moss 26

Upload: dmlsfmm

Post on 09-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Moss 26

    1/6

    1

    Proceedings of the Marine Operations Specialty Symposium 2008

    MOSS-26

    ANALYSIS OF AN ALTERNATIVE PIPELINE INSTALLATION PROCEDURE THATCOMBINES ONSHORE DEFLECTION AND OFFSHORE TRANSPORTATION

    Danilo Machado Lawinscky da Silva1

    Rodrigo Almeida Bahiense1

    Breno Pinheiro Jacob1

    Fernando Gomes da Silva Torres2

    Antonio Roberto Medeiros2

    1LAMCSO Laboratory of Computational Methods and Offshore Systems PEC/COPPE/[email protected] , [email protected] , [email protected]

    2PETROBRAS Petrleo Brasileiro S.A.

    [email protected] , [email protected]

    ABSTRACT

    Conventional offshore pipeline installation operations in

    Brazil have been performed in an S-Lay procedure employing

    the BGL-1 barge, owned by Petrobras. However, this procedure

    has some limits, and may not be feasible in some particular

    scenarios.An alternative procedure used by Petrobras is the so-called

    lateral deflection procedure, which basically consists of

    performing the pipeline assembly on shore, and then deflecting

    it to the sea using a tugboat. After that, the pipeline is towed to

    its installation area.

    The objective of this work is to present numerical

    simulations of both stages of this procedure (the lateral

    deflection procedure itself and the pipeline transportation). The

    simulations were performed to help planning an actual

    operation that was scheduled to occur in the Xaru field, at the

    state of Cear, northeast Brazil. These simulations employ the

    SITUA-Prosim computational tool, which is able to incorporate

    the correct definition of the seabed and shore from bathymetriccurves.

    Regarding the transportation stage, typically it is

    performed using a front and a rear tugboat aligned at the

    transportation route. As a result of the simulations, a different

    scheme was proposed, using only one tugboat.

    INTRODUCTION

    The installation of pipelines is among the most challenging

    offshore operations. The most common method of pipeline

    installation in shallow water is the S-Lay method. In this

    method, the welded pipeline is supported on the rollers of the

    vessel and the stinger, forming the over-bend. Then it is

    suspended in the water all the way to seabed, forming the sag-

    bend. The over-bend and sag-bend form the shape of an S.

    The BGL-1 (a pipeline launching barge owned by the

    Brazilian state oil company - Petrobras) is used to perform S-Lay pipeline installation operations. The BGL-1 is a second

    generation lay barge that performs installation operations by

    moving forward using its own mooring lines. This involves the

    definition of a complex mooring procedure, as a sequence of

    operations that determine the mooring line positions and induce

    the lay barge movement as it lays the pipeline. Basically,

    tugboats drop anchors at some predefined positions; then the

    barge winches release the stern mooring cables, and collect the

    mooring cables located at the bow. This is a delicate operation

    essential to keeping the position and direction of the lay barge

    in accordance with the planned route. The loss of a mooring

    anchor during such operation can cause sudden yawing or

    drifting of the barge, which in turn can result in buckling of thepipe at the end of the stinger due the excessive bending.

    The procedure described above has some limits, such as: i)

    it has a very restrictive limitation according to the weather

    conditions; ii) the procedure is extremely complex when

    performed in congested areas [1].

    Therefore, Petrobras has considered an alternative

    procedure that combines onshore lateral deflection and offshore

    transportation. This work is focused in the numerical

    simulation of this procedure. Several analyses are performed in

    order to assess the behavior of this alternative pipeline

    installation procedure.

  • 8/8/2019 Moss 26

    2/6

    2

    LATERAL DEFLECTION PROCEDURE

    The lateral deflection procedure basically consists of

    performing the pipeline assembly on shore and deflecting it tothe sea using a tugboat. The characterization of this procedure

    involves the determination of the better velocity and direction

    of the tugboat, in order to minimize the efforts on the pipeline

    (especially due to the curvatures).

    Scenario and characteristics of pipeline

    The pipeline was installed to rehabilitate a 10 pipeline

    that was in the end of its lifetime. The pipeline is located at the

    Xaru field, interconnecting the PXA-1 platform to the buoy

    frame, with the basic purpose of transporting the oil production

    of Xaru, Atum and Curim fields, in Cear State (northeast of

    Brazil), to the NT ALIANZA Ship.The pipeline has a total length of 721m and was assembled

    at Canto Beach, in Paracuru city, deflected from shore to the

    sea, and transported with buoys to the installation location,

    where it was positioned on the guideline and sunk by flooding

    the buoys.

    During assembly, the pipeline was positioned on "big-

    bags" (bags of sand) as shown in Figure 1.

    FIGURE 1. PIPELINE ASSEMBLY SCHEME

    The physical and geometric properties of the pipeline and

    of the buoys are presented in the following tables. The buoys

    were fastened to the pipeline at every 8m measured from the

    center of each buoy.

    Numerical Models

    To perform the analyses of the lateral deflection procedure,

    Petrobras considered the use of the SITUA-Prosim system.

    This system has been developed since 1997 [2], in cooperation

    by Petrobras and LAMCSO (Laboratory of Computational

    Methods and Offshore Systems, at the Civil Eng. Dept. of

    COPPE/UFRJ, Federal Univ. of Rio de Janeiro). It is a Finite-

    Element based nonlinear dynamic solver, that performs the

    calculations with an interface with the Petrobras SGO, that

    comprises a database with the seabed bathymetry and obstacles.

    Therefore, the simulation takes into account the actual

    bathymetric information and obstacle positions [3,4].

    Three-dimensional frame elements were employed in the

    generation of the numerical model for the pipeline. Three-dimensional frame elements were employed also for the

    representation of the pipe segments with buoys. An equivalent

    element was used to represent both the pipeline physical

    properties and the buoy hydrodynamic properties. The

    characteristics of the equivalent pipeline+buoy element are

    shown in Table 3.

    TABLE 1. 10 PIPELINE DATA

    Parameter Value Unit

    Outside Diameter 0.27305 m

    Inside Diameter 0.2445 m

    Yield Stress of steel 414000 kN/m2

    Modulus of Elasticity of steel 207000 MPaAxial Stiffness (EA) 2402252.49 kN

    Flexional Stiffness (EI) 20169.39 kN*m2

    Poisson Coefficient 0.3 -

    Density of steel 77 kN/m3

    Corrosion Protection 0.0027 m

    Corr. Protection Specific Mass 9.32 kN/m3

    Hydrodynamic Diameter 0.27875 m

    Tube Length 12 m

    Weight in Air 0.91099 kN/m

    Weight in Water 0.32220 kN/m

    TABLE 2. 10 BUOY DATA

    Parameter Value Unit

    Diameter 0.762 m

    Length 1.129 m

    Weight in Air 1.2851 kN

    Buoyancy 3.4138 kN

    TABLE 3. PIPELINE + BUOY DATA

    Parameter Value Unit

    Outside Diameter 0.27305 m

    Inside Diameter 0.2445 m

    Axial Stiffness (EA) 2402252.49 kN

    Flexional Stiffness (EI) 20169.39 kN*m2

    Hydrodynamic Diameter 0.762 mWeight in Air 2.23530 kN/m

    Weight in Water -3.06225 kN/m

    Performed Analyses

    Several numerical simulations were performed to guide the

    lateral deflection procedure. The objective of these parametric

    studies was to define adequate combinations of tugboat route

    and velocity for the lateral deflection procedure, Figure 2.

  • 8/8/2019 Moss 26

    3/6

    3

    FIGURE 2. DIFFERENT TUGBOAT ROUTES

    Some typical results are shown in the figures that follow:

    Figures 3, 4 and 5 show the maximum values of Von Mises

    stresses along the pipeline for several directions and three

    tugboat velocities (the red line indicates the allowable stress);

    Figures 6, 7 and 8 show the time-history of the tugboat forces

    for the same directions and velocities. The complete description

    and results of these parametric studies is presented in reference

    [5].

    0

    100000

    200000

    300000

    400000

    500000

    600000

    700000

    800000

    0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0

    Pipeline Length (m)

    V

    o

    n

    M

    i

    s

    e

    s

    (

    K

    N

    /

    m

    2

    ) Direction (-5)

    Direction (0)

    Direction (5)

    Direction (10)

    Direction (15)

    Direction (20)

    Yield Stress

    FIGURE 3. VON MISES STRESS IN PIPELINE 3 KM/H

    0

    100000

    200000

    300000

    400000500000

    600000

    700000

    800000

    0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0

    Pipeline Length (m)

    V

    o

    n

    M

    i

    s

    e

    s

    (

    K

    N

    /

    m

    2

    ) Direction (-5)

    Direction (0)

    Direction (5)

    Direction (10)

    Direction (15)Direction (20)

    Yield Stress

    FIGURE 4. VON MISES STRESS IN PIPELINE 2 KM/H

    0

    100000

    200000

    300000

    400000

    500000

    600000

    700000

    800000

    0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0

    Pipeline Length (m)

    V

    o

    n

    M

    i

    s

    e

    s

    (

    K

    N

    /

    m

    2

    ) Direction (-5)

    Direction (0)

    Direction (5)

    Direction (10)

    Direction (15)

    Direction (20)Yield Stress

    FIGURE 5. VON MISES STRESS IN PIPELINE 1 KM/H

    0.0

    50.0

    100.0

    150.0

    200.0

    250.0

    300.0

    0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500

    Time (s)

    T

    r

    a

    c

    t

    i

    o

    n

    (

    K

    N

    )

    Direction (-5)

    Direction (0)

    Direction (5)

    Direction (10)

    Direction (15)

    Direction (20)

    FIGURE 6. TENSION IN THE CABLE 3 KM/H

    0.0

    50.0

    100.0

    150.0

    200.0

    250.0

    300.0

    0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500Time (s)

    T

    r

    a

    c

    t

    i

    o

    n

    (

    K

    N

    )

    Direction (-5)

    Direction (0)

    Direction (5)

    Direction (10)

    Direction (15)

    Direction (20)

    FIGURE 7. TENSION IN THE CABLE 2 KM/H

  • 8/8/2019 Moss 26

    4/6

    4

    0.0

    50.0

    100.0

    150.0

    200.0

    250.0

    300.0

    0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500Time (s)

    T

    r

    a

    c

    t

    i

    o

    n

    (

    K

    N

    )

    Direction (-5)

    Direction (0)

    Direction (5)

    Direction (10)

    Direction (15)

    Direction (20)

    FIGURE 8. TENSION IN THE CABLE 1 KM/H

    Lateral Deflection Operation

    Later, when the actual lateral deflection operation was

    performed, it could be observed that the pipeline behavior was

    the same as predicted by the numerical simulations. Differentstages of this procedure are shown in Figures 9, 10 and 11.

    FIGURE 9. LATERAL DEFLECTION: INITIAL STAGE

    FIGURE 10. LATERAL DEFLECTION: INTERMEDIATE STAGE

    FIGURE 11. LATERAL DEFLECTION: FINAL STAGE

    OFFSHORE TRANSPORTATION

    After the inicial lateral deflection operation was concluded,

    the pipeline installation procedure proceeded by towing the

    pipe using a front and a back tugboat aligned at the

    transportation route, as shown in Figure 12.

    FIGURE 12. TRANSPORT TYPICAL CONFIGURATION

    The objective of the numerical simulations performed for

    this transportation stage was to verify the pipeline behavior

    under environmental loadings with the transport configuration

    defined by Petrobras.

    In this configuration, shown in Figure 12, two cables with

    250m length connect the pipeline and the two tugboats. Thetugboats velocities are about 5km/h (aligned at 355o from

    north). The environmental loads are shown in Table 4. As the

    pipeline remains totally submerged and the buoys at least 50%

    submerged, wind effect was not considered.

    TABLE 4. ENVIROMENTAL LOADS

    Load Azimuth Value

    Current 315o

    1.19m/s

    Wave 30o Hs = 1.6m; Tp = 9.5s

    The minimum and maximum velocities of tow were

    defined by Petrobras as 5km/h and 9.26km/h. The maximum

    velocity was defined to prevent buoy movement on thepipeline. It was verified in previews operations, under similar

    conditions, that buoys can slip if the tow velocity exceed

    9.26km/h. This movement of the buoys makes the pipeline lose

    buoyancy, and may experience excessively higher curvatures at

    these points.

    After several parametric studies, a second configuration

    was proposed. In this configuration the two tugboats are not

    aligned, as indicates in Figure 13.

    FIGURE 13. TRANSPORT - ALTERNATIVE

    CONFIGURATION

    It was observed that, in such configurations, smaller values

    of cable tensions are obtained when the pipeline is nearly

    aligned to the resultant direction of the environmental

    conditions. However, the cable tensions are still relatively high

  • 8/8/2019 Moss 26

    5/6

    5

    during the whole operation. In such cases, maximum tensions

    in the tugboat cable are approximately 51.1kN (5km/h velocity)

    and 223.9kN (9.26km/h velocity).

    It was also analyzed a situation in which the back tugboatis disconnected and only the front tugboat is pulling the

    pipeline. This configuration simulates a situation in which one

    of the tugboats loses control and its cable is disconnected.

    The results of the analyses indicated that, for all cases, the

    maximum values of Von Mises stresses are not an issue, always

    staying well below the yield stress of the material. The

    objective then was to minimize tugboat forces.

    The smaller values of cable tensions were found in

    configurations where the back tugboat is disconnected. In such

    cases, tensions in the cable are approximately 19.9kN (5km/h

    velocity) and 61.0kN (9.26km/h velocity). Therefore,

    significant reductions were obtained in the cable tension: 61%

    for the velocity of 5m/s, and 72.8% for the velocity of9.26km/h.

    Therefore, the results of the analyses indicated that the best

    situation occurs when the back tugboat does not tension the

    pipe, or simply when it is not connected to the pipe. Another

    smaller boat can accompany the transport operation for safety

    reasons, and to perform the maneuvers needed for the

    subsequent pipeline launching process.

    The pipeline transportation was performed by Petrobras

    using only one tugboat and all numerical predictions related to

    the pipeline behavior were confirmed. Different stages of the

    pipeline transportation are shown in Figures 14, 15, 16 and 17.

    FIGURE 14. PIPELINE LEAVING BEACH

    The pipeline assumes different configurations depending

    on transport velocity. The pipeline configuration for the

    minimum tugboat velocity is shown in Figure 15; the

    configuration for the maximum tugboat velocity is shown in

    Figure 16.

    FIGURE 15. LOWER TRANSPORT VELOCITY

    FIGURE 16. HIGHER TRANSPORT VELOCITY

    The maneuvers at installation area are shown in Figure 17.

    At this time an auxiliary boat is already connected to the

    pipeline.

    FIGURE 17. MANEUVERS AT INSTALLATION AREA

  • 8/8/2019 Moss 26

    6/6

    6

    FINAL REMARKS

    This work presented the results of numerical simulations

    and parametric studies on the pipeline behavior during somestages of the installation procedure for the pipeline that

    interconnect Xaru-1 (PXA-1) platform to the buoy frame near

    the coast of Cear state, Brazil.

    Such analyses were intended to verify the pipeline

    behavior during the lateral deflection (when the pipeline leaves

    the beach), and during transport to the installation area.

    The results of the parametric studies allowed the definition

    of the most suitable conditions for each stage of the operation.

    Regarding the transport stage, it was noticed that the best

    configuration to transport the pipeline, where tensions in the

    tugboat cable are minimized, occurs when the pipeline

    direction is close to the resultant of environmental loads and

    the back tugboat is disconnected. The pipeline transportationwas performed using only the front tugboat and all numerical

    predictions related to the pipeline behavior were confirmed. A

    small boat was used just for safety reasons and to help

    performing the necessary maneuvers during the pipeline

    installation.

    REFERENCES

    [1] Masetti, I.Q., Barros, C.R.M., Jacob, B.P., Albrecht, C.H.,

    Lima, B.S.L.P., Sparano, J. V., Numerical Simulation of

    the Mooring Procedures of the BGL-1 Pipeline Launching

    Barge. Procs of the 23rd International Conference onOffshore Mechanics and Arctic Engineering OMAE,

    June 20-25, Vancouver, Canada, 2004.

    [2] Jacob, B.P., Masetti, I.Q., PROSIM: Coupled Numerical

    Simulation of the Behavior of Moored Units (in

    Portuguese), COPPETEC-Petrobras Internal Report, Rio

    de Janeiro, 1997.

    [3] __, SITUA-Prosim Program: Coupled Numerical

    Simulation of the Behavior of Moored Floating Units

    User Manual, ver. 3.0 (in Portuguese), LAMCSO/

    PEC/COPPE, Rio de Janeiro, 2005.

    [4] SGO User Manual (in Portuguese) Petrobras, Rio de

    Janeiro, 2002.

    [5] Silva, D.M.L., Bahiense, R. A., Jacob, B.P., Torres, F.G.S.,Medeiros, A.R., Costa, M.N.V., Numerical Simulation of

    Offshore Pipeline Installation by Lateral Deflection

    Procedure. Procs of the 26rd International Conference on

    Offshore Mechanics and Arctic Engineering OMAE,

    June 10-15, San Diego, USA, 2007.