monkstown village traffic management improvement scheme

4
24/03/2016 1 Monkstown Village Traffic Management Improvement Scheme UPDATE March 2016 History Non Statutory Public Consultation took place in August and September 2012 and 78 submissions were received. A meeting with a representative group of businesses and residents was held in January 2013. A Report on the submissions received was presented to the 4th March 2013 DLAC meeting A presentation on the revised proposals including the public realm elements was given to the Dun Laoghaire Area Committee in April 2015 Project update to Dun Laoghaire Councillors given prior to the Council Meeting in October 2015 Detailed Design commenced Dec 2015 Scheme: Architecture & Culture Department

Upload: michael-merrigan-independent

Post on 27-Jul-2016

219 views

Category:

Documents


1 download

DESCRIPTION

Presentation provided to the Dún Laoghaire Area Committee of the Dún Laoghaire Rathdown County Council on March 30th 2016. This PowerPoint presentation is to update County Councillors on the scheme.

TRANSCRIPT

Page 1: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME

24/03/2016

1

Monkstown Village Traffic Management Improvement Scheme

UPDATE

March 2016

History• Non Statutory Public Consultation took place in August and

September 2012 and 78 submissions were received.

• A meeting with a representative group of businesses and residents was held in January 2013.

• A Report on the submissions received was presented to the 4th March 2013 DLAC meeting

• A presentation on the revised proposals including the public realm elements was given to the Dun Laoghaire Area Committee in April 2015

• Project update to Dun Laoghaire Councillors given prior to the Council Meeting in October 2015

• Detailed Design commenced Dec 2015

Scheme:

Architecture & Culture Department

Page 2: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME

24/03/2016

2

End

Additional element:

Level difference at restaurants

- Reduce carriageway to 6m

- Widen path at restuarants

- Indented parking bays

- Planting

- Discrete drainage

- Crossing point at Avoca

Current Situation

Current Situation:

Avoca

Page 3: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME

24/03/2016

3

Proposed Current Situation

Existing street lighting and cablesImpact on parking

Existing Proposed

Clifton Avenue

+9 spaces

Impact on

parking

Monkstown Crescent: - Loading bays reduced in size - 1 car space lost adjacent to shops - 2 spaces lost opposite Avoca. 3 additional space at Link Road.

Page 4: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME

24/03/2016

4

Carrickbrennan Road

+1 spaceOverall gain of

10 no. spaces

Next steps…….

- Engage with business on Monkstown Crescent

- Detailed design completed July 2016

- Contractor appointed September 2016

- Contract duration approximately 6 months

Questions?