Modeling Tough Scheduling Problems with Software
Alex S. Brownhttp://www.alexsbrown.com
Mitsui Sumitomo Marine Management (USA), Inc.
![Page 2: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/2.jpg)
Objectives• Get Past Frustration (Intermediate)
• Learn New Tools and Techniques (Expert)
• Not For Beginners– Basic Skills Assumed– Assume Experience Using Scheduling Software
• Software-Brand Neutral - Not Taking Sides
• Interactive, Case-Study Format
![Page 3: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/3.jpg)
Key Terms• Network Diagram
• Gantt Chart
• Two Types of Projects
Serial Dependencies Parallel Opportunities
![Page 4: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/4.jpg)
Scenario• Six Tasks
• Three Resources
![Page 5: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/5.jpg)
Four Directions - Pick One!• Resource Leveling
• Representing Hard & Soft Dependencies
• Quickly-Changing Work & Assignments
• Maintaining Schedules During Execution
Go!
Go!
Go!
Go!
![Page 6: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/6.jpg)
Resource Leveling - Key Data• Gather Complete Data At the Start
– Resource start dates and availability– Vacations– Accurate work and duration estimates– Accurate sequence relationships
• Good Data is Essential• When Data Is Good Enough, Level To
Discover The Real End Date
![Page 7: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/7.jpg)
Principles of Leveling• Find a Repeatable Method -- Level
Regularly
• Changes in Any Estimate or Assumption May Require Re-Leveling
• Leveling is Iterative -- Methods Should Allow Small, Frequent Adjustments
![Page 8: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/8.jpg)
Scheduling Tools for Leveling• View Resource Use Over Time
• Adjust Key Task Info– Start Dates– Delays on Tasks– Allocation of Work Over Time by Task
• Resource Availability vs. Work Assigned
Resource/Task Total Work Week 1 Week 2Resource A 40 20 20 Construct #1 20 15 5 Construct #2 20 5 15
![Page 9: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/9.jpg)
Breakout Discussion• Level the Scenario for 40-Hour Weeks, 8-
Hour Days for Each Resource• Different Approaches on the Handouts• Key Questions
– What method do you normally use?– Which is easiest to set up?– Which is easiest to maintain?
• Five Minutes for Discussion
![Page 10: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/10.jpg)
Possible Solutions• Stretch All Work to Five Days Duration
• Make Work Sequential– Move Start Dates– Add Delays
• Break Down the Task List Differently to Simplify Leveling
![Page 11: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/11.jpg)
Selecting A Technique• What is Easiest in Your Software?
• How Hard is Maintenance?
• What Methods Allow for Automation for All or Part of the Work?
• What is the Impact on Reporting and Analysis Techniques?– Critical Path– Earned Value
![Page 12: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/12.jpg)
Questions & Answers on Leveling
Pick NextTopic
![Page 13: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/13.jpg)
Hard & Soft Dependencies• Hard Dependencies MUST Be Obeyed
• Soft Dependencies SHOULD Be Obeyed
• Real-Life Schedules Often Break or Change Soft Dependencies to Achieve Required End Dates
• Challenge Your Assumptions:– Is It Really IMPOSSIBLE for Task B to Start
Until Task A Ends?
![Page 14: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/14.jpg)
Issues with Dependencies• Software Usually Recognizes Only Hard
Dependencies
• Critical Path Analysis is 100% Dependent Upon an Accurate Network Diagram
• Documenting Dependencies is a Challenge
• Documenting Dependencies is Essential
![Page 15: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/15.jpg)
Breakout Discussion• Scenario Uses Soft Dependencies• Soft Dependencies Driven By Resource
Limitations• Questions
– Where do you document dependencies?– What is the critical path?– What do you WANT the critical path to be?– How does the schedule respond to change?
![Page 16: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/16.jpg)
Documenting Dependencies• Many Options
– Two Network Diagrams - “Hard Only” and Current
– Narrative Explanation of Dependencies– Separate Columns or Spreadsheets Track Hard
and Soft Dependencies
• Pick a Method You Can Maintain Easily
![Page 17: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/17.jpg)
Dependencies in Software• Scheduling Software Usually Enforces
Dependencies Strictly (All Hard)
• Options– Only Enter Hard Dependencies - Satisfy Soft
Dependencies During Leveling– Enter Both Hard and Soft Dependencies for
Each Task, Update As Needed– Enter Only the Constraining Dependency
![Page 18: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/18.jpg)
Consequences of Approaches• Calculation of Critical Path
• Clarity of Network Diagram– “Only Hard” is Clearest Diagram– “Hard & Soft” Creates Overlapping Lines– “Only Constraining” Looks Like a Serial
Project’s Network
• Respond to Change Differently -- Task Estimates vs. Task Assignments
![Page 19: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/19.jpg)
Questions & Answers on Dependencies
Pick NextTopic
![Page 20: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/20.jpg)
Quickly-Changing Schedules• Real Schedules Change Every Reporting
Period– Estimate Changes - Work & Duration– Assignment Changes– Resources Added, Removed, and Rescheduled– Resource Availability Changes
• Optimize Schedule, Make New Forecasts• The Only Certainty is Change Itself
![Page 21: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/21.jpg)
Planning for Changes in the Plan• Predict Future Changes
– What is likely to change?– What changed often in the past?– What project risks will cause change?
• Create a Small Schedule with Typical Tasks• Try Making Typical Changes• Experiment, Experiment, Experiment to Find
Best Scheduling Techniques
![Page 22: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/22.jpg)
Breakout Discussion• Start with Initial Scenario
• Apply Changes– Resources No Longer Available– Resources Available More Hours Per Week– Estimate Changes
• Model the Schedule Differently and Repeat– Hard and Soft Dependencies– Different Leveling Techniques
![Page 23: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/23.jpg)
Change is Fundamental• Experiment with Change in a Small
Schedule– Best way to evaluate and compare different
techniques– Great way to explore, understand, and evaluate
scheduling software
• Best Techniques Will Vary -- Find the Best for Your Schedules, for Your Software
![Page 24: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/24.jpg)
Change Drives Automation• Change is Difficult with Hand-Drawn
Schedules and Budgets• Software Facilitates Change by Updating
Every View of a Schedule Simultaneously• WARNING: If the Model is Poor, Software
Can Be MORE Difficult to Update• LESSON: Understand Basic Principles
BEFORE Automating
![Page 25: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/25.jpg)
Questions & Answers on Quickly-Changing Schedules
Pick NextTopic
![Page 26: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/26.jpg)
Maintenance During Execution• Key Steps
– Apply actual work– Update estimates for remaining work– Optimize the schedule and update forecasts
• Many Managers Shelve Schedules After Developing Them
• Schedule Maintenance Key to Learning as an Organization and as a Manager
![Page 27: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/27.jpg)
Benefits of Maintenance• Compare Actuals to Estimates
– Improve estimates for next time– Improve control of work and scope
• Required for Earned Value and Benchmarking
• Accurate, Up-to-Date Forecasts of Delivery Dates
• Prove Scheduling Techniques
![Page 28: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/28.jpg)
Package-Specific Features• Timesheets Automate and Distribute Entry
of Actuals
• Entry of Actuals Vary by Software Package
• Different Packages Reschedule Remaining Work Differently
• Do Not Focus on Software Differences, Focus on Creating a New Forecast
![Page 29: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/29.jpg)
Breakout Discussion• Review Actual Progress After Week 1
• Schedule the Remaining Work
• Questions– Can you predict how your software would
reschedule the remaining work?– Do we change dependencies now that work is
started?
![Page 30: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/30.jpg)
What SHOULD Software Do?• Actuals Sometimes Break “Rules” in the
Schedule– Actual work starts before predecessor is
complete– “Must Meet” deadlines missed
• Software Packages Make Assumptions and Raise Warnings -- Each Has a Different Approach
![Page 31: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/31.jpg)
Responsibility As Software Users• Understand That Actual Work Might Break
Our Model
• Software May React Unpredictably When Our Models Are Wrong
• Understand Software Settings, Defaults, and Options
• Experiment, Experiment, Experiment -- Create Small Schedules to Test and Learn
![Page 32: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/32.jpg)
Important Choices• Techniques Used When Building Schedule
Determine Maintenance Procedures
• Schedule Time to Update the Schedule
• Update the Schedule and Forecast New End Dates Regularly
• Larger Projects = Maintenance is Critical
• Larger Projects = Maintenance is Difficult
![Page 33: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/33.jpg)
Questions & Answers on Schedule Maintenance
Pick NextTopic
![Page 34: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/34.jpg)
Review - Four Tough Problems• Resource Leveling
• Representing Hard & Soft Dependencies
• Quickly-Changing Work & Assignments
• Maintaining Schedules During Execution
![Page 35: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/35.jpg)
In the Paper• Exercises
• More Details on All Four Topics
• Comparison of Novice vs. Expert Use of Scheduling Software
• Ideas to Improve Your Skills
• References and Additional Reading
![Page 36: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/36.jpg)
Complete Your Learning Experience
• This Presentation is a First Step
• Download the Paper
• Run Exercises Using Your Software
• Select Scenarios From Your Schedules and Try New Techniques
• Hear It and You Will Forget It
• Do It and You Will Remember It!
![Page 37: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/37.jpg)
Questions & Answers• Contact Speaker at
http://www.alexsbrown.com or [email protected]
• Evaluation Forms
• Feedback on New Case Study Format Appreciated
![Page 38: Modeling Tough Scheduling Problems with Software Alex S. Brown Mitsui Sumitomo Marine Management (USA), Inc](https://reader035.vdocument.in/reader035/viewer/2022062422/56649f1e5503460f94c368cd/html5/thumbnails/38.jpg)
Modeling Tough Scheduling Problems with Software
Alex S. Brownhttp://www.alexsbrown.com
Mitsui Sumitomo Marine Management (USA), Inc.