monitor & control processes in the integration management 1 mec-6
TRANSCRIPT
![Page 1: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/1.jpg)
Monitor & Control Processesin the
Integration Management
1
MEC-6
![Page 2: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/2.jpg)
Agenda
2
Monitor & Control Project Work Perform Integrated Change Control
![Page 3: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/3.jpg)
Monitor & Control Project Work - Inputs & Outputs
3
Monitor & Control Project Work
1. PMP 2. WPI3. OPA
1. WPR2. Change Requests3. PMP Updates4. PD Updates5. OPA Updates
4. Schedule Forecast5. Cost Forecast6. Validated Changes7. EEF
![Page 4: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/4.jpg)
Monitor & Control Project Work Inputs – 1/5
4
Input Details
Project Management Plan
• Communications management plan• Cost baseline• Cost management plan• Human resource management plan• Process improvement plan• Procurement management plan• Scope baseline• Quality management plan• Requirements management plan• Risk management plan• Schedule baseline• Schedule management plan• Scope management plan• Stakeholder management plan
![Page 5: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/5.jpg)
Monitor & Control Project Work Inputs – 2/5
5
Input Details
Schedule Forecast (from Control Schedule)
• Derived from progress against the schedule baseline and expressed in terms of schedule variance (SV) and schedule performance index (SPI)
• Forecasted Project Completion Date derived from Planned Project Duration and SPI
• The forecast may be used to determine if the project is still within defined tolerance ranges and identify any necessary change requests.
Cost Forecast (from Control Cost)
• Derived from progress against the cost baseline and computed estimates to complete (ETC), expressed in terms of cost variance (CV) and cost performance index (CPI)
• Estimate at completion (EAC) can be compared to the Budget at completion (BAC) to see if the project is still within tolerance ranges or if a change request is required
• Forecast also ascertained through ETC and TCPI
![Page 6: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/6.jpg)
Monitor & Control Project Work Inputs – 3/5
6
Input Details
Validated Changes
• Approved changes that result from the Perform Integrated Change Control process require Validation to ensure that the change was appropriately implemented
• A validated change provides the necessary data to confirm that the change was appropriately executed
WPI • WPI is the WPD collected from various controlling processes, analyzed in context, and integrated based on relationships across areas. Thus WPD data is transformed into WPI
• WPD in itself cannot be used in the decision-making process as it has only out-of-context meaning. Work performance information, however, is correlated and contextualized, and provides a sound foundation for project decisions
• WPI is circulated through communication processes• Examples: Status of deliverables, implementation status for
change requests, and forecasted estimates to complete
![Page 7: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/7.jpg)
Monitor & Control Project Work Inputs – 4/5
7
Input Details
EEF • Governmental or industry standards (e.g., regulatory agency regulations, codes of conduct, product standards, quality standards, and workmanship standards)
• Organization work authorization systems• Stakeholder risk tolerances• Project Management Information System (e.g., an automated tool
suite, such as a scheduling software tool, a configuration management system, an information collection and distribution system, or web interfaces to other online automated systems).
![Page 8: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/8.jpg)
Monitor & Control Project Work Inputs – 5/5
8
Input Details
OPA • Organisational communication requirements• Financial controls procedures (e.g., time reporting, required
expenditure and disbursement reviews, accounting codes, and standard contract provisions)
• Issue and defect management procedures defining issue and defect controls, issue and defect identification, and resolution and action item tracking
• Change control procedures, including those for scope, schedule, cost, and quality variances
• Risk control procedures including risk categories, probability definition and impact, and probability and impact matrix
• Process measurement database used to make available measurement data on processes and products
• Lessons learned database
![Page 9: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/9.jpg)
Monitor & Control Project Work Outputs … 1/3
9
Output Details
Change Requests
• Variances from comparing planned results to actual results• Change Requests expand, adjust, or reduce Project Scope, Product
Scope, or Quality Requirements and Schedule or Cost Baselines• Change Requests may necessitate the collection and documentation
of new requirements• Change Requests can impact the project management plan, project
documents, or product deliverables• Changes that meet the project’s change control criteria should go
through the integrated change control process established for the project
• Changes may include:- Corrective action—An intentional activity that realigns the
performance of the project work with the Proj Management Plan- Preventive action—An intentional activity that ensures the future
performance of the project work is aligned with the Project Management Plan
- Defect Repair—an intentional activity to modify a nonconforming product or product component
![Page 10: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/10.jpg)
Monitor & Control Project Work Outputs … 2/3
10
WPR • WPR are the physical or electronic representation of WPI compiled in project documents, intended to generate decisions, actions, or awareness
• Project information may be communicated verbally from person to person. However, in order to record, store, and sometimes distribute WPI, a physical or electronic representation in the form of project documents is required
• WPR are a subset of project documents, which are intended to create awareness and generate decisions or actions
• Specific work performance metrics may be defined at the start of the project and included in the normal WPR provided to key stakeholders
• Examples: status reports, memos, justifications, information notes, recommendations, and updates
PMP/PD Updates
![Page 11: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/11.jpg)
Monitor & Control Proj Work – Tools & Techniques … 1/2
11
Tools & Techs Details
Expert Judgement
To interpret the information provided by the monitor and control processes, or to resolve any situation emerging from the M&C process, expert judgement from professionals in the industry may be sought
Project Management Information System
Provides access to automated tools, such as scheduling, cost, and resourcing tools, performance indicators, databases, project records, and financials used during the Monitor and Control Project Work process.
Meetings • May include project team members, stakeholders, and others involved in or affected by the project
• Types: User groups, Review Meetings, Focal Groups etc
![Page 12: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/12.jpg)
Monitor & Control Proj Work – Tools & Techniques … 2/2
12
Tools & Techs Details
Analytical Techniques
To forecast potential outcomes based on possiblevariations of project or environmental variables and their relationships with other variables:• Regression analysis• Grouping methods• Causal analysis• Root cause analysis• Forecasting methods (e.g., time series, scenario building,
simulation, etc.)• Failure mode and effect analysis (FMEA)• Fault tree analysis (FTA)• Reserve analysis• Trend analysis• Earned value management (EVM)• Variance analysis
![Page 13: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/13.jpg)
M&C PW – Tools & Techniques - Grouping
13
• Grouping methods• Causal analysis• Root cause analysis• Failure Mode & Effect Analysis (FMEA)• Fault Tree Analysis (FTA)
• Regression Analysis• Forecasting methods• Trend analysis• Earned Value Management• Variance Analysis
• Reserve analysis
Root Cause Analysis
Trend Analysis, Smoothing, Forecasting
Risk Analysis
![Page 14: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/14.jpg)
Grouping Methods
14
Grouping methods are techniques for classifying observations into meaningful categories
Example Defects on a deliverable, say a generator. Grouping by:
By basic engineering: Mechanical, Electrical, Chemical (battery) etc
By Deliverable area: Engine, Generator, Controls, Battery etc
By Load Conditions: Over, Heavy, Medium, Low, Under
![Page 15: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/15.jpg)
Route Cause Analysis (RCA) & Causal Analysis
15
A specific technique used to identify a problem, discover the underlying causes that lead to it, and develop preventive action
The root cause, once removed from the problem fault sequence, prevents the final undesirable event from recurring
Methods:- Cause-and-effect diagrams/fishbone diagrams/Ishikawa
diagrams- The 5 Ws (Whys)- FMEA- FTA- Pareto etc
![Page 16: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/16.jpg)
RCA – Cause & Effect Diagram• Project: Improving the Quality of a University's MBA3.5 (3.5 yrs) Programme• 1st Objective: Root cause the reason for low quality of MBA(3.5 yrs) graduates
16
Weak Inter-Personal Skills
Low Quality Product in MBA (3.5 yrs)
Educational Background
Personality
Extent of Business Education
Other Reasons
Weak FA/FSc
Weak BA/BSc/BCom
BA/BSc/BCom from Low-Key Institutes
BA/BSc in Low-Key subjects
Weak English
3.5 yrs vis-à-vis 5.5/6.5 others
Late StartRelatively
Early Finish
Roadmap unextenable
Time & Cost Fixed
Years since FA/FSc/A-Lvl0 1 2 3 4 5 6 7 8 9
BBA4/Masters MBA 2.5 BBA 4 MBA 1.5
BA/BSc/BCom MBA 3.5
![Page 17: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/17.jpg)
RCA – Cause & Effect Diagram leading to Pareto Analysis
17
Root Causes Count
1 Weak FA/FSc 90
2 Weak BA/BSc/BCom 18
3 BA/BSc/BCom from low-key institutes 7
4 BA/BSc/BCom in low-key subjects 15
5 Weak Inter-Personal Skills 97
6 Weak English 95
7 MBA3.5 roadmap unextendable 12
8 3.5 yrs vis-à-vis 5.5/6.5 others 88
9 Late start 12
10 Relatively early finish 15
11 Time & Cost fixed 10
Count %age Cum %age
5 97 21.1% 21.1%
6 95 20.7% 41.8%
1 90 19.6% 61.4%
8 88 19.2% 80.6%
2 18 3.9% 84.5%
4 15 3.3% 87.8%
10 15 3.3% 91.1%
7 12 2.6% 93.7%
9 12 2.6% 96.3%
11 10 2.2% 98.5%
3 7 1.5% 100.0%
The possible root causes ascertained from the Cause & Effect diagram could next could be short-listed through further RCA. Say a sample of 100 MBA(3.5yrs) students was surveyed which returned the following data which could then be subjected to Pareto analysis to identify those root-causes which would be responsible for 80% of the problem.
Raw Survey Data Pareto Tabulation
![Page 18: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/18.jpg)
RCA – Cause & Effect Diagram leading to Pareto Analysis
18
0
20
40
60
80
100
120
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
![Page 19: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/19.jpg)
RCA – the 5 Whys• Problem: Excavator, an important source on the project, not starting
1st Why Why is the excavator not starting?Flat battery
2nd Why Why Flat battery? Alternator not working
3rd Why Why Alternator not working? Drive belt from the engine broken
4th Why Why Drive belt broken? Poor maintenance
19
Part Not Available5th Why Why Part Not Available?
Old excavator
![Page 20: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/20.jpg)
Failure Mode & Effect Analysis (FMEA)
20
Each potential failure Mode in every component of a product is analyzed to determine its effect on the reliability of that component and, by itself or in combination with other possible failure modes, on the reliability and function of the deliverable, product or system
Primarily a Design/Planning Tool; also used for Monitoring & Control where it provides a basis for identifying Root Failure Causes and developing effective Corrective Actions
![Page 21: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/21.jpg)
FMEA - Application
21
Monitoring & Control: Track changes to process-incorporated to avoid potential failures
![Page 22: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/22.jpg)
FMEA22
• Project: New Fuel-Efficient, Composite Material Commercial Plane (Boeing 787 Dreamliner)
• Deliverable: Lithium Ion Batteries
Product/Deliverable: Lithium Ion BatterySystem: ElectricalSub-System: Back-Up PowerPart No: xxxx-xxxx-xxxx
FMEA Team: ABC (Chief Designer) DEF (Head of Elect Dept) GHI (Battery Specialist) IJK (Configuration Manager)
Page No: 7 of 104FMEA No. 1234Date: 7 Nov 2010
Function Potential Failure Mode
Potential Effect(s) of Failure
Severity (S)
Potential Causes of Failure
Occurrence (O)
Current Controls/ Tests
Detection (D)
Recommend-ed Actions
RPN
Provide back-up power to aircraft instrumentation
Overheating/Meltdown
- Toxic Fumes in cabin
- Explosion in battery compt
- Fire
10 Short-circuiting in Fuel Cells
2 (Test No) 10 Redesign 200
Recharging Malfunction
3 (Test No) 10 Check Elect Charging Sys
300
Unbalanced Chemical Reaction
2 (Test No) 10 Redesign 200
Battery Compt AC failure
3 (Test No) 1 Check AC system
30
![Page 23: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/23.jpg)
FMEA
23
• Project: New Fuel-Efficient, Composite Material Commercial Plane (Boeing 787 Dreamliner)
• Deliverable: Lithium Ion Batteries• Problem: Over-heating & melt-down
- Battery Compartment
![Page 24: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/24.jpg)
Fault Tree Analysis (FTA)
24
A top-down, Deductive failure analysis in which an undesired state of a system is analysed using Boolean logic to combine a series of lower-level events
Helps monitor and control Project Processes and Deliverables Scope
Functions as a diagnostic tool to identify and correct causes of Process failing or a Deliverable not meeting the Scope either in specifications or performance parameters
![Page 25: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/25.jpg)
Fault Tree Analysis• Project: New Commercial Plane• Deliverable: Evacuation Chute• Problem: Failure of Auto-Deployment
25
![Page 26: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/26.jpg)
Fault Tree Analysis• Project: New Commercial Plane• Deliverable: Evacuation Chute• Problem: Failure of Auto-Deployment
26
Auto- Deployment
Failure
Mech Failure
Power Failure
Missing Part
Gen Fault
Faulty Wiring
Faulty Signal
Signal Failure
Part Failure
Lub Failure
Missing Signal
Tx Fault Faulty Wiring
Rx Fault
Servo Failure
Part Failure
1 2
3
4 5 6 7 8 9
![Page 27: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/27.jpg)
Quantitative Forecasting
27
Quantitative Forecasting
Causal Forecasting
Time Series Forecasting
Auto Regression
Moving Average
Exponential Smoothing
Trend Models
![Page 28: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/28.jpg)
Moving Average … 1/3
• Moving Average (Rolling Average or Running Average) is a calculation to analyse data points by creating a series of averages of different subsets of the full data set
• Variations include: Simple, Weighted, Centred, Exponential etc
• Moving Average is used to overcome irregular, random, seasonal or cyclic variations
• Overcoming variations is called "smoothing“
• Moving Average is a smoothing process
• Smoothing by Moving Average is done by taking average of three (or more) recent observations, then dropping the first observation and advancing to the next one, and continuing the process till getting to the period/unit for which forecast is required
28
![Page 29: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/29.jpg)
Moving Average … 2/3
• Each new data point is included in the average as it becomes available, and the oldest data point is discarded
• The number of observations averaged is referred to as the “k” number; the constant number k is specified at the outset
• The smaller the number k, the more weight is given to recent periods; the greater the number k, the less weight is given to recent periods
• A large k is desirable when there are wide, infrequent fluctuations in the series.
• A small k is most desirable when there are sudden shifts in the level of series
• For quarterly data, a four-quarter moving average, MA(4), eliminates or averages out seasonal effects
29
![Page 30: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/30.jpg)
Moving Average … 3/3
• For monthly data, a 12-month moving average, MA(12), eliminate or averages out seasonal effect
• Equal weights are assigned to each observation used in the average
30
![Page 31: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/31.jpg)
Forecasting Variations
31
Trend Long-term movement in dataIrregular variations Caused by unusual circumstancesRandom variations Caused by chance
Trend
Irregularvariation
Cycle Wave-like variations lasting more than one year
Cycle
Seasonal Variations
Seasonality Short-term Regular variations in data
![Page 32: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/32.jpg)
Simple Moving Average (SMA) – Understanding the Basic Concepts
32
Simple and Moving Averages can be used to forecast and smoothen data.
Example: On a multi-housing project, the time of completion of the first 10 houses (H1 to H10) is indicated in the tables, headed Case A and Case B. What can be the forecasted duration of House # 11 (H11) in each case?
House #
Duration to Complete
1 2602 2453 2554 2465 2546 2437 2538 2429 254
10 24811 ?
Case AHouse
#Duration to Complete
1 2502 2803 2304 2205 2606 2507 2608 2309 220
10 24011 ?
Case B
![Page 33: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/33.jpg)
SMA – Understanding the Basic Concepts
33
H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11220
225
230
235
240
245
250
255
260
265260
245
255
246
254
243
253
242
254
248
Forecasted Duration of H11Mean 250.0 Fixed AverageMean (minus 1st) 248.9 (the 1st House it took longer)Mean (last 3) 248.0 Moving Average at k = 3Mean (last 4) 249.3 Moving Average at k = 4Mean (last 5) 248.0 Moving Average at k = 5
House #
Duration to Complete
1 2602 2453 2554 2465 2546 2437 2538 2429 254
10 24811 ?
Case A
![Page 34: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/34.jpg)
SMA – Understanding the Basic Concepts
34
House #
Duration to Complete
1 2612 2573 2604 2535 2566 2457 2478 2409 242
10 23911 ?
Case B
H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11220
225
230
235
240
245
250
255
260
265261
257
260
253256
245
247
240
242239
f(x) = − 2.61818181818182 x + 264.4
Forecasted Duration of H11
Mean 250.0 Fixed AverageMean (minus 1st three) 246.0 (first three houses took longer)Mean (last 3) 240.3 Moving Average at k = 3Mean (last 4) 242.0 Moving Average at k = 4Mean (last 5) 242.6 Moving Average at k = 5Using Trend Line 235.6 (trend line considers all data)
![Page 35: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/35.jpg)
SMA – How to work out
35
House #
Duration to Complete
(a)
1 2602 2453 2554 2465 2546 2437 2538 2429 254
10 24811
Case ASMA(k=3)
(b)
253.3
248.7
251.7
247.7
250.0
246.0
249.7
248.0
SMA(k=4)
(c)
251.5
250.0
249.5
249.0
248.0
248.0
249.3
Error Squared (k=3)
Error Squared (k=4)
(a-b)2 (a-c)2
53.8
28.4 6.3
75.1 49.0
28.4 12.3
64.0 49.0
64.0 36.0
2.8 0.0
6.7 5.0
-(a-b)2/n -(a-c)2/nMean Square Error
![Page 36: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/36.jpg)
SMA – Graphical Representation
36H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11
235
240
245
250
255
260
265
260
245
255
246
254
243
253
242
254
248 248
249.25
Actual Durations SMA (k=3) SMA (k=4)
H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11220225230235240245250255260265260
245
255
246
254
243
253
242
254
248Case A
![Page 37: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/37.jpg)
Weighted Moving Average (WMA)
• WMA is used when it is required to give different weightage to different data. For example it may be required to give more weightage to recent data
• Example: In the original multi-housing project example (Case A), it is required to forecast the duration of the 11th house by giving 1/2 weightage to the most recent house duration, 1/3 to the middle duration and 1/6 to the earliest.
37
8 2409 245
10 25311 Forecast = 240/6 + 245x1/3 + 253x1/2 = 248.2
![Page 38: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/38.jpg)
Centred Moving Average (CMA)
• CMA is used for a number of situations particularly when there is a seasonal component, or when there is a requirement to use the past data
• CMA can be computed, using data equally spaced on either side of the point in the series where the mean is calculated
• When k is even, “smoothing of smoothing” is done
38
![Page 39: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/39.jpg)
House #
Duration to Complete
SMA(k=3)
CMA(k=3)
CMA Error Squared (k=3)
(a) (b) (c) (a-c)2
1 2602 245 253.3 69.43 255 248.7 40.14 246 253.3 251.7 32.15 254 248.7 247.7 40.16 243 251.7 250.0 49.07 253 247.7 246.0 49.08 242 250.0 249.7 58.89 254 246.0 248.0 36.0
10 248 249.711 248.0
Mean Square Error (MSE) 6.6
-(a-c)2/n
CMA
39
k odd (3) Data as per Case A
![Page 40: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/40.jpg)
CMA
40H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11
235
240
245
250
255
260
265
260
245
255
246
254
243
253
242
254
248 248
248.0
Actual Durations SMA (k=3) CMA (k=3)
Data as per Case A
![Page 41: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/41.jpg)
CMA
41
House #
Dur to Complete
SMA (k=4) CMA (k=4) CMA Error Sq (k=4)
(a) (c) (c) (a-c)2
1 2602 245
2.5 250.03 255 249.9 26.3
3.5 249.84 246 249.9 15.0
4.5 250.05 254 251.5 250.1 15.0
5.5 250.36 243 250.0 250.4 54.4
6.5 250.57 253 249.5 248.6 19.1
7.5 246.88 242 249.0 247.8 33.1
8.5 248.89 254 248.0
10 248 248.011 249.3
Mean Square Error (MSE) 5.2-(a-c)2/n
Data as per Case Ak even (4)
![Page 42: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/42.jpg)
CMA
42H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11
235
240
245
250
255
260
265
260
245
255
246
254
243
253
242
254
248249.25
247.75
Actual Durations SMA (k=4) CMA (k=4)
Data as per Case A
![Page 43: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/43.jpg)
Exponential Moving Average (EMA)
• EMA forecasts the value of next event based on:a. Actual Value of the previous itemb. Forecasted Value of the previous itemc. Weight assigned
• EMA weigh past observations using exponentially decreasing weights as the observations get older; recent observations are given relatively more weight than the older observations
• The amount of weight applied to the past observations, or the degree of smoothing required, is determined by the “smoothing constant”
• EMA is in contrast to the SMA. In SMA, the same weights (=1/n) are assigned to the observations. In EMA, there are one or more smoothing parameters to be determined (or estimated) and these choices determine the weights assigned to the observations
43
![Page 44: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/44.jpg)
EMA
• The exponential smoothing equation is:Fn+1 = - yn + (1- -)Fn
where Fn+1 = Forecast for the next unit (to be estimated)a = Smoothing constant, such 0 < - ≤ 1yn = Actual value of the most recent unit
Fn = Forecasted value of the most recent unit• Expanding the Equation:
Fn+1 = - yn + (1- -)Fn
= - (1- -)0yn + (1- -)
= -(1- -)0yn + -(1- -)yn-1 + (1- -)2Fn-1
= -(1- -)0yn + -(1- -)1yn-1 + (1- -)2Fn-1
= -(1- -)0yn + -(1- -)1yn-1 + -(1- -)2
= -(1- -)0yn + -(1- -)1yn-1 + -(1- -)2yn-2+ (1- -)3Fn-2
= -(1- -)0yn + -(1- -)1yn-1 + -(1- -)2yn-2+ -(1- -)3yn-3 ……… -(1- -)n-1F1
= -[(1- -)0yn + (1- -)1yn-1 + (1- -)2yn-2+ (1- -)3yn-3 ……… (1- -)n-1y1]
(F1 is taken as y1)
44
[- yn-1 + (1- -)Fn-1]
[- yn-2 + (1- -)Fn-2]
![Page 45: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/45.jpg)
EMA
45
Fn+1 = - Yn + (1- -)Fn
- Yn (1- -)0+ (1- -) 1Fn
(1- -) 1[-Yn-1 +(1- -)Fn-1]
-(1- -) 1Yn-1 +(1- -)2Fn-1
-(1- -) 1Yn-1 +(1- -)2Fn-1 -(1- -) 1Yn-1
+(1- -)2Fn-1
![Page 46: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/46.jpg)
EMA
• However, in application, EMA is a simple affair. All what is required to be done is:– Select a suitable smoothing constant (-)– Take the most recent observation (yn) and multiply it with the smoothing
constant
– Take what was the forecasted (Fn) value of the most recent observation/ event and multiply it with the complementary of the smoothing constant i.e (1- -)
– Add the two products; the sum is the forecasted value for the next unit
• If the forecasted value (Fn) of the recent most event is not available, then:– Start analysing the data from the start, or from where the last (Fn) is
available, by calculating Fn using the EMA equation
– Continue calculating Fn by applying the EMA equation until the forecasted value of the target event is available
46
![Page 47: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/47.jpg)
EMA47
# Actual Observation
(yn)
Forecasted Observation
(Fn, ,-=0.8)
1 260
2 245 260.0
3 255 248.0
246 253.6
254 247.5
243 252.7
253 244.9
n-2 242 251.4
n-1 254 243.9
n 248 252.0
n+1
# Actual Observation
(yn)
Forecasted Observation
(Fn,-=0.8)
1 260
2 245
3 255
246
254
243
253
n-2 242
n-1 254
n 248
n+1
- 260
260.0
248.0
253.6
247.5
252.7
244.9
251.4
243.9
252.0
248.8248.8
![Page 48: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/48.jpg)
EMA
• Large - (- - 1) would mean:– Maximum consideration to actual/historical data, little consideration to
previously forecasted data– Little smoothing of the data
• Small - (- - 0) would mean:– Little consideration to actual/historical data, maximum consideration to
previously forecasted data– Maximum smoothing of the data
48
![Page 49: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/49.jpg)
EMA – Example (original Case A)
• Consider the data for the original Case A• yn & Fn for various values of - are tabulated:
49
H # Duration to Complete (yn)
1 260 2 2453 2554 2465 2546 2437 2538 2429 254
10 24811
Forecasted Duration (Fn)
- = 1 - = 0.8 - = 0.6 - = 0.5 - = 0.4 - = 0.2 - = 0.1 - = 0.0
260.0 260.0 260.0 260.0 260.0 260.0 260.0 260.0
260.0 260.0 260.0 260.0 260.0 260.0 260.0 260.0
245.0 248.0 251.0 252.5 254.0 257.0 258.5 260.0
255.0 253.6 253.4 253.8 254.4 256.6 258.2 260.0
246.0 247.5 249.0 249.9 251.0 254.5 256.9 260.0
254.0 252.7 252.0 251.9 252.2 254.4 256.6 260.0
243.0 244.9 246.6 247.5 248.5 252.1 255.3 260.0
253.0 251.4 250.4 250.2 250.3 252.3 255.0 260.0
242.0 243.9 245.4 246.1 247.0 250.2 253.7 260.0
254.0 252.0 250.5 250.1 249.8 251.0 253.8 260.0
248.0 248.8 249.0 249.0 249.1 250.4 253.2 260.0
-
![Page 50: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/50.jpg)
EMA – Example (original Case A)50
H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11238
240
242
244
246
248
250
252
254
256
258
260
262
248248.0248.8249.1250.4
253.2
260.0
Yn Fn @ α=1.0 Fn @ α=0.8Fn @ α=0.6 Fn @ α=0.5 Fn @ α=0.4Fn @ α=0.2 Fn @ α=0.1 Fn @ α=0.0
![Page 51: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/51.jpg)
EMA – Example (original Case B)
• Consider the data for the original Case B• yn & Fn for various values of - are tabulated:
51
H # Duration to Complete (yn)
1 2612 2573 2604 2535 2566 2457 2478 2409 242
10 23911
Forecasted Duration (Fn)
- = 1 - = 0.8 - = 0.6 - = 0.5 - = 0.4 - = 0.2 - = 0.1 - = 0.0
261.0 261.0 261.0 261.0 261.0 261.0 261.0 261.0
261.0 261.0 261.0 261.0 261.0 261.0 261.0 261.0
257.0 257.8 258.6 259.0 259.4 260.2 260.6 261.0
260.0 259.6 259.4 259.5 259.6 260.2 260.5 261.0
253.0 254.3 255.6 256.3 257.0 258.7 259.8 261.0
256.0 255.7 255.8 256.1 256.6 258.2 259.4 261.0
245.0 247.1 249.3 250.6 252.0 255.5 258.0 261.0
247.0 247.0 247.9 248.8 250.0 253.8 256.9 261.0
240.0 241.4 243.2 244.4 246.0 251.1 255.2 261.0
242.0 241.9 242.5 243.2 244.4 249.3 253.9 261.0
239.0 239.6 240.4 241.1 242.2 247.2 252.4 261.0
-
![Page 52: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/52.jpg)
EMA – Example (original Case B)52
H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11238
240
242
244
246
248
250
252
254
256
258
260
262
239 239.0239.6240.4241.1242.2
247.2
252.4
261.0
Yn Fn @ α=1.0
Fn @ α=0.8 Fn @ α=0.6
Fn @ α=0.5 Fn @ α=0.4
Fn @ α=0.2 Fn @ α=0.1
Fn @ α=0.0
![Page 53: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/53.jpg)
EMA – Example (original Case A)53
T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12 T1360
62
64
66
68
70
72
74
76
78
80
Yn Fn @ α=1.0Fn @ α=0.8 Fn @ α=0.6Fn @ α=0.5 Fn @ α=0.4Fn @ α=0.2 Fn @ α=0.1
![Page 54: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/54.jpg)
Correlation & Regression
Correlation is a statistical method used to determine whether a linear relationship between variables existsRegression is a statistical method used to describe the nature of the relationship between variables, that is, positive or negative, linear or nonlinear
• Together, Correlation & Regression address these questions statistically:1. Are two or more variables linearly related?2. If so, what is the strength of the relationship?3. What type of relationship exists?4. What kind of predictions can be made from the relationship?
54
![Page 55: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/55.jpg)
Equation of a Straight Line
y = a + bx
where
x = value of independent variable, on the x-axis
y = value of dependent variable, on the y-axis
a = intercept on the y-axis; fixed cost, quantity etc
b = slope of the line; ratio of differential in y-values to corresponding differential in x-values
55
-2 -1 0 1 2 3 4 5
-2
-1
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
f(x) = 2 x + 3
Intercept on Y-axis (= 3 = a)
y-di
ffere
ntial
(=8)
x-differential (=4)
Slope = = = y-diff 8x-diff 4 2 = b
![Page 56: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/56.jpg)
Correlation & Regression - Example
• The amount of cement consumed on a multi-housing project is a function of the covered area of the house
• Independent Variable (x) - Covered Area (deca square meters)Dependent Variable (y) - Cement consumed (deca bags)
• Data as follows:
• Work out the Regression Line and the Correlation Coefficient (R)
56
x
10
12
6
15
8
5
y
30
32
25
46
29
19
![Page 57: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/57.jpg)
Correlation & Regression - Example57
x
10
12
6
15
8
5
y
30
32
25
46
29
19
xy
300
384
150
690
232
95
x2
100
144
36
225
64
25
y2
900
1,024
625
2,116
841
361 - 56 181 1,851 594 5,867
= 6x1,851 – 56x181 = 0.95 -(6x594-562) (6x5,5867-1812)
R
= 181x594 – 56x 1,851 = 9.01 6x56-594
= 6x1,851 – 56x181 = 2.27 6x594-562
y = 2.27x + 9.014
![Page 58: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/58.jpg)
Correlation & Regression - Example
58
4 5 6 7 8 9 10 11 12 13 14 15 16 17 1815
20
25
30
35
40
45
50
Covered Area (sq meter x 10 )
Cem
ent B
ags
(x10
)
y = 2.27x + 9.014R = 0.95
![Page 59: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/59.jpg)
Correlation & Regression
59
![Page 60: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/60.jpg)
Finding the Regression Line Equation & the “R”
60
R
![Page 61: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/61.jpg)
How to Work out “R” & Regression Equation
• Manually (like we did)
• Scientific Calculator
• Trend line on Chart
• Excel Sheet, manually with formula
• Excel Sheet, using SLOPE and INTERCEPT commands
• Excel Sheet, using Data Analysis Feature
• Softwares, eg Minitab
61
![Page 62: Monitor & Control Processes in the Integration Management 1 MEC-6](https://reader035.vdocument.in/reader035/viewer/2022062518/56649f505503460f94c73687/html5/thumbnails/62.jpg)
62