moly mines limited moly mines for personal use only limited
TRANSCRIPT
1
MOLYMINESLIMITED
MOLYMOLYMINESLIMITEDLIMITED
Australian Roadshow PresentationAustralian Roadshow PresentationAustralian Roadshow PresentationAustralian Roadshow Presentation
23 26 November 200923‐26 November 2009
‘Metals For Our Time’
For
per
sona
l use
onl
y
2
MOLYMINESLIMITED
Disclaimer
This presentation includes “forward‐looking statements” as that term within the meaning of securities laws of applicable
jurisdictions. Forward‐looking statements involve known and unknown risks, uncertainties and other factors that are in some
cases beyond Moly Mines’ control. These forward‐looking statements include, but are not limited to, all statements other than
statements of historical facts contained in this presentation, including, without limitation, those regarding Moly Mines’ futurep , g, , g g y
expectations. Readers can identify forward‐looking statements by terminology such as “aim,” “anticipate,” “assume,” “believe,”
“continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “risk,” “should,”
“will” or “would” and other similar expressions. Risks, uncertainties and other factors may cause Moly Mines’ actual results,
f d h d ff ll f h d l d b h f d l kperformance, production or achievements to differ materially from those expressed or implied by the forward‐looking
statements (and from past results, performance or achievements). These factors include the failure to complete and
commission the mine facilities, processing plant and related infrastructure in the time frame and within estimated costs
currently planned; variations in global demand and price for molybdenum and copper; fluctuations in exchange rates betweeny p g p y pp g
the U.S. dollar and the Australian dollar; failure to recover the resource and reserve estimates of the Project; the failure of Moly
Mines’ suppliers and service providers to fulfil their obligations under construction, supply and tolling agreements; unforeseen
geological, physical or meteorological conditions, natural disasters or cyclones; changes in the regulatory environment,
i d t i l di t l b h t liti l d th f t th i bilit t bt i dditi l fi i if i dindustrial disputes, labour shortages, political and other factors; the inability to obtain additional financing, if required, on
commercially suitable terms; and global and regional economic conditions. Readers are cautioned not to place undue reliance
on forward‐looking statements. We assume no obligation to update such information.
For
per
sona
l use
onl
y
3
MOLYMINESLIMITED
Share Purchase Plan
Record date 4 November 2009
PricePrice
• discount to 5 day VWAPA$0.80
27.5%
Total SPP size 20 million sharesTotal SPP size 20 million shares
Limit per shareholder A$15,000
Minimum subscription A$2,000
Offer close 30 November 2009
Allotment date 4 December 2009
SPP offer booklet and application forms at www.molymines.comSPP offer booklet and application forms at www.molymines.com
For
per
sona
l use
onl
y
4
MOLYMINESLIMITED
Project Overview
Spinifex Ridge Molybdenum / Copper ProjectSpinifex Ridge Molybdenum / Copper Project Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
Fully permitted, engineered, ready for development at 20 Mtpa.
Spinifex Ridge Molybdenum / Copper ProjectSpinifex Ridge Molybdenum / Copper Project Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
D.S.O. – 59% iron ore.
1 Mtpa. Engineering underway on 10 Mtpa
start‐up.
A$100M long lead equipment for 20
p
Production mid 2010.
Location on Spinifex Ridge mining leases. A$100M long‐lead equipment for 20 Mtpa mine manufactured in Germany and delivered to Australia.
Australia
Now with a major potential Strategic Investor
Australia
Moly Mines LimitedMoly Mines Limited
For
per
sona
l use
onl
y
5
MOLYMINESLIMITED
Development of Spinifex Ridge
Chinese group Sichuan Hanlong to finance Spinifex Ridge development
Hanlong to invest US$140M
Obtain 51‐55% controlling equity interest
Retire all TCW debt
Receive 35 5 Project Finance Options Receive 35.5 Project Finance Options
Hanlong to provide US$60M project loan
10 year maturity, 10% coupon10 year maturity, 10% coupon
Hanlong to arrange US$500M Project Finance Loan by 30 June 2010.
For
per
sona
l use
onl
y
6
MOLYMINESLIMITED
Sichuan Hanlong Group
Privately owned
Resource Interests – Zn, Mo, Cu, Coal, Au
Electricity production, infrastructure development, pharmaceutical production, food and alcoholic beverages, real estate development,
i t l t h l t i d l tenvironmental technology, tourism development and high tech industries
RMB 9.5 billion revenue 2008 (A$1.5 billion)
12,000 employees
M l Mi Li i dMoly Mines Limited An International Mining House
Major world Mo company
Moly Mines LimitedMoly Mines Limited
For
per
sona
l use
onl
y
7
MOLYMINESLIMITED
Parties Working Toward Rapid Completion
Status
S b i ti A t i d 19 O t b 2009 Subscription Agreement signed 19 October 2009 Notice of shareholder meeting dispatched TCW Restructure Agreements
FIRB Moly Mines shareholder meeting 16 December 2009
Chinese regulatory authorities By 31 January 2010
For
per
sona
l use
onl
y
8
MOLYMINESLIMITED
Benefits of the Transaction
An opportunity to build the Spinifex Ridge Molybdenum / Copper ProjectAn opportunity to build the Spinifex Ridge Molybdenum / Copper Projectsignificantly ahead of when capital and moly markets might support afinancing and capture the high commodity prices in the next metals cycle
Moly Mines will be the world’s leading moly development company Moly Mines will be the world s leading moly development company.
Provides shareholders certainty of funding currently unavailable in thetraditional capital markets.
De‐leverages the Moly Mines balance sheet in favor of a major equity partnerwhose interests are aligned with minority shareholders:
US$200M in equity and debt funding will fully repay existing TCW facilities and US$200M in equity and debt funding will fully repay existing TCW facilities andprovide a significant working capital.
Hanlong is a strong partner with diversified mining interests.
Hanlong is incentivized to procure the US$500M Project Finance Loan otherwise:
Options will not vest.
Significant portion (~75%) of US$60M Hanlong loan will be forgiven.
Less dilutive structure than likely from traditional capital markets.
For
per
sona
l use
onl
y
9
MOLYMINESLIMITED
Capital Structure & Balance Sheet Summary
Pre Transaction Post TransactionPre Transaction Post Transaction
Shares on issue (post SPP 20M) 156.7M 156.7M
TCW Warrants (ex $0.0001) 17.9M 17.9M
Institutional Warrants (ex C$1.00) 14.0M 14.0M
Employee Options 6.1M 6.1M
Hanlong Shares 207 1MHanlong Shares ‐ 207.1M
Hanlong Project Finance Options (ex C$1.00) ‐ 35.5M
194.7M 437.3M
Pro‐forma Balance Sheet Extract US$ US$
Cash 35.7 101.7
E i t 107 5 107 5Equipment 107.5 107.5
TCW Debt (1.5‐2 year) 114.0 ‐
TCW Debt (5 year) 20.0 ‐
Hanlong Debt (10 year) ‐ 60.0
For
per
sona
l use
onl
y
10
MOLYMINESLIMITED
Corporate Governance
Head office to remain in Perth.
No change to existing management in first 12 months following completion.g g g g p
Hanlong granted the right to board control.
Hanlong can appoint 1 executive director (marketing & project finance) reporting to the Managing Director.
Hanlong can appoint 2 non‐executive directors.
B d l i l 2 i d d di Board to always contain at least 2 independent directors.
Any Hanlong offtake agreements require shareholder approval (from non‐aligned).
For
per
sona
l use
onl
y
11
MOLYMINESLIMITED
Experienced Team
Board of DirectorsBoard of Directors Management TeamManagement TeamBoard of DirectorsBoard of Directors Management TeamManagement Team
Mr. David Craig ‐ Chairman
An experienced businessman and lawyer, who has held and holdsExecutive and Board positions in the fields of law, financial services andthe resources industry Appointed as Chairman in 2009
Mr. Collis Thorp – Chief Operating Officer
40 years mining experience, having operated and managed open-pit andunderground mines in Australia and internationally. Experience coversprecious base and specialty metal operations including gold tin tungsten
Over 38 years of worldwide experience in the resource industry, more than 20 years experience as a manager of publicly listed resource companies, in
the resources industry. Appointed as Chairman in 2009
Dr. Derek Fisher – CEO/Managing Director
precious, base and specialty metal operations, including gold, tin, tungsten,titanium and zircon.
A mining engineer with 25 years of extensive industry experience includingopen-pit mine management, mining contractors management.
Mr. Mike Gloyne – General Manager Operations
y p g p y p ,addition to serving as a director of mining companies that developed mines in Australia, Mongolia, Armenia and the DRC.
A professional geologist with over 25 years Canadian and international
Mr. David Constable
Extensive experience, having spent 17 years in senior finance roles in both
Mr. John McEvoy – Chief Financial Officer
open pit mine management, mining contractors management.
exploration and development experience.
Over 25 years investment banking experience having held senior executive
Mr. Michael Senft Mr. Andrew Worland – Company Secretary , General Manager Commercial & Marketing
the public and private mining sector.
Over 25 years investment banking experience having held senior executiveroles with Merrill Lynch and UBS in New York and London.
Mr. David Nixon
Extensive finance, corporate and investor relations experience in the resources sector, over 13 years in senior finance and corporate roles.
Moly Mines has established a quality technical &management team experienced in all aspects of project
A mechanical engineer with 40 years experience in the mining andconstruction industries in Southern Africa, Australia, New Zealand, Canadaand Indonesia.
management team experienced in all aspects of projectfinancing, development, construction, mining & processingand operations, demonstrating low management risk in theproject.
For
per
sona
l use
onl
y
12
MOLYMINESLIMITED
China InformationChina Information
Spinifex Ridge Molybdenum ProjectTransportation of mill sections, Perth Transportation of mill sections, Perth
For
per
sona
l use
onl
y
13
MOLYMINESLIMITED
Reserves and Mineral Resources
hl hhl hReserves
JORC / NI43‐101 classification Mt Mo% Cu% Ag g/t
Proven reserves 199.7 0.06 0.10 1.5
Highlights – 20 Mtpa RateHighlights – 20 Mtpa Rate
23 year Reserve life
E i t ti lProven reserves 199.7 0.06 0.10 1.5
Probable reserves 251.1 0.04 0.07 1.1
TOTAL 450.8 0.05 0.08 1.3
Expansion potential
24Mlb Mo in concentrate
per annum
Resources
JORC / NI43‐101 classification Mt Mo% Cu% Ag g/t
per annum
27Mlb Cu in concentrate per
annum
Measured resources 206.8 0.06 0.10 1.5
Indicated resources 445.4 0.04 0.07 1.1
TOTAL 652.2 0.05 0.08 1.3
Inferred resources 399.0 0.04 0.07 1.1
Note Reserves are a sub set of ResourcesNote—Reserves are a sub‐set of ResourcesR/P—Reserves/Production0.02% Mo cut‐off assumed for resources0.03% Mo cut‐off assumed for reserves
Spinifex Ridge Molybdenum Spinifex Ridge Molybdenum ‐‐ Copper ProjectCopper Project
For
per
sona
l use
onl
y
14
MOLYMINESLIMITED
Low-Risk / Low Cost Open Pit Mining
hl hhl h
Conventional open pit
Pit design has been optimised to maximise grades early and to fit
HighlightsHighlights
Australia
maximise grades early and to fit processing requirements
Favourable mining characteristics
Deposit is porphyry with continuous Mo Camp / Village
Port Hedland (170kms)
AirstripFe Pits
p p p y ymineralisation
Minimal grade control or dilution issue –low grade halo de‐risks mining
Minimal requirement for selective
Waste 2
Waste 1 ROM
Pl t &
Dry Stack Tailings
/ Village
Hi h G dHi h G d Minimal requirement for selective mining
Mining fleet based on conventional open‐pit mining equipment
Pit
Plant &Administration
High GradeStockpileHigh GradeStockpile
Low GradeStockpileLow GradeStockpile
Mo \ Cu Pit
Specified equipment or alternatives can be readily mobilised by contractors
Conventional comminution and flotation processing
Waste 3
Pit Office/
Creek DiversionChannel
Dry stack tailings –operational/environmental advantages
Workshops
Spinifex Ridge Molybdenum Spinifex Ridge Molybdenum ‐‐ Copper ProjectCopper Project
For
per
sona
l use
onl
y
15
MOLYMINESLIMITED
Phase 1 – Startup Project
Results of Scoping Study completed April 2009:
10 Mtpa
10 Mtpa Resource Pit Shell
Initial head‐grade – 0.07% Mo, 0.11% Cu (1st 10 years)
12 13 Million lbs Mo per year20Mtpa
12‐13 Million lbs Mo per year
Utilises same large scale equipment as 20 Mtpa plant.
ResourcePit Shell0.02% Mo Shell
18 month construction period from full project
funding
Capital cost ‐ A$528M (plus A$70M for power station
if not financed by 3rd party)
Operating cost US$8.30/lb (first 10 years – mine gate)0.04% Mo Shell
0.09% Mo Shell‐ High Grade Core
Source: NI43Source: NI43‐‐101 Technical Report dated 25 August 2009101 Technical Report dated 25 August 2009
For
per
sona
l use
onl
y
16
MOLYMINESLIMITED
Long Lead Equipment Orders Completed
Spinifex Ridge Molybdenum Spinifex Ridge Molybdenum ‐‐ Copper ProjectCopper Project
For
per
sona
l use
onl
y
17
MOLYMINESLIMITED
Mine Statistics
Expansion Case Mine Plan (20 Mtpa ‐ year 7 onwards)
Year 1‐10 11‐23 LOM
Waste (Mt) 227 268 495
10 Mtpa Case Mine Plan
Year 1‐10 11‐23 LOM
W t (Mt) 180 47 227 Waste (Mt) 227 268 495
Ore Mined (Mt) 227 224 451
Waste to Ore ratio 1.0 1.2 1.1
Mill F d (M ) 128 323 451
Waste (Mt) 180 47 227
Ore Mined (Mt) 148 88 236
Waste to Ore ratio 1.2 0.5 1.0
ill d ( ) 88 8 236 Mill Feed (Mt) 128 323 451
Mill Feed Mo (% Mo) 0.06 0.04 0.05
Mill Feed Cu (% Cu) 0.1 0.08 0.08
Mill Feed (Mt) 88 148 236
Mill Feed Mo (% Mo) 0.07 0.05 0.06
Mill Feed Cu (% Cu) 0.11 0.08 0.09
Mo Recovery (%) 84 89 87
Cu Recovery (%) 64 67 66
Mo Production (Mlb) 146 282 428
Mo Recovery (%) 84 90 87
Cu Recovery (%) 64 68 66
Mo Production (Mlb) 107 143 250
Cu Production (Mlb) 182 372 554Cu Production (Mlb) 135 181 316
Source: NI43Source: NI43‐‐101 Technical Report dated 25 August 2009101 Technical Report dated 25 August 2009
For
per
sona
l use
onl
y
18
MOLYMINESLIMITED
Economics – High and Low Case Scenarios
10 Mtpa Case10 Mtpa Case
Price Scenario EBITDA (A$M) Pre‐tax NPV (A$M) Pre‐tax IRR (nominal converted)
US$30/lb 292 1,444 26.2%
US$20/lb 149 343 15.3%
US$25/lb (3 Year Average) 244 1,050 22.5%
i C ( 20 )Expansion Case (to 20 Mtpa)
Price Scenario EBITDA (A$M) Pre‐tax NPV (A$M) Pre‐tax IRR (nominal converted)
US$30/lb 459 2,251 28.7%US$30/lb 459 2,251 28.7%
US$20/lb 220 578 16.5%
US$25/lb (3 Year Average) 396 1,669 24.7%
Financial analysis based on 20 Mtpa DFS and 10 Mtpa Scoping Study
Moly Mines believes long term molybdenum prices required to be > US$20/lb to support new primary mine development and meet projected supply shortfall
FX rate based on forward curve rates at 13 August 2009
Project returns vary significantly with commodity price and FX assumptions
Source: NI43Source: NI43‐‐101 Technical Report dated 25 August 2009101 Technical Report dated 25 August 2009
For
per
sona
l use
onl
y
19
MOLYMINESLIMITED
China InformationChina Information
Spinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
20
MOLYMINESLIMITED
Iron Ore Project Overview
Hematite “direct shipped ore” (DSO) – 59% Fe.
Location within Spinifex Ridge Mo mining leases.
Falls under the Mo/Cu permitting.
Commence production Q2/2010 Commence production – Q2/2010.
Close to Port Hedland – within trucking distance.
China market nearby
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
21
MOLYMINESLIMITED
Location Map
EL E l ti Li
Granite
GPL General Purpose Lease
EL – Exploration Licence
Rockchip Sample
1.5kms Iron Ore ResourceIron Ore Resource
6.1 Mt @ 59% Fe6.1 Mt @ 59% Fe
Granite
GPL – General Purpose Lease
Basalt
Basalt59.2% Fe
60 2% Fe55.8% Fe
64.7% Fe
Iron Formation
Ultramafic
Basalt
56 1% F
55.2% Fe
60.2% Fe
Felsics
Basalt
Basalt
56.1% Fe 61.4% Fe 61.9% Fe 61.6% Fe
55.1% Fe
Basalt
Ultramafic
Molybdenum‐Copper ResourceMolybdenum‐Copper Resource
652Mt @ 0.05% Mo, 0.08% Cu652Mt @ 0.05% Mo, 0.08% Cu
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
GraniteBasalt ML – Mining Leases
For
per
sona
l use
onl
y
22
MOLYMINESLIMITED
Resource
6.1 Mt @ 59% Fe6.1 Mt @ 59% Fe
ResourceResource
tonnes Fe% SiO2 Al2O3% P% S% LOI%
Indicated 6,110,000 58.9 8.5 1.7 0.15 0.006 4.7
Inferred 1,160,000 57.2 12.8 0.9 0.15 0.011 4.1
l d h l k d ll f
50% Fe cut‐off
Resource includes Auton, Auton North East, Dalek and Gallifrey.
162 RC and diamond drill holes for 11,011m to an average depth of 70m
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
23
MOLYMINESLIMITED
Site Layout
Waste Dump
Port Hedland (170kms)
NORTHAutonAuton
DalekDalek
G llifG llifSpinifex RidgeMolybdenum‐CopperDeposit (500m)
GallifreyGallifrey
ROM Pad,Crushing,Ore Stockpile
Marble Bar(50kms)6.1 Mt @ 59% Fe6.1 Mt @ 59% Fe
ResourceResource
( )
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
24
MOLYMINESLIMITED
Development Scenarios
Open pit, 3:1 strip ratio.
1 Mtpa production rate.DalekDalek
Capital cost ~A$9.4 Million.
Initial port access fee is estimated at A$2 4 Million Initial port access fee is estimated at A$2.4 Million.
Opex ~A$46 per tonne FOB Port Hedland. AutonAuton
Iron ore spot prices – US$100/t, CFR China (Fines) (source: Platts, Metal Bulletin November 2009)
GallifreyGallifrey
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
25
MOLYMINESLIMITED
Mine Development
O it i i Open pit mining:
3:1, three ore bodies.
Contract mining.Contract mining.
1 Mtpa production rate.
Simple processing; 2 stage crushing and screening –equipment readily available.
Lump / fines – 40/60.
Truck (115 tonne road trains) haulage to Port Hedland – 190km.
Shipping out of Utah Point at Port Hedland – access to pp gport announced September 2009.
First ore production – Q2, 2010 (1)
First ore shipment – Q3, 2010 (1)
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project(1) Provided Utah Point construction completed on time(1) Provided Utah Point construction completed on time
For
per
sona
l use
onl
y
26
MOLYMINESLIMITED
Operating Scenarios
Mining
Numerous contractors available.
Crushing, screening
Contract operators.
Haulage
Numerous contractors in Port H dl d h li MHedland hauling Manganese, Chrome, Iron and Salt.
30km unsealed road then 160k P H dl d160km to Port Hedland.
Haulage rates applied based on third party operating quotation
tsystems.
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
27
MOLYMINESLIMITED
Operations Description
Spinifex Ridge Minesite
Haulage from pit
Stockpiles
Haulage from pit
Fines stockpile (<6.0mm)
C hi & S iCrushing & Screening at siteLump stockpile (>6.0mm – 32.0mm)
Road haulage to Port Hedland
Stockpiles at Port Ship loading & Export
Spinifex Ridge Iron Ore ProjectSpinifex Ridge Iron Ore Project
For
per
sona
l use
onl
y
28
MOLYMINESLIMITED
Financial Parameters
ProductionProduction FinancialFinancialProductionProduction
Ore 5.2Mt
Waste 15 6Mt
Capital Cost ~AUS$9.4M
Operating cost per tonne:
FinancialFinancial
Waste 15.6Mt
Total 20.8Mt
Strip Ratio 3.0
Operating cost per tonne:
Unit Cost ($/t)
Mining 11
Crushing 4p
Grade Fe 59%
Crushing 4
Haulage 19
Port 7
Admin/O/H 5
MarketingMarketing
Traders Capex ~A$9.4 Million pa. (excluding
/ /
A$46
Traders
Mills
p $ p ( gcontingency & port deposit)
Payback expected to be ~18 months from first positive cash flowfrom first positive cash flow .
Source: Spinifex Ridge Iron Ore PFSSource: Spinifex Ridge Iron Ore PFS
For
per
sona
l use
onl
y
29
MOLYMINESLIMITED
Moly Mines Limited
Major strategic partner
The worlds leading moly development company
Strong balance sheet, cash resources
Mo \ Cu Project Mo \ Cu Project
World class, with staged development option
18 month construction period post financing18 month construction period post financing
Fe Project
Short term low cost development Short term, low cost development
Cashflow 2010
Exploration upsidep pFor
per
sona
l use
onl
y
30
MOLYMINESLIMITED
Competence and Responsibility
The information in this release that relates to Molybdenum and
Copper Mineral Resources and Mineral Reserves is based on
information compiled and verified under the supervision of Dr Derek
Fisher who is a fellow of the Australasian Institute of Mining and
Metallurgy. The information in this release that relates to Iron Ore
Mineral Resources is based on information compiled by Mr Clay
Gordon who is a Member of The Australasian Institute of Mining and
Metallurgy and the Australian Institute of Geoscientists.
Dr Fisher is employed by Trillium Investments Pty Ltd which is
contracted to provide management services to Moly Mines, Mr
Cummins is a full‐time employee of Moly Mines and Mr Gordon isCummins is a full‐time employee of Moly Mines and Mr Gordon is
employed by Mining Assets Pty Ltd.
Each of Dr Fisher, Mr Cummins and Mr Gordon have sufficient,
experience which is relevant to the style of mineralisation and type of
deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2004
Edition of the ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’. They consent to the inclusion
in this release of the matters based on their information in the form
and context in which it appears.
For
per
sona
l use
onl
y
31
MOLYMINESLIMITED
50 Kings Park Rd, West Perth, WA, 6005, AUSTRALIA Telephone: +61 8 9429 3300 Fax: +61 8 9429 3399Telephone: +61 8 9429 3300 Fax: +61 8 9429 3399
Telephone: +1 416 777 1801
Fax: +1 416 777 1802Fax: +1 416 777 1802
Email: [email protected]: [email protected]
Website: http://www.molymines.com
Stock market codes: ASX: MOL, TSX: MOL, FWB: HJ1
Moly Mines Contact Details
For
per
sona
l use
onl
y