MKD Reliability run
Viliam SenajTCM meeting 18/11/2014
![Page 2: MKD Reliability run Viliam Senaj TCM meeting 18/11/2014](https://reader036.vdocument.in/reader036/viewer/2022082613/5697bf851a28abf838c8779c/html5/thumbnails/2.jpg)
Tests performed on generators• Since 01/10: – LBDS1: 11 ES up to 7.1 TeV (55 pulses at each energy) + ~
40 pulses @ 7.1 TeV + ~ 15 pulses @ 6.5 TeV + 100s @ 450 GeV
– LBDS2: 14 ES up to 7.1 TeV (70 pulses) + ~ 15 p @ 6.5 TeV– No real reliability run because of too high temperature at
UA63/67 (VAC group maintenance)– Modification performed:
• Compensation voltage setting at low energies (up to 800 GeV) to make R_end curve more flat
• Increase of bias voltage to 280 V (from 270 V) in order to reduce R_1 at low energies (>7.5%)
![Page 3: MKD Reliability run Viliam Senaj TCM meeting 18/11/2014](https://reader036.vdocument.in/reader036/viewer/2022082613/5697bf851a28abf838c8779c/html5/thumbnails/3.jpg)
Problems observed
• B2: 24 V PS inside PTU• B2: 150 V PS inside PTU• Compensation PS • 4 kV PS inside PTU
![Page 4: MKD Reliability run Viliam Senaj TCM meeting 18/11/2014](https://reader036.vdocument.in/reader036/viewer/2022082613/5697bf851a28abf838c8779c/html5/thumbnails/4.jpg)
Still to be done
• New ES; generating new settings, tracking limits…
• Reliability run…