mitigating ecological impacts during construction for a … new section of railway to connect the...
TRANSCRIPT
Copyright of RSK 01 July 2016 1
Mitigating Ecological Impacts during
Construction for a Large Linear Rail Scheme;
Constraints and Lessons Learnt
Tanith Cook BSc (Hons), MSc, CEcol, MCIEEM
Copyright of RSK 01 July 2016 2
What large linear rail scheme?
East West Rail (EWR) Phase 1
Part of a larger scheme to improve the railway connections
between East Anglia, Central, Southern and Western England.
Project to improve the rail line between Oxford and Bicester.
Being delivered by Network Rail, Chiltern Railways, and a joint
venture led by Carillion and Buckingham Group Contracting
(CBJV).
Copyright of RSK 01 July 2016 3
EWR Phase 1
Copyright of RSK 01 July 2016 4
EWR Phase 1
Copyright of RSK 01 July 2016 5
EWR Phase 1
A new section of railway to connect the Bicester to Oxford line to the
Chiltern main line.
Widening the existing track bed.
Doubling over 18 km of track.
Closure of 37 level crossings.
4 new overbridges, underbridges and footbridges.
A new railway station – Oxford Parkway.
Upgrading Bicester Town and Islip stations.
A new signalling system.
Copyright of RSK 01 July 2016 6
EWR Phase 1 History
2008-2010• Full EIA and specialist surveys undertaken
2010
• Application submitted to Secretary of State for Transport
2010 and 2012
• Two public inquiries held
October 2012
• Permission granted for work to begin on EWR Phase 1
January 2014
• Construction Phase. RSK started work on EWR Phase 1
Copyright of RSK
What was RSKs involvement?
01 July 2016 7
RSK formed part of the CBJV. RSK has provided:
a comprehensive environmental and consents management service:
a full-time environmental and consents manager and ecologist.
ecology survey and mitigation work;
landscaping design, implementation and planting;
large-scale noise monitoring, modelling and reporting;
asbestos surveying;
materials management and testing;
CEEQUAL assessment for the civil engineering elements of the project.
looked after stakeholder communications
Set up project website
www.bicestertooxfordcollaboration.com
Copyright of RSK 01 July 2016 8
Topics
• Great Crested Newts
• Badgers
• Constraints and lessons learnt
Copyright of RSK 01 July 2016 9
Great Crested Newts
Water Eaton
Mill Stream
Oddington
Holts Farm
Wendlebury
MOD
Gavray Drive
7 EPS licences were approved for the project.
Licences were prepared by another consultancy from 2011.
Receptor site works and newt fence installation started in 2013 and
translocation was completed for all 7 sites by 2014.
GCN licences transferred to RSK during the summer of 2014 .
Copyright of RSK 01 July 2016 10
GCN Constraints: location of newt fence
1. GCN EPS licence produced in some cases before detailed
design of drainage, haul roads, Network Rail perimeter
fencing.
2. Newt fencing was too close to the construction corridor, the
contractors did not have enough space to work.
3. Newt fencing installed adjacent to active line with open ends,
potential for re-entry of translocated newts.
Copyright of RSK 01 July 2016 11
GCN Lessons Learnt: location of newt fence
1. Be realistic and anticipate future additions to the design – earlier
collaboration between designers, engineers, construction and ecology
teams.
Copyright of RSK 01 July 2016 12
GCN Lessons Learnt: location of newt fence
2. Ensure that there is enough space between the construction footprint and
newt perimeter fencing – likely to require the purchase of more offline land
3. Use of project-wide mitigation licences on large linear route. EWR Phase
1 were able to extend the area covered in the licences.
Copyright of RSK 01 July 2016 13
GCN Constraints: Habitat compensation
Habitat compensation plans produced as part of the GCN EPS licences
were submitted before the final detailed design and didn’t always take
into account:
Drainage
Network Rail’s strict planting policy
Temporary land take agreements
This meant:
Habitat ratios were incorrect – specifically for woodland and scrub
planting.
Terrestrial habitat compensation measures were not realistic under
the confines of the scheme.
5 of the 7 licences had to be modified.
Copyright of RSK 01 July 2016 14
GCN Constraints: Habitat compensation
Temporary land take
Copyright of RSK 01 July 2016 15
GCN Constraints: Habitat compensation
Network Rail 5 m
planting policy
Copyright of RSK 01 July 2016 16
GCN Lessons Learnt: Habitat compensation
1. Bring in a landscape architect early on in the habitat compensation planting
proposal process.
2. Realistically very difficult to re-plant rail embankments with trees and scrub
due to the necessary Network Rail 5 m planting policy.
Copyright of RSK 01 July 2016 17
GCN Lessons Learnt: Habitat compensation
3. Plant embankments with grass seed mix and install more hibernacula/
refugia to compensate for less scrub and tree planting.
Copyright of RSK 01 July 2016 18
GCN Lessons Learnt: Habitat compensation
4. Plant hedgerows along boundaries and focus on adjacent structures to include
tree planting.
Copyright of RSK 01 July 2016 19
Badgers
54 setts (8 main, 5
annexe, 5 subsidiary,
36 outlying).
13 social groups.
9 artificial setts were
built.
46 Badger setts
closed in 2013.
Copyright of RSK
Badgers: What have RSK done?
01 July 2016 20
Jan 2014
• RSK started monthly monitoring surveys
Feb – Mar 2014
• Found that a number of closed setts had become re-occupied
• RSK identified 25 setts
July – Sept 2014
• 10 setts closed and excavated under licence
• 7 setts excavated - not under a licence as disused
• RSK constructed 10th artificial sett and closed/excavated 1 main sett
Copyright of RSK
Badger Constraints: Timeframe
01 July 2016 21
Copyright of RSK
Badger Constraints: Location of artificial
setts
01 July 2016 22
Copyright of RSK
Badger Constraints: Location of artificial
setts
01 July 2016 23
Copyright of RSK 01 July 2016 24
Badgers – Lessons Learnt
1. Monthly walkover of the route by an ecologist and the extensive use of camera
traps very worthwhile.
Copyright of RSK 01 July 2016 25
Badgers – Lessons Learnt
2. More space needed between construction footprint and artificial setts, but
Badgers do tolerate what we would perceive as high levels of disturbance.
Copyright of RSK
Badgers – Lessons Learnt
01 July 2016 26
3. The project benefitted from the use of an integrated online GIS mapping
application. The application delivered improved communication,
collaboration, planning and enhanced understanding of the Badger sett issues.
Copyright of RSK 01 July 2016 27
We could communicate visually which setts had been re-opened and where,
and the weeks that the setts were due to be closed.
Allowed the teams on site and in the office to better plan their works.
Mobile mappers were used by ecologists on site.
Online GIS mapping application
Copyright of RSK 01 July 2016 28
Online GIS mapping application
Copyright of RSK 01 July 2016 29
Conclusion
Difficulties arose due to the EcIA being completed by one company and
construction led by another.
More collaboration needed between engineers, designers, construction
contractors, ecologists, and landscape architects earlier on in the process.
GCN EPS licence produced before detailed final design completed, such as
drainage, acoustic barriers and Network Rail perimeter fencing.
Meant habitat compensation plans had to be modified during construction.
Large infrastructure developments do unfortunately require extensive areas of
vegetation to be cleared. There cannot be a compromise for rail safety and the
smooth running of the rail service. E.g. in 2013 Network Rail reported that:
- vegetation management and incidents caused by vegetation cost the railway
£100 million;
- around 600 trains collided with a fallen tree or large branch; and
- leaves caused 4.5 million hours delays to passengers.
Copyright of RSK 01 July 2016 30
Conclusion
EWR Phase 1 adapted to the restrictions. We modified the habitat
compensation plans for 5 of the 7 GCN EPS licences to a planting scheme that
would be suitable for newts, but also realistic and deliverable under the confines
of the scheme.
May need to see a shift and acceptance of habitat change along rail corridors.
Greater emphasise perimeter planting and species rich grasslands on rail
embankments.
Biodiversity offsetting may be the future for rail improvement schemes like EWR
Phase 1.
Project-wide protected species licences.
The presence of a full-time environmental manager and ecologist was beneficial
to ensure compliance and a swift resolution of issues.
Use of Web-GIS delivered improved communication, collaboration, planning,
and enhanced management of protected species issues. Visually allowed
progress tracking and better understanding of constraints.
Copyright of RSK 01 July 2016 31
Q & A
Copyright of RSK 01 July 2016 32