mobilizing large-scale investments for geothermal ... geothermal 04 migara jayawardena... ·...
TRANSCRIPT
Mobilizing Large-Scale Investments for Geothermal Development in Small Island Economies
June 22, 2015Martinique
Migara JayawardenaSenior Energy Specialist
ISLAND ENERGY TRANSITIONS: PATHWAYS FOR ACCELERATED UPTAKE OF RENEWABLES
2
Should small islands look to mobilizing large‐scale financing for geothermal?
Average Electricity Tariffs in Select Caribbean Islands (in 2011)
Average Residential Tariff in OECS and Oil Prices (2002-2010)
Creates hardships, erodes competitiveness, and stymies economic growth
High and Volatile Electricity Costs….
Fossil Fuel Share (%) in Electricity Generation Mix in Select Caribbean Countries
Net Fuel Imports Relative to GDP in Select Caribbean countries
Dependence on expensive fuel oil drives‐up electricity costs, reliance on imports creates vulnerabilities
…are Primarily Driven by Imported Fuel Oil in Power Generation Mix
In OECS, there is Opportunity to Diversify an Shift from Fuel Oil/Diesel
• Reliable, 24/7 non‐intermittent source of power
• Hedge against volatility of fossil‐based fuels
• Indigenous, providing enhanced energy security
• Clean energy option with local and global environmental benefits
Inst. Capacity 59MWGeo potential 25+MW
Inst. Capacity 27MWGeo potential 500+ MW
Inst. Capacity 89MWGeo potential 75+ MW
Inst. Capacity 52MWGeo potential 30+ MW
Inst. Capacity 51MWGeo potential 75+ MW
Inst. Capacity 490MWGeo Inst. Cap 15MWGeo potential 40+ MW
Total geothermal potential for the Caribbean is 745 + MW which could potentially save approximately 1.3 million tCO2 per year of GHG emissions if it becomes operational
6
Several OECS Countries on Cusp of Commercializing Geothermal Developments
Downstream Plant Construction/OpsUpstream Resource Development
Stages and Risks of Geothermal Development
Cumulative time
ISurface
Reconnaissance($1-2 mil)
IIExploration
Drilling($20-30 mil)
IIIProduction
Drilling(~$20-120 mil)
IVSAGS +
Power Plant(~$20-200 mil)
VOperation + Maintenance
Identification of Resource High Resource Risk Lower Resource Risk
Financing Risk Financing Risk Operational Risk
Cum
ulat
ive C
osts
Risk
s
P
hase
Pro
ject R
isk L
evel
Year 1‐2 Year 2‐3 Year 4‐6 Year 6‐8 Years 8+
8
Common Options for Geothermal Financing
Steam Provider
Steam Supply
Contract
• Power Plant BOO/BTO with Steam Off‐take
• “Brown field”: resource development completed, financing power plant only
• “Green field”: financing resource development and power plant concurrently
Project Finance
: Already developed
: To be financed
: The Borrower
• Multiple existing assets and financing expansions
Corporate
Finance
Easier/Harder?
Downstream Plant Construction
Upstream Resource Development
Adapted from presentation by Shinji Yamamoto, IFC at World Bank Energy Week, March 2011
Easier/Harder?
9
KEY CHALLENGE: Geothermal Development Risks
Geothermal resource risk Nascent sector in many SIDS
countries Small scale markets Risks remain throughout
development until power plant operation
10
KEY CHALLENGE: Attracting Qualified Developers to Meet Technical and Financial Requirements
Limited domestic capacity Lack of funding options
Limited interest by qualified developers
Seek risk reduction and confidence to enter market
Power off‐take uncertainty Require high risk premiums
KEY CHALLENGE: Limitations to Mobilizing Cost‐Effective, Large‐Scale Private Financing
Private Investment in Energy Sector for Select Caribbean Countries1997‐ 2011 (US$ million)
Sources: World Development Indicators, PPI Database, The World Bank, 2015
411
275
63
26
33
17
110
‐ 50 100 150 200 250 300 350 400 450
Jamaica
Belize
Haiti
Dominica
Grenada
St. Kitts and Nevis
St. Lucia
12
Where is geothermal development worth the effort?
13
For further Reference