DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS
(SUPERPOWERS OPTIONAL!)
![Page 2: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/2.jpg)
YOUR SUPERHERO TRAINERS TODAY
ADAM NELSONSenior Arch i tectura l Des igner
CYNTHIA JANESArchi tectura l /Engineer ing Serv ices Director
![Page 3: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/3.jpg)
KNOWING YOUR SUPERHERO TEAM• Project priorities
• Define the superhero team contract entities:
– Owner, Architect/Engineer, General Contractor, Construction Manager (CM), CM Agent
• Type of project delivery methods (contracts)
• When should the project delivery method be selected?
• Compensation methods for professional and construction services
• Advantages and disadvantages
• Which delivery method may be better for your project
![Page 4: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/4.jpg)
PROJECT DELIVERY METHODS
What is most important to you?• Schedule?• Design?• Budget?• Internal resources?• Supplement your level of experience?
When should the project delivery method be selected?• Preferably before contracting with a design firm and contractor
![Page 5: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/5.jpg)
TEAM MEMBERS (Project Entities)
OWNER
ARCHITECT/ENGINEER BUILDER
C
![Page 6: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/6.jpg)
COMPENSATION METHODS
Categories for professional services and construction services:• Lump Sum/Fixed Price (LS)• Guaranteed Maximum Price (GMP)• Reimbursable
– Unit Price– Cost Plus Fixed Fee– Cost Plus Incentive Fee– Cost Plus Award Fee (performance based)– Time and Materials
![Page 7: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/7.jpg)
DELIVERY METHODS
1. Design – Bid – Build (DBB)
2. Construction Manager at Risk (CM at Risk / CMR / CM@R)
3. Construction Manager Agency (CM Agency / CMa)
4. Design – Build (DB)
5. Integrated Project Delivery (IPD)
6. Integrated Services
![Page 8: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/8.jpg)
DESIGN-BID-BUILD
A project delivery method where:• Separate contracts for design (Architect)
and construction (Builder)• Criteria for final selection may include
– lowest total construction cost, – qualifications-based, – or a combination of both
As defined by:The Associated General Contractors of America
![Page 9: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/9.jpg)
DESIGN-BID-BUILD
OWNER
ARCHITECT/ENGINEER
SUBCONTRACTORS
CONTRACTOR
![Page 10: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/10.jpg)
A D V A N T A G E S
• Sometimes adversarial relationship between contractor and design team
• Longer total project schedule for sequential periods of design→bidding→construction
• No contractor input on constructability during design
• Owner has little input on subcontractor selection
• Owner responsible for conflict resolution that may occur during construction
D I S A D V A N T A G E S
• Traditional, time-tested, familiar• Owner has control and is involved
in design; preferred when the owner is still developing project needs
• Competitively bid• Widely accepted by public entities
DESIGN-BID-BUILD
![Page 11: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/11.jpg)
![Page 12: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/12.jpg)
CM AT-RISKA project delivery method where: • Separate contracts for design (Architect) and construction (Builder)• CM acts as a consultant to owner in development and design phases• CM assumes the risk for construction performance
(like a General Contractor)holding all trade subcontracts during the construction phase
As defined by:Construction Management Association of America
![Page 13: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/13.jpg)
CM AT-RISK
OWNER
ARCHITECT/ENGINEER
SUBCONTRACTORS
CONSTRUCTION MANAGER
![Page 14: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/14.jpg)
CM AT-RISK
A D V A N T A G E S
• May be restrictions on public bidding requirements that forbid this form of contracting
• Sometimes adversarial relationship between contractor and design team can occur once a GMP is set
D I S A D V A N T A G E S
• Contractor involved during design and provides constructability and cost savings suggestions
• Competitively bid• Schedule reduced with expedited bid
packages and early purchase of long-lead items
• CM handles all RFIs, field change orders, and conflict resolution as the owner’s representative
![Page 15: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/15.jpg)
CM AGENCY
Management process whereby the Owner utilizes a CM as its principal agent to advise on or manage the process over the life of the project, or during specific phases of the project
As defined by:Construction Management Association of America
![Page 16: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/16.jpg)
CM AGENCY
OWNER
ARCHITECT/ENGINEER
SUBCONTRACTORS
GENERAL CONTRACTOR(S)
CONSTRUCTION MANAGER AGENT
![Page 17: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/17.jpg)
A D V A N T A G E S
• Additional cost for CM Agency entity to administer construction contracts
• Owner holds multiple, separate construction contracts
D I S A D V A N T A G E S
• Provide constructability and cost savings suggestions
• Owner gains experienced advice• Schedule reduced with expedited
bid packages and early purchase of long-lead items
• CM Agent handles all RFIs, field change orders, and conflict resolution as the owner’s representative
CM AGENCY
![Page 18: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/18.jpg)
![Page 19: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/19.jpg)
DESIGN-BUILDA method of project delivery in which one entity (the design-build team) works under a single contract with the project owner to provide design and construction services.
As defined by:Design-Build Institute of America
![Page 20: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/20.jpg)
DESIGN-BUILD
OWNER
CONSTRUCTION MANAGER/ARCHITECT/ENGINEER
SUBCONTRACTORS
![Page 21: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/21.jpg)
DESIGN-BUILD
A D V A N T A G E S
• One source responsibility reduces owner’s time and risk
• Reduced schedule through expedited bid packages and early purchase of long-lead items
• Contractor is involved during design and provides constructability/cost savings suggestions
• Integrated team for efficiency and innovation
• Coordinated communication between contractor and design team
• Reduced litigation claims• Owner can choose early on between
multiple design and construction options
• Project is competitively bid
![Page 22: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/22.jpg)
DESIGN-BUILD
D I S A D V A N T A G E S
• Owner must produce bridge documents to outline exact needs (outline specs, plans, specific project requirements)
• Owner/Design-Builder contract must reflect complete understanding of all owner expectations
• Owner has no input when choosing subcontractors for the project, unless specifically requested during construction
• Restrictions on public bidding requirements forbid this form of contracting
• Less owner design control and involvement
• Owner must be responsive in decision making to take full advantage of the speed of design-build
• Contractor may not fully understand the design process
![Page 23: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/23.jpg)
INTEGRATED PROJECT DELIVERY
A project delivery approach for very large projects that integrates people, systems, business structures, and practices into a collaborative process, harnessing the talents and insights of all participants to:
• Optimize project results• Increase value to the owner• Reduce waste• Maximize efficiency through all design and construction phases• Risk and reward are shared equally among contract parties
As defined by:The American Institute of Architects
![Page 24: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/24.jpg)
![Page 25: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/25.jpg)
ENGINEER
INTEGRATED PROJECT DELIVERY
ARCHITECT CONSTRUCTION MANAGER
LANDSCAPE
CONCRETE
MECHANICAL
CIVIL
ELECTRICAL
INTERIOR DESIGN
SPECIALTY CONSULTANTS
STRUCTURAL
OWNER
![Page 26: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/26.jpg)
INTEGRATED PROJECT DELIVERY
A D V A N T A G E S
• Newer and unfamiliar• Arriving at an agreement on the terms
and conditions of the final contract can be a lengthy process
• Chance of failure dependent on individual behavior, which is difficult to control or correct and can cause a breakdown in collaboration
D I S A D V A N T A G E S
• Owner, Architect/Engineer, CM, subcontractor collaboration and team interests aligned with project goals
• Schedule reduced due to expedited bid packages and early purchase of long-lead items
• Extended design and efficient construction, due to shared risk and interest in success
• Ideal for large complex, uncertain, and quick projects
• Increased “value” of construction
![Page 27: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/27.jpg)
INTEGRATED SERVICES
“An alternative single-source project delivery system which integrates professional design and construction services in a manner which provides the owner an efficient way of confidently controlling their project in regard to design, construction, cost, quality, schedule, and overall project performance.”
![Page 28: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/28.jpg)
INTEGRATED SERVICES
A project delivery approach integrating Owner, Architect/Engineer, and CM into a collaborative team to:
• Optimize project results• Increase value to the owner• Reduce waste• Maximize efficiency through all design and construction phases
As defined by:The American Institute of Architects
![Page 29: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/29.jpg)
INTEGRATED SERVICES
A D V A N T A G E S
• Restrictions on public bidding requirements forbid this form of contracting
• Potential for less owner design control and involvement
• Owner must be responsive in decision making to take full advantage of the speed of design-build
D I S A D V A N T A G E S
• Owner, Architect/Engineer, and CM are a collaborative team
• Seamless communication between design team and contractor
• Owner can choose early on between multiple design and construction options
• Project is competitively bid• Reduced litigation claims
![Page 30: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/30.jpg)
ADVANTAGES SUMMARY
![Page 31: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/31.jpg)
![Page 32: MLA Project Delivery Methods Presentation to... · Microsoft PowerPoint - MLA_Project Delivery Methods Presentation.pptx Author: AKM Created Date: 10/3/2018 4:02:45 PM](https://reader033.vdocument.in/reader033/viewer/2022060211/5f04e6ea7e708231d41046fc/html5/thumbnails/32.jpg)
SUPERHERO TEAM TRAINING COMPLETE!
Owner’s decision factors for a project delivery method:• Project type and scope/scale• Tolerance for risk• Project priorities• Schedule• Level of desired involvement• Owner’s capabilities and internal resources• Regulatory requirements