkar requested to arrange exemption
from social impact study.
Meeting held with Dy. Collector on
19.6.2015, where GoM agreed that this clause is not applicable to Railways. Revised
proposal sent to Dy. Collector / Bandra on
30.6.15.
40 CR
GoM
DRM
Notices have been served on Igatpuri
Municipal Corporation and Manas Resort
to explain the permission granted for
construction and whether they have
Meanwhile GoM will check the authorized
existence of the rear building and the swimming pool
NOCs of Manas resort have been withdrawn by
Page 38 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
resulted in the hill slope being unstable.
The foundation of the Resort’s rear
building has been exposed during the
landslide on 30/7/14 The scheme
submitted by Manas Resort for repairs is
under scrutiny.
Igatpuri corporation OSD(services) to organize clear indication to all authorities that the
construction done in 2010 onwards is dangerous and unsafe for travelling public.
DRM BB: Manas Resorts has submitted the
proposal to carry all protection outside Railway boundary to ensure safety of passengers.
Protection plan has to be cleared by CRS. Plan submitted by Manas Resort in end of
Dec.2014.Division checking by 30.1.2015.
OSD BB: Plan with HQ, who have further send it for proof checking at COEP, Pune. Meanwhile drain is cleared & loose earth is removed in railway boundary
Not present on 10.3.15.
83 CR Sec(Forest),
Revenue & Forest Dept, OSD & Jt
Sec (Rlys), Home (Transport) Dept
of GoM,
CR Dy. Conservator
of Forest (Territorial),
Shahapur and OSD & Jt Sec (Rlys) GoM,
Delay in land acquisition for 3rd line between Kalyan-Kasara.
a) Proposal for acquisition of land
in 38 villages (Kalyan & Shahapura
Taluka) were submitted to District Collector, Thane during June 2014 to
December 2014. Land acquisition still to be initiated. Matter has been taken up by
CAO/C with Secretary (Forest), Revenue
& Forest Dept.GoM with copy to OSD & Joint Secretary (Rlys, Home Dept. to
exempt the Social Impact Assessment study and to expedite the land
acquisition process. Due to delay in land acquisition, the important project is
getting delayed.
b) In the mean while, forest land
(Govt land) may be transferred to
Railways. The matter has been taken up with Dy. Conservator of Forest
(Territorial), Shahapur vide letter no. DyCe/C/GC/41/LA dt. 11.03.15 by Dy
CE/C/GC.
Railway contracts for major bridges
awarded. Earth work is likely to start in August 2015.
Land acquisition proposal will go to Nagpur for transfer of forest land.
94 DFCCIL GoM
Transfer of Government Land Approximately 60.82 Ha of Government Land in Palghar, Thane & Raigad district in 52 villages is
required for the DFC project. Out of these, approval of GoM is given for 0.64 Ha of land in 3
villages for all other villages the proposals are
pending at various stages and needs to be cleared as early as possible.
Meeting held with CPM/DFC on 28.4.15.
Page 39 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
Target details for land acquisition have been fixed.
95 CR
GoM
Electrification of Pune-Daund &
Manmad-Daund sections is in
advance stage of completion. However, the progress of 132 kv
transmission line work for giving feed to Railway’s Traction Sub-
stations, being executed MSETCL is very slow.
1. Yevat 9.76 crore paid on
02.5.13 2. Daund 18.89 crore paid on
02.05.13 3. Nimbalak 10.70 crore paid
on 21.12.10
4. Kopargaon 5.5 crore (2nd circuit) 03.06.15
Sr. no. 1 & 2 work is very slow.
For Sr. 3. Nimbalak – Foundations for 4 Towers
pending since long time. For Sr. 4- Tender for 2nd circuit is yet to be invited
by MSETCL.
Shri Malegaonkar requested to pursue this
matter with Shri D.P. Gupta, CMD/MSETCL.
Page 40 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
33 MRVC
GoM/TMC
CE / G
Commercial Development of
Railway Land at Thane, Mulund & Bhandup
Approval from the Govt. of
Maharashtra for Mulund Additional survey by TMC as directed
by PS/UDD.
Under process with GoM.
New meeting of committee made by CS on this subject is expected to be held by last week of
October. Now last week of November ’14 TMC finished their
work of clearance.
Now pending with GoM. For change of land use and grant of FSI of
3 (PS of UD1) MRVC to hold a meeting with UD1.
No change as on 10.3.15 & 7.4.2015.
Proposal still with PS(UD-I). MRVC to pursue.
34 MRVC
GoM
Redevelopment of 20 suburban Stations
alongwith station area development –
Mumbai Central, Lower Parel, Dadar (W), Bandra, Andheri, Goregaon, Borivali,
Mira Road, Bhayander, Virar on Western Line & Dadar (C), Kurla, Ghatkopar,
Mulund, Thane, Dombivali, Kalyan, Shahad on Central Line and Wadala
Road, Chembur on Harbour line.
This Project needs about Rs. 2000 cr. to
seamlessly transfer commuters between Railways,
Metro and BEST. Most of the Railways rooms will have to go to First floor air space. GoM has to
foot the bill. Presentations made by MRVC to CR on 26.09.14. Details to be finalized and
presented to the new Govt. by Nov. ’14. PDC 7/1/15 by MRVC. Sent to Board by MRVC
for approval as part of MUTP III.
No change as on 10.3.15 & 07.4.2015.
35 MRVC GoM, MMRDA,
MCGM,TMC, CR,WR, LOCAL
MUNICIPAL
BODIES.
Proposed mid-section trespass control works at 20 locations on CR/WR/Harbour
line – finalization of study by J. J. School of Architecture.
44 Locations earmarked. We can do 20 immediately provided GoM shares the cost like
they are sharing on existing 12 stations. Presentation on sites on CR made on 26.09.14.
Detailed proposal will be examined by CR and thereafter by the new Govt.
PDC 7/1/15 by MRVC.
Sent to Board by MRVC for approval as part of MUTP III.
No change as on 10.3.15 & 07.4.2015.
Page 41 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
36 &
57
MRVC CR
CSTE & DRM
Running of 12 car on Harbour line
MRVC is executing the infrastructure works. PDC: Dec.’14 – Wadala. Jan.’15 – CSTM.
CR will have to arrange for measurement of coupler forces (1 in 37) & for new stabling
yards for EMUs.
CSTM block will be for 3 days to extend platform no. 1 & 2. (CR has to arrange rakes by AC-DC
conversion) About 1100 crores required by CR for rolling
stock. No change as on 10.3.15 & 07.4.2015.
37 MRVC CR
CAO /C
5th & 6th line between CSTM-Kurla. 1st phase Kurla-Parel.
Detailed estimate for 5th and 6th line sanctioned. Tenders for works will be invited shortly.
Resettlement to be done expeditiously by MMRDA. For 642 hutments between (10/22 to 12/10) & 47
hutments at Parel. (To be coordinated by MRVC) Partial list of
structure handed over to MMRDA on 30.09.14.
Complete list will be made by SPARC by October 2014.Papers submitted to Distt Collector.
Point to be discussed separately as decided by CM on 3/12/14.
Presentation (CSTM–Sandhurst) submitted to CM office. This was discussed on 08/1/15 between Hon’ble CM & Hon’ble MR. SPARC report on R&R
pending with MRVC. PDC 15.3.15 for MRVC.
PDC shifted to 30.3.2015 & now to
30.4.2015. PDC shifted to 30.6.15.
Page 42 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with
Nodal Agency
38 MRVC GoM, MMRDA,
CIDCO
MUTP III Proposal
Quadrupling of Virar-Dahanu Road, Doubling of Panvel-Karjat,
New suburban corridor between Airoli-
Kalwa on Trans-Harbour Link,Virar-Vasai-Panvel New Suburban Corridor,
Extension of Harbour line from Goregaon to Borivali, 5th & 6th line between
Borivali-Virar, 3rd & 4th line between
Kalyan-Kasara, 3rd & 4th line between Kalyan-Karjat, Capacity enhancement &
augmentation work, Fast elevated corridor between CST-Kurla-Panvel,
Elevated corridor between Oval Maidan-Virar.
With Ministry of Railways.
Part detail estimate costing 38.85cr sanctioned vide letter NO.2013/W1/CR/Kalyan-Kasara dt.
16.01.2014. Full detail estimate under preparation
Pending with Railway Board since 15/11/13. C.Rly to clear these projects.
MRVC has sent these to Board without C.Rly
comments, as per normal procedure.
No change as on 10.3.15 & 07.4.2015.
63 MBMC
WR
Construction 10M wide of subway for
pedestrians and light vehicles at
Bhayandar station at Km 43/5A–6A below platform and running tracks by
trenchless technology.
MBMC deposited Rs.9 lakhs in June 2006 and work
started in May 2015 after CRS & other approvals.
75% work has been completed till June 2014 and further work stopped by WR for ‘Non-payment of
codal charges’ of Rs.16.83 Cr. MBMC requested WR in Sept.2014 for permission
to resume work and assured payments due after getting approval from General Body meeting.
Mira Bhayandar Municipal official Absent on 20.01.2015. 3 Crore being paid today. Rest
will be paid in two installments on June ’15 & Dec ’15.
Meetings held with WR during Jan’15, and as per
letter dated 15.01.2015, WR permitted MBMC to commence work.
MBMC expresses gratitude for cooperation and help.
None present from MBMC on 24.02.2015 and
21.04.15.
No representative of MBMC & no discussions on 05.05.15 & 26.05.15.
Page 44 of 56
ITEM CLOSED:
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
3 MMRDA CR
Mumbai Monorail Project revised GAD for obligatory span crossing railway track at
Currey Road railway station.
Revised GAD approved on 05.08.2014. GAD now under C.R.S. approval.
During CRS inspection on 08.09.2014, modification to GAD has been suggested to
Monorail Authorities (Mr. Murthy) regarding
infringements. Revised GAD received in division sent to CRS on 24.09.2014.
CRS sanction received and conveyed to MMRDA. ITEM CLOSED.
Item reopened on 10.03.15 Launching scheme
to be submitted to CRS on 30.3.15. Launching scheme given on 12.3.2015,
approved by division and HQ and submitted to CRS
Meeting with CRS planned by MMRDA on 08.04.2015.
Sanction of CRS received on 17.4.2015.
ITEM CLOSED
4 MMRDA
CR
DRM/BB
Mumbai Monorail Project obligatory span
crossing railway track crossing Wadala
railway yard.
Compliance to CRS observation dated
13.02,2014 submitted to CRS on 16/9/14. Case
pending with CRS. DRM/BB to give fresh application to CRS.
Presentation in CRS office fixed today at 1600 hrs.
Revised GAD approved by HQ.(25.11.14) During
presentation CRS, wanted revised launching scheme from MMRDA. PDC 01/01/2015.
Revised PDC 15/1/15 (MMRDA decided to discus with CRS)
Presentation was done on 13.01.15 with CRS. Revised launching scheme as advised by CRS is
awaited from MMRDA.
This is being submitted to Division on date. Revised launching scheme submitted to Mumbai
division on 19.01.15 and is under divisional approval.
Approval by Headquarters by 28.02.15
Launching scheme was discussed during
meeting on 24.2.2015 to finalized details of winches and terminology used on
drawings by the consultant. CBE: TAD approved by HQ on 24.02.15.
CRS sanction application submitted to CRS
on 02.03.15. MMRDA has asked a dated from CRS for
presentation. CRS sanction received on 04.03.15
ITEM CLOSED.
Page 45 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
10 CR
MCGM,
GoM
GM
Permission for cutting / transplanting of
62 nos. trees for EMU Carshed at Kurla.
Development of maintenance facility for 15 car rakes is held up.
Under process with Municipal secretary.
TDC 5/10/14 New TDC 15/10/14.
Next meeting of committee after election will clear this. Work sanctioned. Letter likely to be
issued in a week. Letter issued on last week of November.
CAO/C: Money has been deposited by Railways
for tree cutting. Now trees can be cut under supervision of
Superintendent of Gardens / Byculla. ITEM CLOSED.
13 CR
GoM/CIDCO
CAO /C
a) Releasing of funds for cost
sharing of railway projects Thane-Turbhe-Nerul / Vashi and
Nerul/Belapur-Seawood-Uran.
The fund utilization statement for Nerul-Belapur-
Uran corridor upto August 2014 was asked for release of further funds.
The fund utilization statement for Nerul-Belapur-Uran corridor up to August 2014 was given on
15.09.2014 and the process for release of funds
is in progress.
C.Rly will give forecast of fund utilization up to March 2015 also by 30.9.14 to enable CIDCO to
release funds, regularly every month, as discussed.
CIDCO informed Railways that they will have to
submit the proper reconciliation of the funds duly certified by their Accounts Department to
enable Advance Payments made by CIDCO. TDC for release of funds (24 crores) 10/10/14.
Cheque of 24 Crores received on 14/10/14.
Funds for Seawood – Uran have to be sanctioned by 31/12/14 to avoid break in
progress. Rs. 72 Crore deposited by CIDCO ON 25.11.14.
ITEM CLOSED
c) Approval for revised estimate for Belapur-Panvel railway project.
Revised cost of Rs. 438 Crores
CIDCO will convey the terms and the approvals in the week commencing 30/9/14.
Letter issued by CIDCO to Railways on 24.09.2014. Proposal sent to Railway Board on
10.10.14.
Board sanction expected by 31/12/14. CAO (C) is pursuing with Board.
Estimate was put up to MR. Since estimates also will now not go upto MR, revised processing
methodology in Board will be known by 10.3.15.
This is likely to be delayed till 30.3.2015 now. No change as on 24.03.2015 & 07.4.2015.
Estimate sanctioned on last week of April
15 by Railway Board.
ITEM CLOSED ON 05.05.15.
Page 46 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
14 CR
GoM/CIDCO
GM
Approval for sharing of 2/3rd cost of
project and making required land
available to railways for Panvel coaching complex.
Presentation was given to CIDCO on 04.07.14 as
desired. A meeting with Chief Secretary &
CIDCO was also held in July. Draft minutes of the meetings received from CIDCO. GoM
signature still pending. It was decided with CS this presentation of
PANVEL will now have to be repeated again-
Transport Secretary will chair the meetings, may be after UMTA Core meeting on 02.03.2015 as
indicated on 24.02.2015. Still pending with Transport Secretary as on 10.3.2015. Transport
Secretary has, however held an internal meeting.
Meeting with Railways planned on 23.04.15.
ITEM CLOSED ON 05.05.15.
18 CR
GoM
GM
` 5 crs out of ` 10.36 crs has been
released. The remaining funds shall also be transferred to Central Railway so that
developmental works for Kumbh Mela at Nasik can be completed without any
delay.
Release of funds expected by 15.10.14. Any
further delay beyond this will entail in discharge of tenders.
ITEM CLOSED.
23 CR
GoM
CAO / C
Approval for permission of mining the
moorum & stone at Daund-Gulbarga
doubling project.
ITEM CLOSED.
28 WR
MCGM, BEST,
JT COMMISSION
ER POLICE (TRAFFIC)
Construction of Flyover to facilitate
smooth flow of traffic between Bandra and Bandra Terminus. – MCGM has
agreed to hand over 296 sqm of land near water mains for widening of
Existing Road on payment of easement charges. However, there are
encroachments and license vendors on
this land. MCGM is requested to hand over Encumbrance free land early for
widening of road.
BEST officials have inspected the site and
agreed with planning of Railways. Traffic police have agreed to provide additional deployment
during construction of ramp. MCGM was asked to expedite early handing over of encumbrance
free land for widening of road. TDC for hand over of 296 sqm land – 17/10/14.
Assistant commissioner (H ward) MCGM is to be
requested for handing over of land. A cheque of Rs 90 lakhs ready with WR. MCGM to remove
licensees presently occupying the land. MCGM representative assured that this will be
done after elections with the help of police.
MCGM: Action was proposed to be taken on 08.10.14 but due to elections, postponed to
10.11.2014. According to the availability of police protection,
removal of encroachment at Gate no.18 Bandra
(east) is proposed on 10.11.14. Concerned officers of water department (MCGM) and
Railways informed. Work likely to be done today.
Encroachment removed on 11/11/14. 90.45 lakhs deposited on 1/12/14 . Permission
received from MCGM on 11/12/14.
ITEM CLOSED
Page 47 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
30 WR
CR
DRM/BB
Handing over of 2731Sqm land at Curry
Road depot from Central Railways to
Western Railways in connection 6th line work between Mumbai Central to
Borivali.
Joint inspection was carried out on 19/9/14 and
there was agreement for transfer of land.
DRM / BB: The revised drawings to be submitted by WR
and transfer will be ensured after consulting CAO (C) regarding requirements of 5th and 6th
lines and Parel Terminus.
This issue will be decided by CRS on common
drawing to be made by CAO (C) by 30/11/14. WR has given an prima facie acceptable plan on
4/12/14. PDC for CR 7/1/15.
CR agreed that WR can take the narrow strip of
road as shown on drawing after reconstructing the CR structure at nearby locations along with
new boundary wall. ITEM CLOSED.
32 MRVC CR,MbPT,
CIDCO, MMRDA
CAO / C & DRM
Fast elevated corridor between CST-Panvel:
Alignment through BPT
Navi Mumbai Area
Land Acquisition & Resettlement &
Rehabilitation.
Meeting of CIDCO , MMRDA , MRVC, C.Rly as ordered by CM.
20% of land required (air space) is from MbPT. 70% will be air space of C.Rly.
Details with alignment particulars (between Reay Road & Wadala) to be given to
MbPT & MCGM again.
CIDCO has certain issues:
The alignment shown in the Navi Mumbai area needs to be resolved since it infringes on
existing structures. At Seawood station, the MRVC has proposed
Fast Track Corridor at grade passing through the
Seawood Station. The clearance from Central Railway is required since one platform of Nerul-
Uran corridor will be reduced to single discharge facility. This decision is required urgently as
phase –II construction of the new Seawood Railway Station will commence shortly and
accordingly the GAD and the design may have to
be revised for certain column and beams. Land requirement put up by MRVC to the south
of Kharghar Railway Station is also to be decided.
The location of the platforms in Panvel Terminus
for Fast Track Corridor is also to be decided.
Detailed inspection was held by MRVC on 31/10/14 with CAO (C). Concept plan submitted
on 07/11/14. DRM/BB to comment on this along
with CE / Plg. It was decided to merge the two lines of the fast
corridor & two line of harbor on the same alignment from CSTM to
Sandhurst road for the making of station between Hon’ble Minister for Railways and
Hon’ble Chief Minister.
It was also decided to include two roads along with four railway lines for effective disaster
Page 48 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
management.
A meeting may be called by Chief
Secretary on 12.2.15. Meeting held on 13.02.2015. CIDCO to
respond on the proposal made on 13.02.2015
PDC – 30.2.2015.
ITEM CLOSED in view of no interest by State Govt.
41 CIDCO CR
DRM
Whether there is a Railway requirement
for the triangular plot between Thane-
Turbhe & Mankhurd-Belapur Line near
Juinagar Station.
During meeting with CIDCO on 19.09.2014, Railways have asked them to provide
dimensions of the land plan.
Area plan was discussed on 23.09.14. Since the length is about 350 meters, Stabling lines can be
made. To be accepted by C.Rly formally. CIDCO will communicate the terms and
conditions.
The said piece of land has been marked for 25KV substation. CIDCO has been advised
accordingly. C.Rly will try to accommodate few stabling lines also.
CIDCO: The Railways informed that the said piece of
land has been marked for 25 KV sub-station.
CIDCO stated that this triangular piece of land belongs to CIDCO and the terms & conditions
for use of this land for Railway purposes will be conveyed to Railways.
Railway to provide the exact net area of the
triangular plot after deducting the Railway reservation of the three tracks corridors on the
periphery of the plot. Thereafter, CIDCO will communicate the terms & conditions for
providing the CIDCO land of the triangular plot to Railways.
ITEM will be CLOSED after area of the plot is
decided by Railways. Area calculated as 15500 sq.m. by Railways.
Letter to be given to CIDCO PDC 2/1/2015. Letter No. BB.W.6001.LM.Genl.22.DB
dated 06.01.2015 given to CIDCO.
ITEM CLOSED on 24.02.2015.
43 CIDCO
CR
There is demand for providing escalators
at Nerul-Uran Railway Stations Commuter Sub-ways. Necessary
provision need to be provided by Railways in the structures being
constructed by Railways.
Escalators are not to be provided in any subway
as per Railway policy.
(Usually subways are not provided with escalators since number of steps required to be
climbed is substantially less as compared to a FOB).
ITEM CLOSED.
Page 49 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
44 CIDCO
CR
CAO /C
The details of the surcharges have not
been provided to CIDCO till date and it is
an Audit issue with CIDCO. CIDCO needs details of more micro
level. This is to be provided at the earliest.
Central Railway regularly makes payment by
third week of following month to CIDCO. The
information is also regularly conveyed to CIDCO. Copies of the latest acknowledged
communications and its confirmation are available on record.
Information of surcharges paid from the year
1992-93 onwards is also available on records. This is also a Court matter (PIL for stopping
surcharge) with CIDCO. Railways assured to provide the details in next meeting.
New PDC 14/10/14. To be coordinated by CAO (C ).
CIDCO conveyed that there is audit query in
regard to the absence of the details regarding collection of the surcharge. These details are to
be provided by the Railways urgently. Details given on 29/10/14 upto the minutest
level.
CCM & FA&CAO may be able to give further details.
A/c departments of CIDCO & Central Railway to sit together & decide.
ITEM CLOSED.
45 CIDCO CR
GM
The revenue from the rakes plying on the Cost Sharing Projects of Mankhurd –
Belapur - Panvel & Thane – Turbhe - Vashi / Nerul -Panvel are not received
from Railways.
C.Rly agrees to share ‘Revenue Expenses’ with CIDCO as per the agreement between CIDCO
and Railways. This revenue to be passed to CIDCO shall be in
line with the agreed terms.
This will be Revenue minus the operating expenses.
ITEM CLOSED.
46 CIDCO
CR
DRM
The Railways have not filled the form of
application for obtaining HT connection
at the New Seawood Railway station in the name of Railways which is to be
submitted to MSEDCL.
The issue was discussed during the meeting
held on 18.09.2013. MOU for taking up all the
buildings for maintenance by Railways in Seawood-Uran projects is to be formalized
between CIDCO and Central Railway. CIDCO advised to start with two temporary
electricity and water connections so that in due
course, one set can be earmarked for railways stations and hand over to railways
This item may be discussed with CIDCO officials in next meeting scheduled on 17.10.2014.
The maintenance agreement between CIDCO &
Railways for Seawood-Uran project should be finalised now since the diversion to the new
Seawood station shall take place shortly. Draft agreement will be given to CIDCO by
20/1/15. Draft agreement given. Railways will take
electricity connection only on the day of
taking over of station. ITEM CLOSED.
Page 50 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
47 MMRDA
WR
Sparing of Railway Land:
a) At Mumbai Central Station: Metro station is proposed at Mumbai
Central Station, opposite to the long distance terminal on Dr.Nair Marg. The
station will be fully underground with
entry / exit structures and ancillary building being the only structure at
ground level. For the construction of the proposed station entry / exit structures
and ancillary facilities, some land is required in Railway premises.
i. Land for Entry / Exit point and
ancillary structure ii. Land for temporary use during
construction period iii. Land below ground for proposed
sub-ways for passenger connectivity.
b) At Grant Road Station:
1. Land for Entry / Exit points on permanent basis. Approx. 400 sq.
mtrs. 2. Interchange facilities at Mumbai
Central, Churchgate, Mahalaxmi and
Grant Road stations. 3. Crossing of Metro alignment with WR
tacks at Mahalaxmi & Mahim stations. (Harbour and WR).
c) Space for Metro III.
PCE/WR
one reference was received vide MMRDA’s
letter dated 06.09.2013 which was examined and considering the adequate depth of the
proposed tunnels below the railway track and structures, prima facie the proposal appears to
be feasible. The permission will be subject to
drafting necessary agreement and submission of charges as per Railway Board’s extant policy.
(Mahalaxmi opening may not be possible. A
deck over BMC road with lift may be planned )
i. Approximately 400 sq. mtrs. Proposal
submitted to Divisional Railway manager, WR, Mumbai Central vide Letter
No.MMRC/ML-3-CBS/WR/LA/2014 dated 15th September 2014.
ii. Proposal has been submitted to DRM, WR,
Mumbai Central Dn. Vide letter No. T&C/ML3 CBS/WR/LA/2014/99 dated 20th February
2014 for Mumbai Central, Churchgate and Mahalaxmi stations. Proposal has been
submitted to DRM, WR vide letter No.MMRC/ML3-CBS/WR/LA/2014 dated 15th
September 2014 for Grant Road Station.
iii. Proposal has been submitted to WR Rly. HQ, vide letter No. MRTS/ML3/WR Crossing dated
04th February 2014. MMRDA arranged a presentation on Metro III by
their consultants on 23/9/14 which was found
very useful by all members. It was assured by railway that whatever land will be required for
few years to lower TBMs will be made available at rates as applied for Chennai Metro by S.Rly,
without any delay. Google map of sites required
for Metro 3 were handed over to W.Rly on 14/10/14. Joint inspection at all four stations has
been completed on 16.10.14 by BCT division along with MMRDA officials. Based on joint
inspection MMRDA has been given clearance to prepare final drawing duly indicating exact
dimensions vide letter no. W.220/2/737 dated
20.10.14. Copy again given in the meeting to Advisor (Civil) MMRDA.
WR confirmed that Google Maps received on
19/10/14 and detailed inspection done on 20/10/14. Tech clearance given on 20/10/14.
Now MMRDA to submit details by 02/12/14. Fresh PDC 17/12/14.
Another PDC 15/1/15.
MMRDA requested repeatedly to give photographs of land parcels to be handed over
to contractors of 7 segments within 28 days of finalization of contracts (May end). These
photographs can be taken from a high rise building after positioning four men with flags at
Page 51 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
corners of the plot and at corners of the problem
area.
PDC for above photographs - 03.02.15 (during next meeting).
PDC Revised by MMRDA to today afternoon i.e 10.2.15.
Five photographs shown on 24.2.2015 for
two sites of Western Railway at Mumbai Central station. Both the sites will be
spared by Western Railway, in principle. MMRDA can propose the sites as per 5
photographs submitted on 24.2.2015. ITEM CLOSED ON 24.02.2015.
52 MCGM CR
DRM
Work of Kurla Carshed Nallah at Kurla (East) near Kranti Nagar was undertaken
by CR in last fair season, which was stopped during monsoon. Addl Municipal
Commissioner (Eastern Suburb) vide
letter dated 20.05.14 and 07.07.14 had requested GM/CR to give suitable
instructions to concerned staff for restarting the work immediately.
However, same is not still started on site.
The same may be instructed to be
started early.
Meeting between Sr.DEN/S and Director/Project/SWD is scheduled on
14.10.2014. Laying of three pipes (1800mm dia.) out of five
pipes under Yard/Main line completed. In order
to complete the widening project in all respect, four additional works yet to be planned.
Therefore, MCGM has to deposit additional funds of Rs.9,53,58,685/- for completion of balance
work and same has been intimated to MCGM Vide Mumbai division Sr DEN/S/BB letter
no.BB/W/3512/BMC/CLA-nallah/DB dated
24.09.2014. Further, way leave charges of Rs. 3.0Cr has been deposited so far, balance Rs.
6.40 Cr. yet to be deposited by MCGM. Same has been advised vide above letter. To complete
balance work above funds may deposited with
Railway at earliest. Pending approval of AMC for RE . PDC – Feb 2015.
Leftover work of connectivity is being started and shall be completed by 28.02.15. GAD given
by MCGM ON 16.1.15. Approved by Division 30.1.2015. Approved by HQ 10.2.15.
This is Nallah widening by 8 m from the existing
6 to 7m to 14 to 15 m. MCGM to start the encroachment removal and submit photographs
by 03.2.15 in next meeting of before and after condition of removal of encroachments.
Funds will be available in mid March 2015. West side connection is completed. East side works are in progress & likely to be completed by 31.05.15. Nallah widening work is also in progress. Likely to be completed by 15.04.15. MCGM has yet to deposit balance fund.
PDC 30.03.2015. Work is in progress likely to be complete by 31.05.15. MCGM has deposited Rs. 9,53,58,685/- against balance work and Rs. 6.40 Cr against value charges on 01.04.15.
Tender will be floated by 01.6.2015 by Sr. DEN
(south) No change as on 21.4.15.
ITEM CLOSED ON 05.05.15.
Page 52 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
54 MCGM
CR
DRM
MCGM has made payments for the work
of improvement and augmentation of
culvert capacity in Railway area for SWD system at 10 locations in city and
eastern suburbs in the following locations.
i. Dhobighat Nallah – Sion. ii. Swadeshi Mills Kms 14/2-3.
iii. LBS Marg Kurla kms 14/5-6 iv. LBS Marg Kurla kms 14/7-8
v. Chunabhatti Station kms 13/3-4.
vi. Wadala Harbour kms 9/61.
vii. Kurla Railway Colony Nallah
from Carshed culvert to Tilak nagar Station.
viii. Culvert at Nanepada, kms 29/6-7.
ix. Currey Road kms 5/11-12.
x. Chinchpokli kms 5/1-2.
The works at above locations are yet to be carried out by CR.
MCGM:
Proposed augmentation:
i. Box Culvert 2 M x 1 M ii. Box Culvert 2 M x 1 M
iii. Box Culvert 2 M x 1 M iv. Box Culvert 2 M x 1 M
v. Box Culvert 2x2 M x 1 M
For items i. to v above, Rs. 6 Cr deposited on 26.03.2008.
vi. Box Culvert 1.80 M x 1.20 M Rs. 27.11 lakh deposited on 20.03.2003.
vii. For Culvert and Nallah augmentation –
Rs. 12,62,72,125/- deposited on
18.03.2009.
viii. For Culvert augmentation - Rs. 1,75, 96, 987/- deposited on 28.03.2003.
ix. For Pipe culver 1.20 M dia. – Rs.
33,880/- deposited on 01.02.1996. x. For Pipe 2 x 0.90 M.dia – Rs. 2,31,270/-
deposited on 23.04.1996. CBE:
i) & ii) Contract awarded. Segmental box are ready at Bhandup depot.
Iii) Work completed under Main lines. Work
under HB lines balance. Iv) Contract awarded. Segmental box are ready
at Bhandup depot. V) Details of connectivity of this culvert to
creek/ other Nallah system needs to be
furnished by MCGM. vi) Work partially completed. Segmental box
are ready at site. For further work, Downstream side to be augmented by MCGM.
vii)The work for widening of Nallah near Railway
colony and LTT area has been completed except encroachment location at Savale nagar.
viii), ix) & x) Feasibility of augmentation of culvert below Rly. tracks may be furnished after
joint inspection with Rly site Engineer. DRM clarified that 2 or 3 out of 10 items ( Sr No
i & iii ) will be completed in this season during
April 2015. DRM BB: Work of the Dhobhighat and LBS Marg
at km 14/5-6 cannot be planned unless DIVA gate is closed with a ROB.
ITEM CLOSED ON 24.02.2015.
Page 53 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
55 MCGM
CR
DRM
Reconnection of SWD line at
Chunabhatti Railway Station by CR.
(platform no. 1) since damaged and blocked by CR while carrying out the
work of foundation for FOB in 2013. Several letters written to restore the
damaged SWD. Unfortunately as per CR,
existing SWD to be diverted by MCGM outside Railway land.
This pertains to Construction Organization,
Sr.DEN/S/BB Vide letter on 11.04.2014,
construction org. has been advised to restore the Pipe drain which has been damaged by
Construction org. Dy CE (C) DR during the work. Storm water drainage was damaged during
foundation work of FOB. MCGM has to divert the
drain in the BMC area. Railway will pay from deposit work of Wadala – Kurla. Drg will be ready by 10/12/14 by DRM. This drawing is not required as pipe is available under the platform. The Scheme is being developed to be discussed on 3.2.2014 with photographs. Photographs seen. Apparently the site of Rs.66 lakhs work estimated by BMC is outside Railway Boundary. To be inspected jointly by 15.2.15.Inspection
done the work is O/S Railway Boundary. Rs. 66 lakhs to be paid by Railways will be paid by
15.03.2015. No change as on 10.3.15. Rs. 55.13 lakhs deposited to MCGM on 23.03.15 vide Cheque No. 688619 SWD department will start the work. Tender is being invited by Shri Vhatkar.
ITEM CLOSED. 56 MCGM
CR
DRM
1. The work consists of laying 1.60 M.dia. pipe under steel casing of 2.50
M.dia. MCGM has made payment of Rs.
58,40,408/- on 13.01.2001 to CR. The work was reported to have been
completed by CR in the year 2007. Now, MCGM has taken up work of
laying 1.60 M.dia pipe below the MbPT
Railway track on downstream side of the said work.
A Trial pit was for the said work when it is observed that the Railway
authorities have laid only the steel
casing pipe below harbour Railway track and the 1.60 M. dia pipe is not
laid inside the casing pipes. CR to expedite the work of laying 1.60
M.dia RCC pipe inside the casing pipe for the portion below Harbour Railway
track to enable MCGM to lay the
downstream side pipe line with proper connectivity.
2. Further, on upstream side the newly laid drain has to be connected to
the existing drain for which excavation
will be required in the Railway land at km 7/17-18 near Railway track. CR is
requested to grant permission for the same.
DRM / BB: MCGM may give a firm proposal along with the
execution schedule.
CBE: 1) The work of Casing pipe under Railway track
has already been completed in 2007. MCGM is to carry out the work of laying RCC pipe through
the Casing pipe.
2) No proposal received for extension of drain on up stream side at km 7/17-18. On receipt of
proposal matter will be examined by Railway.
Casing pipe to be examined by MCGM and point
recast if there is any problem.
ITEM CLOSED as casing work is over.
Page 54 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
57 MRVC
CR/WR
GM
Running of 15 car on WR and CR:
MRVC has carried out study on the WR
and CR through RITES. The report has been submitted to WR and CR. The
same will be made to CR on the date to be mutually decided.
Presentation planned on 20/10/14.Presentation
made. RITES reports to be modified as per
discussion with of Railways.3 rakes of 12 car
each requested every year w.e.f 2015-16. For
next year for this 360 coaches , 1080 crores
required for Rolling stock.ITEM CLOSED.
58 MRVC
CR/WR
GM
Concept Plan: New Suburban link
between Wadala to Ballard Estate through MbPT.
MRVC has prepared the concept plan for new suburban link between Wadala to
Ballard Estate through MbPT. This will enhance the capacity between South
Mumbai to Panvel and South Mumbai to
Andheri/Goregaon and thus enable direct connection with Central, Western & Navi
Mumbai area. The concept plan has been submitted to Mrs. Jadhav,
Chairperson of MbPT Land
Redevelopment Committee on 10.10.2014.
Joint meeting of MD/MRVC & GM/CR with Mrs
Jadhav to be organized on 16/10/14.
The meeting held on 14/11/14. & 19/11
ITEM CLOSED.
61 MRVC MbPT
Chief Engg.
MRVC has requested MbPT to give the permission to ply vehicles carrying P-way
and construction material on Reynold
Road in Tejasnagar colony near Vadala Road station.
The same needs to be granted.
MbPT Absent on 16/12/14.
Permission given
ITEM CLOSED.
62 MRVC
TMC
Urgent permission is requested from
TMC to cut gulmohar trees on platform 1 on Diva station which are coming in way
of new FOB. Tree authority committed
has already inspected the site on 26-06-2014.
TMC indicated PDC of 15/01/15. TMC Absent on 20/1/15.
ITEM CLOSED.
70 KDMC
CR
Construction of Gutter Foothpath on Murbad Road opp. Breakmans Chawl
Kalyan (W) in Railway Land
During widening of Murbad road about 20 years back the gutter and foot path
was constructed opp. to old Breakmans Chawl. The gutter is about 3.00 mt
inside the Railway land for 10.00M
length. Now KDMC has taken up road concretization work. Recently Railway
provided barbed wire fencing, So work of gutter is pending and unhygienic
condition are created. Railway should give NOC to construct gutter at its old
alignment to avoid bottleneck in road.
Work completed.
ITEM CLOSED.
71 KDMC
CR
Proposal for Improvement of Traffic Circulation area on Kalyan East.
Proposal submitted to Railway vide
Letter No. KDMC/Commissioner/486 Dt.28/06/2013. It is requested to issue
NOC to KDMC.
(Proposal is not available in Division) None present on 24.02.2015 and 10.3.15.
Proposal not acceptable in present format.
ITEM CLOSED. Reframe as SATIS on first floor.
Page 55 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
72 KDMC
CR
Permission for crossing Railway Lines at
3 location in Dombivali for laying rising
Main DI Pipe, under JNNURM scheme. KDMC has deposited Rs 2.52 Cr to
Railway for the Crossing of Tracks. As
KDMC doing work by HDD method, It is
requested to give permission at the
earliest.
(Pending with KDMC due to methodology details
for CRS sanction, letter to KDMC)
None present on 24.02.2015 and 10.3.15. Three – 800 mm casting pipe pushing
work. Awaiting CRS sanction. CRS permission arranged on 18.04.15
ITEM CLOSED.
74 KDMC
CR
ROB at Level crossing No 47-B between
Shahad -Ambivali Station has been completed in Railway portion but work
on approaches by KDMC is delayed. Due to problem of Land acquisition
KDMC could not complete the
approaches. Substructures work completed in available front and land
acquisition is in process. Railway has spend excess amount on
ROB on this level crossing.
None present on 24.02.2015 and 10.3.15.
ITEM CLOSED (money paid to KDMC after
reconciliation)
75 KDMC
CR/
CAO/C
ROB at Level Crossing Gate 1-A between
Vitthalwadi and Kalyan. Work is completed settlement of
accounts is requested. KDMC has submitted the completion cost of the
project to Dy-Chief Engineer [C]GC and
requested to release balance amount of Rs.383.50 lakhs by wide letter KDMC /
CE/434, Dated 20/03/2014. KDMC has spent excess amount on
this ROB. Therefore reconciliation of
above item no 74 & 75 are under process
None present on 24.02.2015 and 10.3.15.
ITEM CLOSED (money paid to KDMC after reconciliation)
78 CR
KDMC
Tree cutting permission (181 nos.) for
construction of 12th Battalion RPSF Complex at Thakurli is pending since
long as a result work is held up.
Tree committee meeting to be held by
KDMC by 15/2/15. None present on 24.02.2015 and 10.3.15.
PDC for KDMC 7.5.15. No representative of KDMC & no
discussions on 05.05.15.
KDMC refused to permit tree cutting.
Railways agreed to transplant the trees. ITEM CLOSED ON 26.05.15.
79 MRVC/CR
GoM, TMC
Encroachments on Railway land at km
38/6 - 16 local line at Retibunder and Rana Nagar between Kalwa and
Mumbra.
For 5th and 6th line between Thane Diva, BSES
survey was carried out in 2012 to identify the hutments in safety Zone at Reti bunder and Rana
Nagar ( km 38/6-16) between Kalwa and Mumbra,
As per the survey, 98 Project Affected Persons
were required to be rehabilitated at Retibunder.
Accordingly, the proposal for rehabilitation of these was processed by MMRDA. However, it has
been observed that about 160 nos. new unauthorized hutments have come up recently
Page 56 of 56
Sr No
Proposing Agency
Name of Work Status of Work
Pending with Nodal Agency
due to which R&R work cannot be taken up.
Similarly at Rananagar, 26 Project Affected Persons/Shops were identified which were to be
rehabilitated and the proposal for rehabilitation was processed by MMRDA. However, it has been
observed that about 40 nos. new unauthorized
hutments have come up inside the Anand Patil Workshop recently which is hampering the R&R
work.
The ongoing works at Thane-Diva will be held up and suffer if these unauthorized hutments
/encroachments are not removed. It is requested
that these encroachments may please be removed early.
Second round of demolition to be planned by Mumbai division in March 15. Thereafter MRVC
to secure land by dumping sleepers or rails
No change as on 10.3.15. Demolition program has been issued by MRVC as on 20.03.15 but could not be carried out due to non-availability of city police.
New date for demolition 28.04.15.
Demolition completed on 28.4.15 ITEM CLOSED ON 05.05.15