Monitoring report of Progress in special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.12

Sl No. Department District Name of the Scheme

Amount Sanctioned

(Rs. in crore) (approx)

Status

Construction of 15 Girls Hostel (50 seated) for Secondary/H.S. Schools

14.40

Construction of 7 new School Building & Hostel for LWE affected area

71.48

Purulia

Construction of 1 PTTI as per NCTE Norms

5.68

Construction of 50 Girls Hostel (50 seated) for Secondary/H.S. Schools

47.99

Construction of 10 new School Building & Hostel for LWE affected area

102.12

Paschim Medinipur

Construction of 1 PTTI as per NCTE Norms

5.68

Construction of 15 Girls Hostel (50 seated) for Secondary/H.S. Schools

14.40

Construction of 6 new School Building & Hostel for LWE affected area

61.27

1.

School

Education

Bankura

Construction of 1 PTTI as per NCTE Norms

5.68

1. In Purulia, work order has been issued for 15 girls hostels being implemented by HRBC. 2. In Purulia, work order has been issued for 3 school building-cum-hostels being implemented by HRBC and 4 by PWD (CB). ------------------------------------------------------------------ 3. In Paschim Medinipur, Out of 50 girls hostels, re-tendering will be done for 20 girls hostels being implemented by HRBC. Work order will be issued on 31.10.2012 if necessary responses received. For 30 girls hostels, being implemented by PWD (CB) 13 work orders have been issued and 14 were under process for re-tendering. 4. In Paschim Medinipur, Out of 10 school building cum hostels, 4 school building & hostels being implemented by HRBC for which tender process will be completed by 31.10.2012. For 6 cases, being done by PWD (CB) re-tendering will be done by 31.10.2012. ------------------------------------------------------------------ 5. In Bankura, 5 girls hostels being implemented by HRBC of which work order issued for 2 hostels. Out of 10 implemented by PWD (CB) 7 work orders have been issued. 6. In Bankura, 5 school building cum hostels being implemented by HRBC. HRBC informed that the 5 school buildings would be completed within 18 months and re-tendering will be done by HRBC by 17.10.2012. For the 1 being done by PWD (CB) re-tendering will be done by 19.10.12

Page 2: Monitoring report of Progress in special plan under ...wbplan.gov.in/docs/BRGF/BRGF-Jungle Maha31.10.12l-update.pdf · Construction of 1 PTTI as per NCTE Norms will be completed by

Monitoring report of Progress in special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.12

Sl No. Department District Name of the Scheme

Amount Sanctioned

(Rs. in crore)(approx)

Status

Improvement of Village Roads on Canal embankment P.S. Lalgarh & Salbani

0.23

Construction of double lane RCC bridge over Kangsabati

50.45

Construction of RCC bridge over Dokhalikhal mouza-kharika to eral

1.66

Improvement to the inspection path over right bank of river Chandia from Barisa to Ranichak

0.24

Construction of RCC bridge at Markandachak over Amrakhali

1.78

Construction of RCC bridge at Mohanbazar over Kalimondop Khal

1.63

Construction of RCC bridge at Shyamsundarpur over Ganpatkhal

1.68

Construction of double lane RCC bridge at Mohinibazar

6.66

Construction of double lane RCC bridge at Baus over Kaplaswari river

8.24

Paschim

Medinipur

Raising & Strengthening alongwith construction of Moorum road at Teihi

5.97

Improvement of strengthening of Roads over crest of Kangsabati and Kumari Dam

2.08

Improvement of Village Road on canal embankment in P.S. - Bishnupur, Kotulpur & Joypur

0.99

2.

Irrigation and Waterways

Bankura

Improvement of Village Road on canal embankment in P.S. - Onda, Taldangra & IndpurTaldangra & Indpur

0.99

1) The improvement of village roads on canal embankment at Lalgarh and Salboni were almost complete.

2) The ANM Building would be shifted as required for the approach road of the proposed Amkola bridge over river Kangsabati. The executing engineer, Midnapore Divn. (PWD) alongwith Irrigation officials held a meeting and the location of the proposed building and also alignment of the approach road have been finalized.

3) Work order issued for morrum road at Teihi. I&W Deptt.will immediately give the land trans proposal to L&LR Deptt.

4) Tender under process for road over Kansabati and Kumari Dam

5) Work order issued for village road in Bishnupur-Kotulpur-Jaipur and at Onda-Taldangra-Indpur.

6) Tender was under process for RCC bridge at Dokhalikhal.

7) Improvement of inspection path has been completed. 8) Work order are due for construction of RCC bridge at

Markandachak, Mohan bazaar, Samsundarpur, MOhini Bazar and Baus.

9) Tender was under process for road over crest of Kangsabati. 10) Work order have been issued for village road in Bishnupur, Kotulpur & Joypur.

Page 3: Monitoring report of Progress in special plan under ...wbplan.gov.in/docs/BRGF/BRGF-Jungle Maha31.10.12l-update.pdf · Construction of 1 PTTI as per NCTE Norms will be completed by

Scheme-wise details for special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.12

Sl No. Department District Name of the Scheme

Amount Sanctioned

(Rs. in crore)(approx)

Status

Purulia Rural housing under BRGF 11.93 Paschim

Medinipur Rural housing under BRGF 17.56

3.

Panchayat &

Rural Development

Bankura Rural housing under BRGF 20.26

1. 10258 dwelling units would be constructed of which 3620 would be in Paschim Medinipur, 4178 would be in Purulia and 2460 would be in Bankura. The beneficiary selection was being done by Dist.Magistrate.

Purulia Infrastructure for Household Electrification under special BRGF

153.91

Paschim Medinipur

Infrastructure for Household Electrification under special BRGF

329.24

4.

Power and NES

Bankura Infrastructure for Household Electrification under special BRGF

158.60

1. Work orders have been issued to the turnkey contractors for 4 packages (2 in Paschim Medinipur, 1 in Bankura and 1 in Purulia 2. Works to be completed by June, 2014

Project for construction of Rural Haat 3.00 Purulia

Natural Fibre Mission - Rural Livelihood Generation Programme

17.74

Project for construction of Rural Haat 3.00 Paschim

Medinipur Natural Fibre Mission - Rural Livelihood Generation Programme

60.86

5.

Micro & Small Scale

Enterprises & Textiles

Bankura

Natural Fibre Mission - Rural Livelihood Generation Programme

17.74

1. Proposal for land transfer for rural haats submitted my M & SSE to L & LR for approval. Tender will be called soon by PWD. 2. C & FC Centre to be finalized by M& SSE in consultation with C&I Deptt.

New pipe & Water Supply Scheme (Phase-I) in: Hirbandh, Khatra, Raniganj 179.47 Simlipal 51.21 Sarenga 39.63

6. Public Health Engineering

Bankura

Raipur 59.37

1. Work order will be issued by 31.10.12 for Hirbandh,Khatra and Ranigunj. 2. Re-tendering has been done for Simlipal. 3. E-tendering will be uploaded for Sarenga and Raipur by 7.11.12. TSC cleared within 30.9.12 and work would start by 15.10.12. 2. Land transfer proposal submitted by PHE Department to L & LR Deptt.

Page 4: Monitoring report of Progress in special plan under ...wbplan.gov.in/docs/BRGF/BRGF-Jungle Maha31.10.12l-update.pdf · Construction of 1 PTTI as per NCTE Norms will be completed by

Monitoring report of Progress in special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.12

Sl No.

Department District Name of the Scheme Amount Sanctioned

(Rs. in crore)(approx)

Status

Purulia Construction of super speciality Hospital at Deben Mahato Sadar

52.00 (approx.)

Paschim Medinipur

Construction of super speciality Hospital at Salboni and Debra

26.00 (approx.) each

7.

Health and

Family Welfare

Bankura Construction of super speciality Hospital at Onda and Chhatna

26.00 (approx.) each

1.Technical bids for appointment of Lead Consultant for construction of multi-speciality hospitals opened on 07.08.2012. Evaluation under process. 2. A proposal for change of site at Onda being reviewed.

8. Technical Education &

Training

Paschim Medinipur

Establishment of 1 Skill Development Centre in Medinipur Sadar

Work order has been issued and work started.

Paschim Medinipur

Construction of 409 BPL houses 0.1845

Bankua Construction of 190 BPL houses 0.086

9. Minority

Affairs and M.E.

Purulia Construction of 147 BPL houses

0.062

Work commenced but date of completion could not be confirmed as yet.

Page 5: Monitoring report of Progress in special plan under ...wbplan.gov.in/docs/BRGF/BRGF-Jungle Maha31.10.12l-update.pdf · Construction of 1 PTTI as per NCTE Norms will be completed by

Monitoring report of Progress in special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.2012

Sl No.

Department District Name of the Scheme Amount Sanctioned (Rs. in crore) (approx) Status

10 P.W. & P.W(Rds)

Purulia

3 Road Schemes under PWD : i) Strengthening of Wilrox Road – length 5.40 km. ii) Strengthening of Barakar-Purulia Road – length 69.25 km. iii) Widening & strengthening of Purulia-Ranchi Road – length 25.50 km 6 roads schemes under PW (Roads) : i) Widening and Strengthening of Sindri-Manbazar-Bansa Road – length 8.30 km. ii) Widening and Strengthening of Balarampur-Barabazar-Sindri road – length 14.00 km. iii) Widening & Strengthening of Barabazar-Bundwan1 road – length 12.66 km. iv) Widening & Strengthening of Hura-Kashipur-Adra-Raghunathpur road – 15.00 km v) Widening & strengthening of Purulia Sainik School to Chaschandankiary road – 10.00 km vi) Widening of strengthening of Damda-Chakoltore-Daradi-Kenda-Manbazar road – 8.00 km.

4.5348 3.6249 34.4506

12.2465

19.6646

12.1566

10.6228

10.0681

10.7670

1) All work orders issued. 2) To be completed within 18 months. 3) Scheme-wise monthly bar chart to be submitted by PWD.

Page 6: Monitoring report of Progress in special plan under ...wbplan.gov.in/docs/BRGF/BRGF-Jungle Maha31.10.12l-update.pdf · Construction of 1 PTTI as per NCTE Norms will be completed by

Monitoring report of Progress in special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.12

Sl No.

Department District Name of the Scheme Amount Sanctioned (Rs. in crore) (approx) Status

10 P.W. & P.W(Rds)

Bankura 2 Road Schemes under PWD : i) Strengthening of Bankura-Khatra-Ranibandh Road – length 48.00 km. ii) Strengthening of Bankura-Taldangra-Simlipal Road – length 29.00 km. 6 roads schemes under PW (Roads) : i) Improvement and Strengthening of Bishnupur-Sonamukhi-Rangamati Road – length 6.00 km. ii) Improvement and Strengthening of Indpur-Belut road – length 20.40 km. iii) Widening & Strengthening of Krishnapur-Raipur-Phulkusma-Benagoria road – length 27.30 km. iv) Widening & Strengthening of Bishnupur Byepass road – 5.20 km v) Widening & strengthening of Ranibandh-Jhilmili road – 21.00 km vi) Widening of Gangajalghati-Saltora road – 2.40 km. and strengthening from 22.00 km.

21.9997

13.7485

5.3273

12.2313

26.2723

7.1949

14.5311

18.5618

1) All work orders issued. 2) To be completed within 18 months. 3) Scheme-wise monthly bar chart to be submitted by PWD.

Page 7: Monitoring report of Progress in special plan under ...wbplan.gov.in/docs/BRGF/BRGF-Jungle Maha31.10.12l-update.pdf · Construction of 1 PTTI as per NCTE Norms will be completed by

Monitoring report of Progress in special plan under Backward Region Grant Fund (BRGF) in Jungle Mahal Area as on 31.10.2012

Sl No.

Department District Name of the Scheme Amount Sanctioned (Rs. In crore ) (approx) Status

10 P.W. & P.W(Rds)

Paschim Medinipur

7 Road Schemes under PWD : i) Improvement of Ranigunge- Midnapore Road – length 5.20 km. ii) Improvement of Sampriti Sarani and N.L.Khan Road – length 6.50 km. iii) Improvement of Kharagpur bye-pass – length 18.00 km iv)Widening and strengthening of Lodhasuli-Dahijuri Road – length 15.00 km. v) Widening and strengthening of Lodhasuli-Dahijuri-Kupannad Road – length 39.00 km. vi) Improvement of Dantan Bye-Pass – 7 km. vii) Improvement of Narayangarh Bye-pass – length – 5.10 km. 10 roads schemes under PW (Roads) : i) Strengthening of Pataspur-Bangurchak – length16.80 km. ii) Strengthening of Mundamari-Pingla-Paramanandapur-Moyna road – length 10 km. iii)Strengthening of Sabang-Mohar – length 10 km. iv) Widening & Strengthening of Panskura-Ghatal – 33.75 km v) Widening & strengthening of Keshpur-Chandrakona – 21.25 km vi) Widening & Strengthening of Khirpai-Ramjibanpur – 9.00 km. vii) Widening and strengthening of Godapiasal-Anandapur – length 8.60 km. viii)Widening and strengthening of Keshpur-Narajole – length 7.68 km. ix) Widening and strengthening of Pirakata Chandra – length 13.30 km. x) Construction of a bridge over river Subarnarekha at Bhansraghat in Keshiary block between Kharagpur-Kesiary Road and Nayagram-Dhumsai Road

4.2823

5.0962

4.1894 7.7631

5.8848

2.0876 1.8094

7.0839 4.0774

4.0714 32.4000 17.6375

7.56

5.2325

6.0615

11.1923

169.4970

1) All work orders issued. 2) To be completed within 18 months. 3) Scheme-wise monthly bar chart to be submitted by PWD.