montessori boq priced
TRANSCRIPT
-
8/3/2019 Montessori BoQ Priced
1/267
NEW CONSTRUCTION WORKS AT MONTESSORI EDUCATION CENTRE
GRAND SUMMARY
Amount
1 PRELIMINARIES 197,264,904 Ugx
2 CLASSROOM BLOCK 1,808,895,200 Ugx
3 MULTI-PURPOSE HALL 547,504,700 Ugx
4 KITCHEN BLOCK 126,923,210 Ugx
5 CHANGING ROOMS 71,721,350 Ugx
6 PRE-PRIMARY BLOCKS 281,167,430 Ugx
7 CARE-TAKERS UNIT 44,369,350 Ugx
8 WAITING SHEDS 63,617,300 Ugx
9 SITE WORKS 495,913,700 Ugx
10 DAYWORKS 7,001,085 Ugx
11 ELECTRICAL INSTALLATION 250,803,450 Ugx
12 MECHANICAL INSTALLATION 247,381,300 Ugx
13 SUB-TOTAL 1 4,142,562,979 Ugx
14 ADD PROVISIONAL SUM FOR CONTINGENCY 5% 207,128,149 Ugx
15 SUB-TOTAL 1 4,349,691,128 Ugx
16 ADD VAT 18% 782,944,403 Ugx
17 TOTAL CARRIED TO CONTRACTOR'S FORM 5,132,635,531 Ugx
Bills of Quantities
Grand Summary
New Construction Works at Montessori Education Centre
Page No. GS/1
-
8/3/2019 Montessori BoQ Priced
2/267
Item Description Qty Unit Rate Amount
Ugx Ugx
BILL No. 1
PRELIMINARIESConditions of Contract
Particulars
1.01Insurance of works, plant and
materials
1.02 Insurance of other property
1.03Insurance against personal
injury or death.
1.04 Testing of materials & samples
1.05 Performance security
Specific Matters
The bidder shall allow here for
the specific items.
1.06 Tools, plant and scaffolding
1.07 Site supervision
1.08 Telephone
1.09 Site office
1.10 Water for works
1.11 Light and power for works
1.12 Site security
1.13 Hoarding
1.14 Signboards
1.15 Removing rubbish and cleaning
1.16 Photographs & site records
TOTAL BILL No. 1 (PRELIMINARIES)
TO GENERAL SUMMARY
Bills of Quantities: Preliminaries
New Construction Works at Montessori Education Centre
Page No. 1/2
-
8/3/2019 Montessori BoQ Priced
3/267
Item Description Qty Unit Rate Amount
Ugx Ugx
BILL No. 2: CLASSROOM BLOCK
SUMMARY
1 SUBSTRUCTURE 211,248,300 Ugx
2 RC SUPERSTRUCTURE 516,082,600 Ugx
3 WALLING 156,457,000 Ugx
4 ROOF & RAINWATER DISPOSAL 146,138,500 Ugx
5 WINDOWS 114,035,500 Ugx
6 DOORS 108,809,000 Ugx
7 EXTERNAL FINISHES 108,072,000 Ugx
8 INTERNAL FINISHES 437,274,300 Ugx
9 FITTINGS & FIXTURES 10,778,000 Ugx
TOTAL BILL No. 2 (CLASSROOM BLOCK) CARRIED TO
GENERAL SUMMARY 1,808,895,200 Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
Page No. 2/3
-
8/3/2019 Montessori BoQ Priced
4/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 1SUBSTRUCTURE
Site preparation
1.01 Excavate oversite to remove vegetable soil average 150mm
thick, remove excavated material from site 1,470 m2
1,800 Ugx 2,646,000 Ugx
Excavations & earthworks
1.02 Excavate for foundation trenches commencing from reduced
level: not exceeding 1.5m deep 676 m
3
5,000 Ugx 3,380,000 Ugx
1.03 Excavate pit for column bases commencing from stripped level;
not exceeding 1.5m deep 451 m3
5,000 Ugx 2,255,000 Ugx
1.04 Return, fill and ram selected excavated materials around
foundations in 150mm layers and compact to 98% MDD. 883 m3
3,000 Ugx 2,649,000 Ugx
1.05 Load, cart, deposit, spread and level surplus excavated
material where directed on site. 244 m3
7,000 Ugx 1,708,000 Ugx
1.06 Extra over all excavations and earthworks for breaking up rock
at any point 34 m3 55,000 Ugx 1,870,000 Ugx
1.07 Allow for provision and subsequent removal of planking and
strutting to uphold and maintain all faces of excavations
generally. 1 item 100,000 Ugx 100,000 Ugx
1.08 Allow for keeping all excavations free from water by pumping,
bailing or other means necessary. 1 item 100,000 Ugx 100,000 Ugx
Hardcore filling.
1.09 230mm filling: deposit, spread, level and compact: 30mm lakesand blinding. 1,090 m
25,600 Ugx 6,104,000 Ugx
Mass concrete mix (1:4:8): in
1.10 50mm thick blinding to foundations 465 m2
9,000 Ugx 4,185,000 Ugx
Total carried to collection 24,997,000 Ugx
Page No. 2/4
-
8/3/2019 Montessori BoQ Priced
5/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
In-situ reinforced concrete class 25/20: vibrated: in
1.11 Strip foundations 72 m3
230,000 Ugx 16,560,000 Ugx
1.12 Steps and ramps 6 m3
230,000 Ugx 1,380,000 Ugx
1.13 Column bases 62 m3
230,000 Ugx 14,260,000 Ugx
1.14 Columns 4 m3
230,000 Ugx 920,000 Ugx
1.15 Ground beams 52 m3
230,000 Ugx 11,960,000 Ugx
1.16 150mm thick ground floor slab 1,180 m2
34,500 Ugx 40,710,000 Ugx
Mesh reinforcement
1.17 Mesh fabric reinforcement ref. A142 weighing 2.22 kg per
square metre: in floor slab: all necessary supports: 200mm side
and end laps 1,180 m2
7,500 Ugx 8,850,000 Ugx
High tensile steel reinforcement to BS 4461 including
cutting to lengths, bending, hoisting and fixing including
all necessary tying wire and spacing blocks.
1.18 12mm bars 1,032 kg 2,500 Ugx 2,580,000 Ugx
1.19 16mm bars 7,629 kg 2,500 Ugx 19,072,500 Ugx
1.20 20mm bars 8,865 kg 2,500 Ugx 22,162,500 Ugx
Mild steel rod reinforcement to BS 4461 as described.
1.21 8mm bars 1,543 kg 2,500 Ugx 3,857,500 Ugx
Sawn formwork: to
1.22 Sides: column bases 163 m2
14,000 Ugx 2,282,000 Ugx
1.23 Sides: columns 82 m2
14,000 Ugx 1,148,000 Ugx
Total carried to collection 145,742,500 Ugx
Page No. 2/5
-
8/3/2019 Montessori BoQ Priced
6/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
Sawn formwork: to
1.24 Sides: ground beams 382 m2
14,000 Ugx 5,348,000 Ugx
1.25 Curved sides: ground beams 69 m2
19,000 Ugx 1,311,000 Ugx
1.26 Sides: ramps 42 m2
14,000 Ugx 588,000 Ugx
1.27 Edges: beds over 75mm but not exceeding 150mm thick
199 lm 4,000 Ugx 796,000 Ugx
Substructure walls
1.28 230mm thick solid concrete block walls: with 2No. 6mm steel
bars every alternate course: bedded and jointed in cement and
sand (1:4) mortar 632 m2
34,000 Ugx 21,488,000 Ugx
Anti-termite treatment
1.29 Gladiator' or other equal approved anti-termite chemical
treatment: applied in accordance with the manufacturer's
instructions 1,645 m2
1,500 Ugx 2,467,500 Ugx
Damp proof membrane
1.30 Gauge 1000 polythene damp proof membrane including
300mm laps. 1,180 m2
2,000 Ugx 2,360,000 Ugx
Hessian based damp proof courses as described bedded,
jointed in cement mortar (1:3).
1.31 Bituminous felt damp proof course: 200mm wide: 230mm laps 315 lm 2,500 Ugx 787,500 Ugx
1.32 Ditto 100mm wide ditto 32 lm 2,500 Ugx 80,000 Ugx
Plinth finishes
1.33 75mm thick selected stone slates to plinth walls and bedded,
jointed and pointed in cement and sand (1:3) mortar.
77 m2
24,000 Ugx 1,848,000 Ugx
Total carried to collection 37,074,000 Ugx
Page No. 2/6
-
8/3/2019 Montessori BoQ Priced
7/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
Splash apron
1.34 75mm thick concrete class 25/20mm aggregate splash
reinforced with and including fabric mesh reinforcement ref
A98. 103 m2
20,500 Ugx 2,111,500 Ugx
1.35 Concrete downstand to ditto size 75 x 125mm deep to egde of
splash apron 176 lm 4,300 Ugx 756,800 Ugx
1.36 38mm thick cement and sand (1:3) paving on splash apron
wood float finish 103 m2
5,500 Ugx 566,500 Ugx
Total carried to collection 3,434,800 Ugx
COLLECTION
Total Page No. 2/2 24,997,000 Ugx
Total Page No. 2/3 145,742,500 Ugx
Total Page No. 2/4 37,074,000 Ugx
Total Page No. 2/5 3,434,800 Ugx
TOTAL ELEMENT No. 1 (SUBSTRUCTURES) CARRIED TO
SUMMARY 211,248,300 Ugx
Page No. 2/7
-
8/3/2019 Montessori BoQ Priced
8/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 2
RC SUPERSTRUCTURE
FRAME
Sawn formwork: to
2.01 Sides: beams 851 m2
14,000 Ugx 11,914,000 Ugx
2.02 Curved sides: beams 43 m2
19,000 Ugx 817,000 Ugx
2.03 Sides: columns 701 m2
14,000 Ugx 9,814,000 Ugx
2.04 Sides and soffites: cantilevered beams 443 m2 14,000 Ugx 6,202,000 Ugx
2.05 Curved sidesand soffites: cantilevered beams 122 m2
19,000 Ugx 2,318,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 as
described including cutting to lengths, bending, hoisting
and fixing including all necessary tying wire and spacing
blocks.
2.06 12mm bars 5,179 kg 2,500 Ugx 12,947,500 Ugx
2.07 16mm bars 6,253 kg 2,500 Ugx 15,632,500 Ugx
2.08 20mm bars 24,290 kg 2,500 Ugx 60,725,000 Ugx
2.09 25mm bars 12,620 kg 2,500 Ugx 31,550,000 Ugx
Mild steel round steel bars to B.S. 4441 as described.
2.10 8mm bars 4,414 kg 2,500 Ugx 11,035,000 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
2.11 Horizontal beams 89 m3
230,000 Ugx 20,470,000 Ugx
2.12 Cantilevered beams 60 m3
230,001 Ugx 13,800,060 Ugx
2.13 Columns 38 m3
230,000 Ugx 8,740,000 Ugx
Total carried to collection 205,965,060 Ugx
Page No. 2/8
-
8/3/2019 Montessori BoQ Priced
9/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
UPPER FLOORS
Sawn formwork: to
2.14 Soffits: suspended composite slab 2,269 m2
14,000 Ugx 31,766,000 Ugx
2.15 Soffits: suspended solid slab 998 m2
14,000 Ugx 13,972,000 Ugx
2.16 Sloping soffits: suspended solid slab 90 m2
14,000 Ugx 1,260,000 Ugx
2.17 Edges: slabs over 150 but not exceeding 225mm girth 597 lm 6,000 Ugx 3,582,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 as
described.
2.18 12mm bars 28,800 kg 2,500 Ugx 72,000,000 Ugx
2.19 16mm bars 3,616 kg 2,500 Ugx 9,040,000 Ugx
Mild steel round steel bars to B.S. 4441 as described.
2.20 8mm bars 1,078 kg 2,500 Ugx 2,695,000 Ugx
2.21 Mesh fabric reinforcement ref. A142 weighing 2.22kg per
square metre: in suspended slab as described. 438 m2
7,500 Ugx 3,285,000 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
2.22 200mm thick solid slab including margin around maxpans 1,088 m2
46,000 Ugx 50,048,000 Ugx
2.23 200mm thick hollow pot suspended slabs construction:
comprising 375 x 150 x 150mm hollow clay blocks in single file:
150mm wide vibrated reinforced concrete class 25/20 ribs
between each line of blocks: 50mm thick vibrated reinforced
concrete class 25/20 topping reinforced with A142 mesh fabric
(m/s) 2,269 m2
38,160 Ugx 86,585,040 Ugx
STAIRS
Sawn formwork: to
2.24 Sloping soffites of staircase 105 m2
14,000 Ugx 1,470,000 Ugx
2.25 Soffits: suspended landings 90 m2
14,000 Ugx 1,260,000 Ugx
Total carried to collection 276,963,040 Ugx
Page No. 2/9
-
8/3/2019 Montessori BoQ Priced
10/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
2.26 Raked edge of staircase, average 287mm girth 63 m2
14,000 Ugx 882,000 Ugx
22.7 Faces of risers, 150mm girth 330 lm 4,000 Ugx 1,320,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 as
described.
22.8 12mm bars 4,984 kg 2,500 Ugx 12,460,000 Ugx
22.9 16mm bars 1,722 kg 2,500 Ugx 4,305,000 Ugx
Mild steel round steel bars to B.S. 4441 as described.
22.10 8mm bars 322 kg 2,500 Ugx 805,000 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
22.11 Staircase 26 m3
230,000 Ugx 5,980,000 Ugx
22.12 150mm thick landing 90 m2
32,250 Ugx 2,902,500 Ugx
Staircase balustrades
22.13 1000mm high balustrading comprising 38 x 38 x 3mm mildsteel square hollow section(SHS) balusters at 1200mm centres
each 950mm high with one end grouted to Concrete floor and
other end welded to flat: 2 No. 38 x 38 x 3mm SHS middle rails
472mm apart welded to balusters: 38 x 38 x 3mm SHS vertical
infill bars at 300mm centres welded to middle rails and flat: 38
x 6mm mild steel flat welded to top of balusters: Ex 75 x 50mm
hardwood handrail fixed to top of flat.
36 lm 95,000 Ugx 3,420,000 Ugx
22.14 Ex 75 x 50mm hardwood handrail fixed to top of flat 42 x 6mm:
flat fixed in position with steel bars 12mm at 300mm centres.36 lm 30,000 Ugx 1,080,000 Ugx
Total carried to collection 33,154,500 Ugx
Page No. 2/10
-
8/3/2019 Montessori BoQ Priced
11/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
COLLECTION
Total Page No. 2/6 205,965,060 Ugx
Total Page No. 2/7 276,963,040 Ugx
Total Page No. 2/8 33,154,500 Ugx
TOTAL ELEMENT No. 2 (R C SUPERSTRUCTURE)
CARRIED TO SUMMARY 516,082,600 Ugx
Page No. 2/11
-
8/3/2019 Montessori BoQ Priced
12/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 3
WALLING
Solid concrete block walling load bearing (4.5N/mm2) to BS
6073 in cement and sand mortar 1:3 mix, laid in suitable
bond, with 6mm mild steel strips laid horizontally every
alternate course.
3.01 200mm thick walling 2,745 m2
34,000 Ugx 93,330,000 Ugx
3.02 200mm thick screen /sunbreaker walling 347 m2
34,000 Ugx 11,798,000 Ugx
3.03 200mm thick walling; curved to profile 638 m2 38,000 Ugx 24,244,000 Ugx
3.04 Labour and materials for eaves filling in 200mm thick walls:
400mm high 80 lm 13,600 Ugx 1,088,000 Ugx
Pompeii grilles or other equal and approved decorative
grilles as 'Uganda Clays' or other equal and approved.
3.05 200mm thick walling 86 m2
24,000 Ugx 2,064,000 Ugx
Precast concrete grade 30 units: reinforced as necessaryand finished fairface on all exposed sides including
hoisting and fixing in position including bedding, pointing
and jointing in cement and sand mortar.
3.06 Copping 350 x 75mm weathered and twice check throated 332 lm 14,000 Ugx 4,648,000 Ugx
Metal work
3.07 1000mm high balustrading comprising 38 x 38 x 3mm mild
steel square hollow section (SHS) balusters at 1200mm
centres each 950mm high with one end grouted to concrete
floor and other end welded to flat: 2 No. 38 x 38 x 3mm SHS
middle rails 472mm apart welded to balusters: 38 x 38 x 3mm
SHS vertical infill bars at 300mm centres welded to middle rails
and 75mm pipe top rail the whole having one coat red oxide
primer and three coats gloss oil paint.
203 lm 95,000 Ugx 19,285,000 Ugx
TOTAL ELEMENT No. 3 (WALLING) TO SUMMARY 156,457,000 Ugx
Page No. 2/12
-
8/3/2019 Montessori BoQ Priced
13/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 4
ROOF
RC works
Sawn formwork: to
4.01 Soffits: suspended roof slab 236 m2
14,000 Ugx 3,304,000 Ugx
4.02 Sides and soffites: ring beams 531 m2
14,000 Ugx 7,434,000 Ugx
4.03 Curved sides and soffites: ring beams 29 m2
19,000 Ugx 551,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 asdescribed including cutting to lengths, bending, hoisting
and fixing including all necessary tying wire and spacing
blocks.
4.04 12mm bars 217 kg 2,500 Ugx 542,500 Ugx
4.05 16mm bars 2,591 kg 2,500 Ugx 6,477,500 Ugx
4.06 20mm bars 4,051 kg 2,500 Ugx 10,127,500 Ugx
4.07 25mm bars 2,821 kg 2,500 Ugx 7,052,500 Ugx
Mild steel round steel bars to B.S. 4441 as described.
4.08 8mm bars 1,605 kg 2,500 Ugx 4,012,500 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
4.09 Ring beams 51 m3
230,000 Ugx 11,730,000 Ugx
4.10 200mm thick solid slab 236 m2
46,000 Ugx 10,856,000 Ugx
Solid concrete block walling load bearing (4.5N/mm2) to BS
6073 as described.
4.11 200mm thick parappet walling 191 m2
34,000 Ugx 6,494,000 Ugx
4.12 200mm thick parappet walling: curved to profile 232 m2
38,000 Ugx 8,816,000 Ugx
Total carried to collection 77,397,500 Ugx
Page No. 2/13
-
8/3/2019 Montessori BoQ Priced
14/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
Waterproofing roof slabs
Cement and sand (1:4) screed with waterproofing agent:
on concrete: wood floated
4.13 25mm thick screed: to receive quarry tiles. 236 m2
9,000 Ugx 2,124,000 Ugx
4.14 Ditto 200mm high skirting 165 lm 1,800 Ugx 297,000 Ugx
Supply and fix 300 x 225mm red clay quarry tiles as
'Uganda Clays' or other equal and approved: on prepared
screed (m/s): joints pointed in matching cement grout
4.15 12mm thick tiles: on screed. 236 m2
26,000 Ugx 6,136,000 Ugx
4.16 Ditto 200mm high skirting 165 lm 5,200 Ugx 858,000 Ugx
Precast concrete grade 30 units: reinforced as necessary
and finished fairface on all exposed sides including
hoisting and fixing in position including bedding, pointing
and jointing in cement and sand mortar.
4.17 Copping 350 x 75mm weathered and twice check throated 95 lm 14,000 Ugx 1,330,000 Ugx
4.18 Ditto curved to profile 69 lm 16,000 Ugx 1,104,000 Ugx
Note: Rendering and parked stone finishes measured
under finishes.
Roof Structure
Sawn cypress: pressure impregnated with preservative
The following in 34No trusses of 8.0m span
4.19 50 x 150mm principal rafter 313 lm 7,000 Ugx 2,191,000 Ugx
4.20 50 x 100mm struts and ties 422 lm 5,500 Ugx 2,321,000 Ugx
4.21 50 x 150mm tie beam 272 lm 7,000 Ugx 1,904,000 Ugx
Total carried to collection 18,265,000 Ugx
Page No. 2/14
-
8/3/2019 Montessori BoQ Priced
15/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
The following in 12No trusses of 7.40m span
4.22 50 x 150mm principal rafter 96 lm 7,000 Ugx 672,000 Ugx
4.23 50 x 100mm struts and ties 138 lm 5,500 Ugx 759,000 Ugx
4.24 50 x 150mm tie beam 89 lm 7,000 Ugx 623,000 Ugx
The following in 7No. trusses of 12.40m span
4.25 50 x 150mm principal rafter 95 lm 7,000 Ugx 665,000 Ugx
4.26 50 x 100mm struts and ties 130 lm 5,500 Ugx 715,000 Ugx
4.27 50 x 150mm tie beam 88 lm 7,000 Ugx 616,000 Ugx
Roof members
4.28 75 x 100mm wall plate including rag bolts to concrete or
masonry at 1000mm centres 497 lm 9,000 Ugx 4,473,000 Ugx
4.29 50 x 150mm purlins 820 lm 9,000 Ugx 7,380,000 Ugx
4.30 25 x 225mm wrot hardwood fascia 101 lm 12,000 Ugx 1,212,000 Ugx
Roof covering
4.31 26gauge pre-painted IT4 roofing sheets fixed with 1 side
corrugated laps and 150mm end laps with and including J bolts
with plastic washers to manufacturer's instructions 899 m2
26,000 Ugx 23,374,000 Ugx
4.32 26 gauge plain (pre-coated) roll top ridge capping complete
with bat proof blocks. 54 lm 12,000 Ugx 648,000 Ugx
Flashings
4.33 24gauge plan (pre-coated) metal flashing and jointing between
masonry or concrete and roof covering. 164 lm 12,000 Ugx 1,968,000 Ugx
Total carried to collection 43,105,000 Ugx
Page No. 2/15
-
8/3/2019 Montessori BoQ Priced
16/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
Unplasticed PVC rain water pipes and fittings as 'Marley'
or other equal and approved complete with all necessaryaccessories.
4.34 110mm streamline gutter complete with gutter unions fascia
clips for fixing to ends of trusses. 106 lm 21,000 Ugx 2,226,000 Ugx
4.35 110mm gutter angles 12 no 20,000 Ugx 240,000 Ugx
4.36 110mm stop ends 4 no 20,000 Ugx 80,000 Ugx
4.37 110 x 75mm gutter outlets 12 no 20,000 Ugx 240,000 Ugx
4.38 75mm rain water down pipe fixed and clipped to walls with
approved holderbats. 154 lm 18,000 Ugx 2,772,000 Ugx
4.39 Extra over down pipe for bends 24 no 20,000 Ugx 480,000 Ugx
4.40 Extra for horse shoe 12 no 20,000 Ugx 240,000 Ugx
Eaves soffits and finishes
4.41 Slatted eaves soffites comprising 50 x 25mm slats at 65mm
centres in 550 x 550mm square chequered perpendicular to
each other complete with coffee tray wire screen and 50 x50mm branderings at 500mm centres. 64 m
211,000 Ugx 704,000 Ugx
Knot prime stop and apply three coats of gloss oil paint to
timber surfaces.
4.42 Slated eaves soffites 64 m2
4,500 Ugx 288,000 Ugx
4.43 Surfaces exceeding 200mm but not exceeding 300mm girth.
101 lm 1,000 Ugx 101,000 Ugx
Total carried to collection 7,371,000 Ugx
Page No. 2/16
-
8/3/2019 Montessori BoQ Priced
17/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
COLLECTION
Total Page No. 2/11 77,397,500 Ugx
Total Page No. 2/12 18,265,000 Ugx
Total Page No. 2/13 43,105,000 Ugx
Total Page No. 2/14 7,371,000 Ugx
TOTAL ELEMENT No. 4 (ROOF & RAINWATER DISPOSAL)CARRIED TO SUMMARY 146,138,500 Ugx
Page No. 2/17
-
8/3/2019 Montessori BoQ Priced
18/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 5
WINDOWS
Precast concrete units: grade 30: reinforced as necessary
and finished fairface on all exposed surfaces including
hoisting and fixing in position.
5.01 75 x 285mm sunk weathered and throated window cill 409 lm 11,500 Ugx 4,703,500 Ugx
Supply and fix purpose made steel casement windows
manufactured from standard window sections:
manufacture, assemble and deliver to site: ironmongery
comprising approved hinges, stays, fasteners to opening
lights and sliding hardware for sliding panes: permanentvents with steel louvre plates: frames drilled, plugged and
screwed or built into walling: one coat red oxide primer
before delivery.
5.02
Window type W1: size 8000 x 1600mm high overall including
outer framing: 300mm high permanent vent above: 4No.sliding
panes size 400 x 1300mm: rest fixed lights. 8 no 1,536,000 Ugx 12,288,000 Ugx
5.03 Window type W2: size 8500 x 1600mm high overall including
outer framing: 300mm high permanent vent above: 4No.sliding
panes size 400 x 1300mm: rest fixed lights. 1 no 1,632,000 Ugx 1,632,000 Ugx
5.04
Window type W3: size 17000 x 1600mm high overall including
outer framing: 300mm high permanent vent above: 8No.sliding
panes size 400 x 1300mm: rest fixed lights. 7 no 3,264,000 Ugx 22,848,000 Ugx
5.05 Window type W4: size 2500 x 10600mm high overall including
outer framing: slit window fixed glass 2 no 3,180,000 Ugx 6,360,000 Ugx
5.06 Window type W5: size 2000 x 1600mm high overall including
outer framing: 300mm high permanent vent above: 2No. top
hung opening lights size 1000 x 1300mm. 70 no 384,000 Ugx 26,880,000 Ugx
Total carried to collection 74,711,500 Ugx
Page No. 2/18
-
8/3/2019 Montessori BoQ Priced
19/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
5.07 Window type W6: size 1200 x 1600mm high overall including
outer framing: 300mm high permanent vent above: 2No. top
hung opening lights size 600 x 1300mm. 60 no 230,400 Ugx 13,824,000 Ugx
Glass and glazing
5.08 8mm thick clear sheet glass in large panes 53 m2
78,000 Ugx 4,134,000 Ugx
5.09 5mm thick clear sheet glass to metal with putty in panes not
exceeding 0.5m2
445 m2
36,000 Ugx 16,020,000 Ugx
Painting
5.10 Prepare touch up primer and apply one undercoat and two
finishing coats of gloss oil paint: on glazed metal windows 891 m2
6,000 Ugx 5,346,000 Ugx
Total carried to collection 39,324,000 Ugx
COLLECTION
Total Page No. 2/16 74,711,500 Ugx
Total Page No. 2/17 39,324,000 Ugx
TOTAL ELEMENT No. 5 (WINDOWS) CARRIED TO
SUMMARY 114,035,500 Ugx
Page No. 2/19
-
8/3/2019 Montessori BoQ Priced
20/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 6
DOORS
Precast concrete units reinforced with 4No. 12mm high
tensile steel bars and 8mm steel stirrups at 200mm
centres.
6.01 200 x 230mm high lintel 124 lm 23,000 Ugx 2,852,000 Ugx
Purpose made steel casement door manufactured from
standard strong Z sections: burglar proofing grille
comprising 20 x 4mm flat bars at 150mm centres as
described: manufacture, assemble and deliver to site:
supply and fix all necessary ironmongery: frames drilled,plugged and screwed or built into walling: permanent vent
with steel louvre plates: one coat red oxide primer before
delivery.
6.02 1800 x 2700mm high overall: permanent vent above 600mm
high: 2No. opening shutter 900 x 2100mm high: glazing bars as
described. 16 no 972,000 Ugx 15,552,000 Ugx
6.03 1200 x 2700mm high overall: permanent vent above 600mm
high: 2No. opening shutter 600 x 2100mm high: glazing bars as
described. 48 no 648,000 Ugx 31,104,000 Ugx
Glass and glazing
6.04 5mm thick clear sheet glass to metal with putty in panes not
exceeding 0.5m2
199 m2
36,000 Ugx 7,164,000 Ugx
Timber doors
50mm thick flush doors: solid core: mahogany veneer:
hardwood lipping to both sides.
6.05 950 x 2075mm high 55 no 100,000 Ugx 5,500,000 Ugx
6.06 850 x 2075mm high 48 no 100,000 Ugx 4,800,000 Ugx
Wrot mahogany: prime grade
6.07 50 x 200mm door frame: rebated: plugged 286 lm 18,500 Ugx 5,291,000 Ugx
Total carried to collection 72,263,000 Ugx
Page No. 2/20
-
8/3/2019 Montessori BoQ Priced
21/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
6.08 50 x 100mm door frame: rebated: plugged 225 lm 12,000 Ugx 2,700,000 Ugx
6.09 15mm quadrant beading 510 lm 4,000 Ugx 2,040,000 Ugx
6.10 40 x 20mm architrave: splayed 1,022 lm 4,000 Ugx 4,088,000 Ugx
Prepare touch up primer and apply one undercoat and
three finishing coats of gloss oil paint: on:
6.11 Glazed metal doors. 415 m2
6,000 Ugx 2,490,000 Ugx
6.12 Burglar proofing grilles 415 m2
6,000 Ugx 2,490,000 Ugx
Knot prime and stop and apply three coats of polyurethane
laquer to general surfaces of:-
6.13 Not exceeding 100mm girth 1,532 lm 1,000 Ugx 1,532,000 Ugx
6.14 Over 200 but not exceeding 300mm girth 511 lm 1,500 Ugx 766,500 Ugx
6.15 General timber surfaces: doors 412 m2
5,000 Ugx 2,060,000 Ugx
Supply and fix: English "Union" or other equal approved
ironmongery: matching screws: locks to include a set of 3keys. (Prices of locks to be inclusive of handles)
6.16
3 lever steel door lock: rebated: complete with lever furniture. 64 no 120,000 Ugx 7,680,000 Ugx
6.17 Three lever mortice lock: cat. no. 2277. complete with lever
furniture. 103 no 75,000 Ugx 7,725,000 Ugx
6.18 Mild steel dowels 10mm x 100mm long: mortice in timber
and concrete 103 no 2,500 Ugx 257,500 Ugx
6.19 250 x 25 x 3mm thick mild steel fixing cramps: one end bent
and screwed to frame: other end flanged and built into block
work or concrete 206 no 2,500 Ugx 515,000 Ugx
6.20 100mm heavy duty steel butt Hinges 155 prs 7,500 Ugx 1,162,500 Ugx
6.21 38mm rubber door stop. 231 no 4,500 Ugx 1,039,500 Ugx
Total carried to collection 36,546,000 Ugx
Page No. 2/21
-
8/3/2019 Montessori BoQ Priced
22/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
COLLECTION
Page No. 2/14 72,263,000 Ugx
Page No. 2/15 36,546,000 Ugx
TOTAL FOR ELEMENT No. 6 (DOORS) CARRIED TO
SUMMARY 108,809,000 Ugx
Page No. 2/22
-
8/3/2019 Montessori BoQ Priced
23/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 7
EXTERNAL FINISHES
External cement and sand(1:4) render: steel trowelled: on
masonry or concrete: to
7.01 15mm thick to walls and concrete surfaces 2,297 m2
6,000 Ugx 13,782,000 Ugx
7.02 12mm thick ditto to reveals externally 150 m2
6,000 Ugx 900,000 Ugx
100mm thick parked stone finish: bedded, jointed and
pointed in cement and mortar (1:3) joints with recessed
joints.
7.03 Stone finish to masonry and concrete 1,874 m2
42,000 Ugx 78,708,000 Ugx
Prepare surfaces: apply three coats weather guard
emulsion paint as 'Sadolin' or other equal and approved:
on steel trowelled plaster: to
7.04 Walls and concrete surfaces externally 2,297 m2
6,000 Ugx 13,782,000 Ugx
7.05 Ditto to reveals 150 m2
6,000 Ugx 900,000 Ugx
TOTAL ELEMENT No. 7 (EXTERNAL FINISHES) CARRIED
TO SUMMARY 108,072,000 Ugx
Page No. 2/23
-
8/3/2019 Montessori BoQ Priced
24/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 8
INTERNAL FINISHES
Floor finishes
Cement and sand (1:4) screeds and pavings: one coat:
wood float finish: laid on concrete
8.01 32mm thick paving to receive ceramic tiles. 4,321 m2
4,000 Ugx 17,284,000 Ugx
8.02 Ditto edge of staircase, average 287mm girth 63 m2
14,000 Ugx 882,000 Ugx
8.03 Ditto risers, 150mm girth 330 lm 4,000 Ugx 1,320,000 Ugx
8.04 Ditto treads, 250mm girth 320 lm 4,000 Ugx 1,280,000 Ugx
8mm thick non-slip coloured ceramic tiles to floor and
bedded jointed in white cement and pointed in matching
mortar joints.
8.05 Ceramic floor tiles 4,321 m2
40,000 Ugx 172,840,000 Ugx
8.06 Ditto edge of staircase, average 287mm girth 63 m2
40,000 Ugx 2,520,000 Ugx
8.07 Ditto risers, 150mm girth 330 lm 8,750 Ugx 2,887,500 Ugx
8.08 Ditto treads, 250mm girth 320 lm 12,250 Ugx 3,920,000 Ugx
8.09 185mm skirting ceramic skirting 2,288 lm 6,750 Ugx 15,444,000 Ugx
Internal wall finishes
Plaster: 15mm thick internal lime plaster
8.10 Walls and concrete surfaces 6,949 m2
6,000 Ugx 41,694,000 Ugx
8.11 Ditto to reveals internally 150 m2 3,200 Ugx 480,000 Ugx
Backing: 10mm cement/sand (1:4): on masonry or
concrete: wood float finished: to
8.12 Walls to receive ceramic tiles (m.s.) 1,465 m2
4,000 Ugx 5,860,000 Ugx
Total carried to collection 266,411,500 Ugx
Page No. 2/24
-
8/3/2019 Montessori BoQ Priced
25/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
200 x 200 x 6mm thick white glazed ceramic wall tiles:
fixed with cement mortar (1:4): to backing (measured
separately): jointed: pointed and grouted in matching
cement mortar: to :-
8.13 Plastered walls 1,465 m2
25,000 Ugx 36,625,000 Ugx
Prepare surfaces: apply three coats vinyl emulsion paint:
on steel trowelled plaster: to
8.14 Walls and concrete surfaces internally 7,099 m2
5,000 Ugx 35,495,000 Ugx
Ceiling finishes
Plaster: 15mm thick internal lime plaster
8.15 Walls and concrete surfaces 3,357 m2
6,000 Ugx 20,142,000 Ugx
8.16 Extra for 100 x 18mm thick cement and sand cornice 2,288 lm 1,400 Ugx 3,203,200 Ugx
Prepare surfaces: apply three coats first grade silk vinyl
emulsion paint: to steel trowelled plastered surfaces
8.17 Horizontal soffites 3,357 m2 6,000 Ugx 20,142,000 Ugx
8.18 Ditto to surfaces not exceeding 100mm girth 2,288 lm 380 Ugx 869,440 Ugx
Sawn cypress or other equal approved including
necessary suspension system: well seasoned: cellcured:
selected and kept clean:
8.19 50 x 50mm branderings 2,258 lm 3,500 Ugx 7,903,000 Ugx
8.20 50 x 100mm joists 2,386 lm 7,000 Ugx 16,702,000 Ugx
8..21 50 x 100mm joists: plugged 1,237 lm 7,000 Ugx 8,659,000 Ugx
8.22 9 x 24 SWG galvanized expanded metal lathing U-nailed to
timber branderings 857 m2
3,500 Ugx 2,999,500 Ugx
Total carried to collection 152,740,140 Ugx
Page No. 2/25
-
8/3/2019 Montessori BoQ Priced
26/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
8.23 6mm cement and sand (1:4) pricking course to metal lathing:11mm lime plaster to ceiling 857 m
212,000 Ugx 10,284,000 Ugx
8.24 Extra for 100 x 18mm thick cement and sand cornice 1,237 lm 1,800 Ugx 2,226,600 Ugx
Prepare surfaces: apply three coats first grade silk vinyl
emulsion paint: to steel trowelled plastered surfaces
8.25 Horizontal soffites 857 m2
6,000 Ugx 5,142,000 Ugx
8.26 Ditto to surfaces not exceeding 100mm girth 1,237 lm 380 Ugx 470,060 Ugx
Total carried to collection 18,122,660 Ugx
COLLECTION
Page No. 2/24 266,411,500 Ugx
Page No. 2/23 152,740,140 Ugx
Page No. 2/24 18,122,660 Ugx
TOTAL ELEMENT No. 8 (INTERNAL FINISHES) CARRIED
TO SUMMARY 437,274,300 Ugx
Page No. 2/26
-
8/3/2019 Montessori BoQ Priced
27/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: CLASSROOM BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 9
FITTINGS & FIXTURES
The following in pinboards
9.02 15mm thick 'cellotex' sofboard (in 24No.) 108 m2
18,000 Ugx 1,944,000 Ugx
9.03 25 x 50mm beading to edges of pinboards 264 lm 4,500 Ugx 1,188,000 Ugx
9.04 Prepare and apply three coats of emulsion paint to surfaces of
pinboards 108 m2
5,000 Ugx 540,000 Ugx
9.05 Knot prime and stop and apply three gloss oil paint to timber
surfaces not exceeding 100mm girth. 264 lm 1,800 Ugx 475,200 Ugx
The following in blackboards
9.06 20mm thick internal lime plaster to walls internally 108 m2
8,000 Ugx 864,000 Ugx
9.07 25 x 50mm timber chalk rails 36 lm 4,500 Ugx 162,000 Ugx
9.08 Prepare and apply three coats of black bitumastic paint to
blackboard surfaces 108 m2
5,000 Ugx 540,000 Ugx
9.09 Knot prime and stop and apply three gloss oil paint to timber
surfaces not exceeding 100mm girth. 36 lm 1,800 Ugx 64,800 Ugx
Provisional sum
9.10 Allow a provisional sum of Ugx 5,000,000 (Five million
shillings) for additional fittings and fixtures to be expended in
part or in whole as directed by the Architect.
1 sum 5,000,000 Ugx 5,000,000 Ugx
TOTAL ELEMENT No. 9 (FITTINGS & FIXTURES) CARRIED
TO SUMMARY 10,778,000 Ugx
Page No. 2/27
-
8/3/2019 Montessori BoQ Priced
28/267
Item Description Qty Unit Rate Amount
Ugx Ugx
BILL No. 3: MULTI-PURPOSE HALL
SUMMARY
1 SUBSTRUCTURE 103,773,100 Ugx
2 RC SUPERSTRUCTURE 84,616,500 Ugx
3 WALLING 62,189,000 Ugx
4 ROOF & RAINWATER DISPOSAL 89,496,000 Ugx
5 WINDOWS 29,464,000 Ugx
6 DOORS 13,316,000 Ugx
7 EXTERNAL FINISHES 54,948,000 Ugx
8 INTERNAL FINISHES 99,702,100 Ugx
9 FITTINGS & FIXTURES 10,000,000 Ugx
TOTAL BILL No. 3 (MULTI-PURPOSE HALL) CARRIED TO
GENERAL SUMMARY 547,504,700 Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
Page No. 3/28
-
8/3/2019 Montessori BoQ Priced
29/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 1SUBSTRUCTURE
Site preparation
1.01 Excavate oversite to remove vegetable soil average 150mm
thick, remove excavated material from site 950 m2
1,800 Ugx 1,710,000 Ugx
Excavations & earthworks
1.02 Excavate for foundation trenches commencing from reduced
level: not exceeding 1.5m deep 320 m
3
5,000 Ugx 1,600,000 Ugx
1.03 Excavate pit for column bases commencing from stripped level;
not exceeding 1.5m deep 185 m3
5,000 Ugx 925,000 Ugx
1.04 Return, fill and ram selected excavated materials around
foundations in 150mm layers and compact to 98% MDD. 399 m3
3,000 Ugx 1,197,000 Ugx
1.05 Load, cart, deposit, spread and level surplus excavated
material where directed on site. 106 m3
7,000 Ugx 742,000 Ugx
1.06 Extra over all excavations and earthworks for breaking up rock
at any point 23 m3 55,000 Ugx 1,265,000 Ugx
1.07 Allow for provision and subsequent removal of planking and
strutting to uphold and maintain all faces of excavations
generally. 1 item 100,000 Ugx 100,000 Ugx
1.08 Allow for keeping all excavations free from water by pumping,
bailing or other means necessary. 1 item 100,000 Ugx 100,000 Ugx
Hardcore filling.
1.09 230mm filling: deposit, spread, level and compact: 30mm lakesand blinding. 679 m
25,600 Ugx 3,802,400 Ugx
Mass concrete mix (1:4:8): in
1.10 50mm thick blinding to foundations 199 m2
9,000 Ugx 1,791,000 Ugx
Total carried to collection 13,232,400 Ugx
Page No. 3/29
-
8/3/2019 Montessori BoQ Priced
30/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
In-situ reinforced concrete class 25/20: vibrated: in
1.11 Strip foundations 34 m3
230,000 Ugx 7,820,000 Ugx
1.12 Steps and ramps 12 m3
230,000 Ugx 2,760,000 Ugx
1.13 Column bases 16 m3
230,000 Ugx 3,680,000 Ugx
1.14 Columns 2 m3
230,000 Ugx 460,000 Ugx
1.15 Ground beams 2 m3
230,000 Ugx 460,000 Ugx
1.16 150mm thick ground floor slab 747 m2
34,500 Ugx 25,771,500 Ugx
Mesh reinforcement
1.17 Mesh fabric reinforcement ref. A142 weighing 2.22 kg per
square metre: in floor slab: all necessary supports: 200mm side
and end laps 747 m2
7,500 Ugx 5,602,500 Ugx
High tensile steel reinforcement to BS 4461 including
cutting to lengths, bending, hoisting and fixing including
all necessary tying wire and spacing blocks.
1.18 12mm bars 2,749 kg 2,500 Ugx 6,872,500 Ugx
1.19 16mm bars 3,720 kg 2,500 Ugx 9,300,000 Ugx
1.20 20mm bars 1,150 kg 2,500 Ugx 2,875,000 Ugx
Mild steel rod reinforcement to BS 4461 as described.
1.21 8mm bars 356 kg 2,500 Ugx 890,000 Ugx
Sawn formwork: to
1.22 Sides: column bases 56 m2
14,000 Ugx 784,000 Ugx
1.23 Sides: columns 23 m2
14,000 Ugx 322,000 Ugx
Total carried to collection 67,597,500 Ugx
Page No. 3/30
-
8/3/2019 Montessori BoQ Priced
31/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
Sawn formwork: to
1.24 Sides: columns 200mm 21 m2
19,000 Ugx 399,000 Ugx
1.25 Sides: ground beams 23 m2
14,000 Ugx 322,000 Ugx
1.26 Sides: ramps 24 m2
14,000 Ugx 336,000 Ugx
1.27 Edges: beds over 75mm but not exceeding 150mm thick
219 lm 4,000 Ugx 876,000 Ugx
Substructure walls
1.28 230mm thick solid concrete block walls: with 2No. 6mm steel
bars every alternate course: bedded and jointed in cement and
sand (1:4) mortar 116 m2
34,000 Ugx 3,944,000 Ugx
1.29 230mm thick Ditto curved to profile 193 m2
34,000 Ugx 6,562,000 Ugx
Anti-termite treatment
1.30 Gladiator' or other equal approved anti-termite chemical
treatment: applied in accordance with the manufacturer's
instructions 946 m2
1,500 Ugx 1,419,000 Ugx
Damp proof membrane
1.31 Gauge 1000 polythene damp proof membrane including
300mm laps. 747 m2
2,000 Ugx 1,494,000 Ugx
Hessian based damp proof courses as described bedded,
jointed in cement mortar (1:3).
1.32 Bituminous felt damp proof course: 200mm wide: 230mm laps 315 lm 2,500 Ugx 787,500 Ugx
1.33 Ditto 100mm wide ditto 32 lm 2,500 Ugx 80,000 Ugx
Plinth finishes
1.34 75mm thick selected stone slates to plinth walls and bedded,
jointed and pointed in cement and sand (1:3) mortar.
99 m2
24,000 Ugx 2,376,000 Ugx
Total carried to collection 18,595,500 Ugx
Page No. 3/31
-
8/3/2019 Montessori BoQ Priced
32/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
Splash apron
1.35 75mm thick concrete class 25/20mm aggregate splash
reinforced with and including fabric mesh reinforcement ref
A98. 131 m2
20,500 Ugx 2,685,500 Ugx
1.36 Concrete downstand to ditto size 75 x 125mm deep to egde of
splash apron 219 lm 4,300 Ugx 941,700 Ugx
1.37 38mm thick cement and sand (1:3) paving on splash apron
wood float finish 131 m2
5,500 Ugx 720,500 Ugx
Total carried to collection 4,347,700 Ugx
COLLECTION
Total Page No. 3/2 13,232,400 Ugx
Total Page No. 3/3 67,597,500 Ugx
Total Page No. 3/4 18,595,500 Ugx
Total Page No. 3/5 4,347,700 Ugx
TOTAL ELEMENT No. 1 (SUBSTRUCTURES) CARRIED TO
SUMMARY 103,773,100 Ugx
Page No. 3/32
-
8/3/2019 Montessori BoQ Priced
33/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 2
RC SUPERSTRUCTURE
FRAME
Sawn formwork: to
2.01 Sides: beams 219 m2
14,000 Ugx 3,066,000 Ugx
2.02 Curved sides: beams 155 m2
19,000 Ugx 2,945,000 Ugx
2.03 Sides: columns 85 m2
14,000 Ugx 1,190,000 Ugx
2.04 Sides: columns 200mm 94 m2
19,000 Ugx 1,786,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 as
described including cutting to lengths, bending, hoisting
and fixing including all necessary tying wire and spacing
blocks.
2.05 12mm bars 5,960 kg 2,500 Ugx 14,900,000 Ugx
2.06 16mm bars 1,905 kg 2,500 Ugx 4,762,500 Ugx
2.07 20mm bars425
kg 2,500 Ugx 1,062,500 Ugx
Mild steel round steel bars to B.S. 4441 as described.
2.08 8mm bars 1,554 kg 2,500 Ugx 3,885,000 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
2.09 Horizontal beams 38 m3
230,000 Ugx 8,740,000 Ugx
2.10 Columns 9 m3
230,000 Ugx 2,070,000 Ugx
UPPER FLOORS
Sawn formwork: to
2.11 Soffits: suspended solid slab 298 m2
14,000 Ugx 4,172,000 Ugx
2.12 Edges: slabs over 150 but not exceeding 225mm girth 130 lm 6,000 Ugx 780,000 Ugx
Total carried to collection 49,359,000 Ugx
Page No. 3/33
-
8/3/2019 Montessori BoQ Priced
34/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
High yield tensile steel bar reinforcement to BS 4461 as
described.
2.13 12mm bars 5,960 kg 2,500 Ugx 14,900,000 Ugx
2.14 16mm bars 312 kg 2,500 Ugx 780,000 Ugx
Mild steel round steel bars to B.S. 4441 as described.
2.15 8mm bars 129 kg 2,500 Ugx 322,500 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
2.16 200mm thick solid slab 298 m2 46,000 Ugx 13,708,000 Ugx
STAIRS
Sawn formwork: to
2.17 Sloping soffites of staircase 10 m2
14,000 Ugx 140,000 Ugx
2.18 Soffits: suspended landings 10 m2
14,000 Ugx 140,000 Ugx
2.19 Raked edge of staircase, average 287mm girth 4 m2
14,000 Ugx 56,000 Ugx
2.20 Faces of risers, 150mm girth 38 lm 4,000 Ugx 152,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 as
described.
2.21 12mm bars 712 kg 2,500 Ugx 1,780,000 Ugx
2.22 16mm bars 246 kg 2,500 Ugx 615,000 Ugx
Mild steel round steel bars to B.S. 4441 as described.
2.23 8mm bars 46 kg 2,500 Ugx 115,000 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
2.24 Staircase 4 m3
230,000 Ugx 920,000 Ugx
2.25 150mm thick landing 4 m2
32,250 Ugx 129,000 Ugx
Total carried to collection 33,757,500 Ugx
Page No. 3/34
-
8/3/2019 Montessori BoQ Priced
35/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
Staircase balustrades
2.26 1000mm high balustrading comprising 38 x 38 x 3mm mild
steel square hollow section (SHS) balusters at 1200mm
centres each 950mm high with one end grouted to Concrete
floor and other end welded to flat: 2 No. 38 x 38 x 3mm SHS
middle rails 472mm apart welded to balusters: 38 x 38 x 3mm
SHS vertical infill bars at 300mm centres welded to middle rails
and flat: 38 x 6mm mild steel flat welded to top of balusters: Ex
75 x 50mm hardwood handrail fixed to top of flat.
12 lm 95,000 Ugx 1,140,000 Ugx
2.27 Ex 75 x 50mm hardwood handrail fixed to top of flat 42 x 6mm:
flat fixed in position with steel bars 12mm at 300mm centres.12 lm 30,000 Ugx 360,000 Ugx
Total carried to collection 1,500,000 Ugx
COLLECTION
Total Page No. 3/6 49,359,000 Ugx
Total Page No. 3/7 33,757,500 Ugx
Total Page No. 3/8 1,500,000 Ugx
TOTAL ELEMENT No. 2 (R C SUPERSTRUCTURE)
CARRIED TO SUMMARY 84,616,500 Ugx
Page No. 3/35
-
8/3/2019 Montessori BoQ Priced
36/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 3
WALLING
Solid concrete block walling load bearing (4.5N/mm2) to BS
6073 in cement and sand mortar 1:3 mix, laid in suitable
bond, with 6mm mild steel strips laid horizontally every
alternate course.
3.01 200mm thick external walling 767 m2
34,000 Ugx 26,078,000 Ugx
3.02 200mm thick gable walling 413 m2
34,000 Ugx 14,042,000 Ugx
3.03 200mm thick internal walling 293 m2 34,000 Ugx 9,962,000 Ugx
3.04 Labour and materials for eaves filling in 200mm thick walls:
400mm high 70 lm 13,600 Ugx 952,000 Ugx
Pompeii grilles or other equal and approved decorative
grilles as 'Uganda Clays' or other equal and approved.
3.05 200mm thick walling 12 m2
24,000 Ugx 288,000 Ugx
Precast concrete grade 30 units: reinforced as necessaryand finished fairface on all exposed sides including
hoisting and fixing in position including bedding, pointing
and jointing in cement and sand mortar.
3.06 Copping 350 x 75mm weathered and twice check throated 118 lm 14,000 Ugx 1,652,000 Ugx
Metal work
3.07 1000mm high balustrading comprising 38 x 38 x 3mm mild
steel square hollow section (SHS) balusters at 1200mm
centres each 950mm high with one end grouted to concrete
floor and other end welded to flat: 2 No. 38 x 38 x 3mm SHS
middle rails 472mm apart welded to balusters: 38 x 38 x 3mm
SHS vertical infill bars at 300mm centres welded to middle rails
and 75mm pipe top rail the whole having one coat red oxide
primer and three coats gloss oil paint.
97 lm 95,000 Ugx 9,215,000 Ugx
TOTAL ELEMENT No. 3 (WALLING) TO SUMMARY 62,189,000 Ugx
Page No. 3/36
-
8/3/2019 Montessori BoQ Priced
37/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 4
ROOF
RC works
Sawn formwork: to
4.01 Soffits: suspended roof slab 38 m2
14,000 Ugx 532,000 Ugx
4.02 Sides and soffites: ring beams 110 m2
14,000 Ugx 1,540,000 Ugx
4.03 Curved sides and soffites: ring beams 155 m2
19,000 Ugx 2,945,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 asdescribed including cutting to lengths, bending, hoisting
and fixing including all necessary tying wire and spacing
blocks.
4.04 12mm bars 760 kg 2,500 Ugx 1,900,000 Ugx
4.05 16mm bars 1,905 kg 2,500 Ugx 4,762,500 Ugx
4.06 20mm bars 425 kg 2,500 Ugx 1,062,500 Ugx
Mild steel round steel bars to B.S. 4441 as described.
4.07 8mm bars 1,104 kg 2,500 Ugx 2,760,000 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
4.08 Ring beams 30 m3
230,000 Ugx 6,900,000 Ugx
4.09 200mm thick solid slab 38 m2
46,000 Ugx 1,748,000 Ugx
Waterproofing roof slabs
Cement and sand (1:4) screed with waterproofing agent:
on concrete: wood floated
4.10 25mm thick screed: to receive quarry tiles. 38 m2
9,000 Ugx 342,000 Ugx
4.11 Ditto 200mm high skirting 12 lm 1,800 Ugx 21,600 Ugx
Total carried to collection 24,513,600 Ugx
Page No. 3/37
-
8/3/2019 Montessori BoQ Priced
38/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
Supply and fix 300 x 225mm red clay quarry tiles as
'Uganda Clays' or other equal and approved: on preparedscreed (m/s): joints pointed in matching cement grout
4.12 12mm thick tiles: on screed. 38 m2
26,000 Ugx 988,000 Ugx
4.13 Ditto 200mm high skirting 12 lm 5,200 Ugx 62,400 Ugx
Precast concrete grade 30 units: reinforced as necessary
and finished fairface on all exposed sides including
hoisting and fixing in position including bedding, pointing
and jointing in cement and sand mortar.
4.14 Copping 350 x 75mm weathered and twice check throated 48 lm 14,000 Ugx 672,000 Ugx
4.15 Ditto curved to profile 70 lm 16,000 Ugx 1,120,000 Ugx
Note: Rendering and parked stone finishes measured
under finishes.
Roof Structure
Mild steel sections and plates.
Framed structural steelwork comprising steel sections toBS 46 (hot rolled section) and grade 43 'C' steel to BS 4360
(weldable structural steel). Fabricate, deliver to site roof
structure including hoisting and fixing 3m above ground
with welded shop and site connections including all
connecting plates, cleats, brackets, bolts, all cutting
drilling, bolting and welding unless otherwise said the
whole having one coat of zinc chromate or lead graphite
primer. All welds to be 6mm fillet weld and gusset plates to
be 6mm thick.
The following in 1No. Truss type T1 spanning 12390mm.
4.16 100 x 50 x 3mm RHS rafter 276 lm 26,000 Ugx 7,176,000 Ugx
4.17 100 x 50 x 3mm RHS bottom tie 276 lm 26,000 Ugx 7,176,000 Ugx
4.18 50 x 50 x 3mm RHS strut / tie 758 lm 16,000 Ugx 12,128,000 Ugx
Total carried to collection 29,322,400 Ugx
Page No. 3/38
-
8/3/2019 Montessori BoQ Priced
39/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
Roof members
4.19 175 x 75 x 3L Zed purlins including 75 x 75 x 3L purlin cleats
on trusses. 420 lm 20,000 Ugx 8,400,000 Ugx
4.20 16mm anti-sag rods. 180 lm 12,000 Ugx 2,160,000 Ugx
Truss fixing
4.21 Truss fixing: 200 x 200 x 6mm thick base plate with and
including 2No. 16mm HD bolts and grout into concrete, 75 x
75 x 4L gusset plates welded to rafters to detail 24 no 40,000 Ugx 960,000 Ugx
Fascia
4.22 25 x 225mm wrot hardwood fascia fixed to ends of rafters to
detail 14 lm 12,000 Ugx 168,000 Ugx
Roof covering
4.23 26gauge pre-painted IT4 roofing sheets fixed with 1 side
corrugated laps and 150mm end laps with and including J bolts
with plastic washers to manufacturer's instructions 757 m2
26,000 Ugx 19,682,000 Ugx
Flashings
4.24 24gauge plan (pre-coated) metal flashing and jointing between
masonry or concrete and roof covering. 118 lm 12,000 Ugx 1,416,000 Ugx
Unplasticed PVC rain water pipes and fittings as 'Marley'
or other equal and approved complete with all necessary
accessories.
4.25 110mm streamline gutter complete with gutter unions fascia
clips for fixing to ends of trusses. 14 lm 21,000 Ugx 294,000 Ugx
4.26 110mm gutter angles 2 no 20,000 Ugx 40,000 Ugx
4.27 110mm stop ends 2 no 20,000 Ugx 40,000 Ugx
4.28 110 x 75mm gutter outlets 12 no 20,000 Ugx 240,000 Ugx
Total carried to collection 33,400,000 Ugx
Page No. 3/39
-
8/3/2019 Montessori BoQ Priced
40/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
4.29 75mm rain water down pipe fixed and clipped to walls with
approved holderbats. 84 lm 18,000 Ugx 1,512,000 Ugx
4.30 Extra over down pipe for bends 24 no 20,000 Ugx 480,000 Ugx
4.31 Extra for horse shoe 12 no 20,000 Ugx 240,000 Ugx
Knot prime stop and apply three coats of gloss oil paint to
timber surfaces.
4.32 Surfaces exceeding 200mm but not exceeding 300mm girth.
28 lm 1,000 Ugx 28,000 Ugx
Total carried to collection 2,260,000 Ugx
COLLECTION
Total Page No. 3/10 24,513,600 Ugx
Total Page No. 3/11 29,322,400 Ugx
Total Page No. 3/12 33,400,000 Ugx
Total Page No. 3/13 2,260,000 Ugx
TOTAL ELEMENT No. 4 (ROOF & RAINWATER DISPOSAL)CARRIED TO SUMMARY 89,496,000 Ugx
Page No. 3/40
-
8/3/2019 Montessori BoQ Priced
41/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 5
WINDOWS
Precast concrete units: grade 30: reinforced as necessary
and finished fairface on all exposed surfaces including
hoisting and fixing in position.
5.01 75 x 285mm sunk weathered and throated window cill 184 lm 11,500 Ugx 2,116,000 Ugx
Supply and fix purpose made steel casement windows
manufactured from standard window sections:
manufacture, assemble and deliver to site: ironmongery
comprising approved hinges, stays, fasteners to opening
lights and sliding hardware for sliding panes: permanentvents with steel louvre plates: frames drilled, plugged and
screwed or built into walling: one coat red oxide primer
before delivery.
5.02
Window type W1: size 900 x 1500mm high overall including
outer framing: 300mm high permanent vent above: 1No. top
hung opening light size 900 x 1200mm: rest fixed lights. 126 no 162,000 Ugx 20,412,000 Ugx
Glass and glazing
5.03 5mm thick clear sheet glass to metal with putty in panes not
exceeding 0.5m2
136 m2
36,000 Ugx 4,896,000 Ugx
Painting
5.04 Prepare touch up primer and apply one undercoat and two
finishing coats of gloss oil paint: on glazed metal windows 340 m2
6,000 Ugx 2,040,000 Ugx
TOTAL ELEMENT No. 5 (WINDOWS) CARRIED TO
SUMMARY 29,464,000 Ugx
Page No. 3/41
-
8/3/2019 Montessori BoQ Priced
42/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 6
DOORS
Precast concrete units reinforced with 4No. 12mm high
tensile steel bars and 8mm steel stirrups at 200mm
centres.
6.01 200 x 230mm high lintel 36 lm 23,000 Ugx 828,000 Ugx
Purpose made steel casement door manufactured from
standard strong Z sections: burglar proofing grille
comprising 20 x 4mm flat bars at 150mm centres as
described: manufacture, assemble and deliver to site:
supply and fix all necessary ironmongery: frames drilled,plugged and screwed or built into walling: permanent vent
with steel louvre plates: one coat red oxide primer before
delivery.
6.02 Door type D1 size 2400 x 2600mm high overall: 2No. opening
shutters 1200 x 2600mm high: glazing bars as described.
1 no 1,248,000 Ugx 1,248,000 Ugx
6.03 Door type D2 size 1200 x 2400mm high overall: sliding panes:
glazing bars as described. 4 no 576,000 Ugx 2,304,000 Ugx
6.04 Door type D3 size 1800 x 2500mm high overall: permanent
vent above 400mm high: 2No. opening shutter 900 x 2100mm
high: glazing bars as described. 4 no 900,000 Ugx 3,600,000 Ugx
Glass and glazing
6.05 6mm thick clear sheet glass to metal with putty in panes not
exceeding 0.5m2
36 m2
36,000 Ugx 1,296,000 Ugx
Timber doors
50mm thick flush doors: solid core: mahogany veneer:hardwood lipping to both sides.
6.06 850 x 2075mm high 6 no 100,000 Ugx 600,000 Ugx
Wrot mahogany: prime grade
6.07 50 x 100mm door frame: rebated: plugged 31 lm 12,000 Ugx 372,000 Ugx
Total carried to collection 10,248,000 Ugx
Page No. 3/42
-
8/3/2019 Montessori BoQ Priced
43/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
6.08 15mm quadrant beading 31 lm 4,000 Ugx 124,000 Ugx
6.09 40 x 20mm architrave: splayed 31 lm 4,000 Ugx 124,000 Ugx
Prepare touch up primer and apply one undercoat and
three finishing coats of gloss oil paint: on:
6.10 Glazed metal doors. 72 m2
6,000 Ugx 432,000 Ugx
6.11 Burglar proofing grilles 72 m2
6,000 Ugx 432,000 Ugx
Knot prime and stop and apply three coats of polyurethane
laquer to general surfaces of:-
6.12 Not exceeding 100mm girth 62 lm 1,000 Ugx 62,000 Ugx
6.13 Over 200 but not exceeding 300mm girth 31 lm 1,500 Ugx 46,500 Ugx
6.14 General timber surfaces: doors 23 m2
5,000 Ugx 115,000 Ugx
Supply and fix: English "Union" or other equal approved
ironmongery: matching screws: locks to include a set of 3
keys. (Prices of locks to be inclusive of handles)
6.15
3 lever steel door lock: rebated: complete with lever furniture. 9 no 120,000 Ugx 1,080,000 Ugx
6.16 Three lever mortice lock: cat. no. 2277. complete with lever
furniture. 6 no 75,000 Ugx 450,000 Ugx
6.17 Mild steel dowels 10mm x 100mm long: mortice in timber
and concrete 6 no 2,500 Ugx 15,000 Ugx
6.18 250 x 25 x 3mm thick mild steel fixing cramps: one end bent
and screwed to frame: other end flanged and built into block
work or concrete 12 no 2,500 Ugx 30,000 Ugx
6.19 100mm heavy duty steel butt Hinges 9 prs 7,500 Ugx 67,500 Ugx
6.20 38mm rubber door stop. 20 no 4,500 Ugx 90,000 Ugx
Total carried to collection 3,068,000 Ugx
Page No. 3/43
-
8/3/2019 Montessori BoQ Priced
44/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
COLLECTION
Page No. 3/15 10,248,000 Ugx
Page No. 3/16 3,068,000 Ugx
TOTAL FOR ELEMENT No. 6 (DOORS) CARRIED TO
SUMMARY 13,316,000 Ugx
Page No. 3/44
-
8/3/2019 Montessori BoQ Priced
45/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 7
EXTERNAL FINISHES
External cement and sand(1:4) render: steel trowelled: on
masonry or concrete: to
7.01 15mm thick to walls and concrete surfaces 413 m2
6,000 Ugx 2,478,000 Ugx
7.02 12mm thick ditto to reveals externally 36 m2
6,000 Ugx 216,000 Ugx
100mm thick parked stone finish: bedded, jointed and
pointed in cement and mortar (1:3) joints with recessed
joints.
7.03 Stone finish to masonry and concrete 1,180 m2
42,000 Ugx 49,560,000 Ugx
Prepare surfaces: apply three coats weather guard
emulsion paint as 'Sadolin' or other equal and approved:
on steel trowelled plaster: to
7.04 Walls and concrete surfaces externally 413 m2
6,000 Ugx 2,478,000 Ugx
7.05 Ditto to reveals 36 m2
6,000 Ugx 216,000 Ugx
TOTAL ELEMENT No. 7 (EXTERNAL FINISHES) CARRIED
TO SUMMARY 54,948,000 Ugx
Page No. 3/45
-
8/3/2019 Montessori BoQ Priced
46/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 8
INTERNAL FINISHES
Floor finishes
Cement and sand (1:4) screeds and pavings: one coat:
wood float finish: laid on concrete
8.01 32mm thick paving to receive ceramic tiles. 897 m2
4,000 Ugx 3,588,000 Ugx
8.02 Ditto edge of staircase, average 287mm girth 6 m2
14,000 Ugx 84,000 Ugx
8.03 Ditto risers, 150mm girth 38 lm 4,000 Ugx 152,000 Ugx
8.04 Ditto treads, 250mm girth 42 lm 4,000 Ugx 168,000 Ugx
8mm thick non-slip coloured ceramic tiles to floor and
bedded jointed in white cement and pointed in matching
mortar joints.
8.05 Ceramic floor tiles 897 m2
40,000 Ugx 35,880,000 Ugx
8.06 Ditto edge of staircase, average 287mm girth 6 m2
40,000 Ugx 240,000 Ugx
8.07 Ditto risers, 150mm girth38
lm 8,750 Ugx 332,500 Ugx
8.08 Ditto treads, 250mm girth 42 lm 12,250 Ugx 514,500 Ugx
8.09 185mm skirting ceramic skirting 202 lm 6,750 Ugx 1,363,500 Ugx
Internal wall finishes
Plaster: 15mm thick internal lime plaster
8.10 Walls and concrete surfaces 1,353 m2
6,000 Ugx 8,118,000 Ugx
8.11 Ditto to reveals internally36
m2
3,200 Ugx 115,200 Ugx
Backing: 10mm cement/sand (1:4): on masonry or
concrete: wood float finished: to
8.12 Walls to receive ceramic tiles (m.s.) 36 m2
4,000 Ugx 144,000 Ugx
Total carried to collection 50,699,700 Ugx
Page No. 3/46
-
8/3/2019 Montessori BoQ Priced
47/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
200 x 200 x 6mm thick white glazed ceramic wall tiles:
fixed with cement mortar (1:4): to backing (measuredseparately): jointed: pointed and grouted in matching
cement mortar: to :-
8.13 Plastered walls 36 m2
25,000 Ugx 900,000 Ugx
Prepare surfaces: apply three coats vinyl emulsion paint:
on steel trowelled plaster: to
8.14 Walls and concrete surfaces internally 1,389 m2
5,000 Ugx 6,945,000 Ugx
Ceiling finishesPlaster: 15mm thick internal lime plaster
8.15 Walls and concrete surfaces 298 m2
6,000 Ugx 1,788,000 Ugx
8.16 Extra for 100 x 18mm thick cement and sand cornice 130 lm 1,400 Ugx 182,000 Ugx
Prepare surfaces: apply three coats first grade silk vinyl
emulsion paint: to steel trowelled plastered surfaces
8.17 Horizontal soffites 298 m2
6,000 Ugx 1,788,000 Ugx
8.18 Ditto to surfaces not exceeding 100mm girth 130 lm 380 Ugx 49,400 Ugx
Suspended ceiling
8.19 Mineral fibre suspended ceiling as 'Tile Centre' or equal and
approved in 600 x 600mm compartments complete with
aluminium ceiling structure and secured to roof trusses
747 m2
50,000 Ugx 37,350,000 Ugx
Total carried to collection 49,002,400 Ugx
COLLECTION
Page No. 3/24 50,699,700 Ugx
Page No. 3/23 49,002,400 Ugx
TOTAL ELEMENT No. 8 (INTERNAL FINISHES) CARRIED
TO SUMMARY 99,702,100 Ugx
Page No. 3/47
-
8/3/2019 Montessori BoQ Priced
48/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: MULTI-PURPOSE HALL
New Construction Works at Montessori Education Centre
ELEMENT No. 9
FITTINGS & FIXTURES
Provisional sum
9.01 Allow a provisional sum of Ugx 10,000,000 (Ten million
shillings) for additional fittings and fixtures to be expended in
part or in whole as directed by the Architect.
1 sum 10,000,000 Ugx 10,000,000 Ugx
TOTAL ELEMENT No. 9 (FITTINGS & FIXTURES) CARRIED
TO SUMMARY 10,000,000 Ugx
Page No. 3/48
-
8/3/2019 Montessori BoQ Priced
49/267
Item Description Qty Unit Rate Amount
Ugx Ugx
BILL No. 4: KITCHEN BLOCK
SUMMARY
1 SUBSTRUCTURE 24,727,800 Ugx
2 RC SUPERSTRUCTURE 24,131,000 Ugx
3 WALLING 10,620,800 Ugx
4 ROOF & RAINWATER DISPOSAL 17,336,500 Ugx
5 WINDOWS 9,663,500 Ugx
6 DOORS 5,192,500 Ugx
7 EXTERNAL FINISHES 8,238,000 Ugx
8 INTERNAL FINISHES 22,013,110 Ugx
9 FITTINGS & FIXTURES 5,000,000 Ugx
TOTAL BILL No. 4 (KITCHEN BLOCK) CARRIED TO
GENERAL SUMMARY 126,923,210 Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
Page No. 4/49
-
8/3/2019 Montessori BoQ Priced
50/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 1SUBSTRUCTURE
Site preparation
1.01 Excavate oversite to remove vegetable soil average 150mm
thick, remove excavated material from site 317 m2
1,800 Ugx 570,600 Ugx
Excavations & earthworks
1.02 Excavate for foundation trenches commencing from reduced
level: not exceeding 1.5m deep 145 m
3
5,000 Ugx 725,000 Ugx
1.03 Excavate pit for column bases commencing from stripped level;
not exceeding 1.5m deep 54 m3
5,000 Ugx 270,000 Ugx
1.04 Return, fill and ram selected excavated materials around
foundations in 150mm layers and compact to 98% MDD. 154 m3
3,000 Ugx 462,000 Ugx
1.05 Load, cart, deposit, spread and level surplus excavated
material where directed on site. 45 m3
7,000 Ugx 315,000 Ugx
1.06 Extra over all excavations and earthworks for breaking up rock
at any point 12 m3 55,000 Ugx 660,000 Ugx
1.07 Allow for provision and subsequent removal of planking and
strutting to uphold and maintain all faces of excavations
generally. 1 item 100,000 Ugx 100,000 Ugx
1.08 Allow for keeping all excavations free from water by pumping,
bailing or other means necessary. 1 item 100,000 Ugx 100,000 Ugx
Hardcore filling.
1.09 230mm filling: deposit, spread, level and compact: 30mm lakesand blinding. 145 m
25,600 Ugx 812,000 Ugx
Mass concrete mix (1:4:8): in
1.10 50mm thick blinding to foundations 72 m2
9,000 Ugx 648,000 Ugx
Total carried to collection 4,662,600 Ugx
Page No. 4/50
-
8/3/2019 Montessori BoQ Priced
51/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
In-situ reinforced concrete class 25/20: vibrated: in
1.11 Strip foundations 13 m3
230,000 Ugx 2,990,000 Ugx
1.12 Steps and ramps 2 m3
230,000 Ugx 460,000 Ugx
1.13 Column bases 4 m3
230,000 Ugx 920,000 Ugx
1.14 Columns 1 m3
230,000 Ugx 230,000 Ugx
1.15 150mm thick ground floor slab 155 m2
34,500 Ugx 5,347,500 Ugx
Mesh reinforcement
1.16 Mesh fabric reinforcement ref. A142 weighing 2.22 kg per
square metre: in floor slab: all necessary supports: 200mm side
and end laps 155 m2
7,500 Ugx 1,162,500 Ugx
High tensile steel reinforcement to BS 4461 including
cutting to lengths, bending, hoisting and fixing including
all necessary tying wire and spacing blocks.
1.17 12mm bars 256 kg 2,500 Ugx 640,000 Ugx
1.18 16mm bars 298 kg 2,500 Ugx 745,000 Ugx
Mild steel rod reinforcement to BS 4461 as described.
1.19 8mm bars 122 kg 2,500 Ugx 305,000 Ugx
Sawn formwork: to
1.20 Sides: column bases 17 m2
14,000 Ugx 238,000 Ugx
1.21 Sides: columns 19 m2
14,000 Ugx 266,000 Ugx
1.22 Sides: ramps 12 m2
14,000 Ugx 168,000 Ugx
1.23 Edges: beds over 75mm but not exceeding 150mm thick 48 lm 4,000 Ugx 192,000 Ugx
Total carried to collection 13,664,000 Ugx
Page No. 4/51
-
8/3/2019 Montessori BoQ Priced
52/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
Substructure walls
1.24 200mm thick solid concrete block walls: with 2No. 6mm steel
bars every alternate course: bedded and jointed in cement and
sand (1:4) mortar 120 m2
34,000 Ugx 4,080,000 Ugx
Anti-termite treatment
1.25 Gladiator' or other equal approved anti-termite chemical
treatment: applied in accordance with the manufacturer's
instructions 227 m2
1,500 Ugx 340,500 Ugx
Damp proof membrane
1.26 Gauge 1000 polythene damp proof membrane including
300mm laps. 155 m2
2,000 Ugx 310,000 Ugx
Hessian based damp proof courses as described bedded,
jointed in cement mortar (1:3).
1.27 Bituminous felt damp proof course: 230mm wide: 230mm laps 89 lm 2,500 Ugx 222,500 Ugx
Plinth finishes
1.28 75mm thick selected stone slates to plinth walls and bedded,
jointed and pointed in cement and sand (1:3) mortar.
16 m2
24,000 Ugx 384,000 Ugx
Splash apron
1.29 75mm thick concrete class 25/20mm aggregate splash
reinforced with and including fabric mesh reinforcement ref
A98. 32 m2
20,500 Ugx 656,000 Ugx
1.30 Concrete downstand to ditto size 75 x 125mm deep to egde ofsplash apron 54 lm 4,300 Ugx 232,200 Ugx
1.31 38mm thick cement and sand (1:3) paving on splash apron
wood float finish 32 m2
5,500 Ugx 176,000 Ugx
Total carried to collection 6,401,200 Ugx
Page No. 4/52
-
8/3/2019 Montessori BoQ Priced
53/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
COLLECTION
Total Page No. 4/2 4,662,600 Ugx
Total Page No. 4/3 13,664,000 Ugx
Total Page No. 4/4 6,401,200 Ugx
TOTAL ELEMENT No. 1 (SUBSTRUCTURES) CARRIED TO
SUMMARY 24,727,800 Ugx
Page No. 4/53
-
8/3/2019 Montessori BoQ Priced
54/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 2
RC SUPERSTRUCTURE
Sawn formwork: to
2.01 Sides and soffites: beams 182 m2
14,000 Ugx 2,548,000 Ugx
2.02 Sides: columns 38 m2
14,000 Ugx 532,000 Ugx
2.03 Soffites: roof slab 55 m2
14,000 Ugx 770,000 Ugx
2.04 Sides: upstand beams 51 m2
14,000 Ugx 714,000 Ugx
2.05 Edges: slabs over 75mm but not exceeding 150mm thick 3 lm 4,000 Ugx 12,000 Ugx
High yield tensile steel bar reinforcement to BS 4461 as
described including cutting to lengths, bending, hoisting
and fixing including all necessary tying wire and spacing
blocks.
2.07 12mm bars 475 kg 2,500 Ugx 1,187,500 Ugx
2.08 16mm bars 3,160 kg 2,500 Ugx 7,900,000 Ugx
Mild steel round steel bars to B.S. 4441 as described.
2.09 8mm bars 461 kg 2,500 Ugx 1,152,500 Ugx
In-situ reinforced concrete class 25/20: vibrated: in
2.10 Horizontal beams 17 m3
230,000 Ugx 3,910,000 Ugx
2.11 Columns 2 m3
230,000 Ugx 460,000 Ugx
2.12 Gutter upstand beams 16 m3 230,000 Ugx 3,680,000 Ugx
2.13 100mm thick suspended slab 55 m2
23,000 Ugx 1,265,000 Ugx
TOTAL ELEMENT No. 2 (R C SUPERSTRUCTURE)
CARRIED TO SUMMARY 24,131,000 Ugx
Page No. 4/54
-
8/3/2019 Montessori BoQ Priced
55/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 3
WALLING
Solid concrete block walling load bearing (4.5N/mm2) to BS
6073 in cement and sand mortar 1:3 mix, laid in suitable
bond, with 6mm mild steel strips laid horizontally every
alternate course.
3.01 200mm thick external walling 94 m2
34,000 Ugx 3,196,000 Ugx
3.02 200mm thick walling; curved to profile 110 m2
38,000 Ugx 4,180,000 Ugx
3.03 200mm thick internal walling 17 m2
34,000 Ugx 578,000 Ugx
3.04 200mm thick walling; curved to profile 53 m2
38,000 Ugx 2,014,000 Ugx
3.05 Labour and materials for eaves filling in 200mm thick walls:
400mm high 48 lm 13,600 Ugx 652,800 Ugx
TOTAL ELEMENT No. 3 (WALLING) TO SUMMARY 10,620,800 Ugx
Page No. 4/55
-
8/3/2019 Montessori BoQ Priced
56/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 4
ROOF
Waterproofing roof slabs
Cement and sand (1:4) screed with waterproofing agent:
on concrete: wood floated
4.01 25mm thick screed: to receive quarry tiles. 55 m2
9,000 Ugx 495,000 Ugx
4.02 Ditto 200mm high skirting 48 lm 1,800 Ugx 86,400 Ugx
Supply and fix 300 x 225mm red clay quarry tiles as'Uganda Clays' or other equal and approved: on prepared
screed (m/s): joints pointed in matching cement grout
4.03 12mm thick tiles: on screed. 55 m2
26,000 Ugx 1,430,000 Ugx
4.04 Ditto 200mm high skirting 48 lm 5,200 Ugx 249,600 Ugx
Roof Structure
Mild steel sections and plates.
Framed structural steelwork comprising steel sections toBS 46 (hot rolled section) and grade 43 'C' steel to BS 4360
(weldable structural steel). Fabricate, deliver to site roof
structure including hoisting and fixing 3m above ground
with welded shop and site connections including all
connecting plates, cleats, brackets, bolts, all cutting
drilling, bolting and welding unless otherwise said the
whole having one coat of zinc chromate or lead graphite
primer. All welds to be 6mm fillet weld and gusset plates to
be 6mm thick.
The following in 1No. Truss type T1 spanning 12390mm.
4.05 65 x 65 x 4mm MSA rafter 15 lm 18,000 Ugx 270,000 Ugx
4.06 65 x 65 x 4mm MSA bottom tie 12 lm 18,000 Ugx 216,000 Ugx
4.07 50 x 50 x 3mm MSA strut / tie 19 lm 16,000 Ugx 304,000 Ugx
Total carried to collection 3,051,000 Ugx
Page No. 4/56
-
8/3/2019 Montessori BoQ Priced
57/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
The following in 1No. Truss type T2 spanning 11390mm.
4.08 65 x 65 x 4mm MSA rafter 14 lm 18,000 Ugx 252,000 Ugx
4.09 65 x 65 x 4mm MSA bottom tie 11 lm 18,000 Ugx 198,000 Ugx
4.10 50 x 50 x 3mm MSA strut / tie 17 lm 16,000 Ugx 272,000 Ugx
The following in 4No. Truss type T3 - T6
4.11 65 x 65 x 4mm MSA rafter 43 lm 18,000 Ugx 774,000 Ugx
4.12 65 x 65 x 4mm MSA bottom tie 34 lm 18,000 Ugx 612,000 Ugx
4.13 50 x 50 x 3mm MSA strut / tie 47 lm 16,000 Ugx 752,000 Ugx
Roof members
4.14 175 x 75 x 3L Zed purlins including 75 x 75 x 3L purlin cleats
on trusses. 136 lm 20,000 Ugx 2,720,000 Ugx
4.15 16mm anti-sag rods. 64 lm 12,000 Ugx 768,000 Ugx
Truss fixing
4.16 Truss fixing: 200 x 200 x 6mm thick base plate with and
including 2No. 16mm HD bolts and grout into concrete, 75 x
75 x 4L gusset plates welded to rafters to detail 12 no 40,000 Ugx 480,000 Ugx
Fascia
4.17 25 x 225mm wrot hardwood fascia fixed to ends of rafters to
detail 51 lm 12,000 Ugx 612,000 Ugx
Roof covering
4.18 26gauge pre-painted IT4 roofing sheets fixed with 1 side
corrugated laps and 150mm end laps with and including J bolts
with plastic washers to manufacturer's instructions 160 m2
26,000 Ugx 4,160,000 Ugx
4.19 26 gauge plain (pre-coated) roll top ridge capping complete
with bat proof blocks. 14 lm 12,000 Ugx 168,000 Ugx
Total carried to collection 11,768,000 Ugx
Page No. 4/57
-
8/3/2019 Montessori BoQ Priced
58/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
Gutter lining
4.20 2mm tick mild steel plate gutter lining 3100mm girth 30 lm 26,000 Ugx 780,000 Ugx
4.21 Labour for forming 75mm hole for downpipe and dressing
arround pipe. 8 no 10,000 Ugx 80,000 Ugx
Unplasticed PVC rain water pipes and fittings as 'Marley'
or other equal and approved complete with all necessary
accessories.
4.22 110 x 75mm gutter outlets 8 no 20,000 Ugx 160,000 Ugx
4.23 75mm rain water down pipe fixed and clipped to walls with
approved holderbats. 27 lm 18,000 Ugx 486,000 Ugx
4.24 Extra over down pipe for bends 16 no 20,000 Ugx 320,000 Ugx
4.25 Extra for horse shoe 8 no 20,000 Ugx 160,000 Ugx
Eaves soffits and finishes
4.26 Slatted eaves soffites comprising 50 x 25mm slats at 65mm
centres in 550 x 550mm square chequered perpendicular to
each other complete with coffee tray wire screen and 50 x50mm branderings at 500mm centres. 31 m
211,000 Ugx 341,000 Ugx
Knot prime stop and apply three coats of gloss oil paint to
timber surfaces.
4.27 Slated eaves soffites 31 m2
4,500 Ugx 139,500 Ugx
4.28 Surfaces exceeding 200mm but not exceeding 300mm girth.
51 lm 1,000 Ugx 51,000 Ugx
Total carried to collection 2,517,500 Ugx
COLLECTION
Total Page No. 4/8 3,051,000 Ugx
Total Page No. 4/9 11,768,000 Ugx
Total Page No. 4/10 2,517,500 Ugx
TOTAL ELEMENT No. 4 (ROOF & RAINWATER DISPOSAL)
CARRIED TO SUMMARY 17,336,500 Ugx
Page No. 4/58
-
8/3/2019 Montessori BoQ Priced
59/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 5
WINDOWS
Precast concrete units: grade 30: reinforced as necessary
and finished fairface on all exposed surfaces including
hoisting and fixing in position.
5.01 75 x 285mm sunk weathered and throated window cill 17 lm 11,500 Ugx 195,500 Ugx
Supply and fix purpose made steel casement windows
manufactured from standard window sections:
manufacture, assemble and deliver to site: ironmongery
comprising approved hinges, stays, fasteners to openinglights and sliding hardware for sliding panes: permanent
vents with steel louvre plates: frames drilled, plugged and
screwed or built into walling: one coat red oxide primer
before delivery.
5.02 Window type W1: size 2000 x 1450mm high overall including
outer framing: 2No. side hung opening lights size 500 x
1450mm: rest fixed lights. 1 no 348,000 Ugx 348,000 Ugx
5.03 Window type W2: size 900 x 3000mm high overall including
outer framing: fixed lights. 6 no 324,000 Ugx 1,944,000 Ugx
5.04 Window type W3: size 1000 x 1200mm high overall including
outer framing: 2No.side hung opening lights size 500 x
1200mm: rest fixed lights. 5 no 144,000 Ugx 720,000 Ugx
5.05 Window type W4: size 1200 x 2400mm high overall including
outer framing: slit window fixed glass 4 no 345,600 Ugx 1,382,400 Ugx
Wrot mahogany: prime grade
5.06 50 x 230mm window frame: rebated: plugged 50 lm 14,000 Ugx 700,000 Ugx
5.07 50 x 230mm window frame: rebated: plugged 25 lm 14,000 Ugx 350,000 Ugx
5.08 40 x 20mm architrave: splayed 100 lm 4,000 Ugx 400,000 Ugx
Total carried to collection 6,039,900 Ugx
Page No. 4/59
-
8/3/2019 Montessori BoQ Priced
60/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
Louvre carrier frame.
5.09 Louvre carrier frame: aluminium heavy duty: 600mm high: as
'Naco' or other equal and approved. 40 prs 25,000 Ugx 1,000,000 Ugx
Glass and glazing
5.10 5mm thick clear sheet glass to metal with putty in panes not
exceeding 0.5m2
36 m2
36,000 Ugx 1,296,000 Ugx
5.11 5 x 150mm wide glass louvres with both edges ground and
polished 88 lm 7,200 Ugx 633,600 Ugx
Painting
5.12 Prepare touch up primer and apply one undercoat and two
finishing coats of gloss oil paint: on glazed metal windows74 m
26,000 Ugx 444,000 Ugx
Knot prime and stop and apply three coats of polyurethane
laquer to general surfaces of:-
5.13 Not exceeding 100mm girth 100 lm 1,000 Ugx 100,000 Ugx
5.14 Over 200 but not exceeding 300mm girth 100 lm 1,500 Ugx 150,000 Ugx
Total carried to collection 3,623,600 Ugx
COLLECTION
Total Page No. 4/11 6,039,900 Ugx
Total Page No. 4/12 3,623,600 Ugx
TOTAL ELEMENT No. 5 (WINDOWS) CARRIED TO
SUMMARY 9,663,500 Ugx
Page No. 4/60
-
8/3/2019 Montessori BoQ Priced
61/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
ELEMENT No. 6
DOORS
Precast concrete units reinforced with 4No. 12mm high
tensile steel bars and 8mm steel stirrups at 200mm
centres.
6.01 200 x 230mm high lintel 12 lm 23,000 Ugx 276,000 Ugx
Purpose made steel casement door manufactured from
standard strong Z sections: burglar proofing grille
comprising 20 x 4mm flat bars at 150mm centres as
described: manufacture, assemble and deliver to site:
supply and fix all necessary ironmongery: frames drilled,plugged and screwed or built into walling: permanent vent
with steel louvre plates: one coat red oxide primer before
delivery.
6.02 Door type D1 size 2000 x 2100mm high overall: 2No. opening
shutter 1000 x 2100mm high: glazing bars as described.
1 no 840,000 Ugx 840,000 Ugx
6.03 Door type D3 size 1800 x 2100mm high overall: 2No. opening
shutter 900 x 2100mm high: glazing bars as described.
1 no 756,000 Ugx 756,000 Ugx
6.04 Door type D4 size 1200 x 2100mm high overall: 2No. opening
shutter 600 x 2100mm high: glazing bars as described.
2 no 504,000 Ugx 1,008,000 Ugx
Glass and glazing
6.05 5mm thick clear sheet glass to metal with putty in panes not
exceeding 0.5m2
13 m2
36,000 Ugx 468,000 Ugx
Timber doors50mm thick wrot mahogany framed door: 200 x 50mm top,middle and bottom rails: 150 x 50mm stiles: bevelled, raised
and fielded panels as architect's detail.
6.06 850 x 2075mm high 2 no 250,000 Ugx 500,000 Ugx
Total carried to collection 3,848,000 Ugx
Page No. 4/61
-
8/3/2019 Montessori BoQ Priced
62/267
Item Description Qty Unit Rate Amount
Ugx Ugx
Bills of Quantities: KITCHEN BLOCK
New Construction Works at Montessori Education Centre
Wrot mahogany: prime grade
6.07 50 x 200mm door frame: rebated: plugged 10 lm 18,500 Ugx 185,000 Ugx
6.08 15mm quadrant beading 10 lm 4,000 Ugx 40,000 Ugx
6.09 40 x 20mm architrave: splayed 10 lm 4,000 Ugx 40,000 Ugx
Prepare touch up primer and apply one undercoat and
three finishing coats of gloss oil paint: on:
6.10 Glazed metal doors. 26 m2
6,000 Ugx 156,000 Ugx
6.11 Burglar proofing grilles 26 m2
6,000 Ugx 156,000 Ugx
Knot prime and stop and apply three coats of polyurethane
laquer to general surfaces of:-
6.12 Not exceeding 100mm girth 20 lm 1,000 Ugx 20,000 Ugx
6.13 Over 200 but not exceeding 300mm girth 10 lm 1,500 Ugx 15,000 Ugx
6.14 General timber surfaces: doors 4 m2
5,000 Ugx 20,000 Ugx
Supply and fix: English "Union" ironmongery as
described.
6.15
3 lever steel door lock: rebated: complete with lever furniture. 4 no 120,000 Ugx 480,000 Ugx
6.16 Three lever mortice lock: cat. no. 22