mohegan sun palmer traffic assessment
TRANSCRIPT
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
1/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 1
`MEMORANDUM
TO: Mr. John Thomas
Beals and Thomas, Inc.
Reservoir Corporate Center144 Turnpike Road (Route 9)
Southborough, MA 01772-2104
FROM: Scott W. Thornton, P.E
Vanasse & Associates, Inc.
10 New England Business Center DriveSuite 314
Andover, MA 01810(978) 474-8800
DATE: June 7, 2013 RE: 6438
SUBJECT: Traffic Impact Assessment Mohegan Sun at MassachusettsPalmer, Massachusetts
INTRODUCTION
Vanasse & Associates, Inc. (VAI) has prepared this technical memorandum to determine traffic impacts
associated with the development of the Proposed Mohegan Sun at Massachusetts casino facility in
Palmer, Massachusetts. This memorandum is intended as a technical document containing reviews in the
subjects of Study Area; Traffic Volumes; Future Conditions with and without the Project; Trip
Generation; Trip Distribution; resulting Level-of-Service (LOS) analysis for intersections; and the
proposed roadway improvements intended to mitigate the Projects impact at critical locations.
PROJECT DESCRIPTION
The Mohegan Sun at Massachusetts facility is proposed to be a destination type resort casino proposed forthe western part of Massachusetts. The development is proposed to contain approximately 3,450 gaming
positions, a 300-room hotel, attached meeting space and restaurants within a casino facility. In addition, a
1,800-seat Cineplex, an indoor/outdoor water park with accompanying 300-room hotel, and
approximately 250,000 square feet (sf) of general retail space are also part of the proposal. The Project
will be located on the east side of Route 32 (Thorndike Street) near the intersection of the Massachusetts
Turnpike Exit 8 interchange Toll Road with Route 32. The development is proposed to be completed in a
single phase.
Two potential alternatives have been identified to provide access to the Project: an At-Grade Alternative
and a Grade-Separated Flyover. The At-Grade Alternative would involve the construction of a
Site Access Road that would be built opposite the existing Exit 8 I-90 ramp roadway at the signalized
intersection of Route 32. The ramp roadway would be widened to provide five lanes from the
Massachusetts Turnpike and Route 32 would be widened to provide four lanes southbound and five lanes
northbound. The Grade-Separated Flyover alternative requires a bridge structure from the existing Exit 8
I-90 ramp roadway over Route 32 which transitions into a loop ramp/interchange design that intersects
Route 32 at a signalized intersection approximately 500 feet north of the existing Exit 8 I-90 ramp
roadway intersection with Route 32. Access to the Project would be provided via a Site Access Road that
would be built opposite Shearer Street at its intersection with Route 32. In addition, there are other
improvements identified at local intersections within the Town of Palmer that are proposed to remedy
existing shortfalls in capacity or improve safety over present conditions.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
2/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 2
STUDY AREA
The study area for this traffic analysis was selected to include the critical locations expected to receive the
majority of the traffic flow from the project. These include intersections along Route 32, Route 20, and
Route 181 as these form major gateway corridors into and out of the area. A full inventory of these
locations including traffic control, geometric conditions, and traffic volumes was conducted to developbaseline conditions for the traffic analysis. The following identifies the traffic volume count procedures
followed for the Project.
Route 32 Traffic Volumes
Traffic counts were conducted over a two week period on Route 32 in early May 2012. Traffic volumes
were measured through use of pneumatic Automatic Traffic Recorder (ATR) count devices used tomeasure hourly and daily traffic volumes. Counts collected volumes over the period Tuesday May 8
through Monday May 21, 2012. Follow-up counts were conducted in April 2013 to determine growth
over the previous year, with a weighted average rate of increase between the four observed time periods
(Friday, Friday evening peak hour, Saturday, Saturday evening peak hour) of 0.73 percent. Therefore, the
2012 Existing volumes were adjusted upwards by 1.0 percent to reflect 2013 conditions.
Intersection Volume Counts
Intersection Turning Movement and vehicle Classification Counts (TMC) were conducted at
15 intersections in the town of Palmer on Friday May 18 and Saturday May 19, 2012. These locations are
identified below:
1. Route 181 at Thorndike Street2. Route 181/Main Street at Mt. Dumplin Road3. Route 181/Main Street at Shearer Street4. Route 181/Main Street at Route 20/Wilbraham Street5. Route 20/Main Street at Route 32/Thorndike Street6. Route 20/Route 32/Park Street at Breckenridge Street7. Route 20 Route 32/Park Street at Stone Street8. Route 32/Main Street/Stone Street at South Main Street9. Route 20/Route 32/Park Street at Thorndike Street10.Route 32/Thorndike Street at Lawrence Street11.Route 32/Thorndike Street at Turnpike Ramps12.Route 32/Thorndike Street at Shearer Street/Site Drive13.Route 32/Thorndike Street at Big Y Drive14.Route 32/Thorndike Street at Mt. Dumplin Road15.Route 32/Thorndike Street at High Street
The intersections are graphically depicted on Figure 1.
For this analysis, the same intersections were also counted during the Saturday midday time period on
Saturday April 6, 2013, due to the inclusion of a significant retail component to the project.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
3/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 3
Insert figure 1
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
4/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 4
Traffic counts were conducted during the time periods expected to receive the majority of activity from
the proposed casino. These time periods were previously identified by both Mohegan Sun and by VAIs
review of Mohegan Sun traffic count data as Friday Afternoon-evening and Saturday Afternoon-evening
time periods. The Friday Afternoon -evening time period also overlaps the exiting employee peak with
the arriving casino patron peak. The Friday time periods were selected to be 3:00 to 6:00 PM and the
Saturday time period was selected to be 4:00 to 7:00 PM. These time periods were collected to observe
traffic conditions when public schools were in session and vacations were at a minimal level. In general,traffic volumes on Friday were observed to peak between 4:30 PM and 5:30 PM while the volumes on
Saturday were observed to peak between 4:00 PM and 5:00 PM. The Saturday midday time periodgenerally occurred between 11:30 AM and 12:30 PM.
Figure 2 provides the traffic volumes for the 2013 Friday Evening Peak Hour conditions, while Figure 3
provides the traffic volume for the 2013 Saturday Midday Peak Hour conditions. Figure 4 provides the
traffic volume for the 2013 Saturday Evening Peak Hour conditions. A brief review of the intersectionconditions is provided in Table 1.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
5/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 5
Insert figure 2
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
6/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 6
Insert Figure 3
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
7/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 7
Insert Figure 4
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
8/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 8
Table 1GENERAL INTERSECTION CHARACTERISTICS
LocationNo. Location Control Conditions
1 Route 181/ at Thorndike Street Unsignalized Good, no clear issu
2 Route 181/Sykes Street at Mt. Dumplin Road Unsignalized Fair, potential sight distance restrictio
3 Route 181/Main Street at Shearer Street Unsignalized Good, close proximity to Loc. 4 crea
conflict for exiting vehic
4 Route 181/North Main Street at Route 20/Wilbraham
Street
Signalized Good, near-roundabout geomet
potential queuing impacts on North MStreet northbou
5 Route 20/Main Street at Route 32/Thorndike Street Signalized Good, some pedestrian activ
6 Route 20/Route 32/Park Street at Breckenridge Street Unsignalized Fair, pavement conditions and number
curb cuts and driveways closeintersection, truck volu
7 Route 20 Route 32/Park Street at Stone Street Unsignalized Good to Fair, flashing beacon, truck vol
8 Route 32/Main Street/Stone Street at South Main Street Unsignalized Good to Fair, awkward geometry, tru
volu
9 Route 20/Route 32/Park Street at Thorndike Street Signalized Good, some pedestrian activ
10 Route 32/Thorndike Street at Lawrence Street Unsignalized Good, close proximity to Loc. 10 c
create conflict for exiting vehic
11 Route 32/Thorndike Street at Turnpike Ramps Signalized Good, heavy volume from ramps, exist
need for dual left-turn lan12 Route 32/Thorndike Street at Shearer Street/Site Drive Unsignalized Good, potential sight distance issu
13 Route 32/Thorndike Street at Big Y Drive Signalized Good, short lanes for queue stora
14 Route 32/Thorndike Street at Mt. Dumplin Road Unsignalized Good, no clear issu
15 Route 32/Thorndike Street at High Street Signalized Good, no clear issu
aVolume Classification: Low = Intersection Volume < 1,500 vehicles per hour (vph), Medium = < 2,200 vph, High = > 2,200 vph.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
9/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 9
bRelation to Site Traffic in context of study purposes for local (
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
10/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 10
Summary of Intersection Conditions
Table 1 indicates that in general, most intersections are in Fair to Good condition, with several locations
presenting no clear issues requiring improvements. A volume classification was developed to group the
locations in terms of their existing traffic demands. As shown, higher volume locations generally require
traffic signal control. Most of the locally originating traffic (expected to originate from locations within
15 miles of the Project) is expected to travel on main routes such as Routes 20, 32, and 181; intersectionsalong these routes are the main intersections providing access to the project. Some of the locations
further from the site are classified as Regional as these are expected to be routes that traffic outside ofPalmer will use. Other locations have been classified as Local locations that could be seen as potential
cut-through routes to avoid downtown congestion or delay at specific intersections.
Exit 8 Toll Plaza
Entering and exiting movements from the Massachusetts Turnpike at Exit 8 are controlled by a 5-lane toll
plaza with typical configurations presenting two lanes entering and exiting, with a center reversible lane.
There are dedicated EZ Pass automated toll collection lanes on the outer lanes of the plaza, with manned
lanes on the inner exiting lanes and an automatic ticket dispenser or spitter machine on the innerentering lane. A graphic depicting the toll plaza and proximity to Route 32 is shown as Figure 5.
Counts conducted in September 2012 indicate a high processing rate for each lane at the plaza. The
following volumes were observed:
Movement Lane Function Actual Volume
Entrance Lane 5 E-ZPass 444 vph or 7.4 vpm
Entrance Lane 4 Attendant/Spitter 293 vph or 4.88 vpm
Exit Lane 3 Attendant 203 vph or 3.38 vpm
Exit Lane 2 Attendant 253 vph or 4.21 vpm
Exit Lane 1 E-ZPass 665 vph or 11.08 vpm
The total Interchange was observed to process the following volumes:
On Booths (2) 737 vph
Off Booth (3) 1,121 vph
Total 1,858 vph
Observed values for lane processing capacity are assumed to date to be:
Movement Lane Function Actual Volume
Entrance Ramp Lane 5 E-ZPass 720 vph or 12 vpm MaxEntrance Ramp Lane 4 Attendant/Spitter 540 vph or 9 vpm Max
Exit Ramp Lane 3 Attendant 300 vph or 5.0 vpm
Exit Ramp Lane 2 Attendant 300 vph or 5.0 vpm
Exit Ramp Lane 1 E-ZPass 900 vph or 15 vpm Max
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
11/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 11
Insert figure 5
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
12/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 12
Consequently, for the Toll Booth alone, the excess capacities calculated to date are:
Max Booth
Capacity* Usage Reserve Total
Entrance 5 E-ZPass
Entrance 4 Attendant/
Spitter
Exit 3 Ramp Attendant
Exit 2 Ramp- Attendant
Exit 1 Ramp E-ZPass
720 vph
540 vph
300 vph
300 vph
900 vph
444 vph
293 vph
203 vph
253 vph
665 vph
276 vph
247 vph
97 vph
97 vph
235 vph
On Reserve
523 vph
Off Reserve
429 vph
with existing configuration
* Attendant processing time was measured and then adjusted downward to produce a conservative estimate.
As shown in Figure 5, the toll plaza is located approximately 375 feet from the stop bar at the Route 32intersection. This short road segment becomes a limiting factor, as vehicle queues occasionally back upfrom the Route 32 intersection to the plaza. Any increases in volume through the toll plaza would ideally
be accompanied by increases in capacity at the approach to the Route 32 intersection and/or increases in
capacity at the toll plaza. This is discussed in a later section.
MOTOR VEHICLE CRASH DATA
Motor vehicle crash information for the study area intersections was provided by the MassDOT Highway
Division Safety Management/Traffic Operations Unit for the most recent three-year period available
(2008 through 2010) in order to examine motor vehicle crash trends occurring within the study area. The
data is summarized by intersection, type, severity, and day of occurrence, and presented in Table 2.
The study area intersections were found to have averaged less than four (4) reported motor vehicle
crashes per year over the three-year review period, with the exception of the Route 181/Shearer Street
intersection, the Route 20/Route 32 intersection, and the Route 32/High Street intersection, which each
averaged 5 to 7 crashes per year. Four of the fifteen study area intersections experienced a crash rate
higher than the MassDOT average for a signalized or unsignalized intersection, as appropriate, for
the MassDOT Highway Division District in which the project is located (District 2): Route 181/
Thorndike Street, Route 181/Shearer Street, Route 20/Route 32/Breckenridge Street, and Route 32/
High Street. No fatal motor vehicle crashes were reported at the study area intersections over the three-
year review period.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
13/79
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
14/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 14
2023 NO BUILD TRAFFIC VOLUMES
Traffic volumes in the study area were projected to the year 2023, which reflects a ten-year planning
horizon. While State traffic study guidelines for Traffic Impact Assessments typically require a five-year
planning time frame, recent comments from MassDOT suggest the use of a ten-year horizon is more
appropriate for the casino projects currently undergoing review in Massachusetts. Independent of the
project, traffic volumes on the roadway network in the year 2023 under No-Build conditions include allexisting traffic and new traffic resulting from background traffic growth. Anticipated project-generated
traffic volumes superimposed upon this 2023 No-Build traffic network reflect the 2023 Build conditionswith the project.
Future Traffic Growth
Future traffic growth is a function of the expected land development in the immediate area and the
surrounding region. Several methods can be used to estimate this growth. A procedure frequently
employed estimates an annual percentage increase in traffic growth and applies that percentage to all
traffic volumes under study. The drawback to such a procedure is that some turning volumes may
actually grow at either a higher or a lower rate at particular intersections.
An alternative procedure identifies the location and type of planned development, estimates the traffic to
be generated, and assigns it to the area roadway network. This procedure produces a more realistic
estimate of growth for local traffic. However, the drawback of this procedure is that the potential growth
in population and development external to the study area would not be accounted for in the traffic
projections.
To provide a conservative analysis framework, both procedures were used, the salient components of
which are described below.
Specific Development by Others
The Planning Department of the Town of Palmer was contacted in order to determine if there were any
projects planned within the study area that would have an impact on future traffic volumes at the study
intersections. Based on these discussions, the following projects were identified:
Residential Development - This proposed project consists of the construction of a 36-unitresidential condominium development across from Cemetery Hill further south of the site on
Route 32 which is currently in construction. Traffic volumes expected to be generated by this
project were generated using trip-generation statistics published by Institute of Transportation
Engineers (ITE)1 for a similar use and were assigned onto the study area roadway network based
on the observed traffic patterns.
No other developments were identified that are expected to result in an increase in traffic within the studyarea beyond the background traffic growth rate. The Town of Palmer had prepared a Chapter 43D Traffic
Impact Study for five Priority Development Sites (PDS) in the town where development is encouraged.
Discussions with the town indicate that of the five sites, four have had no significant development activity
and the fifth site, known as Thorndike Realty, is the site of the proposed casino.
1Trip Generation, Ninth Edition; Institute of Transportation Engineers; Washington, DC; 2012.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
15/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 15
There has been discussion of a potential development on property controlled by Northeast Realty in the
vicinity of the project site. This development would be located in the triangle of property formed by the
Exit 8 I-90 ramp roadway, Route 32, and Shearer Street. Nothing formal has been proposed and no plans
or application has been submitted to the Planning Board. If in the future, a known program becomes
public and files with the town prior to the Project local application submittal, that program will be
included in traffic projections and a review of mitigation for the area.
General Background Traffic Growth
Traffic-volume data compiled by MassDOT from permanent count stations and historic traffic counts in
the area were reviewed in order to determine general background traffic growth trends. Data collected
from locations in and surrounding the town of Palmer indicate that traffic volumes in the area have
decreased or stayed consistent since 2000, based on counts conducted by MassDOT. A summary of thesedata is provided in Table 3 below.
Table 3
TRAFFIC VOLUME COMPARISON
Town
Number of
Count Locationsa
Average Annual
Growth Rate, Percentb
Palmer 3 -2.5
Ludlow 1 1.1
Monson 3 0.8
Ware 4 1.4
Belchertown 2 5.2
Wilbraham 3 0.3
Warren 1 0.0
Average Change, Percent 0.9aNumber of count locations in each town.bBased on counts compiled by MassDOT over the period 2000-2009.
In addition, a review of daily data for Friday and Saturday as well as peak hour counts for the relevant
Friday evening and Saturday evening periods indicated an overall growth rate of 0.7 percent between May
2012 and April 2013 on Route 32 adjacent to the site.
Based on a review of this data, and given the 10-year horizon period, it was determined that an annual
growth rate of 0.9 percent per year was used in order to account for future traffic growth and presently
unforeseen development within the study area.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
16/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 16
Roadway Improvement Projects
MassDOT and the Town of Palmer were contacted in order to determine if there were any planned
roadway improvement projects expected to be completed within the study area. There are no proposed
changes or roadway improvements expected that will change traffic flow conditions in the study area over
the horizon year time frame.
No-Build Traffic Volumes
The 2023 No-Build peak-hour traffic-volume networks were developed by applying the 0.9 percent per
year compounded annual background traffic growth rate to the 2013 Existing peak-hour traffic volumes
and then superimposing the peak-hour traffic volumes expected to be generated by the identified specific
development project by others. The resulting 2023 No-Build Friday Evening, Saturday Midday, andSaturday Evening peak-hour traffic volume networks are shown on Figures 6 through 8.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
17/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 17
insert figure 6
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
18/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 18
insert figure 7
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
19/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 19
insert figure 8
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
20/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 20
PROJECT TRIP GENERATION
Casino Facility
Data was provided from Mohegan Sun related to the projected development program for Mohegan Sun at
Massachusetts, as well as demographics of patrons in terms of originating location, temporal distribution
on hourly, daily, and monthly time periods, mode splits, average vehicle occupancies, along with similardata for employees. The current Mohegan Sun at Massachusetts program was summarized as follows:
Table 4MOHEGAN SUN AT MASSACHUSETTS DEVELOPMENT PROGRAM
Component Metric
Casino Facility
Patron Visits 3,800,000 annually
Gaming Positions 3,450Hotel, rooms 300
Meeting Space, sf 25,000Other Components
Water Park, sf (includes 300 room hotel) 75,000
Cineplex, seats 1,800
Shopping Center, sf 250,000
Driveway Counts
Data was provided in the form of hourly traffic volumes for the roadways leading into Mohegan Sun at
Uncasville, Connecticut. The volumes were categorized by hour of day, day of week, and were providedon a monthly basis for the period between January and July 2009. Peak time periods were observed to
occur on Friday and Saturday between 4:00 PM and 7:00 PM, and on Sunday between 3:00 PM and
4:00 PM. These times roughly correspond to peak entering and peak exiting time periods. Patron vehicle
occupancy was estimated by Mohegan Sun Transportation at between 1.8 and 2.2 persons per vehicle.
Bus patronage was also provided which represents approximately 12 percent of the total arrival mode at
the Uncasville site.
Trip Generation Model
To predict the trip generation of Mohegan Sun at Massachusetts, a trip generation model was developed.
Data was compiled from observed volume counts and visitation at the Mohegan Sun site in Uncasville,
Connecticut to determine trips for the Mohegan Sun at Massachusetts site. Gaming patrons, mode splits,vehicle occupancy rates, employee Full Time Equivalents (FTEs), observed rates of hourly and daily
traffic flow were combined to result in the daily and peak hour trip projections for the Project.
Correlation with any major events or arena shows was not specifically accounted for in the model, but
was neither discounted, so that any increases due specifically to shows are included in the projections.
The volumes and hourly adjustment factors were combined to develop an empirical model that was first
used to predict the trip generation of the Mohegan Sun facility for peak conditions. Based on a visitation
of approximately 13,000,000 visitors and 7,800 FTEs, an average of Saturday daily trips were predicted
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
21/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 21
within 2.3 percent of observed values. The model volumes were then adjusted based on the number of
gaming positions at the Uncasville site. Peak hourly totals were then adjusted and calibrated to represent
portions of daily trip totals between one and four percent of daily trips. The resulting Peak Hour trip
totals average between one and two percent higher than observed values.
Hotel trips are implicit in the counts provided by Mohegan Sun for the casino trip generation, as the
Connecticut site contains a hotel with 1,175 rooms. Records indicate the hotel historically operates at a94 percent occupancy rate.
In addition to the above factors, the potential existence of competing casinos was also accounted for in
this analysis. The Legislature of Massachusetts has indicated casinos could be constructed in the western
region, the eastern region, and the southeastern region of the Commonwealth. Since a portion of the
effective population of the areas in the east and southeast would be closer to casinos in these areas than
the Palmer site, assumptions were made to eliminate approximately 50 percent of the population base. Inaddition, the population in Plymouth County was neglected entirely, as existing casinos in Rhode Island
and the sites in Connecticut are closer to these residents than Palmer. These changes resulted in a
correction factor of approximately 20 percent in the predicted trip generation model for the project.
Other Components
In addition to the Casino Facility anticipated for the Interim Build phase, an Indoor/Outdoor Water Park,
Cineplex, and general retail developments are all proposed for the Project. For these components, the ITE
publication Trip Generation was used to predict trips for the various time periods under consideration.
ITE Land Use Codes (LUCs) 414 (Water Slide Park), 445 (Multiplex Movie Theater), and 820 (Shopping
Center) were used with the currently projected development sizes for each component.
Trip Type Adjustments
The casino facility is currently anticipated to be a destination-type facility. However, the other
components of the Project have the potential for the drawing of vehicle traffic from the existing adjacent
traffic stream as well as from the casino itself and vice versa, representing internal trip-making or internaltrip capture. In this regard, not all of the trips expected with the Project represent new trips on the area
road network.
Internal Capture. The existing Mohegan Sun site in Uncasville provides nearly 900,000 sf of totaldevelopment, including hotel rooms, restaurants, and retail shops. The retail component of the site totals
approximately 80,000 sf. It is reasonable to assume that few of the trips to the retail components are
single purpose and only to the retail components. However, the Uncasville site does not contain the size
of non-casino uses or the variation of non-casino uses proposed for the Palmer site, and therefore is not
strictly comparable. A review of available literature on multi-use developments2 indicates that in general,
retail to retail internal capture rates on developments can range between 20 and 31 percent depending on
time periods. There are several points to be considered in calculating internal capture rates:
Competing Markets In general, internal capture rates between on-site uses increase withincreasing distance to similar developments. The closest water parks to Palmer are approximately
25 miles from the site in Agawam, south of Springfield. The same case is true for cineplexes and
large retail facilities, as the closest movie theaters and large shopping centers are in Springfield.
The closest casino development is Mohegan Sun in Uncasville. There is no one site that contains
2Trip Generation Manual, Volume 1, 9th Edition; Institute of Transportation Engineers; Washington, D.C.; 2012.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
22/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 22
all these uses within walking distance. Therefore a high internal capture among the projected
uses is expected with the Project.
Proximity and Density of On-Site Land Uses As the density and proximity to land uses increase,the internal capture rates increase. The casino building contains a hotel, but the retail and
Cineplex are all attached, leading to easy connections between uses. The water park is
approximately 1,200 feet from the main casino building, but a sidewalk is provided to allow
patrons to move between the uses easily. With three of the four uses interconnected and thefourth use accessible via a five-minute walk, a high internal capture rate is expected due to this
factor.
Based on these factors, the overall internal capture rate is estimated at 25 percent. This equates to the
overall capture between the retail (shopping center) trips, and the remainder of the component trips,
specifically the casino, water park, and Cineplex trips. This average is across the four peak hours that
were reviewed (Friday Evening, Saturday Midday, Saturday Evening, Sunday Evening: 25 percent
average for all) and the three daily periods (Friday, Saturday, Sunday: 24 percent average for all).
Pass-By Trips. State guidelines for the preparation of Traffic Assessments allow a 25 percent pass-byrate for retail developments. Due to the relative scarcity of retail development in the area and the
projected volume on Route 32 exclusive of the Project, the 25 percent rate was determined to beapplicable for this Project. Consistent with standard industry practice, the pass-by trips were calculatedusing the shopping center trips less half of the internal trips (assuming half of the internal trips were due
to the shopping center).
A summary of the expected trip generation for the critical time periods is shown in Table 5.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
23/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 23
Table 5TRIP GENERATION SUMMARY
Time Period/
Directional Distribution Casino Totala Water Parkb Cineplexc Shopping Centerd TOTALe
Friday Evening Peak Hour
Enter 534 76 308 531 1,449
Exit 423 68 214 576 1,280 Total 956 144 522 1,107 2,729
Saturday Midday Peak Hour
Enter 417 151 117 825 1,510
Exit 302 118 45 761 1,226
Total 719 269 162 1,586 2,736
Saturday Evening Peak Hour
Enter 367 104 208 406 1,216
Exit 426 122 208 374 1,529
Total 793 226 416 780 2,745
Sunday Evening Peak Hour
Enter 367 104 208 406 1,084
Exit 426 122 208 374 1,131
Total 793 226 416 780 2,215
Weekday Daily 13,566 1,556 2,314 12,320 29,756
Saturday Daily 15,446 2,004 2,452 16,458 36,360
Sunday Daily 11,460 1,560 1,886 6,310 21,216
a Based on 3,450 gaming positions and 300 room hotel.b Based on ITE LUC 414 Water Slide Park and 75,000 sf.
c Based on ITE LUC 445 Multiplex Movie Theater and 1,800 seats.d Based on ITE LUC 820 Shopping Center and 250,000 sf. Friday evening data assumed as Weekday evening ITE data; Saturday evening data assumed as 71% of Saturday M
e Sum of unadjusted trip generation totals.f Computed as 25 percent of lower trip generation totals of Shopping Center and non-Shopping Center uses.g Computed as 25 percent of Shopping Center trips reduced by half of Internal Trips.
h Total trips (-) internal trips. Total trips at Site Access Road.i Total External trips (-) pass-by trips. Total trips new to site road network beyond Site Access Road.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
24/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 24
TRIP DISTRIBUTION
Several components of trip distribution were developed for the Mohegan Sun at Massachusetts site. The
first component was related to the proportion of existing Mohegan Sun at Uncasville patrons likely to
divert to the Palmer location due to its closer location and reduced travel time. The second component
was a more conventional type of latent demand model, using populations from the 2000 US Census and
assigning approximate weights to populations based on location and travel time. These were combinedto provide an equalized distribution of trip origins between existing patron and existing population data.
In addition, the population based distribution was used exclusively in the assignment for the non-casinotrips.
CASINO TRIP DISTRIBUTION
Mohegan Sun Patron Data
Patron Data was provided by Mohegan Sun which provided a measure of the geographic distribution of
the existing patron base traveling to the Uncasville site. Travel times were compared between the patron
home towns and the Mohegan Sun at Massachusetts site and the Mohegan Sun at Uncasville site in orderto determine the extent of existing trips likely to be captured by the Mohegan Sun at Massachusetts site.
Trips from towns and cities in Connecticut, Massachusetts, New York, New Hampshire, Maine, and
Vermont were routed using generalized travel times and regional roadways (I-90, I-91, I-84, etc.).
This data was then adjusted to account for the competing casino location in eastern Massachusetts. It was
assumed that patrons in Essex, Norfolk, and Middlesex Counties were two times more likely to travel to
an eastern casino in the Greater Boston area than to travel an hour or more to Palmer. Patrons in Suffolk
County were assumed to be three times more likely to travel the short distance to an eastern casino than to
travel to Palmer. The patron trip base from these counties was adjusted accordingly, which generally
resulted in an approximately 15 percent reduction in the patron base. Using these assumptions, the
distribution of the patron data shown in Table 6 was calculated.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
25/79
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
26/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 26
Table 7SORTED LOCAL PATRON TRIP DATA
Town County Patron Trips
Palmer Hampden 369Three Rivers Hampden 107
Monson Hampden 444Brimfield Hampden 80Wilbraham Hampden 478Ludlow Hampden 876Wales Hampden 50
Hampden Hampden 216Springfield Hampden 295Indian Orchard Hampden 212Springfield Hampden 330
Springfield Hampden 201East Longmeadow Hampden 877
Springfield Hampden 531Holland Hampden 90
Springfield Hampden 639Westover AFB Hampden 121
Chicopee Hampden 1497Springfield Hampden 714Springfield Hampden 926Springfield Hampden 143
Springfield Hampden 64Chicopee Hampden 918Ware Hampshire 393Belchertown Hampshire 462
Granby Hampshire 263South Hadley Hampshire 562Stafford Springs Tolland (CT) 955Somers Tolland (CT) 596
Warren Worcester 108
West Warren Worcester 34West Brookfield Worcester 135Fiskdale Worcester 108
Brookfield Worcester 131Sturbridge Worcester 217Gilbertville Worcester 20
East Brookfield Worcester 58New Braintree Worcester 23North Brookfield Worcester 79
TOTAL 14,322
Trips from the local distribution were assigned to the localized routes in the cardinal directions. Based ontravel times, some trips from areas in Springfield and Chicopee were determined to be more likely to use
I-90 to arrive at the Project than local roads, as travel times would be twice as long using secondary
roadways. In general, most travel times for the areas in the local distribution were determined to be less
than 30 minutes to the Project.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
27/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 27
Population Based Trips
Populations for the New England and New York areas were obtained from 2000 US Census data and then
categorized into the counties consistent with the Patron data. The populations were then adjusted using
travel time from the population centroids of the counties or states as applicable to derive weighted
populations. As with the patron data, the population data from the four counties expected to frequent an
eastern casino in varying likelihoods as described previously were also adjusted to account forcompetition.
These adjustments resulted in an original population of slightly over 8,000,000 persons across the target
area reduced to a population just over 93,000 using travel time as a factor. This also indicates that target
areas of Middlesex and Worcester County in Massachusetts and a portion of Hartford County in
Connecticut combined result in nearly half of the weighted population.
As with the Patron data, the population data was also adjusted for the local distribution of areas within
15 miles of the Project. It was determined that due to the limited population of Tolland County within
this area accuracy would not be significantly affected by using the regional distribution for the entire
county.
Aggregation of Trip Distribution
A method of combining the two trip components (Patrons and Populations) was determined using the
existing data and some additional assumptions. This would determine the relative proportion of trips
which would originate within and outside of the 15 mile local zone. The method used quantifies the local
and regional proportions using the Patron Data and Populations totals, adjusted for anticipated visitation
and the travel time factors discussed above. Local visitation is assumed at 10 percent, meaning one of
every 10 persons within the 15 mile zone is likely to travel to the Project, and this is compared against the
travel time factored regional population. Table 8 presents a summary of the data points and the resulting
values.
Table 8CASINO TRIP DISTRIBUTION
Component Local Trips Regional Trips Total
Patrons
Populations
Average
Average (Percent)
14,322
33,521
47,843
20
94,599
93,361
187,960
80
108,921
126,882
235,803
100
As shown in Table 8, the relative proportions of 20 percent for the local basis and 80 percent for the
regional basis were calculated, and applied to the trip generation estimates discussed earlier. As applied
to the Saturday Evening peak time period for instance, the expectation is that of the total 1,686 hourly
vehicle trips, approximately 338 would originate within the 15 mile local zone and the remaining
1,348 trips would originate outside that zone.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
28/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 28
NON-CASINO TRIP DISTRIBUTION
Population Based Trips
The population-based gravity model was used for the distribution for the Cineplex, Water Park, andShopping Center visitors. There was assumed to be some relationship between the casino target area and
the non-casino target area, in that the existence of one or more component may be a draw for visitors thatplanned to visit the casino only. In this regard, the distribution is shaped by the same regional attraction
as the casino, likely larger than would be the case for any one component alone. Relying on solely the
population-based distribution resulted in a trip assignment for the non-casino trips of approximately
74 percent regional trips and 26 percent local trips. This is shown below in Table 9.
Table 9NON-CASINO TRIP DISTRIBUTION
Component Local Trips Regional Trips Total
Populations
Average (Percent)
33,521
26
93,361
74
126,882
100
Pass-by trips were determined to be based on an equal north/south distribution from Route 32, based on
traffic volumes for the respective peak hour time periods of analysis.
The resulting general local and regional trip distributions for the entire Project are shown graphically inFigures 9 and 10.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
29/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 29
insert figure 9
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
30/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 30
insert figure 10
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
31/79
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
32/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 32
Insert figure 11
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
33/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 33
Insert figure 12
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
34/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 34
Insert figure 13
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
35/79
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
36/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 36
Insert figure 15
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
37/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 37
Insert figure 16
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
38/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 38
Site Access Full Build
There are two current alternatives for site access required for the Full Build scenario under review. The
first is an At-Grade alternative which creates the fourth leg of an intersection with the Exit 8 I-90 ramp
roadway and Route 32 intersection. The intersection would be signalized and each approach would be
substantially widened from the current configuration. Volumes for this condition are shown in Figure 17
for the respective 2023 Build Friday Evening, Saturday Midday, and Saturday Evening peak-hourconditions.
The second alternative is a flyover design. The I-90 ramp roadway would overpass Route 32 and connect
north of the existing ramp/Route 32 intersection through a partial cloverleaf/trumpet-type interchange
with ramps intersecting Route 32 at a signalized intersection. Volumes for this condition are shown in
Figure 18 for the respective 2023 Build Friday Evening, Saturday Midday, and Saturday Evening peak-
hour conditions.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
39/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 39
Insert figure 17
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
40/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 40
Insert figure 18
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
41/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 41
TRAFFIC OPERATIONS ANALYSIS
Measuring existing and future traffic volumes quantifies traffic flow within the study area. To assess
quality of flow, roadway capacity analyses were conducted under Existing, No-Build and Build traffic-
volume conditions. Capacity analyses provide an indication of how well the roadway facilities serve the
traffic demands placed upon them.
Methodology
Levels of Service
A primary result of capacity analyses is the assignment of level of service to traffic facilities under
various traffic-flow conditions.3 The concept of level of service is defined as a qualitative measuredescribing operational conditions within a traffic stream and their perception by motorists and/or
passengers. A level-of-service definition provides an index to quality of traffic flow in terms of such
factors as speed, travel time, freedom to maneuver, traffic interruptions, comfort, convenience, and safety.
Six levels of service are defined for each type of facility. They are given letter designations from A to F,with level-of-service (LOS) A representing the best operating conditions and LOS F representing
congested or constrained operating conditions.
Since the level of service of a traffic facility is a function of the traffic flows placed upon it, such a facility
may operate at a wide range of levels of service, depending on the time of day, day of week, or period of
year.
Unsignalized Intersections
The six levels of service for unsignalized intersections may be described as follows:
LOS A represents a condition with little or no control delay to minor street traffic. LOS B represents a condition with short control delays to minor street traffic. LOS Crepresents a condition with average control delays to minor street traffic. LOS D represents a condition with long control delays to minor street traffic. LOS Erepresents operating conditions at or near capacity level, with very long control delays to
minor street traffic.
LOS Frepresents a condition where minor street demand volume exceeds capacity of an approachlane, with extreme control delays resulting.
The levels of service of unsignalized intersections are determined by application of a procedure described
in the 2010Highway Capacity Manual.4 Level of service is measured in terms of average control delay.
Mathematically, control delay is a function of the capacity and degree of saturation of the lane group
3The capacity analysis methodology is based on the concepts and procedures presented in the Highway Capacity Manual
(HCM 2010); Transportation Research Board; Washington, DC; 2010.4Highway Capacity Manual; Transportation Research Board; Washington, DC; 2010.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
42/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 42
and/or approach under study and is a quantification of motorist delay associated with traffic control
devices such as traffic signals and STOP signs. Control delay includes the affects of initial deceleration
delay approaching a STOP sign, stopped delay, queue move-up time, and final acceleration delay from a
stopped condition. Definitions for level of service at unsignalized intersections are also given in the
2000Highway Capacity Manual. Table 10 summarizes the relationship between level of service and
average control delay.
Table 10LEVEL-OF-SERVICE CRITERIA FORUNSIGNALIZED INTERSECTIONSa
Average Control Delay
(Seconds Per Vehicle)
Level of Service
v/c 1.0
Level of Service
v/c >1.0
< 10.0
10.1 to 15.0
15.1 to 25.025.1 to 35.0
35.1 to 50.0
>50.0
A
B
CD
E
F
F
F
FF
F
F
aSource: Highway Capacity Manual; Transportation Research Board;
Washington, DC; 2010; Volume 3, Exhibit 19-2.
Signalized Intersections
The six levels of service for signalized intersections may be described as follows:
LOS A describes operations with very low control delay; most vehicles do not stop at all. LOS B describes operations with relatively low control delay. However, more vehicles stop thanLOS A. LOS Cdescribes operations with higher control delays. Individual cycle failures may begin to
appear. The number of vehicles stopping is significant at this level, although many still pass
through the intersection without stopping.
LOS D describes operations with control delay in the range where the influence of congestionbecomes more noticeable. Many vehicles stop and individual cycle failures are noticeable.
LOS Edescribes operations with high control delay values. Individual cycle failures are frequentoccurrences.
LOS Fdescribes operations with high control delay values that often occur with over-saturation.Poor progression and long cycle lengths may also be major contributing causes to such delay
levels.
Levels of service for signalized intersections are calculated using the operational analysis methodology of
the HCM 2010. This method assesses the effects of signal type, timing, phasing, and progression; vehicle
mix; and geometrics on delay. Level-of-service designations are based on the criterion of control or
signal delay per vehicle. Control or signal delay is a measure of driver discomfort, frustration, and fuel
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
43/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 43
consumption, and includes initial deceleration delay approaching the traffic signal, queue move-up time,
stopped delay and final acceleration delay. Table 11 summarizes the relationship between level of service
and control delay. The tabulated control delay criterion may be applied in assigning level-of-service
designations to individual lane groups, to individual intersection approaches, or to entire intersections.
Table 11LEVEL-OF-SERVICE CRITERIAFOR SIGNALIZED INTERSECTIONSa
Control (Signal)
Delay Per Vehicle (Seconds)
Level of Service
v/c 1.0
Level of Service
v/c >1.0
80.0
A
B
CD
E
F
F
F
FF
F
F
aSource: Highway Capacity Manual; Transportation Research Board; Washington, DC; 2010;
Volume 3, Exhibit 18-6.
Currently there are a number of technical issues surrounding the implementation of the HCM 2010 for
signalized intersections, chiefly that there are unresolved inconsistencies related to signal phasing
between the HCM methodology and actual signal design practice. MassDOT has issued a directive
allowing the use of the Synchro software LOS calculation for signalized intersections as the HCM
methodology will not calculate level-of-service for all signal phasing designs. Therefore, the signalized
analyses and LOS results are based on Synchro LOS calculations and the unsignalized analyses and LOS
results are based on HCM 2010 methodology.
ANALYSIS RESULTS
Level-of-service analyses were conducted for 2013 Existing, 2023 No-Build and 2023 Build conditions
for the intersections within the study area. The results of the intersection capacity analyses are
summarized in Table 12 for the signalized intersections and Table 13 for the unsignalized intersections.
The results are presented by individual movement as well as overall intersection level of service (LOS)
for signalized intersections and by critical movement for unsignalized intersections.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
44/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 44
Table 12
SIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Signalized Intersection/Peak Hour/Movement V/Ca Delayb LOSc
Queued
Ave/95th V/C Delay LOS
Q
Av
4 Route 181/North Main Street at Route
20/Wilbraham Street
Friday Evening:
Wilbraham Street EB LT
Wilbraham Street EB TH/RTNorth Main Street WB LT/TH
North Main Street WB RT
Private Drive NB LT/TH/RT
Route 181 SB LT/TH
Route 181 SB RT
OverallSaturday Midday:
Wilbraham Street EB LT
Wilbraham Street EB TH/RTNorth Main Street WB LT/TH
North Main Street WB RT
Private Drive NB LT/TH/RT
Route 181 SB LT/TH
Route 181 SB RT
OverallSaturday Evening:
Wilbraham Street EB LT
Wilbraham Street EB TH/RT
North Main Street WB LT/TH
North Main Street WB RTPrivate Drive NB LT/TH/RT
Route 181 SB LT/TH
Route 181 SB RT
Overall
0.63
0.610.73
0.52
0.11
0.74
0.27--
0.45
0.450.71
0.41
0.07
0.60
0.21--
0.31
0.44
0.55
0.380.02
0.55
0.23
--
19.0
13.127.3
5.2
16.0
29.0
2.2
16.4
11.2
10.025.5
4.7
17.7
23.2
2.2
14.1
9.0
9.8
20.1
5.10.0
21.1
2.1
11.7
B
BC
A
B
C
A
B
B
AC
A
B
C
A
B
A
A
C
AA
C
A
B
2/54/11
4/11
0/3
0/1
4/11
0/1--
1/3
3/84/11
0/2
0/1
3/7
0/1--
1/3
2/7
3/6
0/20/0
3/6
0/1
--
0.79
0.700.82
0.56
0.12
0.82
0.30--
0.54
0.500.76
0.43
0.08
0.64
0.23
--
0.36
0.48
0.59
0.390.02
0.59
0.25
--
32.5
17.335.0
5.5
16.7
36.4
2.3
21.7
15.0
10.828.4
4.7
17.2
24.7
2.2
15.6
9.7
10.5
20.9
5.00.0
22.1
2.2
12.3
C
BD
A
B
D
A
C
B
BC
A
B
C
A
B
A
B
C
AA
C
A
B
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
45/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 45
Table 12 (Continued)
SIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Signalized Intersection/Peak Hour/Movement V/Ca Delayb LOSc
Queued
Ave/95th V/C Delay LOS
Q
Av
5 Route 20/Main Street at Route 32/Thorndike
Street
Friday Evening:
North Main Street EB LT
North Main Street EB THSouth Main Street WB TH
South Main Street WB RT
Thorndike Street SB LT
Thorndike Street SB RT
OverallSaturday Midday:
North Main Street EB LT
North Main Street EB TH
South Main Street WB THSouth Main Street WB RT
Thorndike Street SB LTThorndike Street SB RT
OverallSaturday Evening:
North Main Street EB LTNorth Main Street EB TH
South Main Street WB TH
South Main Street WB RT
Thorndike Street SB LTThorndike Street SB RT
Overall
0.67
0.530.54
0.270.69
0.43
--
0.69
0.38
0.570.23
0.390.46
--
0.450.32
0.32
0.21
0.400.34
--
13.1
9.118.0
3.332.6
4.3
13.0
13.9
7.3
18.63.3
23.65.4
11.6
7.96.7
14.6
3.4
23.72.8
9.0
B
AB
AC
A
B
B
A
BA
CA
B
AA
B
A
CA
A
3/4
5/75/8
0/2
4/8
1/3
--
3/4
3/5
5/70/1
2/41/3
--
2/42/4
3/4
0/1
2/40/2
--
0.78
0.580.59
0.290.76
0.49
--
0.81
0.42
0.620.25
0.440.52
--
0.510.35
0.34
0.22
0.440.36
--
19.9
9.919.0
3.337.1
6.3
15.5
22.3
7.7
19.93.3
24.57.6
14.4
8.77.0
15.0
3.3
24.52.9
9.4
B
AB
AD
A
B
C
A
BA
CA
B
AA
B
A
CA
A
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
46/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 46
Table 12 (Continued)
SIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
LocationNo. Signalized Intersection/Peak Hour/Movement V/Ca Delayb LOSc
QueuedAve/95th V/C Delay LOS
QA
9 Route 20/Route 32/Park Street at Thorndike
Street
Friday Evening:
Park Street WB LT
Park Street WB RTThorndike Street NB TH/RT
Thorndike Street SB LTThorndike Street SB TH
OverallSaturday Midday:
Park Street WB LT
Park Street WB RT
Thorndike Street NB TH/RT
Thorndike Street SB LTThorndike Street SB TH
OverallSaturday Evening:
Park Street WB LTPark Street WB RT
Thorndike Street NB TH/RT
Thorndike Street SB LT
Thorndike Street SB TH
Overall
0.51
0.420.72
0.870.34
--
0.62
0.33
0.69
0.640.32
--
0.470.32
0.62
0.47
0.24--
23.9
4.219.5
36.9
6.4
18.0
25.0
2.6
19.7
15.87.1
14.3
21.62.8
16.7
8.4
5.6
11.3
C
AB
D
A
B
C
A
B
BA
B
CA
B
A
A
B
3/5
1/26/11
3/11
2/5
--
3/6
0/2
5/9
2/52/4
--
2/50/2
4/9
1/3
2/3--
0.58
0.450.81
1.090.42
--
0.67
0.36
0.75
0.720.36
--
0.500.35
0.67
0.55
0.27--
26.3
5.824.9
>80.0
7.6
31.4
27.5
2.7
21.9
22.37.6
16.6
22.52.8
18.3
11.9
6.0
12.6
C
AC
F
A
C
C
A
C
CA
B
CA
B
B
A
B
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
47/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 47
Table 12 (Continued)
SIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Signalized Intersection/Peak Hour/Movement V/Ca Delayb LOSc
Queued
Ave/95th V/C Delay LOS
Q
Av
11 Thorndike Street at the I-90 RampsFriday Evening:
I-90 Ramp EB LT
I-90 Ramp EB RT
Thorndike Street NB LTThorndike Street NB TH
Thorndike Street SB TH
Thorndike Street SB RT
OverallSaturday Midday:
I-90 Ramp EB LTI-90 Ramp EB RT
Thorndike Street NB LT
Thorndike Street NB THThorndike Street SB TH
Thorndike Street SB RT
OverallSaturday Evening:
I-90 Ramp EB LT
I-90 Ramp EB RTThorndike Street NB LT
Thorndike Street NB TH
Thorndike Street SB TH
Thorndike Street SB RT
Overall
0.89
0.49
0.610.51
0.70
0.32
--
0.630.28
0.44
0.380.66
0.31--
0.66
0.280.39
0.35
0.62
0.24--
42.6
3.6
16.815.7
40.02.3
19.8
29.51.8
8.8
8.728.9
1.4
12.6
28.5
1.69.0
9.2
28.6
1.3
13.2
D
A
BB
DA
B
CA
A
AC
A
B
C
AA
A
C
A
B
12/23
1/4
4/66/9
5/9
1/2
--
4/90/2
2/4
3/64/10
0/1--
4/10
0/12/4
3/6
4/9
0/1--
1.01
0.55
0.670.54
0.730.35
--
0.660.31
0.51
0.420.71
0.34--
0.70
0.300.45
0.38
0.67
0.26--
66.1
5.4
18.715.9
41.23.5
26.2
32.22.9
10.5
9.932.4
2.5
14.4
30.9
1.810.3
10.1
31.2
1.3
14.4
E
A
BB
DA
C
CA
B
AC
A
B
C
AB
B
C
A
B
1
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
48/79
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
49/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 49
Table 12 (Continued)
SIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
LocationNo. Signalized Intersection/Peak Hour/Movement V/Ca Delayb LOSc
QueuedAve/95th V/Ca Delayb LOSc
QAv
15 Route 32/Thorndike Street at High Street
Friday Evening:
High Street EB LT/THHigh Street EB RT
High Street WB LT/TH/RTThorndike Street NB LT
Thorndike Street NB TH/RTThorndike Street SB LT/TH
Thorndike Street SB RT
OverallSaturday Midday:
High Street EB LT/TH
High Street EB RT
High Street WB LT/TH/RTThorndike Street NB LT
Thorndike Street NB TH/RT
Thorndike Street SB LT/TH
Thorndike Street SB RT
OverallSaturday Evening:
High Street EB LT/TH
High Street EB RTHigh Street WB LT/TH/RT
Thorndike Street NB LTThorndike Street NB TH/RT
Thorndike Street SB LT/TH
Thorndike Street SB RT
Overall
0.420.54
0.050.67
0.640.78
0.15--
0.26
0.60
0.040.46
0.33
0.72
0.08--
0.32
0.470.01
0.420.44
0.66
0.15
--
23.56.3
16.214.3
9.7
27.5
3.4
14.5
20.8
7.1
16.07.1
5.4
22.8
0.8
11.7
21.9
6.815.0
6.36.0
19.8
3.0
10.5
CA
BB
A
C
A
B
C
A
BA
A
C
A
B
C
AB
AA
B
A
B
2/30/2
0/12/6
5/115/12
0/1--
1/2
0/2
0/11/3
2/5
5/11
0/0--
1/2
0/20/0
1/23/6
4/8
0/1
--
0.440.56
0.050.79
0.70
0.85
0.16--
0.27
0.62
0.040.55
0.37
0.79
0.09--
0.34
0.500.01
0.480.48
0.72
0.16
--
24.06.3
16.024.8
11.5
32.9
3.9
18.1
20.9
7.0
15.79.6
6.0
27.1
1.1
13.4
22.5
6.8
15.0
7.36.5
22.7
3.5
11.7
C
A
BC
B
C
A
B
C
A
BA
A
C
A
B
C
AB
AA
C
A
B
aVolume-to-capacity.bControl (signal) delay per vehicle in seconds.cLevel-of-Service.dQueue length in vehicles.EB = eastbound; WB = westbound; NB = northbound; SB = southbound; LT = left-turning movements; TH = through movements; RT = right-turning movements.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
50/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 50
Table 13
UNSIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Unsignalized Intersection/Peak Hour/Movement Demanda Delayb LOSc
Queued
95th Demand Delay LOS
Que
95
1 Route 181/ at Thorndike Street
Friday Evening:
Thorndike Street WB LT/RT
Route 181 NB TH/RTPalmer Street SB LT/TH
Saturday Midday:
Thorndike Street WB LT/RT
Route 181 NB TH/RT
Palmer Street SB LT/TH
Saturday Evening:
Thorndike Street WB LT/RT
Route 181 NB TH/RT
Palmer Street SB LT/TH
170
253513
142
251
340
146
212
294
11.7
0.08.2
11.1
0.0
8.1
11.3
0.0
8.1
B
AA
B
A
A
B
A
A
1
01
1
0
1
1
0
1
187
276564
159
274
375
160
232
322
12.3
0.08.3
11.6
0.0
8.3
11.8
0.0
8.2
B
AA
B
A
A
B
A
A
2 Route 181/Sykes Street at Mt. Dumplin Road
Friday Evening:
Mt. Dumplin Road WB LT/RT
Route 181 NB TH/RT
Skyes Street SB LT/TH
Saturday Midday:
Mt. Dumplin Road WB LT/RT
Route 181 NB TH/RT
Skyes Street SB LT/TH
Saturday Evening:
Mt. Dumplin Road WB LT/RT
Route 181 NB TH/RT
Skyes Street SB LT/TH
15
538
458
19
375
324
13
299
322
16.8
0.0
8.9
12.9
0.0
8.2
12.5
0.0
7.9
C
A
A
B
A
A
B
A
A
1
00
1
0
0
0
0
0
17
588501
21
410
354
15
327
352
18.8
0.09.1
13.7
0.0
8.3
13.2
0.0
8.0
C
AA
B
A
A
B
A
A
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
51/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 51
Table 13 (Continued)
UNSIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Unsignalized Intersection/Peak Hour/Movement Demanda Delayb LOSc
Queued
95th Demand Delay LOS
Que
95
3 Route 181/Main Street at Shearer Street
Friday Evening:
Shearer Street Extension EB LT/TH/RT
Shearer Street WB LT/TH/RTRoute 181 NB LT/TH/RT
Route 181 SB LT/TH/RT
Saturday Midday:
Shearer Street Extension EB LT/TH/RTShearer Street WB LT/TH/RT
Route 181 NB LT/TH/RT
Route 181 SB LT/TH/RT
Saturday Evening:
Shearer Street Extension EB LT/TH/RTShearer Street WB LT/TH/RT
Route 181 NB LT/TH/RT
Route 181 SB LT/TH/RT
1
251592
495
10187
429
344
5197
343
641
11.5
>50.08.4
8.9
16.829.2
7.9
8.4
12.132.1
8.0
8.1
B
FA
A
CD
A
A
BD
A
A
0
160
1
04
0
0
05
0
0
1
274647
541
10205
469
376
5176
375
373
11.9
>50.08.6
9.2
18.442.3
7.9
8.5
12.749.5
8.0
8.3
B
FA
A
CE
A
A
BE
A
A
2
6 Route 20/Route 32/Park Street at Breckenridge Street
Friday Evening:
Park Street EB LT/TH
Park Street WB TH/RT
Breckenridge Street SB LT/RT
Saturday Midday:
Park Street EB LT/TH
Park Street WB TH/RT
Breckenridge Street SB LT/RT
Saturday Evening:
Park Street EB LT/TH
Park Street WB TH/RTBreckenridge Street SB LT/RT
638420
192
431
445
148
399
429152
8.50.0
>50.0
1.0
0.0
27.1
8.4
0.025.2
AA
F
A
A
D
A
AD
10
12
0
0
3
0
03
700462
210
476
493
162
438
471166
8.70.0
>50.0
8.7
0.0
37.7
8.6
0.033.2
A
A
F
A
A
E
A
AD
1
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
52/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 52
Table 13 (Continued)
UNSIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Unsignalized Intersection/Peak Hour/Movement Demanda Delayb LOSc
Queued
95th Demand Delay LOS
Q
7 Route 20 Route 32/Park Street at Stone Street
Friday Evening:
Park Street EB TH/RT
Park Street WB LT/TH
Stone Street NB LT/RT
Saturday Midday:
Park Street EB TH/RT
Park Street WB LT/TH
Stone Street NB LT/RT
Saturday Evening:
Park Street EB TH/RTPark Street WB LT/TH
Stone Street NB LT/RT
693
410
256
494
400
165
466399
171
0.0
9.6
>50.0
0.08.6
27.3
0.08.7
31.6
A
A
F
AA
D
AA
D
0
1
13
00
3
02
4
760
449
282
546440
183
512437
188
0.0
10.0
>50.0
0.08.9
39.5
0.08.9
48.3
A
A
F
AA
E
AA
E
8 Route 32/Main Street/Stone Street at South Main Street
Friday Evening:
South Main Street EB LT/TH
Route 32 WB TH/RT
Stone Street SB LT/RT
Saturday Midday:
South Main Street EB LT/TH
Route 32 WB TH/RT
Stone Street SB LT/RT
Saturday Evening:
South Main Street EB LT/TH
Route 32 WB TH/RTStone Street SB LT/RT
436
459
228
271
417
149
263
318181
8.7
0.0
>50.0
8.4
0.0
20.1
8.2
0.020.5
A
A
F
A
A
C
A
A
C
1
0
8
1
0
2
1
0
3
477
504
251
297
459
166
287
348
199
8.9
0.0
>50.0
8.6
0.0
24.9
8.3
0.025.2
A
A
F
A
A
C
A
AD
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
53/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 53
Table 13 (Continued)
UNSIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Unsignalized Intersection/Peak Hour/Movement Demanda Delayb LOSc
Queued
95th Demand Delay LOS
10 Route 32/Thorndike Street at Lawrence Street
Friday Evening:
Lawrence Street EB LT/TH/RT
Driveway WB LT/TH/RT
Thorndike Street NB LT/TH/RTThorndike Street SB LT/TH/RT
Saturday Midday:
Lawrence Street EB LT/TH/RT
Driveway WB LT/TH/RT
Thorndike Street NB LT/TH/RT
Thorndike Street SB LT/TH/RT
Saturday Evening:
Lawrence Street EB LT/TH/RT
Driveway WB LT/TH/RTThorndike Street NB LT/TH/RT
Thorndike Street SB LT/TH/RT
110
1
661916
77
0
570
571
62
0503
538
>50.0
>50.0
10.39.1
37.4
0.0
8.7
8.7
31.4
0.08.8
8.5
F
F
BA
E
A
A
A
D
AA
A
10
1
00
3
0
0
0
2
00
0
121
1
7281,013
84
0
636
641
68
0554
604
>50.0
>50.0
10.99.3
>50.0
0.0
8.9
8.9
42.8
0.09.0
8.6
F
F
BA
F
A
A
A
E
AA
A
12 Route 32/Thorndike Street at Shearer Street
Friday Evening:
Shearer Street EB LTShearer Street EB RT
Thorndike Street NB LT/TH
Thorndike Street SB TH/RT
Saturday Midday:
Shearer Street EB LT
Shearer Street EB RT
Thorndike Street NB LT/TH
Thorndike Street SB TH/RT
Saturday Evening:
Shearer Street EB LTShearer Street EB RT
Thorndike Street NB LT/TH
Thorndike Street SB TH/RT
13871
977
842
152
41603
827
11727
581
761
>50.016.5
10.0
0.0
>50.0
15.99.9
0.0
>50.013.8
9.4
0.0
FC
B
A
F
CA
A
FB
A
A
131
0
0
11
10
0
51
0
0
15178
1,071
926
166
45666
913
12830
638
835
>50.018.4
10.5
0.0
>50.0
17.610.4
0.0
>50.014.8
9.7
0.0
FC
B
A
F
C
B
A
FB
A
A
See notes at end of table.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
54/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 54
Table 13 (Continued)UNSIGNALIZED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY
2013 Existing 2023 No-Build
Location
No. Unsignalized Intersection/Peak Hour/Movement Demanda Delayb LOSc
Queued
95th Demand Delay LOS
14 Route 32/Thorndike Street at Mt. Dumplin Road
Friday Evening:
Mt. Dumplin Road EB LT/RT
Thorndike Street NB LT/TH
Thorndike Street SB TH/RT
Saturday Midday:
Mt. Dumplin Road EB LT/RTThorndike Street NB LT/TH
Thorndike Street SB TH/RT
Saturday Evening:
Mt. Dumplin Road EB LT/RT
Thorndike Street NB LT/TH
Thorndike Street SB TH/RT
49
1,069
732
38640
766
19
727
587
>50.0
9.6
0.0
20.6
9.60.0
21.3
8.8
0.0
F
A
A
C
AA
C
A
A
3
1
0
1
00
1
0
0
54
1,171
806
42
707846
21
798
645
>50.0
10.10.0
24.9
9.90.0
25.6
9.1
0.0
F
BA
C
AA
D
A
A
aDemand in vehicles per hour.bAverage control delay per vehicle in seconds.cLevel-of-Service.dQueue length in vehicles.EB = eastbound; WB = westbound; NB = northbound; SB = southbound; LT = left-turning movements; TH = through movements; RT = right-turning movements.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
55/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 55
SUMMARY OF RESULTS
As shown in Table 12 and Table 13, the project is not expected to have a significant impact on local
roadways, due to the regional attraction of the Project. However, there are a number of locations where
improvements were identified to address deficiencies, either based on existing conditions (safety-related
or operationally-related) or due to impacts caused by the Project. These locations are listed below:
MITIGATION LOCAL INTERSECTIONS
Locations 3/4 North Main Street at Shearer Street and Wilbraham Street
The unsignalized intersection of North Main Street with Shearer Street has a crash rate above the
District 2 average. Most of the crashes are listed as angle or rear-end collisions. The intersection has
awkward geometry and is in close proximity to the signalized intersection of Main Street with WilbrahamStreet, but operates under STOP-sign control. Sight distance to the north is also limited for the
westbound Shearer Street approach.
It is recommended that the intersection be placed under signalized control and coordinated with the
adjacent Wilbraham Street intersection. Pavement markings and signage are also recommended. AConceptual Improvement Plan of this intersection is shown in Figure 19.
Locations 6/7 Park Street at Breckenridge Street and Stone Street
The unsignalized intersection of Park Street with Breckenridge Street has a crash rate above the District 2
average. Most of the crashes are listed as angle or rear-end collisions. A high degree of delay is
associated with the Breckenridge Street unsignalized approach, where left- and right-turns are contained
in one lane. Due to the high traffic volumes on Park Street but comparatively low volumes on
Breckenridge Street, there are no improvements that can effectively eliminate the high delay for vehicles
exiting Breckenridge Street.
However, to reduce the delay for right-turning vehicles, it is suggested that a minor strip widening of theapproach to Park Street be implemented. This will allow the right-turns to execute their movements
without waiting for left-turning vehicles to first execute their turn. The existing worn pavement markings
should also be updated at this intersection and also at the adjacent unsignalized intersection of Park Street
and Stone Street. A Conceptual Improvement Plan of this intersection is shown in Figure 20.
Location 8 Stone Street at South Main Street
The unsignalized intersection of Stone Street with South Main Street operates with a high degree of delay.
The crash rate is not significant (crash rate below the District 2 average). Due to the high traffic volumes
on South Main Street but comparatively low volumes on Stone Street, there are no improvements that can
effectively eliminate the high delay for vehicles exiting Stone Street.
It is suggested that the existing worn pavement markings be updated at this intersection. A Conceptual
Improvement Plan of this intersection is shown in Figure 21.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
56/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 56
Insert figure 19
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
57/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 57
Insert figure 20
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
58/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 58
Insert figure 21
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
59/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 59
Location 9 Thorndike Street at Park Street
The signalized intersection of Thorndike Street with Park Street operates with a high degree of delay.
The crash rate is not significant (crash rate below the District 2 average). Due to the limited property
available for roadway widening, there are no improvements that can be made to effectively eliminate the
high delay for vehicles at the intersection.
To improve operations for the Park Street approach, it is suggested that pavement markings be installed to
formalize the use of separate right-turn and left-turn lanes at this intersection. High-visibility diagonalcrosswalk markings should also be applied at the intersection. A Conceptual Improvement Plan of this
intersection is shown in Figure 22.
Location 14 Thorndike Street at Mount Dumplin Road
The unsignalized Mount Dumplin Road approach to Thorndike Street operates with a high degree of
delay. No crashes have been recorded at the intersection. Due to the high traffic volumes on
Thorndike Street but comparatively low volumes on Mount Dumplin Road, there are no improvements
that can effectively eliminate the high delay for vehicles exiting Mount Dumplin Road.
It is suggested that the existing worn pavement markings be updated at this intersection. A Conceptual
Improvement Plan of this intersection is shown in Figure 23.
Location 1 Thorndike Road at Sykes Street/Palmer Street (Route 181)
The unsignalized intersection of Thorndike Road with Route 181 does not operate with a high degree of
delay, but the crash rate is above the District 2 average. Most of the crashes are listed as rear-end
collisions, but there have also been two head-on collisions. Half of the collisions resulted in personal
injuries.
It is suggested that the existing worn pavement markings be updated at this intersection. In addition,
signage to identify southbound Route 181 motorists that they are approaching an intersection with skewedgeometry is recommended, as is removal of vegetation within the right-of-way to improve visibility. A
Conceptual Improvement Plan of this intersection is shown in Figure 24.
Location 15 Thorndike Street at High Street
The signalized intersection of Thorndike Street with Park Street has a crash rate above the District 2
average. Most of the crashes are listed as rear-end or angle collisions. In addition, a large number (8 of
21 or 38 percent) resulted in personal injuries. A number of crashes were the result of collisions between
northbound left-turning vehicles and southbound through vehicles. The northbound left-turn movement
operates with a protected-plus-permissive operation, requiring turning vehicles to yield to opposing
through vehicles during the permissive operation.
To improve safety at the intersection, it is suggested that the permissive operation be eliminated and the
left-turn movement operate through a protected-only operation. This will require a new timing plan for
the intersection. In addition, the existing worn pavement markings should be updated at this intersection.
A Conceptual Improvement Plan of this intersection is shown in Figure 25.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
60/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 60
Location 5 Thorndike Road at North Main Street (Route 20)
The signalized intersection of Thorndike Road with North Main Street (Route 20) operates with a high
degree of delay on the North Main Street eastbound approach. The crash rate is not significant (crash rate
below the District 2 average).
To improve operations for the North Main Street approach, it is suggested that the eastbound left-turn andthrough movements be allocated more green time. This will require a modification of the existing timing
plan for the intersection. In addition, the existing worn pavement markings should be updated at thisintersection. A Conceptual Improvement Plan of this intersection is shown in Figure 26.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
61/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 61
Insert figure 22
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
62/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 62
Insert figure 23
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
63/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 63
Insert figure 24
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
64/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 64
Insert figure 25
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
65/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 65
Insert Figure 26
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
66/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 66
MITIGATION SITE ACCESS INTERSECTIONS
Significant impacts are expected at the intersections of the Exit 8 I-90 ramp roadway and Shearer Street
with Route 32. As identified previously, two concepts are currently being reviewed for access:
1. At-Grade Alternative In this concept, a Site Access Roadway is constructed opposite the Exit 8I-90 ramp roadway and continues around the north of the site. The I-90 ramp roadway andRoute 32 are significantly widened and expanded, and a new traffic signal is installed. A
boulevard-type Access Road consisting of two lanes per direction and a raised median will serveas the access to the Project.
2. Flyover Alternative Separate flyover ramps are proposed for the traffic exiting and entering theTurnpike that will bypass the Route 32 intersection with the I-90 ramp roadway. Local traffic
will be able to access the Project via the Site Access Road intersection with Route 32 andShearer Street. The ramps will connect to Route 32 at a new signalized intersection, with a slip
ramp for traffic destined to the Project from I-90. The Access Road would consist of two lanes
per direction and a raised median.
These conceptual alternatives are shown on Figures 27 and 28, respectively.
Tables 14 and 15 present the LOS results of the intersections for 2023 No Build, 2023 Build unmitigated,
and 2023 Build with proposed mitigation in place for both Local Intersections and the Site Access
Intersections.
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
67/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 67
Insert figure 27
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
68/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 68
Insert figure 28
-
7/28/2019 Mohegan Sun Palmer Traffic Assessment
69/79
G:\6438 Palmer, MA\Memos\J. Thomas 060713.docx 69
Table 14MITIGATED INTERSECTION LEVEL-OF-SERVICE AND VEHICLE QUEUE SUMMARY LOCAL INTERS
2023 No-Build 2023 Build
Location
No. Signalized Intersection/Peak Hour/Movement V/Ca Delayb LOSc
Queued
Ave/95th V/C Delay LOS
Qu
Ave
4 Route 181/North Main Street at Route20/Wilbraham Streete
Friday Evening:
Wilbraham Street EB LT
Wilbraham Street EB TH/RT
North Main Street WB LT/TH
North Main Street WB RTPrivate Drive NB LT/TH/RT
Route 181 SB LT/TH
Route 181 SB RT
OverallSaturday Midday:
Wilbraham Street EB LT
Wilbraham Street EB TH/RT
North Main Street WB LT/TH
North Main Street WB RTPrivate Drive NB LT/TH/RT
Route 181 SB LT/TH
Route 181 SB RT
OverallSaturday Evening:
Wilbraham Street EB LTWilbraham Street EB TH/RT
North Main Street WB LT/TH
North Main Street WB RT
Private Drive NB LT/TH/RTRoute 181 SB LT/TH
Route 181 SB RT
Overall
0.79
0.70
0.82
0.560.12
0.82
0.30
--
0.54
0.50
0.76
0.430.08
0.64
0.23
--
0.360.48
0.59
0.39
0.020.59
0.25
--
32.5
17.3
35.0
5.516.7
36.4
2.3
21.7
15.0
10.8
28.4
4.717.2
24.7
2.2
15.6
9.710.5
20.9
5.0
0.022.1
2.2
12.3
C
B
D
AB
D
A
C
B
B
C
AB
C
A
B
AB
C
A
AC
A
B
2/7
5/14
5/13
0/30/1
5/12
0/1
--
1/4
3/9
5/13
0/20/1
3/8
0/1
--
1/33/8
3/7
0/2
0/03/7
0/1
--
0.80
0.77
0.90
0.570.12
0.85
0.30
--
0.57
0.58
0.83
0.270.09
0.66
0.23
--
0.420.53
0.70
0.23
0.020.62
0.26
--
33.9
20.2
44.3
5.516.8
39.9
2.3
25.1
16.7
12.2
33.0
1.417.3
25.5
2.2
17.0
10.811.4
25.0
1.4
0.023.4
2.2
13.5
C
C
D
AB
D
A
C
B