KINGDOM OF MOROCCO National Meteorological Service of Morocco MOROCCAN WIGOS DEMONSTRATION PROJECT 1 STANDARDIZATION AND TRACEABILITY OF THE MOROCCAN METEOROLOGICAL OBSERVING SURFACE NETWORK

Upload: lei

Post on 19-Feb-2016

52 views

Category:

Documents


0 download

DESCRIPTION

KINGDOM OF MOROCCO National Meteorological Service of Morocco. MOROCCAN WIGOS DEMONSTRATION PROJECT. STANDARDIZATION AND TRACEABILITY OF THE MOROCCAN METEOROLOGICAL OBSERVING SURFACE NETWORK. PLAN:. KINGDOM OF MOROCCO National Meteorological Service of Morocco. Moroccan WIGOS DP Objectives - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

MOROCCAN WIGOS DEMONSTRATION PROJECT

1

STANDARDIZATION AND TRACEABILITY OF THE MOROCCAN METEOROLOGICAL

OBSERVING SURFACE NETWORK

Page 2: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

•Moroccan WIGOS DP Objectives

• Implementation Plan

• Achievement Progress

•Experience gained and problems encountered

2

PLAN:

Page 3: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

WIGOS- DP

Demonstration projects conducted by NMHSs are considered as an essential component in WIGOS implementation:

• Helps WMO Members to more fully understand WIGOS concept and keeping them current on its practical development. • Feedback and lessons learnt from these NMHSs will be extremely beneficial in understanding others’ expectations of WIGOS/WIS concept and implementation.

3

Introduction:

Page 4: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Moroccan WIGOS Demonstration project

•To Improve the quality of climatic and meteorological observed data in the perspective of a better integration of the climate in the National sustainable development,• To ensure that the national metrological measurements respond to WMO standards.

• What is the quality of the measurements of the National Meteorological Surface Observing Network, and

• In which conditions they are made???? 4

WIGOS Priorities: • To ensure the quality of the observation to meet climate en environmental

requirements, and• Metadata and Homogeneity for long term stability..

Page 5: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

WIGOS Demonstration Project in Morocco consists on standardization and traceability project that include: 1. Strengthening material capacities and human knowledge of the Moroccan Regional Instrumentation Center (RIC) for AR-I and improving its technical procedures to allow it to accomplish its task of calibration in link to recognized Metrological International chain ,

2. Establishment of Metadata catalogues of the whole synoptic, marine, aeronautic and automatic weather stations constituting the Moroccan Meteorological Surface observing Network.

To calibrate and to achieve traceability of the national

meteorological observing Surface Network

Specific Goals:

5

Page 6: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

6

National Surface

Network

RIC of Morocco

• Sensitization• Calibrating instruments…

• Calibrating standards • Inter-comparison• Training and Assistance for certification…• Share of knowledge RIC of OTHER WMO-

RCEx: African RICs, France, Japan, USA, …

Other NMHS calibrating Laboratory

• Calibrating standards • Training of staff• Assistance for certification…

NMHSSurface

Network• Calibrating instruments• Training and sensitization

Link associated to the project

Link that could exist after achieving the project

Page 7: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

IMPLEMENTATION PLAN:Project 1:

As suggested by CIMO, the four following domains were selected as areas of enhancement : a) Setting up of laboratories and purchase of standardization devices; b) Quality Insurance and control;

c) Training;

d) Assessment of the RIC.

7

Page 8: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Project 2: • Seeing the rapid expansion of cities, more and more synoptic station had seen their sitting environment modified and in some cases not fulfilling to standards. • Information related to calibration, renewing instruments and sensor exposure are not archived. By this project, it’s expected to produce documents describing instrument metadata, as well as, equipment life-cycle:

o Instrument/network sitting, o Calibration, renewing and maintenance.

8

IMPLEMENTATION PLAN:

Page 9: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Preliminary actions: • Upgrade of existing laboratory equipments: repairing existing equipments and connecting sensors and standards used with the different equipments to a computer in order to optimize data collection).

• Construction of a new building to house the laboratory

9

Page 10: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Achievement Progress:

For the strengthening of RIC capabilities, three stages were defined: 1.Acquisition of standards and calibrating equipments to calibrate instruments measuring atmospheric pressure,

2. Acquisition of standards and calibrating equipments to calibrate instruments measuring temperature and humidity,

3. Acquisition of calibrating equipments for rain gages.

10

Page 11: MOROCCAN WIGOS DEMONSTRATION PROJECT

11

Atmopsheric Pressure: An automatic solution for calibrating digital barometers on laboratory

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Page 12: MOROCCAN WIGOS DEMONSTRATION PROJECT

12

An automatic solution for

calibrating digital barometers

on site

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Atmopsheric Pressure:

Page 13: MOROCCAN WIGOS DEMONSTRATION PROJECT

13

• A new and completely

automatic solution for

calibrating temperature probes

• Two SPRTs as working

standards

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Temperature:

Liquid BathRange: -65 to +300 °CStability : <±0,001°C Uniformity : < ±0,003°C

SPRT 25 & SPRT 100Range: -200 to +600 °C (450°C for SPRT100)Accuracy : <±0,01°C Drift : < ±0,001°C

Page 14: MOROCCAN WIGOS DEMONSTRATION PROJECT

14

• Two fixed points cells (Gallium

and Triple point of Water)

• A mini liquid bath and working

temperature standards

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Temperature:

Manufacturer: WIKA (9441)Range: -40 to +150 °CStability : ±0,01°C Uniformity : < ±0,01°CWorking standard: Pt100 WIKA modèle CTH 6500Range: -200 to +850°C Accuracy: ±0,03°C

Page 15: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

15

Humidity:

• A new climatic chamber

• A chilled mirror hygrometer as a

humidity standard

Page 16: MOROCCAN WIGOS DEMONSTRATION PROJECT

16

• Portable Humidity generator

• Saline solutions for four points

(11%, 33%, 75% and 97%)

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Humidity:

Page 17: MOROCCAN WIGOS DEMONSTRATION PROJECT

17

Precipitation: A solution to calibrate tipping bucket rain gages

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Page 18: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Evolution of the annual cost for the acquisition process of the new laboratory equipment

18

Page 19: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Training Activities:

19

• 2008: RIC Staff received training on metrology of pressure and on installing and handling the new pressure calibrating system,

•December 2009: NMS of Morocco hold the French session of the WMO course on metrology for the AR-I French speaking countries,

• May 2010: The technical staff of the calibrating laboratory follows the training in matter of metrology organized by the African Commission of Metrology (CAFMET).

Page 20: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

Quality Insurance:•NMS of Morocco started, in 2008, a quality circles for support processes like maintenance and calibration.

• Standards Intercomparison with Meteo-France calibrating Laboratory (RIC for AR VI) was also achieved in July 2010,

• During the meeting of the CIMO ET on RICs held in Casablanca, the participants have engaged an assessment test of the RIC of Morocco with regards to the ISO 17025 requirements and RIC TOR using the new template evaluating Scheme developed by the ET.

• NMS of Morocco launched the project of certification of the RIC with regards to the ISO 17025 standard. (the certification project is expected to be achieved by the end of 2011)

20

Page 21: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

METADATA Catalogue:

21

• The data collected from the hole meteorological manned station are under process.

• A database should be established by 2011.

Echelle de la carte: 1/4000 Document prepared by Mr Mohamed Oujadi

owever

Page 22: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

22

Synoptic Station of Beni Mellal

Page 23: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

23

N

Page 24: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

24

Experiences gained and problems encountered:

The NMS of Morocco and especially its calibrating laboratory considers that experiences have been acquired in the following areas:

• Making benefit from WIGOS values and taking part, while being satisfied, to its implementation, • Definition of needs and establishment of technical specifications of each materiel to be acquired,• Management of the acquisition process (budget, acquisition project achievement…),• Acquiring knowledge in matter of Metrology and processes related to the calibration of meteorological instruments,• Implementing quality control process.

Page 25: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

25

Experiences gained and problems encountered:

• A real difficulty was encountered during the development of calibrating software. In fact, there was a need of help of technical expert for providing the way to calculate and determine metrological parameters (uncertainty, hysteresis, repeatability…).

To overcome this problem, a technical assistance was provided by RIC of AR -VI.

In this context, WIGOS should encourage cooperation between developing and developed countries in matter of interest.

This cooperation should lead to a real knowledge transfer.

Page 26: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

26

Experiences gained and problems encountered:

• Difficulties were also encountered when bringing barometers from station to laboratory (need of replacement).

RIC acquired, to resolve this problem, necessary digital barometers with LCD screen to replace mercury barometers not fulfilling WMO standards. (18 digital barometers were acquired in 2009).

WIGOS should emphasize the practical application of its terms of reference.

The implementation of the concept of WIGOS at different levels (observation, coding and transmission, modeling, dissemination ...) will generate some friction that may be exceeded by the definition of clear and comprehensible procedures and deliverables.

Page 27: MOROCCAN WIGOS DEMONSTRATION PROJECT

KINGDOM OF MOROCCONational Meteorological Service of Morocco

27

Conclusions:• NMS of Morocco took into charge the actions mentioned above and the progress of the project is consistent with the timetable presented to the EC WG on WIGOS.

• The NMS of Morocco has just completed a large part of the project with regards to the IP and more efforts are now oriented to develop, to practice and to assess technical procedures for calibrating processes according to ISO 17025 standards.

• During the accreditation process, a certified consultant will assist the RIC staff. However, Experience of developed and certified RICs will be a precisous aid seeing the fact that, in general, RICs uses to calibrate similar instruments working in same ranges and responding to the same WMO tolerances.