module 12 session 12.1 visual 1 module 12 terminating the project session 12.1: terminating the...

23
Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Upload: neil-hopkins

Post on 13-Jan-2016

228 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 1

Module 12

Terminating the Project

Session 12.1: Terminating the Project

Page 2: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 2

Instructional Objectives

At the end of the session, the learner will able to

1. List at least five tasks a project manager typically

must perform during termination.

2. Describe at least three problems commonly encountered during project termination.

3. Describe at least three best practices that may make the transition from project to operations more successful.

Page 3: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 3

Steps Involved in Closing a Project

Step 1. Ensure that project deliverables and objectives have been achieved.

Step 2. Complete close-out activities: Complete paperwork. Plan for the operational phase. Transfer personnel.

Step 3. Carry out postproject audit.

Page 4: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 4

Step 1: Ensure That Project Objectives

are Achieved.

Agree with contractors and consultants on remaining deliverables.

Agree with suppliers on outstanding commitments.

Page 5: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 5

Step 2: Complete Close-Out Activities

Responsibility of Project Management

Responsibility of Contractors or Consultants

Joint Responsibility

• Plan for maintenance (done jointly with contractor or supplier and your organization’s maintenance department).

• Close out contracts and settle disputes.

• Transfer files and documentation.

• Obtain needed government approvals and certification.

• Plan inspection and acceptance procedures.

• Inspect and accept deliverables.

• Plan for ex post evaluation; design monitoring system.

• Close out project accounts, including work orders and work packages.

• Close project facilities.

• Arrange for transfer of personnel.

• Coordinate planning for commissioning of facilities and start-up of operations, including training.

• Perform postproject audit.

• Notify affected communities.

• Close contractor facilities.

• Prepare as-built drawings (or the equivalent) and other project documentation.

• Prepare operational manuals.

• Complete punch list.

Page 6: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 6

Project Termination Paperwork

Review and agree on termination checklist with contractors, consultants, and suppliers.

Prepare termination plan of action, including all activities that need to be carried out, who is responsible, and dates: Project accounts Contracts Drawings, files, reports, and other documents Approvals and certifications

Page 7: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 7

Planning for Start-Up of Operations

Project management’s role:

Coordinate transition to operations Notify those responsible for operations. Assist in preparation of operational plan. Ensure training needs are known and addressed. Ensure operational policies, systems, and

procedures are prepared. Transfer any files, documents, or materials

necessary for operations, such as maintenance manuals.

Page 8: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 8

Step 3: Postproject Audit

Purpose: To learn from experience Identify mistakes. Determine impact of mistakes. Identify how mistakes can be avoided on future

projects. Make appropriate changes and improvements in

project management and functional policies and procedures.

Source: Russell Archibald. 1992. Managing High Technology Projects and Programs, 2nd ed. New York:John Wiley Publishers.

Page 9: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 9

Components of a Postproject Audit

1. What were the original and final objectives? Performance (Scope) Cost Schedule

2. Were the objectives met?

3. Were there problems in the process of implementation?

4. What factors contributed to successful aspects?

5. What factors contributed to problems and mistakes?

6. What policy or procedural changes could avert future problems?

7. Implement any necessary changes.

Page 10: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 10

Step 2: Complete Close-Out Activities

Responsibility of Project Management

Responsibility of Contractors or Consultants

Joint Responsibility

• Plan for maintenance (done jointly with contractor or supplier and your organization’s maintenance department).

• Close out contracts and settle disputes.

• Transfer files and documentation.

• Obtain needed government approvals and certification.

• Plan inspection and acceptance procedures.

• Inspect and accept deliverables.

• Plan for ex post evaluation; design monitoring system.

• Close out project accounts, including work orders and work packages.

• Close project facilities.

• Arrange for transfer of personnel.

• Coordinate planning for commissioning of facilities and start-up of operations, including training.

• Perform postproject audit.

• Notify affected communities.

• Close contractor facilities.

• Prepare as-built drawings (or the equivalent) and other project documentation.• Prepare operational manuals.

• Complete punch list.

Page 11: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 11

Potential Behavioral Problems

1. Fear of no future work

2. Loss of interest in tasks remaining

3. Loss of project-derived motivation

4. Loss of team identity

5. The effect of personnel reassignment

6. Reassignment methodology

7. Diversion of effort

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 12: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 12

Potential Behavioral Problems

Contractors’ and consultants’ concerns at project termination

1. Changes in attitude

2. Loss of interest

3. Change of personnel

4. Unavailability of key personnel

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 13: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 13

Potential Behavioral Problems

Dealing with low interest and lack of team identity

1. Define termination as a project.

2. Provide a team identity.

3. Bring the team together frequently.

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 14: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 14

Potential Behavioral Problems

Dealing with project staff’s concerns about reassignment

1. Be honest about reassignment and future work.

2. Make each reassignment decision a conscious, deliberate choice.

3. Hold the right personnel.

4. Carry out reassignments openly.

5. Play an active role in reassignment.

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 15: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 15

Staff Characteristics Needed at Termination

Flexibility Independence Attention to detail Highly developed skills

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 16: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 16

Potential Behavioral Problems

Things the contractor, supplier, and consultant should do:

1. Outline availability of future support for the project’s deliverables.

2. Identify warranty obligations and the start and completion dates.

3. Be willing to negotiate.

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds.. New York: Van Nostrand Reinhold.

Page 17: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 17

Technical Problemsat

Termination

Have To Do WithDetails

Page 18: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 18

Technical Problems: Close-Out Activities Identifying and agreeing on remaining deliverables Certifying and accepting Identifying and agreeing on outstanding commitments Controlling charges to the project Screening uncompleted tasks that are no longer needed Closing work orders and work packages Identifying, closing, and/or transferring physical facilities Accumulating and structuring project historical data:

post-project audit Disposing of project material Implementing the warranty program and other

postcontract efforts Communicating closures

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 19: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 19

Dealing With Potential Technical Problems

Analytical Tools

Tree Diagrams

Matrixes

List

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Page 20: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 20

Tree Diagram for Termination

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., NewYork: Van Nostrand Reinhold.

Project close-out

Organization Financial Purchasing Site

Close-out meeting

Reassignment plan

Personnel reports

Collect receivables

Supplier notifications

Final payments

Compliance documents

Charge audits

Final report

Close down facilities

Equipment/material disposal

Page 21: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 21

Matrix Model for Relationship Among Commitments, Vendors, and Status

Co

mp

any

1

Co

mp

any

2

Co

mp

any

3

Co

mp

any

4

Co

mp

any

5

Stand pipes

I

Note:

D - To take delivery

N - In negotiation

I - Awaiting information

C - Closed

Blank indicates no commitment, past or present

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Pumps D

CChemical

Water tanks

Vehicles

I

D

D

C

C I

N

D

DN CMeters

N

Page 22: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 22

Matrix Model for Assignment of Records in Project Termination

Source: Herbert F. Spirer and David H. Hamburger. 1990. “Phasing Out the Project,” in Project Management Handbook, David I. Cleland and William R. King, eds., New York: Van Nostrand Reinhold.

Note:

P - Prepare

A - Approve

R - Review

E - Execute

Quality assurance manual P

PQA procedures index

Drawings, auto equipment

Drawings, calibration blocks

A

A

P/E R

Spare parts specifications

Calculation notebooks

QA audit schedule

A

A

A

P R

P

P

R

A

P

R P

Dir

ecto

r o

f p

roje

cts

Tas

k en

gin

eer

Au

tom

atic

eq

uip

. m

anag

er

Vic

e p

res

iden

t o

per

ati

on

s

Pro

jec

t m

ana

ger

Qu

alit

y a

ssu

ran

ce m

anag

er

Page 23: Module 12 Session 12.1 Visual 1 Module 12 Terminating the Project Session 12.1: Terminating the Project

Module 12 Session 12.1 Visual 23

A Project Manager Needs

Knowledge of financial systems and accounting

Technical knowledge of project

Negotiating skills

A sense of urgency about details