PRE-CONSTRUCTION OSH PLANNING

CONSTRUCTION SAFETY & HEALTH OFFICER

Page 2: Module 4 pre construction

a) identify basic OSH requirements to be considered during pre-construction stage; and

b) make necessary arrangements during pre-construction stage.

To enable the participants to:

Page 3: Module 4 pre construction

Proper planning should be an integral part of efficient running of a construction operation.

It is not only for overall preparation and budgeting purposes but also a proactive measure for handling and managing occupational safety and health matters for the work to be carried out.

Page 4: Module 4 pre construction
Page 5: Module 4 pre construction

Examine contract documents, specifications and drawings - to establish

any constrains which might affect the site layout or method of construction

CONTRACT

DOCUMENT

CONTRACT

DOCUMENT

Page 6: Module 4 pre construction

Location of Sites

Environmental Matters

Nature of Site

Page 7: Module 4 pre construction

Determine logical sequence of work and identify any high risk operations,

hazardous process, etc.

Site Clearance

Demolition

Page 8: Module 4 pre construction

Construction Operations

High Risk Operations

Determine logical sequence of work and identify any high risk operations,

hazardous process, etc.

Page 9: Module 4 pre construction

Access Equipment

Determine the type and capacity of plant and need for competent operators:

Lifting Appliances & Gears

Mobile Plant

Site Transport

Power Supplies

Workshop Requiremen

ts

Page 10: Module 4 pre construction

Determine requirements for temporary accommodations

Welfare & First Aid Facilities

Offices Canteen

Temporary Living Accommodation

Laboratory

Facilities?

Page 11: Module 4 pre construction

Determine storage requirements e.g. for:

a) Steel.b) Formwork.c) Cements.d) Pre-cast Units.e) Scaffolding.f) Bricks, Blocks & Sand.g) Structural elements.Hh) Highly flammable liquids,

LPG, explosives and waste.

Page 12: Module 4 pre construction

Define areas of the site for: a) access for plant,

materials and emergency services.

b) fixed plant, e.g. tower cranes, batching plant, bar bending and workshops.

c) mobile plant, e.g. cranes, dumpers, fork lifts, concrete trucks, pumps, etc.

d) temporary accommodation.e) material storage.

Page 13: Module 4 pre construction

Determine measures for site security and protection of the public, particularly children.

Determine arrangements for liaison with neighbourhood.

Page 14: Module 4 pre construction
Page 15: Module 4 pre construction

1. Sets out the arrangements for securing OSH at work.

2. Based on preliminary assessment outcome.

Project Safety

& Health Plan

Project Safety

& Health Plan

Page 16: Module 4 pre construction

It deals with:

OSH risks to workers & others

Arrangements for

Control & Monitoring

of OSH

Arrangements for HIRARC, ERP, etc.

Project Safety &

Health Plan

Project Safety &

Health Plan

Page 17: Module 4 pre construction

It should include:

Project Safety &

Health Plan

Project Safety &

Health Plan

1. OSH Policy & Objectives

2.Assignment of OSH responsibilities

3.Methods for HIRAC, JSA, etc.

4.Accident investigation & reporting

5.On-site ERP6.Site communications

7.Safety audit program

8.Co-ordination of on-site trade activities

Page 18: Module 4 pre construction

Outline – Heading Information

Co. Reg. No : 12345-X

Proposed Construction and Completion of Water Treatment Plant at Bandar

Baru Wangi, SELANGOR DARUL ENSHAN

Contract No : JPP/WT/1/2005

Revision No : 0 Date : 28 Oct 2004

28/10/04Approved ByAriffin Ahmad

Project Manager

Ariffin

DateTaskName &

DesignationSignature

21/10/04Prepared ByMohammad Razali Mamat Safety & Health Officer

MRM

25/10/04Checked ByKamarulzaman bin

Musa Safety & Health Manager

Kamarul

Document No : XYX/WT/SH/01

Document Revision

No & Effective

Date

Document No

Contractor’s Name

Issue No

Project Title &

Contract No

Page 19: Module 4 pre construction

Outline – Contract Description

Office : 03-87841008 Fax : 03-87841009 H/P : 012-3456789

The Construction & Completion of Water Treatment Plant at Bandar Baru Wangi, Selangor Darul Ehsan.

Scope of Work

RM 25 million

To construct a reinforced concrete water reservoir of 1 million liter capacity.

To install electrical and mechanical equipment for the treatment work.

1 Oct 2004 – 31 March 2005 (18 Months)

Ariffin bin Ahmad

Project Title

Contract No JPP/WT/1/2005

Contract SumContract PeriodProject ManagerContact Number

Page 20: Module 4 pre construction

SAFETY & HEALTH POLICY

3,000,000 MAN-HOURS WITHOUT LTI THROUGH OUT DURATION OF CONTRACT

At XYZ Construction Sdn. Bhd our Safety & Health Policy is based on a belief that the well-being of person employed at work or person affected by our work is a major priority and must be considered during all our undertakings.

Employees are our most important asset and their safety & health is our greatest responsibility. The public should be given equal priority to that of our employees.We are committed in ensuring all our legal obligations as stipulated under the Occupational Safety & Health Act 1994, Regulations & Orders and other applicable legislative requirements are complied with.

1.provide necessary resources for implementing all arrangements made under the policy.

2.make safety & health as an integral part of and culture within the project – all employees shall cooperate and responsible in all safety & health matters.

3.ensure Safety & Health shall be given utmost priority in all activities – SAFETY FIRST.

4.establish an effective consultation and communication mechanism, in particular through the Safety & Health Committee.

5.provide necessary education and training for all employees.

The prime objective of our Safety & Health Policy for this Project is to achieve:

The Project Manager shall be assisted by the Safety and Health Officer in ensuring the intent of this policy being translated into action effectively and smoothly .

In order to achieve the above-mentioned objective and to comply with relevant statutory obligations, so far as is practicable XYZ Construction Sdn. Bhd. will:

Date : 25 Oct 2004Tan Sri Ahmad bin Dollah Managing Director

1.Contractor’s written statement confirming OSH commitment.

2.Quantifiable Objective.

3. Arrangements to achieve OSH objectives.

4.Person responsible for effective implementation & monitoring.

6.Dated by organisation’s highest authority.

5.Signed by organisation’s highest authority.

Page 21: Module 4 pre construction

How is the accountability

fixed - delegated responsibilities

are undertaken?How is the policy

implementation monitored?

Who is responsible to whom and for

what?

Page 22: Module 4 pre construction

Commitment & Leadership

Policy

Planning & Implementation

OrganisingEvaluationCorrective

Action

Continual Improvement

Other organizational features should include:

1.individual job descriptions having a safety content.

2.details of specific safety responsibilities.

3.the role and function of safety committee(s).4.the role and

function of SHO & SSS.

5.an organization chart - lines of responsibility & accountability

Page 23: Module 4 pre construction

DESIGNATED PERSON

MANAGING DIRECTOR

PROJECT MANAGER

SHO

PROJECT ENGINEER / SITE

AGENT

CONSTRUCTION MANAGER

DESIGNATED PERSON

DESIGNATED PERSON

Communication

Responsibility & Accountability

Page 24: Module 4 pre construction

Responsibilities, Authority & Accountability – An ExampleXYZ Construction Sdn. Bhd. will provide the following key personnel on site. Their

roles and responsibilities, authority and accountability regarding safety on site are outlined below.PROJECT MANAGERMr. Ariffin bin Ahmad as the Project Manager is responsible, authorised and accountable for safety and health on the project. Duties include:1. implementing the company Occupational Health Safety and Rehabilitation

procedures;2. using the principles of the Hierarchy of Controls in all design, fabrication and

construct activities to minimise the risk to all personnel in the workplace;3. carrying out a design review with the Client’s representative to assist in the

identification of further risk reduction controls measures;4. participating in the planning and design stages of trade activities;5. stimulating a high level of safety awareness at all times;6. identifying safety training needs;7. leading by example;8. ensuring safe equipment and plant is provided and maintained;9. insisting on correct and safe work practices at all times;10.assisting in the identification and preparation of safe work procedures;11.reviewing safety reports and inspections and initiating rectification where

necessary;12.participating in accident/incident investigations;13.participating in safety meetings and programs; and14.monitoring compliance with safe work methods (controls).

Page 25: Module 4 pre construction

Responsibilities, Authority & Accountability – An Example

SITE SUPERVISORMr. Lee Chong Meng as the Site Supervisor is responsible, authorised and accountable for safety and health on the project. Duties include:1. implementing the company Occupational Health Safety policy and procedures;2. observing all OHS requirements and statutory rules and regulations;3. ensuring that all works are conducted in a manner that is safe and without risk to

employees health and safety;4. planning to do all work safely; 5. providing advise and assistance on OHS to all employees; 6. participating in the planning and design stages of trade activities; 7. ensuring current OHS and other relevant legislative requirements are met in the

workplace; 8. identifying OHS training programs in advance and allowing for employee/s identified as

requiring training to attend the training; 9. actioning safety reports and carrying out workplace inspections; 10.preparing and participating in safety meetings and safety programs; 11.facilitating the preparation of Safe Work Procedures and Method Statement for the

trade; 12.insisting and ensuring on safe work practices at all times; 13.investigating hazard reports and ensuring that corrective actions are undertaken; 14.conducting project inductions, toolbox talks and daily team briefings; 15.participating in accident/incident investigations; 16.leading by example and promoting OHS at every opportunity; 17.supervising and ensuring compliance with safe work procedures; and18.providing suitable employment to assist rehabilitation initiatives; and stimulating a high

level of safety awareness at all times.

Page 26: Module 4 pre construction

a) Site Safety Induction.b) Risk Management.c) Safe Work Procedures.d) Workplace Inspection.e) Consultation & Communication.f) Emergency Preparedness.g) Incident Investigation & Reporting.h) Occupational Health Arrangements.i) Performance Monitoring.j) Non-Compliance.k) Promotion, etc.

1. This part deals with the practical arrangements by which the policy will be effectively implemented.

2. These include:

ARRANGEMENTS

Page 27: Module 4 pre construction
Page 28: Module 4 pre construction

to protect the public from site

hazards

to prevent children straying

on the site

provided with suitable perimeter

fencing

Page 29: Module 4 pre construction

Standard of fencing required for a particular site will depend on the hazards and environmental conditions of the worksite as well as its location.

Page 30: Module 4 pre construction

Some factors to consider:

building height (e.g. more than 1 storey).

location near shops, offices, schools, residential areas.whether there are any trenches and trench depth.

whether the site is vacant outside work hours

Page 31: Module 4 pre construction

Consideration for level of risk: High risk - Areas that the public would normally access or pass through - it is necessary to prevent public access to the work site.Medium risk - Areas with moderate public traffic, such as suburban residential areas - it is necessary to restrict access to the worksite, and provide warning of the hazard.Low risk - Areas with minimal public access such as rural areas or new sub-divisions require a lower level of protection.

Page 32: Module 4 pre construction
Page 33: Module 4 pre construction

separate padestrian

route

safe access and good visibility

trained banksman/

traffic controller

one-way systems

routes must be

maintained in good order

suitable warning and directional

signs

Page 34: Module 4 pre construction
Page 35: Module 4 pre construction

Location of store and storage areas will be determined by:

availability of space nature of the materials

statutory requirementssuitable off loading areas and lifting

equipment

Page 36: Module 4 pre construction
Page 37: Module 4 pre construction

Physical features on the site, building under construction and environmental constraints will determine positioning of cranes, hoist and other lifting appliances.

Page 38: Module 4 pre construction
Page 39: Module 4 pre construction

The positioning and marking of temporary services should be carefully undertaken to avoid possibility of accidental damage.

Page 40: Module 4 pre construction
Page 41: Module 4 pre construction

Adequate space must be allowed for lighting towers and for scaffolding and other support work.

Page 42: Module 4 pre construction
Page 43: Module 4 pre construction

1. Rubbish dumping area must be allocated. 2. Arrangements for regular disposal must

be determined particularly for scheduled waste.

Page 44: Module 4 pre construction
Page 45: Module 4 pre construction

Consideration should be given in parking facilities either on or off site.

Page 46: Module 4 pre construction
Page 47: Module 4 pre construction

To appoint full time qualified safety and health officer for work with contract sum more than RM20 million.

Occupational Safety & Health (Safety & Health Officer) Orders1997.

3

To appoint qualified person as safety and health officer.

Occupational Safety & Health (Safety & Health Officer) Regulations 1997.

2

Appointment of safety and health officer.

Section 29, Occupational Safety & Health Act 1994.

1

ACTIVITIESACT/REGULATIONNO

Page 48: Module 4 pre construction

ACTIVITIESACT/REGULATIONNO

To appoint competent person as designated person for controlling public vehicular traffic.

Sub-Reg. 18 (1), F&M (BOWECS) 1986 – Public Vehicular Traffic

6

Other contractor than the main contractor to appoint part-time contractors’ safety supervisors if employ more than 20 workers.

Regulation 26, Factories & Machinery (Building Operations & Works of Engineering Construction) (Safety) Regulations 1986.

5

Main contractor to appoint a part-time site safety supervisors.

Regulation 25, Factories & Machinery (Building Operations & Works of Engineering Construction) (Safety) Regulations 1986.

4

Page 49: Module 4 pre construction

ACTIVITIESACT/REGULATIONNO

To appoint competent person as designated person for inspection and maintenance of safety belts/harnesses.

Sub-Reg. 54(1), F&M (BOWECS) 1986 – Safety Belt / Safety Harness

8

To appoint competent person as designated person for supervising concrete work, formwork, shoring and other support systems.

Sub-Reg. 29 (1), (2) & (3), F&M (BOWECS) 1986 – Concrete Work, Formwork, Shoring & Other Supports

7

To appoint competent person as designated person for controlling public vehicular traffic.

Sub-Reg. 18 (1), F&M (BOWECS) 1986 – Public Vehicular Traffic

6

Page 50: Module 4 pre construction

ACTIVITIESACT/REGULATIONNO

To appoint competent person as designated person for supervising demolition works.

Reg. 103, F&M (BOWECS) 1986 – Demolition

11

To appoint competent person as designated person for erection, alterations, dismantling and maintenance of scaffolds.

Sub-Reg. 74 (1) & 85 (1), F&M BOWECS) 1986 - Scaffolds

10

To appoint competent person as designated person for inspection and maintenance of safety nets.

Sub-Reg. 57 (1), F&M (BOWECS) 1986 – Safety Net

9

Page 51: Module 4 pre construction

ACTIVITIESACT/REGULATIONNO

To appoint competent person as designated person for supervising works related to the use of explosives and blasting.

Reg. 135, F&M (BOWECS) 1986 – Blasting & Handling of Explosives

14

To appoint competent person as designated person for supervising pile driving and load tests.

Reg. 125 & 127, F&M (BOWECS) 1986 – Piling

13

To appoint competent person as designated person for supervising excavation works.

Sub-Reg. 111 (2) & 113 (2), F&M (BOWECS) 1986 – Excavation Work

12

Page 52: Module 4 pre construction

ACTIVITIESACT/REGULATIONNO

To establish Safety & Health Committee when employing 40 or more workers or as directed by the Director General of DOSH.

Section 30, Occupational Safety & Health Act 1994

16

To appoint chemical risk assessor when using chemical hazardous to health.

Regulation 11, Occupational Safety & Health (Use & Standards of Exposure of Chemicals Hazardous to Health) Regulations 2000

14

Page 53: Module 4 pre construction
Page 54: Module 4 pre construction

1. Copies of main contractor’s safety policy should be given to all sub-contractors name of Safety & Health Officer/Supervisor.

2. All sub-contractors shall furnish main contractor with copies of their policies and name of their Safety & Health Officer/Supervisor.

3. Relevant codes and standards to be adopted as term of references should be identified and agreed.

Page 55: Module 4 pre construction

4. Requirements for sub-contractors representatives in the project Safety & Health Committee should be discussed and appropriate arrangements made.

5. Procedures and arrangements for any necessary mandatory and site specific induction training and other necessary training through out the duration of the contract should be identified and agreed.

6. Establish and agree procedures for reporting injuries, diseases and dangerous occurrences both to relevant authority and site management.

Page 56: Module 4 pre construction

7. Arrangements welfare and first aid facilities are to be agreed and any shared facilities are to be confirmed.

8. First aid arrangements should include the appointment of first aiders and procedures for responding quickly to an accident and for calling emergency services.

9. Requirements and provision of appropriate items to be agreed, together with arrangements for storage, inspection and any necessary training.

Page 57: Module 4 pre construction

10. Agree on any processes or operation requiring a permit-to-work/enter system. Determine which sub-contractors are affected and establish formal procedures.

11. Responsibilities and procedures for dealing with access problems common to all sub-contractors (such as scaffolds, floor openings, etc.) and disputes on safety matters.

12. Agree provision of appropriate fire fighting equipment for work processes and, stores, accommodation and offices.

Page 58: Module 4 pre construction

14. Agree procedures in the event of fire, rescue from confined spaces and any other emergency that occurred at the workplace.

15. Agree arrangements for the storing of materials and the cleaning of waste on a regular basis. Provision should be made for the main contractor to contra-charge sub-contractors where these arrangements are not followed.

16. Determine site rules, to include where appropriate, client’s rules. Copies of site rules to be issued to all sub-contractors.

Page 59: Module 4 pre construction

17. Arrangements for early installation of a telephone or any other suitable means of communication are essential for both business and safety reasons.

18. Telephone numbers to be contacted in the event of an emergency should be displayed.

19. A specific general site rules outline the do’s and dont’s should be established.

Page 60: Module 4 pre construction

DOEDOSH

Page 61: Module 4 pre construction

Construction Industry Development Board

APPLICATIONNO LEGAL PROVISIONS

Contractor Registration & Levy for Contract Sum More Than RM500,000.00

2 Part VIII, Lembaga Pembangunan Industri Pembinaan Malaysia 1994

Contractor Registration 1 Part VI, Lembaga Pembangunan Industri Pembinaan Malaysia 1994

Page 62: Module 4 pre construction

Department of Occupational Safety & Health

APPLICATIONNO LEGAL PROVISIONS

Registration of construction sites when work is expected to be completed for a period more than six weeks – JKJ 103.

2 Section 35, Factories & Machinery Act 1967 and Regulation 3, Factories and Machinery (Notification, Certificate of Fitness and Inspection) Regulations 1970

Registration of factories such as casting yard and batching plant – JKJ 101.

1 Section 34, Factories & Machinery Act 1967 and Regulation 3, Factories and Machinery (Notification, Certificate of Fitness and Inspection) Regulations 1970

Page 63: Module 4 pre construction

Department of Occupational Safety & Health

APPLICATIONNO LEGAL PROVISIONS

Employer to notify JKKP on the appointment and termination of Safety & Health Officer within one month

5 Reg. 14, Occupational Safety & Health (Safety & Officer), Regulations 1997

Permission to install machinery requiring Certificate of Fitness such as tower cranes, gantry, etc. – JKJ 105 & JKJ 127.

3 Section 36(2) of the Act and Regulation 7(1) of Factories and Machinery (Notification, Certificate of Fitness and Inspection) Regulations 1970

Permission to use/operate other machinery (not requiring COF) for the first time – JKJ 106.

4 Section 34, Regulation 7(2) of Factories and Machinery (Notification, Certificate of Fitness and Inspection) Regulations 1970

Page 64: Module 4 pre construction

Department of Environment

APPLICATIONNO LEGAL PROVISIONS

Approval of plans to carry out on any premises or land that may result in a new source of effluent discharge.

2 Regulations 5(1) Environmental Quality (Sewage and Industrial Effluents) Regulations 1979

Approval of plans to carry out work that would cause land or building to become prescribed premises.

1 Section 20(1), Environmental Quality Act 1974

Page 65: Module 4 pre construction

Local Authorities

APPLICATIONNO LEGAL PROVISIONS

Notice of Commencement of Resumption of Building Operations.

3 By-Law 21(1) of the Uniform Building By-Laws

Submission of Plans for Approval.

1 By-Law 3(1)(c) and 16(2) of the Uniform Building By-Laws

Application for temporary permits for erection of sheds for store, depositing of materials on streets, etc.

2 By-Law 19 of the Uniform Building By-Laws

Page 66: Module 4 pre construction

Local Authorities

APPLICATIONNO LEGAL PROVISIONS

Certificate of Fitness for Occupations.

6 By-Law 25(1) of the Uniform Building By-Laws

Notice of Completion of Setting Out.

4 By-Law 23(1) of the Uniform Building By-Laws

Notice of Completion of Excavation for Foundation.

5 By-Law 24 of the Uniform Building By-Laws

Page 67: Module 4 pre construction

OTHER DEPARTMENTS / AGENCIES

APPLICATIONNO AGENCIES

Handling & Use of Explosives.

3 Police Department

Storage of Flammable Materials.

1 Fire & Rescue Department

Food Handler to be Vaccinated.Report on Epidemics.

2 Health Department

Page 68: Module 4 pre construction
Page 69: Module 4 pre construction

1. As with other potential hazards that may arise in the course of any construction work, a temporary traffic management must be developed before commencement of work.

2. The objective is to safeguard not only the workers involved in the work but also members of the public who might be affected by the work activities.

Page 70: Module 4 pre construction

Consider the following:

1. Width of road – is there enough room for traffic and plant to manoeuvre safely?

2. Can the road shoulders be used to provide an additional traffic lane.

3. Traffic density – what will be the likely effects on safety and health, and delays in traffic movements and construction time of the alternative option.

Page 71: Module 4 pre construction

3. Percentage of heavy vehicles – consider seasonal operations.

4. Terrain – will terrain introduce additional hazards such as curves, swamp, etc.

5. Environmental factors – take into account the range of environmental conditions, such as wet conditions, poor visibility and darkness.

Page 72: Module 4 pre construction

1. Pedestrian detours are clearly defined, and pedestrians protected from the dangers of road traffic when using any detour.

2. The passage of vehicles across footpaths is to be supervised, to remove danger to the public.

3. Flagmen, barriers, signs or traffic lights are used to stop the public passing under suspended loads (unless there is a protective gantry).

4. Excavations are fenced, and, if they are like to retain water, are covered and securely fenced to prevent access for children. If in public places, they should have warning signs, and warning lights at night

Page 73: Module 4 pre construction

5. Pneumatic tools are to have silencers, and piling dollies are to be of timber or neoprene so that noise is kept to acceptable levels.

6. If scaffolding must intrude on to footpaths, it is to be clearly marked, and padded if there is any risk of causing injury.

7. Adequate security of the site is to be provided during non-working periods.

Page 74: Module 4 pre construction

1. Define speed limit.2. Minimize the

amount of noise workers are exposed through administrative or engineering control.

3. Protection for slope /sides of excavation.

Page 75: Module 4 pre construction

1. through the work site; or 2. around the work site; or 3. redirected past the work site by detour,

which may be via an existing road or side track.

4. should meet the standard requirements as stipulated under Arahan Teknik Jalan JKR or relevant local authorities

Depending on the circumstances, movement of traffic may be achieved in one of three ways:

Page 76: Module 4 pre construction
Page 77: Module 4 pre construction

Unless required by the law, PPE should be opted as the last line of defence after due considerations have been given to other alternative controls – elimination, substitution, isolate and administrative control.

Page 78: Module 4 pre construction

a) the need for provision of personal protective equipment;

b) training in the use of personal protective equipment;

c) standards which apply to personal protective equipment;

d) signs to inform persons about personal protective equipment;

e) the system of control over the supply allocation, maintenance and repair of personal protective equipment, and documentation.

Every employer must be aware of:

Page 79: Module 4 pre construction

1. Every employer should assess the need for personal protective equipment on the basis of risk.

2. Once risk has been assessed, personal protective equipment can be selected according to availability, appropriateness and suitability for the wearer.

Page 80: Module 4 pre construction

3. When selecting personal protective equipment for a particular work process or series of tasks, consider the following general principles: a) Be familiar with the risks of the work

process - involve evaluating the nature of the risk, circumstances and restrictions of the tasks to be performed.

b) Be aware of the acceptable level of risk to which the worker may be exposed and hence the performance requirement of the chosen equipment.

c) Compare performance requirements with the capability of different types of personal protective equipment.

Page 81: Module 4 pre construction

d) Make sure that the item chosen is appropriate to the risk.

e) Where several types of personal protective equipment are required to control multiple risks presented by the one work process, make sure that the items are compatible.

f) Make sure that the item will fit properly, as ‘inadequate fit’ can limit an item’s protective capability.

Page 82: Module 4 pre construction

g) Consider workers’ medical conditions, which can influence whether they can use certain items of equipment.

h) Consider the comfort of the item when choosing equipment.

i) Make sure that the item is worn correctly.

j) Consult with those workers and others who must wear the equipment when choosing the items.

k) Give preference to items of personal protective equipment, which comply with the relevant standards

Page 83: Module 4 pre construction

1. Store personal protective equipment in a clean and fully operational condition.

2. Storage arrangements should ensure that the equipment is safe from interference and damage, and easily accessible when needed.

3. Items of personal protective equipment should also be checked regularly, as specified by the manufacturer or supplier.

4. Repair or discard damaged or defective personal protective equipment.

5. Institute a program to ensure that personal protective equipment is being properly maintained

Page 84: Module 4 pre construction

a) maintenance duties and responsibilities.b) designation of personnel;c) storage procedures;d) cleaning procedures.e) checking procedures.f) information about the duration of

protection from gloves, respiratory canisters, etc; and

g) criteria for replacement.

6. As part of the maintenance program, determine and record:

Page 85: Module 4 pre construction
Page 86: Module 4 pre construction

1. With the multi background of construction workers, safety signs play vital role in disseminating information and instruction to the workers and others.

2. The purpose of hazard and safe signs is to draw attention to objects and situation which may affect or could affect safety or health.

3. Unfortunately the safety signs being used on most construction sites are of various types and standards.

Page 87: Module 4 pre construction

1. Safey Colour - A colour to which a specific safety or health meaning or purpose is assigned.

2. Contrasting Colour - A colour that contrasts with the safety colour in order to make the latter more conspicuous.

3. Symbols - A pictorial representation used on a safety or health sign

Page 88: Module 4 pre construction
Page 89: Module 4 pre construction

1. If identification is required of places where there is risk of collision, falling, stumbling, falling objects or where there are steps, holes in floor or similar hazards.

2. Combination of fluorescent orange-red* or safety colour yellow in either black case.

Page 90: Module 4 pre construction
Page 91: Module 4 pre construction
Page 92: Module 4 pre construction
Page 93: Module 4 pre construction
Page 94: Module 4 pre construction
Page 95: Module 4 pre construction

1. Accurately forecasting the cost of future projects is vital to the survival of any business.

2. Cost estimators develop the cost information that business owners or managers need to make a bid for a contract or to determine budget for the work to be executed efficiently.

3. They also determine which endeavors are making a profit.

4. Construction Safety & Health Officer could assist the cost estimator in identifying safety and health requirements for a particular project.

Page 96: Module 4 pre construction

a) Will the work involve any special or unusual hazards (i.e. asbestos, lead, isocyanates, excessive noise, process chemical, etc.).

b) Will any Statutory provisions need to be complied with.

c) Is there any codes of practice, guidelines or standards that need to be referred to?

1. Special Hazards – Applicable Acts, Codes of Practice, Standards and Guidelines

Page 97: Module 4 pre construction

a) Is relevant government agencies (i.e. DOSH, CIDB, DOE, BOMBA, etc.) to be notified prior to commencement of work?

b) Will any Statutory provisions need to be complied Are there any legal requirements for appointment of designated persons for the work activities (i.e. scaffold erector, authorized gas tester, etc.) to be carried out?

c) If any of the above is applicable, has the necessary notification and arrangements been made?

2. Statutory Notification & Other Requirements

Page 98: Module 4 pre construction

a) Are all personnel to be employed have attended the mandatory Safety Induction for Construction Workers ?

b) Is specific site safety induction required?c) How long is the site safety induction to be?d) Where and when the site safety induction will

take place?e) Is there any other training required?f) What categories of employees will be

trained?g) What, where and where the training is to be

conducted?h) Who will structure and conduct the training?i) What follow-up training will be carried out

during the project?

3. Induction & Other Training Requirements

Page 99: Module 4 pre construction

a)Does the size and nature of the project justify the appointment of site safety supervisor to assist the full-time Safety & Health Officer?

b)Is there any other surveillance required?

4. Control and Monitoring

Page 100: Module 4 pre construction

a) Is there ready vehicle access to the site?b) Is this access wide enough?c) Is there a need for special access road for delivery

vehicles?d) Is there a need for appointment of designated

traffic controller at the site entrance?e) What types of warning and directional signs are

needed at the site entrance?f) Is a dust nuisance occasioned by vehicle movement

on site in dry weather likely to arise?g) If so, is provision being made for a water-spray

vehicle, etc.?h) Is there any requirement by the local authority for

the provision of washing ramp/bay at the site entrance for vehicle leaving the site?

5. Site Access

Page 101: Module 4 pre construction

a) What will be the scaffolding requirements throughout the work?

b) Who will provide the scaffolds?c) Is it possible to make one company responsible

for all scaffolding on site, including erection, maintenance and inspection?

d) Is there a need for appointment of designated traffic controller at the site Will any special access equipment be needed during the work (i.e. cherry-picker, mobile tower scaffold, power elevated mast platform, etc.)?

e) Who will provide ladder and who will be responsible for checking the safe condition and use of those ladders?

6. Safe Means of Access/Work Place

Page 102: Module 4 pre construction

a)What part of the site will require artificial lighting?

b)What sort of lighting will be used and at what stage will it be used?

c) Who will be responsible for installing external and internal artificial lighting?

d)Are there any other lighting aspects to be considered?

7. Temporary Lighting

Page 103: Module 4 pre construction

a) During the work, will there be any operations involving repetitive manual handling of heavy objects?

b) What are these operations?c) What provision is being made for

mechanical lifting aids?d) Are there any other lighting aspects to

be Is special training of manual handling to be conducted?

8. Manual Lifting/Handling

Page 104: Module 4 pre construction

a) Will the work involve mechanical lifting and/or use of mobile cranes?

b) Will tower cranes be involved?c) If so, have the supplier been identified?d) Will it possible to establish and

implement a system whereby mobile cranes are not allowed to enter the site unless the operator and signalman are competent and the machine is possessing valid PMA?

8. Mechanical Lifting/Handling

Page 105: Module 4 pre construction

a)Are there any known buried services on site (electric cables, gas/water mains, sewers, etc.)?

b)Has the survey been carried out to identify those services?

c) Are there any requirements for the establishment and implementation of Permit-to-Excavate system ?

9. Buried Services

Page 106: Module 4 pre construction

a) Are there any overhead services on the site?

b) If so, what is their nature (voltage carried by cables, etc.)?

c) At what height above ground are these overhead services?

d) Will these overhead services intrude upon crane operation?

e) If so, what is to be done to minimize any danger?

f) Will construction/vehicle operations have to take place under these overhead services?

g) Will provision of height restriction (goal post barrier) necessary?

9. Overhead Services

Page 107: Module 4 pre construction

a) Is a competent electrician is required?b) What type portable electrical tools will

be used on site?c) Who will be responsible for temporary

electrical installation?d) Who will be responsible for testing and

commissioning permanent electrical installation?

e) Will the use of electrical ‘Permit-to-Work’ and ‘Lock-Out Tag-Out’ systems be necessary?

10.Electrical Safety

Page 108: Module 4 pre construction

a) Will any significant or abnormal fire risks be associated with the work?

b) What are these risks?c) Should specific site personnel be trained in

fire-fighting techniques? If so, when and how?d) Will there be a need for organized Fire

Fighting/Rescue Team?e) What type of fire fighting equipment is

needed?f) Will there be any need for LPG to be used on

site?g) If, so, what are the storage arrangements?h) Is the Fire & Rescue Department to be

notified for highly flammable material stored on site?

11.Fire Protection

Page 109: Module 4 pre construction

a) Will toxic substances being used on site?b) If so, what provisions are to be made to mitigate

the potential hazards?c) Is plant/machinery capable of producing sound

levels more than 90dBA during the work?d) If, so what are the provisions to be made to avoid

risk of site personnel of noise induced hearing loss?

e) Is there any activities might pose employees to hazardous substances?

f) If so, are provisions for authorized gas tester and suitable respiratory protective equipment required?

g) Will workers expose to biological hazards?h) If so, what provisions are to be made to mitigate

the potential hazards?

12.Occupational Health Risks

Page 110: Module 4 pre construction

a)What provisions are to be made for toilets, washing and sanitary facilities?

b) Is site canteen required and who will provide it?

c) How and by whom site accommodation be kept clean?

d)How and by whom waste to be regularly removed from site?

13.Welfare Amenity Provisions

Page 111: Module 4 pre construction

Construction Safety & Health Officer (CSHO) Module 1

111