mom elv coordination
TRANSCRIPT
-
8/13/2019 MOM ELV Coordination
1/1
Date: 6/2/2013
Subject : ELV -MEP Coordination Meeting Venue : Project Office
Attend
ees:Time: 11 a.m.
IL & FS Parvez , Vinay
ANC: Azib Hussain,
ETA: Sukhwan , Rahul, Bhavesh
HAIL Chaitanya , Rajendra , Sameer , Praveen , Rajesh
Sr. No. Items discussed Action By Target Date
A. DESIGN:
1Tenant AHU (16th floor and above):Four AHUs are considered for Two office lay out
in four separate AHU rooms. HAIL to update its design accordinglyETA/ HAIL 11/2/2013
2System Architecture:HAIL to submit revised system Architecture to Mr Vinay for
ApprovalHAIL 11/2/2013
3Shop Drwings : Prep are & Submit Shop Drawings for complete Floors & System Base
on Revised System ArchitectureHAIL 20/2/2013
4Flap Barrier : The BOQ item will remain unchanged . Final decision will be given by IL
& FsIL & FS ASAP
5 PA Console : THAIL will keep Provision for two PA Cnsole on one reception HAIL Revision
6 Stair Case Smoke Detector : Provision of Smoke Detector in Stair Case is Deleted . HAIL/ IL & FS Revision
7Lift Lobby Presurisation : Application of Presssure sensor has to be defined &
Discussed with client for further site implication.HAIL/ IL & FS 11/2/2013
8HRW VFD Control Logic : Clear logic is to be defined for application of VFD with HRW
.ETA ASAP
9 ACS: ACS Not required for Telephone Closet HAIL / IL & FS Revision
B. Document Submission
1 Transfer Pumps : Technical Data with Control system to be submitted to HAIL by ETA ETA 8/2/2013
2 Fire Suppression System : The Tehnical Data to be submitted for PMC Approval ETA 8/2/2013
3BTU Meter :Modbus Detail to be submitted to HAIL by ETA . HAIL to confirm
acceptance .ETA/HAIL Immediate
4 400 Dia BTU Meter: HAIL to revert on Availibility Or its substitute HAIL Immediate
5MEP Coordinated Drawing : Revised MEP Coordinated Drawing to be submitted by
ETA to HAILETA Immediate
6 LIFT DATA: ANC to provide LIFT Data to HAIL ANC Immediate
C. Approvals
1Revised BOQ:HAIL to prepare Revised BOQ based of final Engineering & get it
approved by Mr Vinay and submit the same to ANCHAIL 11/2/2013
2
Revised Data Sheet : HAIL to Submit & Get Approval for revised Data Sheet by Mr
Vinay. However Mr Vinay has permitted the Use of Black / Gray / White color ofcables for PAS .
HAIL 11/2/3013
3Cause & Effect Logic : HAIL to get the Approval on Cause & Effect Logic by Mr
Mahapatra.HAIL 11/2/2013
4 I/O Summary: Revised I/O Summary to be submitted for Approval by Mr Vinay HAIL 11/2/2013
Minutes of Meeting
Page
Print to PDFwithout this message by purchasing novaPDF (http://www.novapdf.com/)
http://www.novapdf.com/http://www.novapdf.com/http://www.novapdf.com/http://www.novapdf.com/