miros design build approach 2 26 10
DESCRIPTION
Walter Miros presents "Design/Build Approach" at AIA Design+Technology Seminar, Miami Feb 26th. http://www.aiamiami.com/pdf/2010/dte_seminarday2010.pdfTRANSCRIPT
Design/Build Approach
Design + Technology Seminar Day
Miami Chapter
February 26, 2010
Presentation By: Walter Miros Vice President - Contex Construction Co., Inc.
Design/Build Approach
Course # DTS 019
Design / Build Approach
Design/Build Approach
BIOGRAPHICAL OVERVIEW - WALTER MIROS
• Mr. Miros has been responsible for in excess of $1 billion of capital improvement projects.
• Projects have been major in scope with several above $100 million and encompass a wide range of facilities.
• Prior to joining Contex Construction Co., he was regional Vice President of Operations with Skanska USA Building, Inc. Responsible for over $275 million in revenue.
• From 1986 to 2001, his assignments were throughout the entire United States as he progressed to the position of Program Director at Carlson Design/ Construct Corp., a national design-build firm.
• For the last decade, he has represented diverse repeat educational, healthcare and corporate clients. Clients include American Express, Verizon, Capital Health, U. of Pennsylvania, Princeton U., Florida International U., and Miami-Dade School District.
• EducationAS, Civil Engineering – Middlesex County College, Edison, NJ
BS, Building Construction – University of Florida, Gainesville, FL
MS, Organizational Dynamics – University of Pennsylvania, Philadelphia, PA
• FL Licensed General Contractor CGC059336
Design/Build Approach
Agenda Team Structures – AIA Contract Relationship Diagrams Design / Build Team Structure
Proposal Phase Design Phase Build Phase
AIA Document A141 – Agreement between Owner & Design-Builder Design / Build Process Guaranteed Maximum Price (GMP) Process Practical Approaches and Procedures Design / Build – Time vs. Money Summary
Design/Build Approach
Design/Build Approach
Team Structures –
AIA Contract Relationship Diagrams
Design/Build Approach
Conventional (A201) Design-Bid-Build Team Key Attributes:• For use when the owner’s project is divided into separate contracts for design
(architect) and construction (contractor)
• Suitable for conventional project delivery (design-bid-build)
• Owner retains Architect
• Architect and consultants prepare drawings and specifications
• Architect assists Owner in obtaining bids/proposals and then Owner awards contract(s) for construction
• Contractor(s) and Surety(ies) obligate to owner for bid, performance and payment bonds
• Contractor and Subcontractors build the work
Design/Build Approach
C o n v en tio n al (A 2 0 1 ) D es ig n -B id -B u ild C o n trac tR ela tio n sh ip D iag ra m
C onsu ltantC 401
C onsu ltantC 401
A rch itec tA 201
O w ner
S ubcontrac torA 401
S ubcontrac torA 401
C on trac torA 201
S ure ty
Contracts used
Design/Build Approach
Construction Manager as Adviser (CMa) Team Key Attributes:• Owner retains an Architect and a Construction Manager who acts as an
independent adviser to the owner.
• Prime contractor(s) responsible for construction, labor and materials.
• Construction Manager gives owner construction management advice through design and construction phases.
• Increases expertise in managing a project from start to finish.
Design/Build Approach
C o n stru c tio n M an ag er as A d v iso r (C M a )C o n trac t R ela tio n sh ip D iag ra m
C onsu ltantC 401
C onsu ltantC 401
A rch itec tB 132
C onst. M gr. Adv iso r (C M a)C 132
S ubcontractor
C on trac torA 401
S ubcontractor
C on trac torA 401
M u ltip le Prim e C on trac to rsA 132
O w ner
Contracts used
Design/Build Approach
Construction Manager as Constructor (2009-CMc) Team
Key Attributes:• Single party (Construction Manager) provides construction management
services in pre-construction phase AND then completes construction constructor).
• Gives Construction Manager (constructor) responsibility and control over construction work via direct contracts with sub-contractors.
• Construction phase services paid on the basis of cost of work plus a fee either with (A133) or without (A134) a Guaranteed Maximum Price.
Design/Build Approach
C o n stru c tio n M an ag er as C o n s tru c to r (2 0 0 9 -C M c )C o n trac t R ela tio n sh ip D iag ra m
C onsu ltantC 401
C onsu ltantC 401
A rch itec tB 103
S ubcontrac torA 401
S ubcontrac torA 401
C onst. M gr. C onstruc to r (C M c)A 133 o r A 134
O w ner
Contracts used
Design/Build Approach
Small Projects Team Key Attributes:• Suitable for residential or small commercial projects and other projects
of relatively low cost and brief duration.
• These documents (B105 & A105) are in effect conventional Design-Bid-Build documents (B101 & A101/A201) “stripped down” to essentials.
• These feature use of Stipulated Sum and Integrated General Conditions.
Design/Build Approach
S m all P ro jec ts - C o n trac tR ela tio n sh ip
D iag ra m
C onsu ltantC 401
A rch itec tB 105
S ubcontractorA 401
C on tractorA 105
O w ner
Contracts used
Design/Build Approach
Integrated Project Delivery Team: Transitional Documents
Key Attributes:• Integrated Project Delivery is an emerging process and these
Transitional Agreements are a comfortable first step into IPD.
• A collaborative project delivery approach that utilizes the talents and insights of all project participants through all phases of design and construction.
• Structured similar to existing construction manager agreements.
Design/Build Approach
In teg ra ted P ro jec t D eliv ery T eam : T ra d itio n al D o cu m en tsC o n trac t R ela tio n sh ip D iag ra m
C onsu ltantC 401
C onsu ltantC 401
A rch itectA 295
S ubcontrac torA 401
S ubcontrac torA 401
C on tractorA 295
O w ner
Contracts used
Design/Build Approach
Integrated Project Delivery Team: Single Purpose Entity
Key Attributes:• These Agreements more fully integrate the project parties into IPD.
• Creates a limited liability company for the purpose of planning, designing and constructing the project.
• The Single Purpose Entity (SPE) allows for complete sharing of risk and reward in a fully integrated collaborative process.
Design/Build Approach
In teg ra te d P ro jec t D eliv ery T eam :S in g le P u rp o se E n tity D o cu m en ts
C o n trac t R ela tio n sh ip D iag ra m
Arch itectC 197
C onstruction M anagerC 197
C onsu ltantC 198
C onsu ltantC 198
T rade C on tractorC 199
T rade C on tractorC 199
O w ner/ Arch itect/ CM / O the r M em bersC 195
O w ner
C 196
Design/Build Approach
Design-Build Team Key Attributes:• Owner enters into a contract with a single entity Design-Builder.
• Design-Builder is then obligated to both design and construct the project.
• Design-Builder then enters into contracts with architect and construction
contractor(s) if necessary.
• Design-Builder may be:– A Developer or Single Purpose Entity (design and construction in one shop)
– An Architect-led organization
– A Contractor-led organization (most often the case)
Design/Build Approach
D esig n / B u ild T ea mC o n trac t R ela tio n sh ip D iag ra m
C onsu ltantB 142
C onsu ltantC 441
C onsu ltantC 441
A rch itec tB 143
S ubcontractorA 441
S ubcontractorA 441
C on trac torA 142
D esign-B u ilderA 141
O w ner
Contracts used
Design/Build Approach
Design/Build Approach
Design / Build Team Structure Proposal Phase Design Phase Build Phase
Design/Build Approach
Design/ Build Team Structure – Proposal Phase The Planner is the Proposal Lead
Should have a strong construction background Should have strong Program Management experience Has good client interaction Must have good writing skills Must be part politician Must be a scheduler and estimator Must be a good business person Must have strategic planning skills Must be part presenter
Schedule Budget Scope
B usinessD eve lopm ent
A rch itec t
P lanner
Design/Build Approach
B usinessD eve lopm ent
P rog ram M anager
A rch itec t E lectr ica l M echan ical C onsu ltan ts
A /E P M
A & N D esignT eam
A & N P M
P lanner
Design/ Build Team Structure – Design Phase
Design/Build Approach
B usinessD evelopm en t
P lanner
C onstruc tionTeam
C onstruc tion P M
A rch itect E lectr ical M echan ical C onsu ltan ts
A /E P M
A & NIm plem en tation
Team
A & N P M
P rogram M anager
Design/ Build Team Structure – Build Phase
Design/Build Approach
Design/Build Approach
AIA Document A141 – Agreement Between Owner & Design-Builder
Preliminary Design & Pre-Construction Planning
Final Design & Implementation
Design/Build Approach
Preliminary Design & Pre-construction Planning
• Project Goals• Information Gathering• Interviews• Projected Space Needs• Adjacencies• Infrastructure Criteria• Security Criteria• Voice/Data Criteria• A&N Requirements• Deliver Project Program
Preliminary Design Documents• Site-Plan• Elevations• Floor Plans• Equipment Layouts• Mechanical Scope• Drawings• Electrical Scope
Drawings• A&N Drawings• Prioritize Early
Documents• Civil• Foundation/Structural• MEP Equipment
Refinement of Schematic Design• Complete Final Design
Scheme• Refine Floor Plan• Complete MEP Scope• Refine Building
Sections and Elevations
Programming Schematic Design Design Development
Owner Approval
GMP
A141 Services Design Build Contract
Design/Build Approach
Final Design & Implementation
Construction Documents
Drawings & Specifications• Architecture• Electrical
Engineering• Mechanical
Engineering• Structural
Engineering• Civil Engineering
• Pre-qualify Preferred Contractors
• Pre-qualify Trades and Vendors• Value Engineering &
Estimating• Prepare Bid Packages for Early
Construction• Prepare Agencies for Phased
Permits• Pre-order Long Lead
Materials/Equip.• Start Site Work
• Manage Design Consultation• Obtain Permits• Complete Competitive Bidding• Select Contractors and
Vendors• Mobilize Site• General Construction• Migration Planning &
Implementation• Integrated Testing• Applications& Network
Services
Final Design Construction Documents
Pre-construction Planning Construction and A&N
A141 Services Design Build Contract
Design/Build Approach
Design/Build Approach
Design Build Process
Design/Build Approach
Implementation Documents
Construction & Systems
Integration
Integrated Testing & Start Up
The Design-Build Process
Programming & Strategic Planning
Detailed Design
GMP
Permitting & Procurement
ProjectCompletion
Design/Build Approach
Program Definition Program goals Team Organization Program Schedule & Budget Site Selection Criteria Overview Single Line Drawings Conceptual Block Diagrams Major Equipment List Architectural Space Program Work Flow Chart & Program Matrix Reliability & Operation
Programming & Strategic Planning
Detailed Design
GMP
Implementation Documents
Permitting & Procurement
Construction Systems & Integration
Integrated Testing & Start Up
Project Completion
Design/Build Approach
Team Tasks Resolve Code and Zoning Issues Complete Final Design Schemes Refine Floor Plan for Specific Site Refine Building Sections and
Elevations Complete Technology Scope Complete MEP Scope Pre-Implementation Planning Order Long Lead Items
Detailed Design
Programming & Strategic Planning
GMP
Implementation Documents
Permitting & Procurement
Construction Systems & Integration
Integrated Testing & Start
Up
Project Completion
Design/Build Approach
Team Tasks Subcontractor Selection Process Prepare Detail Project Schedule Present GMP Proposal Owner Review/Approval Pre-purchases Mobilize Construction
GMP
Programming & Strategic Planning
Detailed Design
Implementation Documents
Permitting & Procurement
Construction Systems & Integration
Integrated Testing & Start Up
Project Completion
Design/Build Approach
Team Tasks Schedule Documents Coordination Documents Construction Documents Technology Documents Complete Interior Finish Package Digital Updates Via WAN Lead Team Meetings Maintain Adherence to Budget
Implementation Documents
Programming & Strategic Planning
Detailed Design
GMP
Permitting & Procurement
Construction Systems & Integration
Integrated Testing & Start Up
Project Completion
Design/Build Approach
Team Tasks Obtain Permits Complete Procurement Procurement Coordination Value Engineering
Permitting & Procurement
Programming & Strategic Planning
Detailed Design
GMP
Implementation Documents
Construction Systems & Integration
Integrated Testing & Start Up
Project Completion
Design/Build Approach
Team Tasks On-Site Supervision Early Access for Technology Installation Generate RFI’s Write Trade Contracts Implement Fast-Track Manage Entire Construction Process &
Change Process Maintain Costs and Schedule Reports Manage Quality Control and Safety
Construction & Systems
Integration
Programming & Strategic Planning
Detailed Design
GMP
Implementation Documents
Permitting & Procurement
Integrated Testing & Start Up
Project Completion
Design/Build Approach
Team Tasks Integrated technology Systems Testing Integrated Building Systems Testing Seal and Secure Spaces Manage Equipment Subcontractors Security Plan Delivery and Storage of Equipment
Integrated Testing & Start Up
Programming & Strategic Planning
Detailed Design
GMP
Implementation Documents
Permitting & Procurement
Construction & Systems Integration
Project Completion
Design/Build Approach
Team Tasks Construction Close-out Punch List Final Inspection
Project Complete
Programming & Strategic Planning
Detailed Design
GMP
Implementation Documents
Permitting & Procurement
Construction & Systems Integration
Integrated Testing & Start Up
Design/Build Approach
Design/Build Approach
Guaranteed Maximum Price (GMP) Process
Design/Build Approach
Programming
Schematic Arch. Designs
Schematic Eng. Designs
DDs - 30% CDs
Constructability Review #1
Prepare GMP
GMP Presentation & Approval
Mid
Cou
rse
Cor
rect
ion
Rough Order of (Cost)
Magnitude ROM #1 ROM #2 ROM #3 ROM #4
Bas
is o
f G
MP
Kickoff Meetings Internal & With Client:• Schedule• Roles & Responsibilities• Deliverables• Make Sure Internal Financial Controls are in Place
GMP Process Timeline
Design/Build Approach
DDs - 30% CDs
Prepare GMP
Identify & Order Long Lead Items
Permitting
ROM #4
Bas
is o
f G
MP
Grading & Foundations
StructuralM
id C
ours
e C
orre
ctio
n
Constructability Review #2
GMP Presentation & Approval
Sub
mit
for
Per
mit
- D
on’t
Pul
l
• Base Building• TI• FF&E• Catch-up Bulletins
• Once a Month
GMP Process Timeline, continued
Design/Build Approach
Define Scope for Construction Admin Services
Project Scope Site Specific Programming Services Scope Prepare a ROM
Partially Completed Drawings
Partially Completed Specs Pre-purchase Specs
Written Code Analysis Design Performance Criteria Project Narrative
This is a contractual document that shall be combined with drawings and specs to be the basis of the overall agreement
Scope Shorthand An internal coordination tool to
help build the GMP
GMP Development Phase: During Design Services Phase
Design/Build Approach
GMP Package Shall Include: Drawings Specifications Project Scope Narrative Organizational Chart Schedule GMP ($)
Exclusions / Contingency Allowances
Executive Summary May include:
Cover Letter AIA 142 Services Contract between Design-Builder and Contractor
Design/Build Approach
GMP Preparation Checklist: Have the planner and the design and A&N teams had a design review meeting to go over
missing design elements that need to be incorporated into the GMP? Have the additional scope items been incorporated into the subcontractor/vendor scope
letters and quote analysis checklist? Has a master project schedule been developed, from which general conditions are applied? Are GAC’s included @ .25% of Cost of Work? Is Warranty included @ .25% of Cost of Work? Is General Liability Insurance included @ 1.5% of Cost of Work? Is the design fee broken down into “Design Services” and “Design Reimbursables?” Discuss the logistical issues surrounding the proposed project and how those issues are
accounted for in the GMP. Did we receive subcontractor and equipment quotes from vendors to support the GMP?
Did those quotes include sales tax, shipping, handling and an allowance for off-loading at the site?
Design/Build Approach
Design/Build Approach
Practical Approaches and Procedures
Design/Build Approach
Practical Approaches & Procedures: Day-to-day interaction of operations, design and A&N teams
Weekly design review meetings Pre-bid meetings to define project approach and methodology When going out to bid to subcontractors and other vendors
Include the design teams (A&E and A&N) in pre-bid meetings Include the design teams in the scope writing phase Include the design teams in the bid analysis
Design will provide the field with estimated plan check and permit dates The Planner and Program Manager shall attend code review sessions with the A/E team. Catch up bulletins
To be reviewed by the construction PM and A/E PM prior to issuance, to review scope. Shall include a narrative prepared by the A/E PM
Architect/Engineer field visits The architect and engineers are required to give a verbal briefing to the filed upon leaving the site The architect and engineers shall prepare a formal Field Observation Report
Integrated Testing is an “Add Service” to basic implementation services Electronic as-built drawings may be an “Add Service” to basic design services At the end of a project the Construction PM is to prepare a Project Information Form (PIF)
Design/Build Approach
Design/Build Approach
Design / Build – Time vs. Money
Design/Build Approach
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
GMP Single Source Implementation
Concept Design
Design Development
Construction Documents
Critical Delivery Purchase and ConstructionCost Savings
Cost Savings opportunities decrease as time passes through the design process
Traditional ApproachFirm Price
Concept Design
Design Development
Construction Documents
Bid Critical Delivery Purchases and Construction
$
Project Delivery Schedule
Tim
e/C
ost
Ad
van
tage
months
Design/Build Approach
Design/Build Approach
Keys to Success of the Design/ Build Process: Cultural Change required
More of a team approach Owner experience may be factor
Control of process Need to Compromise Clashes could occur between design creativity and builder
schedule/ budget control Successful Design/ Build is based on behaviors not
processes or contracts.
Design/Build Approach
Other Advantages of the Design/ Build Approach: One Point Source of Responsibility Time Savings
Requests for Information (RFI) reduced Cost Savings
Value Engineering Constructability Reviews Reduced change orders
Cost Control Improved Throughout Process Reduced Risk for Design Errors Efficiency of project delivery – reduction in Admin.
Design/Build Approach
Summary Team Structure
Proposal Phase Design Phase Build Phase
A141 Services Design/ Build Contract Design Build Process GMP Process Practical Approaches and Procedures Design/Build – Time vs. Money
Design/Build Approach
Questions & Discussion
Design/Build Approach
Thank You!
Miami Chapter