  • 8/13/2019 MOM ELV Coordination

    1/1

    Date: 6/2/2013

    Subject : ELV -MEP Coordination Meeting Venue : Project Office

    Attend

    ees:Time: 11 a.m.

    IL & FS Parvez , Vinay

    ANC: Azib Hussain,

    ETA: Sukhwan , Rahul, Bhavesh

    HAIL Chaitanya , Rajendra , Sameer , Praveen , Rajesh

    Sr. No. Items discussed Action By Target Date

    A. DESIGN:

    1Tenant AHU (16th floor and above):Four AHUs are considered for Two office lay out

    in four separate AHU rooms. HAIL to update its design accordinglyETA/ HAIL 11/2/2013

    2System Architecture:HAIL to submit revised system Architecture to Mr Vinay for

    ApprovalHAIL 11/2/2013

    3Shop Drwings : Prep are & Submit Shop Drawings for complete Floors & System Base

    on Revised System ArchitectureHAIL 20/2/2013

    4Flap Barrier : The BOQ item will remain unchanged . Final decision will be given by IL

    & FsIL & FS ASAP

    5 PA Console : THAIL will keep Provision for two PA Cnsole on one reception HAIL Revision

    6 Stair Case Smoke Detector : Provision of Smoke Detector in Stair Case is Deleted . HAIL/ IL & FS Revision

    7Lift Lobby Presurisation : Application of Presssure sensor has to be defined &

    Discussed with client for further site implication.HAIL/ IL & FS 11/2/2013

    8HRW VFD Control Logic : Clear logic is to be defined for application of VFD with HRW

    .ETA ASAP

    9 ACS: ACS Not required for Telephone Closet HAIL / IL & FS Revision

    B. Document Submission

    1 Transfer Pumps : Technical Data with Control system to be submitted to HAIL by ETA ETA 8/2/2013

    2 Fire Suppression System : The Tehnical Data to be submitted for PMC Approval ETA 8/2/2013

    3BTU Meter :Modbus Detail to be submitted to HAIL by ETA . HAIL to confirm

    acceptance .ETA/HAIL Immediate

    4 400 Dia BTU Meter: HAIL to revert on Availibility Or its substitute HAIL Immediate

    5MEP Coordinated Drawing : Revised MEP Coordinated Drawing to be submitted by

    ETA to HAILETA Immediate

    6 LIFT DATA: ANC to provide LIFT Data to HAIL ANC Immediate

    C. Approvals

    1Revised BOQ:HAIL to prepare Revised BOQ based of final Engineering & get it

    approved by Mr Vinay and submit the same to ANCHAIL 11/2/2013

    2

    Revised Data Sheet : HAIL to Submit & Get Approval for revised Data Sheet by Mr

    Vinay. However Mr Vinay has permitted the Use of Black / Gray / White color ofcables for PAS .

    HAIL 11/2/3013

    3Cause & Effect Logic : HAIL to get the Approval on Cause & Effect Logic by Mr

    Mahapatra.HAIL 11/2/2013

    4 I/O Summary: Revised I/O Summary to be submitted for Approval by Mr Vinay HAIL 11/2/2013

    Minutes of Meeting