monroe county drain commission storm … commission/detention methodology (full... · monroe county...
TRANSCRIPT
MONROE COUNTY DRAIN COMMISSION
STORM WATER DETENTION METHODOLOGY
MONROE COUNTY DRAIN COMMISSION
1005 SOUTH RAISINVILLE ROAD
MONROE, MICHIGAN 48161
TABLE OF CONTENTS I. INTRODUCTION
A. Purpose..........................................1
B. Objective........................................1
C. Technical Procedures.............................1 II. RUNOFF HYDROGRAPHS
A. General..........................................2
B. Philosophy for Hydrologic Studies................2
C. Selection of a Method............................2
D. Overview of Steps in Hydrograph Development......3
E. Hydrograph Development Procedure.................3
Step 1, Design Storm Frequency..............3
Step 2, Determine Tributary Area............4
Step 3, Estimate Runoff Coefficient.........4
Step 4, Estimate Basin Time of Concentrate..6
Step 5, Determine Rainfall Intensity........7
Step 6, Estimate Peak Flow..................7
Step 7, Development of a Hydrograph........10 III. DETENTION POND
A. Preliminary Design..............................14
B. Detention Pond Layout...........................14 IV. OUTFALL STRUCTURE
A. Preliminary Design..............................16
B. Hydraulics of Outfall Structure
1. Simple Pipe Outfall Structure..............17
2. Drop Inlet Outfall Structure...............17
3. Horizontal Weir Outfall Structure..........21 V. FLOOD ROUTING
A. Background and Procedure........................27
B. Review of Results...............................31 VI. DESIGN EXAMPLES
Example Problem 1....................................32
Example Problem 2....................................42
REFERENCES
LIST OF FIGURES No. Description 1 Overland Flow Curves..................................8 2 Rainfall Intensity - Duration Curves..................9 3 Hydrograph Width at 50% and 75% Peak Flow............13 4 Orifice Pipe Discharge Curves, Outfall Structure.....19 5 Horizontal Weir Discharge Curves.....................26
LIST OF FORMS 1 Peak Flow Computation, Summary Sheet.................11 2 Detention Volume Estimate............................12 3 Storage - Elevation Curve............................15 4 Simple Pipe Hydraulics, Orifice Control..............18 5 Simple Pipe Hydraulics, Pipe Flow Control............20 6 Drop Inlet Hydraulics.............................22-24 7 Weir Hydraulics......................................25 8 Outfall Versus Storage Curve.........................29 9 Detention Basin Routing..............................30
LIST OF TABLES 1 Rational Method Runoff Coefficients...................5 2 Runoff Coefficient, Composite Analysis................6
INTRODUCTION
1. INTRODUCTION
A. Purpose
The purpose of this technical paper is to provide a
uniform method for the computation and submittal of design
plans for review by Monroe County, Michigan. In particular,
this paper deals with the hydrology and hydraulics of
detention facility design.
B. Objective
The major emphasis of the Drain Commissioner’s policy is
to control increases in runoff resulting from development.
Developments that increase runoff rate or volume shall be
required to control the discharge rate of runoff to acceptable
levels similar to existing undeveloped site conditions. All
new and redeveloped projects disturbing over 1 acre of land
(or are less than 1 acre but are part of a larger common plan
of development or sale that would be over 1 acre) must adhere
to the following standards:
a. The minimum treatment volume standard shall be one
inch of runoff from the entire site. The minimum
treatment volume shall have a minimum of 80% removal
of TSS (Total Suspended Solids), as compared with
uncontrolled runoff.
b. Channel protection measures must be met by means of
maintaining a post-development site runoff volume and
peak flow rate at or below existing levels for all
storms up to the 2-year/24-hour event.
c. A long term Operations & Maintenance (O&M) plan for
maximum design performance must be submitted to this
office to ensure the above mentioned measures will
continue to be addressed.
C. Technical Procedures
The procedures presented represent methodologies that are
likely to be familiar to most practitioners. State-of-the-art
approaches, which might place an unwarranted burden on
development submittals, have been avoided. Average values for
hydraulic formulas have been selected and are presented in a
detailed step-by-step format.
The basic procedures for the detention basin design will
be as follows:
1. Develop a hydrograph for existing undeveloped
conditions.
2. Develop a hydrograph for proposed conditions.
3. Limit outfall from the site to existing undeveloped
conditions by storing the difference between existing
and proposed conditions.
4. Determine the type of detention basin to use for the
project. (IE Dry Detention Basin where the basin will
eventually drain dry; Detention Basin with Forebay; Wet
Detention Basin that will retain a permanent water
pond).
5. The detention volume must consider and provide for
first flush runoff from the development site. First
flush runoff shall be computed based upon ½” rainfall
over the development site drainage area. Where dry
detention basins are proposed, the first flush volume
must be included in the total detention volume (IE
Total detention volume – required site detention +
first flush volume). Detention basins with Forebay
basin shall have the Forebay designed to meet the first
flush volume and the primary detention basin designed
to accommodate the required site detention volume. Wet
detention basins shall be designed to accommodate the
required first flush volume in the permanent wet pond
volume and the required site detention within the
remainder of the detention basin above the wet pond.
6. Detention systems may be designed as an above ground
or an underground system. Under ground systems may be
as manufactured by Advanced Drainage Systems, Inc.
(ADS), StormTech Chamber Systems, Kennedy Solutions,
Inc or as approved by the Monroe County Drain
Commissioner.
7. Evaluate the operation of the detention facility
through flood routing.
8. All detention system plans shall include a detailed
operating and Maintenance schedule that must be
followed by the detention system owner.
9. All detention systems shall be designed in accordance
with the Monroe County Drain Commissioner Storm Water
Detention methodology and the Low Impact Development
Manual for Michigan. Where conflicts occur between
these standards, the Monroe County Drain Commissioner
Storm Water Detention Methodology shall govern.
RUNOFF HYDROGRAPHS
II. RUNOFF HYDROGRAPHS
A. General
For the detention basin design, a storm hydrograph must be
developed in addition to an estimate of the peak runoff rate.
The hydrograph is required to study the effectiveness of the
proposed storage facility.
The method described herein (Reference 1) is applicable to
small watersheds and studies that are too small to justify
installing a stream gage or undertaking a more sophisticated
computer simulation study. Note, however, that the Design
Engineer should always search for existing streamflow records or
more sophisticated hydrologic analysis that might be available
for the area.
B. Philosophy of Hydrologic Studies
The Engineer has an obligation to provide the best estimate
possible at a cost commensurate with the scope of his project.
He must recognize that error is always present in hydrologic
estimation and that probable error increases if the information
is approximate. The Engineer needs to continually compare and
review his results for consistency and reasonableness.
C. Selection of a Method
The hydrologic method presented is based on the Rational
Method and the assumption that the critical hydrograph is
produced by runoff from the maximum intensity rainfall over a
time duration equal to the basin time of concentration. Most
practicing engineers are familiar with the Rational Method.
The basic equation for the Rational Method is:
Q = CiA (Equation 1)
Q = peak flow (cubic feet per second)
i = design rainfall intensity (inches per hour)
A = drainage area (acres
C = runoff coefficient
D. Overview of Steps in Hydrograph Development
The following outline is a general overview of the steps
required to develop a hydrograph:
1. Select design storm return period
2. Determine tributary area
3. Estimate runoff coefficient
4. Estimate time of concentration
5. Determine rainfall intensity
6. Estimate peak flow
7. Develop the hydrograph
E. Hydrograph Development Procedure
Step 1: Design Storm Frequency
The hydrograph generated for existing conditions will be
based on the ten (10) year frequency rainfall event. The peak
discharge from this hydrograph will be the maximum allowable
outfall from the detention basin. Ultimately, the discharge
from the detention pond should be similar to this hydrograph.
The hydrograph generated for proposed conditions will be
based on the twenty-five (25) year frequency rainfall event.
This hydrograph will be used as the inflow hydrograph for the
storage routing computations.
Step 2: Determine Tributary Area (A)
To apply the Rational Method, a topographic map is used to
define the boundaries of all relevant drainage basins. All
basins tributary to the area of study and sub-basins within the
study area are normally defined. A field check and possibly
field surveys should also be considered. Typically, the
delineated area is determined from the map using a planimeter or
by computation.
Step 3: Estimate Runoff Coefficient (C)
The runoff coefficient is the variable of the Rational
Method that is determined by the Engineer using judgment and
understanding of the basin. Its use in the formula implies a
fixed ratio between runoff and rainfall for any given drainage
area. In reality, this is not totally the case. The
coefficient represents the integrated effects of infiltration,
evaporation, retention, flow routing, and interception which all
affect the time distribution and peak of runoff (Reference 4).
TABLE 1 (REFERENCE 4)
RATIONAL METHOD RUNOFF COEFFICIENTS
Description of Area Runoff Coefficients
Business:
Downtown areas
Neighborhood areas
0.70 to 0.95
0.50 to 0.70
Residential:
Single-family areas
Multi units, detached
Multi units, attached
0.35 to 0.50
0.40 to 0.60
0.60 to 0.75
Residential (1/2 acre lots or more) 0.30 to 0.45
Apartment dwelling areas 0.50 to 0.70
Industrial:
Light areas
Heavy areas
0.50 to 0.80
0.60 to 0.90
Parks, cemeteries 0.10 to 0.25
Playgrounds 0.20 to 0.35
Railroad yard areas 0.20 to 0.40
Unimproved areas 0.10 to 0.30
It is often desirable to develop a composite runoff
coefficient based on the percentage of different types of
surface in the drainage area. This procedure is often applied
to typical “sample” blocks as a guide to selection of reasonable
values of the coefficient for an entire area.
Table 2 is a list of specific runoff coefficients that
shall be used for determining composite runoff coefficients.
TABLE 2
RATIONAL METHOD RUNOFF COEFFICIENTS FOR COMPOSITE ANALYSIS
MONROE COUNTY DRAIN COMMISSIONER
Character of Surface Runoff Coefficients
Streets 0.90
Paved Shoulders 0.90
Gravel Shoulders 0.50
Drives and Walks 0.90
Paved Parking Lots 0.90
Roofs 0.90
Lawns 0.20
Unimproved Areas 0.20
Step 4: Estimate Basin Time of Concentration (Tc)
The basin time of concentration is generally defined as the
time it takes direct runoff to travel from the furthermost point
in the basin to the point at which a hydrograph is desired. In
the application of the Rational Method, the time of
concentration must be estimated so that the average rainfall
rate of corresponding duration can be determined from the
rainfall intensity-duration-frequency curves.
When dealing with pipe systems, the time of concentration
may be readily calculated from the inlet time plus time of flow
in each successive pipe run. The time of flow in each pipe can
be calculated from the velocity of flow as given by the Manning
Formula for the hydraulic conditions prevailing in the pipes.
The inlet time can be estimated by calculating the various
overland distances and flow velocities taken from the most
remote point. A common mistake is to assume velocities that are
too small for the areas near the collections (Reference 4).
Often the remote areas have flow that is very shallow and
velocities cannot be calculated by “channel” equations such as
Manning’s but special overland flow analysis must be considered
(Reference 4). Figure 1 can be used to help estimate time of
surface overland flow.
It is not unusual for the time of concentration at an
initial pickup point to be in the vicinity of ten to fifteen
minutes. Clearly, many factors must be considered in
determining time of concentration including: slope, type of
cover, vegetation, distance, initial wetting period, depression
storage and infiltration characteristics. (Figure 1).
Step 5: Precipitation Intensity-Duration Curve
Figure 2 will be used for rainfall intensity-duration.
Typically, this type of curve is generated from a frequency
analysis of an annual series of peak rainfall events for a given
duration from data for a long-term recording gage (Reference 2
and 3). This figure presents both the ten (10) year and the
twenty-five (25) year storm intensity duration curves. The
graph is entered with the time of concentration and the
associated rainfall intensity is determined. (Figure 2)
Step 6: Estimate Peak Flow
The instantaneous peak flow is calculated using Equation 1:
Q = CiA (cfs.)
Steps 3, 4 and 5 are used to define the parameters on the right
side of the equation. The peak flow is computed directly. Form
1 can be sued to summarize the peak flow computations. (Form 1)
GRAPH
FIGURE 1 – OVERLAND FLOW CURVES
(REFERENCE 4)
GRAPH
Step 7: Development of a Hydrograph
Using the peak flow generated in Step 6, the following
procedure outlines the development of the existing and proposed
hydrographs. (See Form 2).
1. Plot the peak flow calculated in Step 6 at a time to
peak equal to the time of concentration (Tc)
determined in Step 5.
2. Estimate length of hydrograph base (Tb) as three times
the time of concentration (Tc).
Tb = 3 Tc
3. Divide the peak flow (Qp) by the drainage area in
square miles.
4. Enter Figure 3 for the width of the hydrograph at
fifty percent (50%) and at seventy-five percent (75%)
of the peak flow.
5. Divide the widths at fifty percent (50%) and at
seventy-five percent (75%) of the peak flow such that
one third occurs before and two thirds occurs after
the peak.
6. Sketch the total hydrograph from the above points.
7. Determine area between curves.
8. Estimate required volume.
9. Allowable peak discharge equals existing peak.
FORM 1 Project Name: ____________________
DETENTION POND PEAK FLOW COMPUTATION SUMMARY SHEET
Rational Formula Q=CiA
PARAMETER EXISTING
CONDITIONS PROPOSED CONDITIONS
1. Design Storm Frequency 10 Year Design 25 Year Design 2. Tributary Area A = Acres A = Acres 3. Runoff Coefficient C = C = 4. Time of Concentration Tc = Min. Tc = Min. 5. Rainfall Intensity i = In./Hr. i = In./Hr. 6. Peak Flow Q10 = CFS Q25=
= CFS
NOTE: Allowable Discharge = Acres x 0.20 CFS / Acre = CFS
PROCEDURE:
1. Design Storm (Frequency Given).
2. Delineate and Planimeter Tributary Area.
3. Determine Runoff Coefficient, See Tables 1 & 2.
4. Determine Time Of Concentration For Site, See Figure 1,
May Require Sewer Velocity Computations
5. Enter Figure 2 With Time Of Concentration To Determine Rainfall
Intensity, 10 Year Design - Existing, 25 Year Design - Proposed.
6. Calculate Peak Flow Using Rational Formula, Q = CiA
7. Calculate the Allowable Discharge from the site: (.20 CFS / Acre)
DETENTION POND
III. DETENTION POND
A. Preliminary Design
Based on the hydrographs developed in Chapter II, Runoff
Hydrographs, a preliminary estimate of detention pond volume can
be made. This estimate is made by plotting both the existing
condition hydrograph and the proposed condition hydrograph on a
common scale and determining the area between the two
hydrographs. This area represents the volume of storage that is
required assuming that the final detention pond discharge
hydrograph resembles the existing condition hydrograph (See Step
8, Form 2).
B. Detention Pond Layout
Following the preliminary estimate of volume, the designer
must prepare a detention pond layout plan. Typically, this
would be done on a topographic map that would show both the plan
and the grading of the proposed pond. From this plan and
grading layout, a detention pond storage-elevation curve can be
developed. See Form 3 for the procedure. This curve is
required for the detailed flood routing computation that will be
conducted to verify the operation of the proposed system. (Form
3)
OUTFALL STRUCTURE
IV. OUTFALL STRUCTURE
A. Preliminary Design
Following the generation of inflow hydrographs and a
preliminary layout of a detention pond, an outfall structure
must be selected. The hydraulic characteristics of the outfall
structure are summarized on a discharge-rating curve for use in
the flood routing analysis of the detention pond.
The hydraulics of the discharge structure must be such that
under the maximum available head condition, the outflow does not
exceed the peak flow for existing conditions. The maximum
available head condition typically occurs when the detention
pond is full and the outlet is not subject to backwater
restrictions. It is also desirable for the outfall hydrograph
to be similar to the existing condition inflow hydrograph.
Several types of outfall structures can be designed or
utilized including pipes, weirs, drop inlets, or combinations of
pipes and weirs. The Design Engineer must select the type of
outfall structure best suited for his particular installation
and the outflow characteristics he is attempting to achieve.
B. Hydraulics of Outfall Structure
Once the type of structure is selected, the hydraulic
characteristics need to be established. The maximum discharge
must not exceed the maximum of the existing inflow hydrograph.
Ideally, the detention pond outflow hydrograph should be similar
to the existing inflow hydrograph.
1. Simple Pipe Outfall Structure
The hydraulics of a typical simple pipe outlet
are a function of two controls: Case 1, the size of
the pipe inlet (orifice control); Case 2, the length
of the pipe (pipe flow control). For pipe inlet
control, the depth of water above the pipe in the pond
is controlled by the restrictive characteristics of
the inlet. This is typically analyzed using the
orifice equation. The phenomenon is similar to inlet
control in culvert hydraulics.
Pipe flow control (similar to outlet control in
culvert hydraulics) is based on a headloss analysis of
the outlet pipe, including losses for friction and
minor losses such as entrance and exit conditions.
Both orifice and pipe flow conditions must be
plotted on a common graph with the final outfall curve
being a combination of both orifice and pipe flow.
The controlling condition is that which gives the
higher pond level relative to discharge.
Form 4 presents a detailed procedure for
evaluating orifice control characteristics for a
simple pipe. Figure 4 presents a series of orifice
pipe discharge curves that can be used to simplify the
analysis. Form 5 presents a detailed procedure for
evaluating pipe flow control characteristics for a
simple pipe.
2. Drop Inlet Outfall Structure (Circular Stand
Pipe)
The hydraulics of the drop-inlet type outfall
structure are more complex than the simple pipe
outfall. In addition to orifice control (inlet) and
pipe flow control (outlet), weir control is also a
consideration. During the initial outflow, prior to
development of an orifice flow condition, the crest of
the drop-inlet will act as a weir. In this range,
weir hydraulics will control the pond elevation and
the discharge rating curve. Whichever condition gives
the higher pond level relative to discharge is the
controlling condition.
Procedure
A. Select Outfall Structure Type
B. Evaluate Hydraulics of Structure
- Maximum discharge not to exceed peak of
existing inflow hydrograph
- Orifice Control, Pipe Control, Weir
Control
C. Plot Discharge Rating Curve
- Combination of Highest Control Elevations
D. See Form 6, Drop Inlet Hydraulics
3. Weir Outfall Hydraulics
The hydraulics of a horizontal rectangular weir are
the least complex of the alternatives illustrated. Form 7
presents the procedure for generating a discharge rating
curve for this type of structure. Figure 5 can be used to
simplify the computations.
FORM 4 PROJECT NAME: _____________________
DETENTION POND SIMPLE PIPE HYDRAULICS
CASE 1, ORIFICE CONTROL
PIPE DATA D = DIAMETER (INCHES) A = PIPE AREA (SQ. FT.) I.E. = INVERT ELEVATION
PIPE DATA D= __________ " A= __________ SQ.FT. I.E.= __________ FT. G= 32.2
(1)
H (FT)
(2)
Q (CFS)
(3)
WSU
DISCHARGE FORMULA FOR H GREATER THAN D Q = 0.6 A√(2Gh) = (C.F.S.) h= H - (D/24) = FT. G = 32.2 FT/SEC2 Q = C.F.S. DISCHARGE FORMULA FOR H LESS THAN D Q = 3L (H3/2) = (C.F.S.) (Weir Flow) H = FT. Q = C.F.S. L = D/12 = FT. PROCEDURE BY COLUMN (1) ASSUME VALUES FOR H. (2) CALCULATE Q BY FORMULA
OR USE DISCHARGE CURVES (3) DETERMINE UPSTREAM ELEVATION
WSU = I.E. + H (4) PLOT DISCHARGE RATING CURVE
FORM 5
PROJECT NAME: DETENTION POND
SIMPLE PIPE HYDRAULICS CASE 2 – PIPE FLOW CONTROL
PIPE DATA D = DIAMETER (INCHES) A = PIPE AREA (SQ. FT.) I.E. = INVERT ELEVATION WP = WETTED PERIMETER N = ROUGHNESS L = LENGTH (FEET)
WP = L = N =
(3)
ENT (FT)
(5)
WSD (FT)
PIPE DATA D = IN A = SQ.FT. I.E. = FT.
(1) Q(CFS)
(2)
V (FPS)
(4) HF
(FT)
(6)
WSU
G= 32.2
PROCEDURE BY COLUMN (1) ASSUME DISCHARGE VALUES (2) COMPUTE PIPE VELOCITY; V = Q/A (ASSUME PIPE FULL) (3) CALCULATE ENTRANCE LOSS; ENT = 0.5 V2/2G; G = 32.2 FT./SEC.2 (4) CALCULATE FRICTION LOSS; HF = 0.45 V2N2L/R4/3 R=A/W P= R4/3= HF=V2 (5) ASSUME DOWNSTREAM ELEVATION = ELEVATION OF CROWN OF PIPE = WSD (6) DETERMINE UPSTREAM INLET ELEVATION; WSU = ENT + HF + WSD (7) PLOT DISCHARGE RATING CURVE
FORM 6: (Page 2 of 3)
OUTFALL HYDRAULICS – CIRCULAR DROP INLET
C. PIPE FLOW CONTROL (NO BACKWATER)
(1) (2) (3) (4) (5) (6)
Q (CFS) V (FPS) ML (FT) HF (FT WSD WSU
PROCEDURE BY COLUMN:
(1) Assume discharge values (ie, 0.00, 0.10, 0.20, ETC)
(2) Compute pipe velocity (V=QiA)
(3) Calculate minor losses
(Entrance = 0.5 V2 / 2G) + (90° Bend = 0.75 V2 / 2G) = 1.25 V2 / 2G
(4) Calculate friction loss, HF = 0.45 V2 N2 LP / R1/3
WP = Wetted pipe Perimeter _______, R = A / WP = _________
R 1/3 = ___________, HF = V2 ________
(5) Assume downstream elevation (WSD) = Elevation of crown of pipe
(6) Determine upstream elevation WSU = ML + HF + WSD
(7) Plot the discharge rating curve (Page 3 of 3)
FLOOD ROUTING
V. FLOOD ROUTING
A. Background and Procedure
Following the generation of hydrographs, the preliminary
layout of a detention pond, and selection of an outfall
structure, the design must be checked to assure that it
functions as intended. Flood routing calculations are performed
to provide this check.
Flood routing is an accounting technique that inventories
flow at the site. The basic principal of the technique is as
follows:
INFLOW - OUTFLOW = STORAGE (Equation 2)
Flood routing is typically performed on a time interval
basis for the duration of the storm. A convenient time
interval, DT is selected. The time interval must be short
enough to adequately account for hydrograph peaks. The
detention pond storage for time interval DT is:
(Equation 3)
[INFLOW (FT3) - OUTFLOW (FT3)] DT (SEC) = STORAGE (FT.3) SEC SEC
If the beginning of the interval is designed by subscript
“1" and the end of the interval is designated by subscript “2",
the following relations can be used to express storage, inflow,
and outflow for an interval DT
DS (change in storage for DT) = S2 - S1
Inflow (average rate of inflow x DT) = I1 + I2 DT 2
Outflow (average rate of outflow x DT) = 01 + 02 DT 2
Substitution of these relations into Equation 3 gives:
I2+I1 ∆T - 01+02 DT = S2 - S1 (Equation 4) 2 2
Typically, quantities, I1, 01 and S1 are known at the
beginning of a storm event. For example; inflow, outflow and
storage would normally be zero at the beginning of an event.
Assuming an inflow hydrograph has been developed, I2 would also
be known.
Grouping the known values together, Equation 4 can be
rewritten as:
I1 + I1 + 2S1 - 01 = 2S2 + 02 (Equation 5) DT DT
Although S2 and 02 are unknown, they are related by the storage-
elevation relationships. Knowing the storage-elevation
relationships of the proposed pond (See Storage-Elevation Curve)
and the discharge-elevation characteristics of the outflow
structure (See Discharge-Rating Curve), a graph can be generated
relating:
2S + 0 versus 0
DT
Form 8 presents the procedure for generating this Outfall
versus Storage Curve.
The flood routing computations can now be undertaken by
solving Equation 5 for successive time intervals DT. The result
will be the ordinates of the outflow hydrograph routed through
the proposed detention pond and proposed outfall structure.
The use of this procedure is further discussed by an
example in the following section using Form 9, Detention Basin
Routing.
FORM 8
FLOOD ROUTING COMPUTATIONS PROJECT NAME ____________________
FLOOD ROUTING COMPUTATIONS OUTFLOW VS. STORAGE
PROCEDURTE BY COLUMN: (1) Pond elevation, increments from bottom (2) Outflow at the pond elevation (See discharge – rating curve) (3) Outflow at pond elevation, (See storage – elevation curve) (4) Calculate 2S / T, T = 300 seconds (5) Calculate (2S / T) + O (6) Plot outfall VS storage relation, Column (2) VS Column (5)
(1) (2) (3) (4) (5)
POND
ELEVATION
O
OUTFLOW
(CFS)
S
STORAGE (FT3)
2S / DT
CFS
(2S / DT) + O
(2S
/DT)
+O
O = OUTFLOW (CFS)
DETENTION BASIN ROUTING (FORM 9)
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
Routing Interval
Inflow Time Min.
T1 Min
T2 Min
I1 Inflow CFS
I2 Inflow CFS
2S1 DT CFS
01 CFS
2S2 + 02 DT CSF
02 CFS
2S2 DT CFS
S2 C.F.
Procedure by Column (1) Number of Interval, for Accounting Only (2) Inflow time from Inflow Hydrograph (3) Time at Beginning of Interval (4) Time at End of Interval (5) Inflow at Beginning of Interval (6) Inflow at end of Interval Note: (2) to (6), From Inflow Hydrograph
(7) Calculate 2S1 (8) Outflow at T1, T1 (initial Interval) = 0.0 (9) (5) + (6) + (7) - (8) = (9), Equation 5 (10) Outflow at T2 (from Outflow-Storage Curve)(11) (9) - (10) = (11) (12) Calculate Storage at T2, S2 = (11) x DT 2
DESIGN EXAMPLES
B. Review of Results
Following the flood routing computations, the Engineer
should review the results to assure that the detention pond
maximum outflow and the outflow hydrograph is consistent to the
allowable limits as determined by the existing condition inflow
hydrograph.
The results should also be reviewed for reasonableness and
overall performance in relation to the site development.
Example Problem 1
Problem:
A commercial development of 10.00 acres is being
proposed. The drainage plan for the site must meet
the Monroe County, Michigan criteria for design of
detention facilities for developing areas. The
designer must submit for review a detention pond
design and appropriate flood routing calculations.
Given:
Existing
Proposed
Area (acres
10.00
10.00
Runoff Coefficient
0.25
0.80
Time of Concentration
(min.)
40.00
25.00
Solution:
1. Generate Peak Flows, Form 1.
2. Estimate Detention Volume, Form 2.
3. Layout Detention Pond and Generate Storage-Elevation Curve,
Form 3.
4. Selected Outflow Structure and Generate Discharge Rating
Curve(Use Simple Pipe, Form 4, Form 5, and Figure 4.)
5. Generate Outflow-Storage, Flood Routing Curve, Form 8.
6. Conduct Flood Routing Using Form 9.
7. Review Results.
EXAMPLE PROBLEM #1
FORM 1
PEAK FLOW COMPUTATION
SUMMARY SHEET
RATIONAL FORMULA
Q = CiA
PARAMETER
EXISTING CONDITIONS
PROPOSED CONDITIONS
1. Design Storm
Frequency
2. Tributary Area
3. Runoff
Coefficient
4. Time of
Concentration
5. Rainfall
Intensity
6. Peak Flow
10 - Year
A = 10.00 Acres
C = 0.25
Tc = 40 Min
i = 2.5 In/Hr.
Q = 6.2 CFS
25 - Year
A = 10.00 Acres
C = 0.80
Tc = 25 Min
i = 3.9 In/Hr.
Q = 31.2 CFS
PROCEDURE
1. Design storm (frequencies given)
2. Delineate and planimeter tributary area
3. Determine runoff coefficient, See Tables 1 & 2
4. Determine time of concentration for site, see Figure 1, may
require sewer velocity computations
5. Enter Figure 2 with time of concentration to determine
rainfall intensity 10-year existing, 25-year proposed
6. Calculate peak flow using rational formula: Q = CiA
I1 + I2 + 251 - 01 = 2S2 + 02 DETENTION BASIN ROUTING (FORM 9) DT DT EXAMPLE
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
ROUTING INTERVAL
INFLOW TIME MIN
T1 MIN
T2 MIN
I1 INFLOW CFS
I2 INFLOW CFS
2S1 DT CFS
01 CFS
2S2 + 02* DT CFS
02 CFS
2S2 DT CFS
S2 C.F.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
0
1.9
4.2
8.2
13.8
31.2
24.2
15.6
12.0
9.1
7.0
5.3
3.8
2.4
1.2
0.0
0.0
0.0
1.9
4.2
8.2
13.8
31.2
24.2
15.6
12.0
9.1
7.0
5.3
3.8
2.4
1.2
0.0
0.0
0.0
0.0
0
1.9
7.3
17.5
38.0
76.0
121.8
150.6
166.7
176.0
179.9
179.8
176.6
170.8
162.7
152.4
141.1
130.1
0
0.0
0.7
1.5
2.7
4.3
5.3
5.7
5.8
6.0
6.2
6.2
6.1
5.9
5.8
5.7
5.6
5.4
1.9
8.0
19.0
38.0
80.3
127.1
156.3
172.5
182.0
186.1
186.0
182.7
176.7
168.5
158.1
146.7
135.5
124.7
0.0
0.7
1.5
2.7
4.3
5.3
5.7
5.8
6.0
6.2
6.2
6.1
5.9
5.8
5.7
5.6
5.4
5.3
1.9
7.3
17.5
35.5
76.0
121.8
150.6
166.7
176.0
179.9
179.8
176.6
170.8
162.7
152.4
141.1
130.1
119.4
285
1095
2625
5295
11400
18270
22590
25005
26400
26985
26970
26490
25620
24405
22860
21165
19515
17910
PROCEDURE BY COLUMN (1) Number of Interval for Accounting Only (2) Inflow time from inflow hydrograph (3) Time at beginning of interval (4) Time at end of interval (5) Inflow at beginning of interval (6) Inflow at end of interval. Note: (2) to (6) from inflow hydrograph
(7) Calculate 2S1, _T = Routing interval (Sec) or from (11) T S, (initial interval) = 0.0 (8) Outflow at T1, T1 (initial interval) = 0.0 (9) (5) + (6) + (7) - (8) = (9), Equation 5 (10) Outflow at T2 (From outflow-storage curve) (11) (9) - (10) = (11) (12) Calculate storage at T2, S2 = [(11)xDT] / 2
Results, Example Problem 1
The results of the flood routing analysis indicates that a
maximum discharge of 6.2 cfs is generated and a maximum storage
capacity of 26,935 c.f. is required. The elevation in the
detention pond at maximum storage is 87.8 which allows 2.2 feet
of free board on the pond. The discharge velocity from the 10-
inch pipe at maximum flow is 114 fps, therefore some erosion
protection should be provided downstream. Not that 6.2 cfs
discharge from the retention pond is equal to the discharge from
a ten year rainfall on the undeveloped site.
Example Problem 2
Problem:
As an alternate design to Example Problem 1, the designer is
considering a wet design detention pond to improve the
landscaping characteristics of the site. To maintain a level in
the detention pond, he will use a drop inlet structure. Also,
he has agreed to improve the downstream receiving ditch so that
an allowable outflow of 10 cfs can be discharged from his site.
Design a circular pipe drop inlet with a crest elevation of 85.0
to maintain 3.0 feet of water in the pond at all times. Perform
flood routing computations to verify the operation of the
system.
Given:
- Proposed Inflow Hydrograph, See Problem 1
- Allowable Discharge Equals 10.0 cfs
- Pipe Length Equals 50 feet
- Storage-Elevation Curve
DETENTION BASIN ROUTING (FORM 9)
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
Routi
ng
Inter
val
Inflo
w
Time
Min
T1
Min
T2
Min
I1
Inflo
w
CFS
I2
Inflo
w CFS
2S1
DT
CFS
01
CFS
2S2 + 02
DT
CFS
02
CFS
2S2
DT
CFS
S2
C.F.
1
2
3
4
5
6
7
8
9
10
11
0
5
10
15
20
25
30
35
40
45
50
0
5
10
15
20
25
30
35
40
45
50
5
10
15
20
25
30
35
40
45
50
55
0
1.9
4.2
8.2
13.8
31.2
24.2
15.6
12.0
9.1
7.0
1.9
4.2
8.2
13.8
31.2
24.2
15.6
12.0
9.1
7.0
5.3
0
1.6
5.7
13.7
29.2
65.3
109.3
136.0
149.9
157.1
159.1
0
.3
1.7
2.7
3.8
5.1
6.3
6.8
6.9
7.0
7.1
1.9
7.4
16.4
33.0
70.4
115.6
142.8
156.8
164.1
166.2
164.3
.3
1.7
2.7
3.8
5.1
6.3
6.8
6.9
7.0
7.1
7.0
1.6
5.7
13.7
29.2
65.3
109.3
136.0
149.9
157.7
159.1
157.3
240
855
2055
4380
9795
16395
20400
22485
23565
23865
23595
12
13
14
15
16
17
18
19
20
55
60
65
70
75
80
85
90
95
55
60
65
70
75
80
85
90
95
60
65
70
75
80
85
90
95
100
5.3
3.8
2.4
1.2
0.0
0.0
0.0
0.0
0.0
3.8
2.4
1.2
0.0
0.0
0.0
0.0
0.0
0.0
157.3
157.5
144.9
134.8
122.6
109.7
97.4
85.6
74.3
7.0
6.9
6.9
6.8
6.6
6.3
6.0
5.8
5.5
159.4
151.8
141.6
129.2
116.0
103.4
91.4
79.8
68.8
6.9
6.9
6.8
6.6
6.3
6.0
5.8
5.5
5.1
152.5
144.9
134.8
122.6
109.7
97.6
85.6
74.3
63.7
22875
21735
20220
18390
16455
14610
12840
11145
9555
Procedure by Column
(1) Number of Interval, for Accounting
Only
(2) Inflow time from Inflow Hydrograph
(3) time at beginning of Interval
(4) Time at end of Interval
(5) Inflow at beginning of Interval
(6) Inflow at end of Interval
Note: (2) to (6), from Inflow
Hydrograph
(7) Calculate
(8) Outflow at T1, T1 (Initial Interval) =
0.0
(9) (5) + (6) + (7) - (8) = (9), Equation 5
(10) Outflow at T2 (from Outflow-Storage
Curve)
(11) (9) - (10) = (11)
(12) Calculate Storage at T2, S2 = (11) x
DT
2
Review Results, Example Problem 2
With a drop inlet type outfall structure, the discharge rating
curve is controlled by weir and orifice hydraulic properties.
The maximum required storage is 23,865 c.f. This corresponds to
an elevation of 88.3 which provides 1.7 feet of freeboard. The
maximum discharge from detention is 7.1 cfs which is below the
allowable of 10.0 cfs from this problem. The associated maximum
discharge
velocity is 9.0 fps. Some type of erosion protection should be
provided.