modification number: 052914-03
TRANSCRIPT
limiteci-M.--shedsrenelosed-lean4os:ramp-houses.
small-animal-housing,
Record of Modification to the
Response Action Work Plan (RAWP) Revision 6.0
Modification Number: 052914-03 (six-digit date code — sequential number
Date: 05/29/2014
Section to be Modified:
4.7 Vermiculite and ACS Removal from Secondary Buildings and Structures
4.7.1 Definitions
Secondary buildings and secondary structures are fully defined in CDM-Libby-06 Site-specific
Procedure for Semi-Quantitative Visual Estimation of Vermiculite. This procedure is provided in
Appendix B of the General Property Investigation Quality Assurance Project Plan (CDM Smith
2014, or current revision).
Once the RC has completed removal of all gmss-visible-vennieulite ral4 vinibleNemneuliter and all ACS to planned depth, TQA will be notified to facilitate inspection and collection of
confirmation samples. Confirmation sampling will be conducted in accordance with the
Response Action Sampling and Analysis Plan (CDM 2011b, or current revision).
VCI removals within enclosed secondary structures will follow interior removal process as stated
in section four of this document.
1 of 3
Details regarding action levels and clearance criteria are found in the Libby Asbestos Site
Residential/Commercial Cleanup Action Level and Clearance Criteria Technical Memorandum
(EPA 2003) and its revisions. Action levels and clearance criteria are subject to revision by the
EPA.
4.7.21'1:Inning and Removal Process
Finished secondary buildings with solid-construction floors (e.g.. concrete, wood, etc.) will
undergo removal actions similar to a primary building.
Secondary buildings often include unfinished, soil floors. Contaminated soil within a building
presents unique removal challenges. In general, removal will be completed with a combination
of interior and exterior techniques. The following steps will be followed for addressing the soil
floor of a secondary building in which Eleteetable4evels-of greater than or equal to one percent
LA is detected.
1. Complete vermiculite insulation removal (attic) in accordance with Section 2
2. Remove and clean or dispose of all items within the building
3. Complete a bulk/gross cleaning of the interior
4. Excavate soil floor to a depth of 6-inches below ground surface (bgs)
5. Contain interior of building (negative pressure enclosure/containment)
6. Detail clean interior of building
7. Collect soil clearance samples
8. Backfill the floor of the excavated area (area will still be considered within the exclusion
zone)
9. Return all items back into the structure
10. Collect air clearance samples
11. Remove NPE after clearance has been achieved
12. Complete backfilling, if necessary
If a secondary buildings has only soil contamination with analytical results of less than one
percent or trace LA and is called out on the work plan for removal, the removal will follow the
process listed above except negative pressure enclosure and final air clearance is not required.
Negative pressure enclosure and final air clearance may be conducted at the direction of
USACE/EPA.
2 of 3
Soil areas within secondary structures will be treated as normal excavation. No additional cleaning is required.
. Negative pressure enclosure and final air clearance will not be required. Due to potential for undermining the foundation, excavation within secondary
structures will typically be limited to a minimum of 6 -inches bgs. All excavation and restoration will be conducted in accordance with Section 3 and Section 4.
Attach the referenced section to this record. Strike the language to be removed. Underline additions to existing language.
Si m ature Name Date
6 /,, WiV EPA Approval: bk--62-------. itt.a.,9-e. ( e.. ( (- fat._ USAGE Approval: r-Ired, ------
DM855. ----- Lawrence J. Woscyna 6/24/14
A&E Approval: = 1.417-10^NS . .aest_- G -t9 - I r G. 43-74/ RC Approval: "Ilizokic.L. .3--Acgsr..) n
04
3 of 3