monterey peninsula water management district 1 consider authorization of funds to employ consultant...
TRANSCRIPT
1
Monterey Peninsula Water Management District Consider Authorization of Funds
to Employ Consultant to Promote Resolution 2003-01
April 19, 2004
2
Monterey Peninsula Water Management District
Background• SB 149 was introduced by State Senator
Bruce McPherson during the 2003 legislative session
• SB 149 proposed to remove the directly elected Board and replace it with appointed mayors and/or council members
• SB 149 also proposed to delete the existing requirement that water projects be placed before the District voters
3
Monterey Peninsula Water Management District
Background (continued)
• Resolution 2003-01 opposing SB 149 was adopted by the Board on May 2, 2003
• District employed Sacramento based firm of Edelstein & Gilbert to provide legislative advocacy services at the State Legislature
• SB 149 was not enacted last session, however, Senator McPherson has introduced SB 149/SB 1529 during the current legislative session with similar provisions
• The first hearing is scheduled for Wednesday, April 21, 2004, at 8:30 AM
4
Monterey Peninsula Water Management District
Advocacy Proposals
• District staff has received three proposals to provide legislative advocacy services related to SB 149/SB 1529 during the current legislative session Edelstein & Gilbert Sacramento Advocates The Gualco Group
5
Monterey Peninsula Water Management District
Edelstein & Gilbert
• Base fee of $40,000 $8,000 to be paid upon commencement of services Additional payments of $8,000 each on June 15, July 15, August 15 and September 15, 2004
• Services provided during the 2004 legislative session• Ordinary expenses (telephone, copies, etc.) included• Extraordinary expenses (travel, etc.) are additional,
but only after prior authorization• No termination provision
6
Monterey Peninsula Water Management District
Sacramento Advocates• Base fee of $36,000
$18,000 due upon execution of contract $18,000 due July 1, 2004
• Services provided from execution of agreement through September 30, 2004
• Ordinary expenses (telephone, copier, etc.) are additional and billed monthly
• Extraordinary expenses (travel, etc.) are additional, upon prior authorization, and are billed monthly
• Either party may terminate the agreement on 30 days advance written notice
7
Monterey Peninsula Water Management District
The Gualco Group• Base fee of $42,000
Monthly payment of $7,000 beginning May 1, 2004 and ending October 1, 2004
• Services provided May 1, 2004 through October 31, 2004
• Ordinary expenses (telephone, copier, etc.) are additional and billed monthly
• Extraordinary expenses (travel, etc.) are additional, upon prior authorization, and are billed monthly
• No termination provision
8
Monterey Peninsula Water Management District
Recommendation
• The Administrative Committee Considered this matter on April 13, 2004 and recommended consideration by the full Board
• District staff recommends that the Board should consider whether or not to retain a consultant to promote Resolution 2003-01 (SB 149/SB1529)
• If the Board votes to retain a consultant, it should authorize the General Manager to execute a contract with the desired consultant for an amount consistent with the applicable proposal