mqs 312

Upload: nida-malim

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 MQS 312

    1/25

    1

    S U B M I T T E D B Y : M S . R A F A T F O D K A R

    R E G I S T R A T I O N N O : 2 1 2 - 0 7 - 2 7 - 1 0 7 7 2 - 2 1 4 1

    COURSE TITLE : LAWS

    OF SURVEYORS

    COURSE NO : MQS 312 ASS IGNMENT NO : F IFTY SEVEN

    [NATIONALINSTITUTEOFCONSTRUCTIONMANAGEMENTAND

    RESEARCH]

  • 7/28/2019 MQS 312

    2/25

    2

    ASSIGNMENT

    NICMAR/SODEOFFFICE

    1.COURSE NO : MQS 312

    2.COURSETITLE : LAWS FOR SURVEYORS

    3.ASSIGNMENT NO : FIFTY SEVEN

    4.DATEOFDISPATCH :

    5.LAST DATE OF RECEIPT OF

    ASSIGNMENT AT SODE OFFICE :

    ASSIGNMENT

    1.IN CIVIL ENGINEERING CONSTRUCTION PROJECTS THE PARTIES NORMALLY INVOLVED

    ARE CLIENT, ARCHITECT, ENGINEER, QUANTITY SURVEYOR AND THE CONTRACTOR.

    STUDY THE COMPANY/SITE YOU ARE WORKING AT PRESENT AND WRITE AN ASSIGNMENT

    ON THE RESPECTIVE DUTIES AND ROLES OF EACH PARTY. WHAT IS LACKING IN THE

    FUNCTIONING OF THESE PARTIES AND HOW CAN IT BE IMPROVED , IF REQUIRED, IF

    REQUIRED TO BE?

    2.WHAT ARE THE POWERS OF COURTS UNDER ARBITRATION AND CONCILIATION ACT

    1996?

  • 7/28/2019 MQS 312

    3/25

    3

    ARCHITECT

    1. TO UNDERSTAND THE REQUIREMENT OF THE PROJECT FROM THE CLIENT.2. PREPARATION OF THE INITIAL SKETCHES AND DRAWINGS FOR APPROVALS .3. GUIDELINES FOR PREPARATION OF BROCHURES/SELLING PLANS.4. PREPARATION OF MUNICIPAL DRAWINGS WITH AREA CALCULATIONS AS PER THE

    MUNICIPAL/GOVERNMENT AUTHORITY BYE LAWS.

    5. SUBMITTING PLANS AND OBTAININGN.O.C. FROM DRAINAGE DEPARTMENT ANDOTHER DEPARTMENT.

    6. OBTAINING DRAWING SANCTIONS FROM MUNICIPAL AUTHORITIES FOR LAYOUTSAND BUILDINGS.

    7. SUBMISSION OF RECORD PLANS/DRAWINGS TO MUNICIPAL AUTHORITIES.8.

    COMPILING ALL THE DRAWING WHICH IS TOTALLY SELF EXPLANATORY IN ALLRESPECT, STATING ALL SPECIFICATION, SIZES AND LEVELS AS PER THE LIST AND

    DETAILS.

    9. VISIT THE EXECUTION WORK PERIODICALLY TO SOLVE ANY QUERIES RAISED BY THESITE ENGINEER/CONTRACTOR.

    10.VISIT THE SITE TO INSPECT AND CERTIFY QUALITY AND WORKMANSHIP OF EVERYCONSTRUCTION ACTIVITY.

    11.HE MUST ENSURE THAT HIS PROFESSIONAL ACTIVITIES DO NOT CONFLICT WITH HISGENERAL RESPONSIBILITY TO CONTRIBUTE TO THE QUALITY OF THE ENVIRONMENT AND

    FUTURE WELFARE OF THE SOCIETY.

    12.HE SHALL APPLY HIS SKILL TO THE CREATIVE , RESPONSIBLE AND ECONOMICDEVELOPMENT OF OUR COUNTRY.

    ARCHITECTANDSOCIETY

    1. HE HAS TO PROMOTE THE ADVANCEMENT OF ARCHITECTURE , STANDARD OFARCHITECTURAL EDUCATION RESEARCH TRAINING AND PRACTICE.

    2. HE MUST CONDUCT HIMSELF IN A MANNER WHICH IS NOT DEROGATORY TO HISPROFESSIONAL CHARACTER NOR LIKELY TO LESSEN THE CONFIDENCE OF THE PUBLIC

    IN THE PROFESSION NOR BRING ARCHITECTS INTO DISREPUTE.

    3. WHEN WORKING IN OTHER COUNTRIES HE MUST OBSERVE THE REQUIREMENT OFCODES OF CONDUCT APPLICABLE TO THE PLACE WHERE HE IS WORKING.

  • 7/28/2019 MQS 312

    4/25

    4

    ARCHITECT ANDCLIENT

    1. IF IN PRIVATE PRACTICE TO MAKE KNOW ONE`S CLIENT ABOUT THE CONDITIONS OFENGAGEMENT AND SCALE OF CHARGES AND TO AGREE THAT THESE CONDITIONS

    SHALL BE THE BASIS OF HIS APPOINTMENT.

    2. NOT TO SUB-COMMISSION ANOTHER ARCHITECT OR ARCHITECTS THE WORK FORWHICH HE HAS BEEN COMMISSIONED WITHOUT PRIOR CONSENT OF THE CLIENT.

    3. HE IS PROHIBITED TO GIVE DISCOUNT, COMMISSION OR OTHER GIFTS OR INDUCEMENTFOR THE INTRODUCTION OF THE CLIENT TO B OBTAIN THE WORK.HE MUST MAINTAIN

    A HIGH STANDARD OF INTEGRITY.

    4. EVEN THOUGH HE HAS BEEN APPOINTED BY THE CLIENT AND HE IS HIS PAYMASTER,YET HE HAS TO ACT WITH FAIRNESS AND IMPARTIALITY WHEN ADMINISTRATING A

    BUILDING CONTRACT.

    ARCHITECTANDHISEMPLOYEESASSOCIATESAND

    CONSULTANTS

    THE ARCHITECT IS TO:

    1. PROVIDE HIS EMPLOYEES OR ASSOCIATES WITH SUITABLE WORKING ENVIRONMENTCOMPENSATE THEM FAIRLY AND FACILITATE THEIR PROFESSIONAL DEVELOPMENT.

    2. RECOGNISE AND RESPECT THE PROFESSIONAL CONTRIBUTION OF HIS EMPLOYEES ANDASSOCIATE AND CONSULTANT.

    3. ENTER INTO AGREEMENT WITH THEM DEFINING THEIR SCOPE OF WORK RESPONSIBILITIESFUNCTIONS FEES AND MODES OF PAYMENT.

  • 7/28/2019 MQS 312

    5/25

    5

    QUANTITYSURVEYOR

    THE FUNCTION OF A QUANTITY SURVEYOR WHICH ARE OF HIGHLY SPECIALIZED NATURE

    ARE:-1. TO PREPARE ESTIMATE OF THE WORKS.2. TO PREPARE SCHEDULE TO BE PRICED BY THE TENDERER.3. NEGOTIATING AND OBTAINING QUOTATIONS FOR WORKS FROM SPECIALISTS .4. ADVISE ON THE VALUE OF WORK FOR INTERIM CERTIFICATES.5. MEASURE AND VALUE ALL VARIATIONS UNDER THE CONTRACT .6. PREPARE A BUILDING CONTRACT.7. ADVISE ON THE VALUE OF WORK FOR THE FINAL CERTIFICATE.

    HIS FEES ARE USUALLY PAID BY THE CONTRACTOR AS PER THE PENULTIMATE

    CERTIFICATE ISSUED UNLESS OTHERWISE PROVIDED. IN FOREIGN COUNTRIES THESEWORK ARE BEEN DONE BY SPECIALIZED FIRM OF QUANTITY SURVEYORS WHEREAS IN

    OUR COUNTRY MAJORITY OF THE ARCHITECT AND ENGINEERS PERFORM THESE

    DUTIES.

    ENGINEER

    IT IS A TERM OF WIDE CONNOTATION RANGING FROM DESIGNING AND

    SUPERVISING EXECUTING CONSTRUCTION WORKS IN GENERA INCLUDING BUILDING,

    ROADS, BRIDGES, RAILWAYS. ON ACCOUNT OF SPECIALIZATION IN ONE OR MORE

    BRANCHES OF CIVIL ENGINEERING THE WORD ENGINEER CARRIES WITH IT THE PREFIX

    LIKE:ELECTRICAL ENGINEER,RAILWAY ENGINEER, MECHANICAL ENGINEER. FOR

    CONSTRUCTION OF BUILDING THE PREFIX GENERALLY USED IS CONSULTING ENGINEERINGOR STRUCTURAL DESIGNER OR R.C.C SPECIALIST HIS FUNCTION LIMITED TO DESIGN AND

    SUPERVISION OF BUILDING FROM VIEW POINT OF STRUCTURAL SOUNDNESS AS ALSO

    ADVISE AND COLLABORATE WITH THE ARCHITECT FROM TIME TO TIME .

  • 7/28/2019 MQS 312

    6/25

    6

    DUTIES OF ENGINEER INCHARGE

    TO PLAN THE PROPER EXECUTION OF THE WORK ON BEHALF OF THE CONTRACTOR.

    1. TO SET OUT THE WORK AND TO GIVE PROPER DIRECTIONS FOR THEIR EXECUTION.2. TO SEE THAT ADEQUATE SUPPLY OF MATERIALS IS MAINTAINED AT THE POINT OF

    WORKING.

    3. TO KEEP CONTROL OVER THE LABOUR.4. TO KEEP A SYSTEMATIC RECORD OF WORKS DONE DAILY AND TO PRESENT THE

    REPORT THAT EFFECT TO THE CONTRACTOR.

    5. TO DISCUSS THE MATTER WITH THE ARCHITECT TO NOTE DOWN HIS INSTRUCTION ANDTO CARRY OUT THE WORK ACCORDINGLY.

    6. TO TAKE JOINT MEASUREMENT OF THE WORKS EXECUTED WITH THE CLERKS OF THEWORKS.

    ARCHITECT RIGHTSANDCONTRACTOR DUTIES

    THE VARIATION CAN BE ORDERED BY THE ARCHITECT AND THE SAME SHALL NOT

    VITIATE THE CONTRACT. THE CONTRACTOR CANNOT REFUSE TO DO FURTHER WORKS ON

    ACCOUNT OF VARIATIONS OR DEMAND MONEY ON VALUATION BASIS AND NOT ON

    CONTRACT BASIS.

    AT TIMES THE ARCHITECT IS REQUIRED TO MAKE THE NECESSARY MODIFICATIONS IN

    CONSTRUCTIONAL DETAILS AS COMPARED TO THOSE GIVEN IN THE CONTRACT. THE

    CONTRACTOR CANNOT REFUSED TO DO THE WORK ON THE GROUND THAT IT FORMS AN

    EXTRA. HE WILL BE AT THE MOST ENTITLE TO THE DIFFERENCE IN THE COST BETWEEN

    THE MODIFIED DETAILS AND THE ORIGINAL DETAILS. IT SHOULD BE CLEARLY

    UNDERSTOOD THAT IF SUCH MODIFICATIONS INVOLVE EXTRAS , THE SAME SHOULD BE GOT

    CONFIRMED FROM THE ARCHITECT AS OTHERWISE THE ARCHITECT WILL FEEL THAT THE

    CONTRACTOR HAS AGREED TO CARRY OUT THE MODIFIED WORK WITHOUT CLAIMING

    ANYTHING EXTRA.

    IN CASE OF OMISSION THE CONTRACTOR WILL NOT BE ENTITLED TO THE LOSS OF

    PROFIT UNLESS IT IS AGREED TO IN ADVANCE. THE CONTRACTOR CAN DEVIATE FROM

    THE DRAWINGS OR SPECIFICATIONS OR THE INSTRUCTIONS OF ARCHITECT AS OTHERWISE

    HE WILL NOT BE ENTITLE TO ANY EXTRA . WHEN OWNER KNOW THAT EXTRA ARE

    ESSENTIAL AND STANDS BY THE DECISION OF ARCHITECT AND FURTHER ALLOW THE

    WORK ORDER TO BE CARRIED OUT, HE WILL BE HELD TO BE RATIFIED THE CONTRACT

    MADE OR TO HAVE IMPLIEDLY PROMISED TO PAY A REASONABLE PRICE FOR THE WORK.

  • 7/28/2019 MQS 312

    7/25

    7

    THE VARIATIONS MUST BE CONFIRMED BY THE ARCHITECT WITHIN THE REASONABLE

    TIME AND RATES IF POSSIBLE. IF THE RATES ARE NOT AGREED UPON THEN THE SAME

    ARE TO BE VALUED AS PER THE MODE GIVEN IN THE ACCOUNT . THE MEASUREMENT AND

    THE BILLS OF EXTRA SHOULD BE COMPLETED WITHIN THE PERIOD OF FINAL

    MEASUREMENT AND IF NOT SPECIFIED THEN WITHIN SIX MONTH FROM THE DATE OF THE

    COMPLETION OF THE BUILDING.

    RIGHTS OF THE CONTRACTOR

    1. THE CONTRACTOR TO REMOVE ALL GOODS, PLANTS, SCAFFOLDINGS, MACHINERIESSHED FROM SITE WITH SUCH PRECAUTIONS SO AS TO PREVENT INJURY DEATH OR

    DAMAGE OF ANYONE. HE SHALL AFFORD THE SAME FACILITIES TO HIS SUB

    CONTRACTORS FOR THE ABOVE

    2. THE CONTRACTOR IS TO BE PAID FOR THE WORK EXECUTED OR PARTLY EXECUTED.3. CONTRACTOR TO BE PAID FOR ALL UNFIXED MATERIALS LYING ON SITES AND ALSO

    FOR COST OF REMOVAL OF GOODS, PLANTS (UNFIXED MATERIAL TO BELONG TO

    OWNER AFTER HE HAS MADE PAYMENTS FOR THE SAME ) THE SAME PROPOSITION

    WILL HOLD GOOD FOR MATERIAL OR GOODS ORDERED FOR THE WORK.

    4. ANY DIRECT LOSS OR DAMAGE CAUSED TO THE CONTRACTOR BY THEDETERMINATION .

    IN ADDITION TO THE ABOVE THE CONTRACTOR WILL HAVE TO LIEN OVER ALL

    UNFIXED MATERIALS TILL THE PAYMENT IS RECEIVED FROM THE OWNER.

    CONTRACTORDUTIESANDLIABILITIES

    THE CONTRACTOR DUTIES AND LIABILITIES ARE GIVEN IN THE CONDITIONS OF THE

    CONTRACT. MOREOVER THERE ARE CERTAIN IMPLIED DUTIES AND LIABILITIES FROM

    WHICH THE CONTRACTOR CANNOT ESCAPE.

    1. THE CONTRACTOR CANNOT RECOVER ANY PAYMENT FOR THE WORKS EXECUTED IFTHE CONTRACT IS AN ENTIRE CONTRACT WHICH SPECIFIES NO PAYMENT ON ACCOUNT

    AS THE WORK PROGRESS UNLESS HE COMPLETES THE WORK. UNDER SUCH

    CIRCUMSTANCES THE CONTRACTOR CANNOT RECOVER THE PAYMENT ON QUANTUM

    MERE IT AND FURTHER CANNOT FILE A SUIT FOR THE RECOVERY.

    2. THE DESIGN ALSO INCLUDE THE CORRECT CHOICE OF THE MATERIALS AND GOODWORKMANSHIP AND A LIMITED LIABILITY OF THE DESIGN REST ON THE CONTRACTOR

    ALSO.IF THE CONTRACTOR DOES NOT SPECIFY THE MIX OF THE CONCRETE FOR R.C.C

    WORKS THE CONTRACTOR IS EXPECTED TO SELECT AND PROVIDE A SUITABLE MIX FOR

    THE INTENDED FUNCTIONS OF CONCRETE .

  • 7/28/2019 MQS 312

    8/25

    8

    3. THE OWNER WHEN HE EMPLOYS A CONTRACTOR RELIES ON HIS KNOWLEDGE, SKILL,JUDGEMENT, HONESTY.AND THUS THERE IS A IMPLIED WARRANTY BY THE

    CONTRACTOR FOR THE WORK FINISHED TO SHAPE AND SIZE WITHOUT PAYMENT OF

    EXTRA AMOUNT FOR THE WASTAGE.PRECAST R.C.C PILES ARE CAST BY THE

    CONTRACTOR TO LENGTH RECOMMENDED BY THE ARCHITECT FOR THE FOUNDATION .

    AFTER THEY ARE DRIVEN IN ADD LENGTH REMAIN ABOVE GROUND LEVEL IN THE

    FORM OF WASTAGE, AND FOR THEIR CUTTING THE CONTRACTOR IS RESPONSIBLE DUE

    TO FOLLOWING FACTS: A)THAT THE LENGTH WERE RECOMMENDED AND NOT

    SPECIFIED IN THE FORM OF SURETY. B)THE CONTRACTOR INCLUDE ALL THE WASTAGE

    AND CUTTING. HENCE HE CANNOT CLAIM FOR THE WASTAGE OF STEEL IN R.C.C

    WORK OR FOR THE WASTAGE OF WOOD IN CASE OF DOORS AND WINDOWS .

    4. IF THE CONTRACTOR SUGGEST AN ALTERNATIVE BUILDING MATERIAL AN IMPLIEDWARRANTY IS THERE THAT HE WILL BE RESPONSIBLE FOR IT EVEN THOUGH THE

    SAME HAS BEEN APPROVED BY THE OWNER.

    5.

    THERE IS AN IMPLIED LIABILITY FOR THE SAFETY OF THE ADJOINING BUILDING WHENEXECUTING THE WORK. AN ADJOINING OLD BUILDING WAS DAMAGED DUE TO THE

    HEAVY VIBRATION CREATED DUE TO THE PILING WORK. IT WAS HELD THAT THE

    CONTRACTOR WAS RESPONSIBLE FOR THE SAME EVEN THOUGH THE ADJOINING

    BUILDING WAS THE OLD MAN.

    6. THE CONTRACTOR HAS NO IMPLIED OR AUTHORITY TO VARY THE WORK EVEN UNDERTHE INSTRUCTION FROM THE OWNER WITHOUT PRIOR CONSULTATION OF THE

    ARCHITECT. CONTRACTOR MAY VARY THE WORK UNDER INSTRUCTION FROM THE

    OWNER THUS INFRINGING THE RULES AND REGULATIONS OF LOCAL AUTHORITY ,THE

    CONTRACTOR WILL NO T BE ABLE TO RECOVER ITS EXTRA COST AND SAME WILL HAVE

    TO BE RECTIFIED AT OWN COST.7. AT TIMES AFTER THE CONTRACT FOR THE ITEM RATE HAS BEEN EXECUTED THE

    OWNER DECIDES TO SUPPLY THE MATERIALS AND WOULD LIKE THE CONTRACTOR TO

    DO LABOUR WORK. UNDER SUCH CIRCUMSTANCES IT WILL NOT BE POSSIBLE FOR THE

    CONTRACTOR TO PERFORM HIS DUTIES AND HENCE CONTRACT CAN BE DISCHARGED

    ON THE GROUND OF IMPOSSIBLE PERFORMANCE. THE CONTRACTOR UNDER SUCH

    CIRCUMSTANCES WILL BE ENTITLE FOR THE LOSS OF PROFIT WHICH SHOULD BE

    CALCULATED KEEPING IN VIEW THE FOLLOWING FACTS NAMELY:

    a) NO RISK IS INVOLVED FOR THE CONTRACTOR.b) CONTRACTOR HAS NOT LOCKED UP HIS CAP ITAL IN WORKc) PRESENT VALUE OF THE PROFIT AS THE PROFIT WOULD HAVE BEEN RECEIVED

    AFTER CERTAIN DURATION WHEN THE WORK WAS COMPLETE.

  • 7/28/2019 MQS 312

    9/25

    9

    RESPONSIBILITIES OF THE CONTRACTOR

    RESPONSIBILITIES OF THE CONTRACTOR INCLUDE:

    UNDERSTANDING THE CONTRACT, INCLUDING THE SPECIFIC CONTRACT OBLIGATIONS AND

    PERFORMANCE INDICATORS BY WHICH PERFORMANCE WILL BE MONITORED.

    ASSESSING THE RISKS RELATED TO THE PROJECT BEFORE CONTRACTING FOR SERVICES TO

    DETERMINE THE EXTENT OF MONITORING APPROPRIATE TO THE CONTRACT.

    ENSURING THE CONTRACTOR HAS A CLEAR UNDERSTANDING OF HOW THE CONTRACT WILL BE

    MANAGED AND MONITORED.

    PROVIDING THE CONTRACTOR WITH GUIDANCE AND TECHNICAL ASSISTANCE, AS NEEDED, TO

    PROMOTE EFFECTIVE CONTRACT PERFORMANCE.

    IDENTIFYING THE EXTENT AND SOURCE OF OTHER PUBLIC FUNDING, IF ANY, THE

    CONTRACTOR

    IS USING TO FUND SERVICES PROVIDED UNDER THE CONTRACT.

    MONITORING THE CONTRACTORS ACTIVITIES THROUGH A VARIETY OF MEANS TO ENSURE

    QUALITY SERVICE DELIVERY.

    ENSURE FUNDING IS USED ONLY FOR AUTHORIZED PURPOSES.

    RESOLVING ISSUES OR PROBLEMS THAT ARISE DURING THE CONTRACT .

    IDENTIFYING AND REDUCING FISCAL OR PROGRAM RISKS, THUS PROTECTING PUBLIC FUNDS.

    MEASURING AND TRACKING AGENCY SATISFACTION WITH CONTRACTOR PERFORMANCE.

    REVIEWING INVOICES AND VERIFYING THAT DELIVERY OF SERVICES IS RENDERED.

    NOTIFYING MANAGEMENT AND THE OFFICE OF THE ATTORNEY GENERAL IF SERIOUS

    PROBLEMS ARISE.

    COMPLYING WITH FEDERAL AND STATE RULES AND REGULATIONS PERTAINING TO CONTRACT

    MANAGEMENT.

    COLLABORATING WITH OTHER STATE AGENCIES USING THE SAME CONTRACTOR TO ENSURE

  • 7/28/2019 MQS 312

    10/25

    10

    PROJECT ENGINEER:

    PROJECT ENGINEER IS THE MAIN COORDINATOR FOR THE PROJECT BETWEEN THE EMPLOYER

    AND THE CONTRACTOR.HE IS THE PERSON WHO DOES THE PLANNING OF SCHEDULE OF WORK

    PROGRESS AND MONITORS THEPERIODICAL PROGRESS

    OFTHEWORK. HEISINVOLVEDINALLTHETECHNICAL/ REVIEWMEETINGSWITHTHE

    CONTRACTOR DURING THE EXECUTION OF THE PROJECT.CONTRACTOR SHOULD ADDRESS ANY

    DISCREPANCY ARISES DURING THE EXECUTION OF THE PROJECT TO THE PROJECT ENGINEER

    ONLY WITH DUE COORDINATION OF THE SITE ENGINEERFROM THE DEPARTMENT

    SITE ENGINEER:SITE ENGINEER IS THE PERSON DEPUTED ON THE SITE FOR CLOSE MONITORING OF THE

    PROGRESS OFTHE PROJECT.HE COMMUNICATES ALL THE TECHNICAL INFORMATION TO THE

    REPRESENTATIVES OF THE CONTRACTORWORKING DIRECTLY ON SITE.HE RECEIVESINSTRUCTIONS FROM THE PROJECT ENGINEER AND EXECUTES THE PROJECT UNDER HIS

    GUIDANCE WITH THE HELP OF SUPERVISORS ASSISTING HIM.HE IS RESPONSIBLE FOR TIMELY

    RECORDING OFTHE MEASUREMENTS OFTHE WORKS AND CALCULATING THE QUANTITIES

    OFITEMS FOR RUNNING BILLS AND FINAL BILLS.HE COORDINATES WITH ALL CONCERNED

    DIVISIONS OF THE DEPARTMENT LIKE SAFETY,UTILITIES, ETC. FOR OBTAINING THE PERMITS

    AND THE SMOOTH COORDINATION OF THE SITE EXECUTION OF THE PROJECT.HE IS THE PERSON

    RESPONSIBLE FOR THE FOLLOW UP WITH CONTRACTOR FOR DAILY PROGRESS OF THE WORK.

    PROJECT ENGINEER:

    PROJECT ENGINEER IS THE KEY COORDINATOR BETWEEN THE CLIENT AND THE MANAGEMENT

    OF THE COMPANY.HE COORDINATES REGULARLY WITH THE PROJECT ENGINEER FROM THE

    DEPARTMENT (EMPLOYER/CLIENT) FOR ALL THE ACTIVITIES PERTAINING TO THE PROGRESS

    OF THE PROJECT.HE IS THE PERSON WHO COMMUNICATES ALL THE MATTERS TO THE CLIENT

    ON BEHALF OF THE CONTRACTOR THROUGH THEIRPROJECT ENGINEER.HE IS THE SOLE

    RESPONSIBLE PERSON FORTHE PROGRESSAND QUALITYOFCONSTRUCTION OFTHE

    PROJECT. HEHAS TOMAKEPERIODICAL SCHEDULES ANDPLAN FOR THE RESOURCESLIKE

    MATERIAL ANDMAN-POWER.

  • 7/28/2019 MQS 312

    11/25

    11

    DETERMINATIONOF THECONTRACTBYTHE

    CONTRACTOR

    THE CONTRACTOR CAN DETERMINE THE CONTRACT ON THE FOLLOWING GROUNDS :

    1. AMOUNT OF INTERIM CERTIFICATE IS NOT RECEIVED WITHIN THE PERIODMENTIONED IN THE APPENDIX AND CONTINUOUS DEFAULT FOR SEVEN DAYS

    AFTER RECEIPT OF NOTICE THAT CONTRACT WILL BE DETERMINED IF PAYMENT IS

    NOT MADE WITHIN SEVEN DAYS FROM THE RECEIPT THEREOF.

    2. IF THE OWNER INTERFERES WITH OR OBSTRUCT THE ISSUE OF ANY CERTIFICATEDUE UNDER THE CONTRACT.

    3. CARRYING OUT THE WHOLE OR SUBSTANTIALLY THE WHOLE OF INCOMPLETEWORK IS SUSPENDED FOR A CONTINUOUS P ERIOD OF LENGTH BY REASONS OF:

    FORCE MAJEURE ,LOSS OR DAMAGE OCCASIONED BY ANYONE OR MORE OF THECONTINGENCIES REFERRED TO IN CLAUSE OF INSURANCE AGAINST FIRE, CIVIL

    COMMOTION, DELAY BY ARCHITECT IN ISSUING NECESSARY PLANS OR

    INSTRUCTION, DELAY ON PART OF AGENCIES EMPLOYED BY THE OWNER OF THE

    WORK OUTSIDE FRAMEWORK OF CONTRACT OR, OPENING OF THE WORK COVERED

    UP FOR INSPECTION WORK AND MATERIAL USED BEING AS PER THE CONTRACT

    DOCUMENT ( UNLESS THESE ARE NOT AS PER THE CONTRACT DOCUMENTS.

    CLIENT

    RIGHT OF ACCESS TO THE SITE THE EMPLOYER SHALLGIVE THE CONTRACTOR RIGHT OF

    ACCESSTO, ANDPOSSESSION OF, ALL PARTS OF THE SITE WITHIN THE TIME (OR TIMES) STATED

    IN THE CONTRACT DATA.THE RIGHT AND POSSESSION MAY NOT BE EXCLUSIVE TO THE

    CONTRACTOR.IF, UNDER THE CONTRACT, THE EMPLOYER IS REQUIRED TO GIVE (TO THE

    CONTRACTOR) POSSESSION OF ANY FOUNDATION, STRUCTURE, PLANT OR MEANS OF ACCESS,

    THE EMPLOYER SHALL DO SO IN THE TIME AND MANNER STATED IN THE SPECIFICATION.

    HOWEVER, THE EMPLOYER MAY WITHHOLD ANY SUCH RIGHT OR POSSESSION UNTIL THE

    PERFORMANCE SECURITY HAS BEEN RECEIVED.

    IF NO SUCH TIME IS STATED IN THE CONTRACT DATA, THE EMPLOYER SHALL GIVE THE

    CONTRACTOR RIGHT OF ACCESS TO, AND POSSESSION OF, THE SITE WITHIN SUCH TIMES AS

    REQUIRED TO ENABLE THE CONTRACTOR TO PROCEED WITHOUT DISRUPTION IN ACCORDANCE

    WITH THE PROGRAMMED SUBMITTED UNDERSUB-CLAUSE 8.3

  • 7/28/2019 MQS 312

    12/25

    12

    IF THE CONTRACTOR SUFFERS DELAY AND/OR INCURS COST AS A RESULT OF A FAILURE BY THE

    EMPLOYER TO GIVE ANY SUCH RIGHT OR POSSESSION WITHIN SUCH TIME, THE CONTRACTOR

    SHALL GIVE NOTICE TO THE ENGINEER AND SHALL BE ENTITLED SUBJECT TO SUB-CLAUSE 20.1

    CONTRACTORS CLAIMS

    TO:(A) AN EXTENSION OF TIME FOR ANY SUCH DELAY, IF COMPLETION IS OR WILL BE DELAYED,

    UNDERSUB-CLAUSE 8.4[EXTENSION OF TIME FORCOMPLETION ], AND(B) PAYMENT OF ANY

    SUCH COST PLUS PROFIT, WHICH SHALL BE INCLUDED IN THE CONTRACT PRICE.

    CLIENTSRESPONSIBILITIESTHE FOLLOWING SHALL BE THE RESPONSIBILITIES OF THE CLIENT:

    1. PROVIDE DETAILED REQUIREMENT OF THE PROJECT.2.

    PROVIDE A CORRECT SITE PLAN TO SUITABLE SCALE SHOWING BOUNDARIES ATSUITABLE INTERVALS.

    3. FURNISH REPORT ON SOIL CONDITIONS AND SOIL TEST AS REQUIRED BY THEARCHITECT.

    4. IN THE CASE OF CLIENT BEING A GOVERNMENT AGENCY IT WILL FURNISH PUBLICWORKS DEPARTMENT SCHEDULE OF RATES.

    5. PAY THE FEES OF THE ARCHITECT WITHIN ONE MONTH OF SUBMISSION OF BILLS.6. TAKE NOTE OF THE OBSERVATION MADE BY THE ARCHITECT ON HIS INSPECTIONS

    AND VISITS AND ENSURE THE CORRECTION OF DEFICIENCIES IN THE WORK POINTED

    OUT BY HIM.

    7. ON THE ADVICE OF THE ARCHITECT PREP ARE A SHORT LIST OF APPROVEDCONTRACTORS WHO WOULD BE ALLOWED TO TENDER, SELECT THE CONTRACTOR FOR

    PROJECT IN CONSULTATION WITH ARCHITECT.

  • 7/28/2019 MQS 312

    13/25

    13

    GUIDELINES

    1. AN EXPERT KNOWLEDGE OF THE TECHNIQUES AND SKILLS REQUIRED TO CARRY OUTTHE DESIGN.

    2. A THOROUGH UNDERSTANDING OF THE PURPOSES AND FUNCTIONS OF THE BUILDINGTO BE ERECTED.

    3. A WORKING KNOWLEDGE OF THE ACT, BYE-LAWS AND OTHER REGULATIONSAFFECTING BUILDINGS.

    4. THE ABILITY TO ADVISE ON COSTS.5. SKILLS IN THE PREP ARATIONS OF DRAWING PLANS TO ENSURE THAT BUILDING WILL

    FULFIL ALL REQUIREMENTS AT MOST ECONOMIC COST.

    6. THE ABILITY TO SUPERINTEND THE DESIGN AND CONSTRUCTION OF THE BUILDING.7. THE ABILITY TO ISSUE CERTIFICATE OF PAYMENT.

    CLIENTS DUTIESANDLIABILITIES

    BESIDE THE RIGHTS DUTIES AND LIABILITIES FLOWING FROM THE BUILDING CONTRACT

    SOME OF THE SPECIFIC DUTIES AND LIABILITIES OF THE OWNER ARE AS UNDER:

    1. TO APPOINT ARCHITECT, ENGINEER, SURVEYOR AND OTHER CONSULTANT AND TO PAYTHEIR PROFESSIONAL FEES.

    2. TO GIVE INSTRUCTION TO THE ARCHITECT ABOUT HIS REQUIREMENT OF THE PROJECT .3. DISCUSS BID EVALUATION WITH THE ARCHITECT SO THAT RIGHT CONTRACTOR FOR

    THE JOB IN QUESTION IS SELECTED AND GENUINE MISTAKES BE CORRECTED .

    4. ACCEPT THE TENDER OR AUTHORIZE THE ARCHITECT TO ACCEPT THE TENDER ON HISBEHALF.

    5. TO ENTER INTO A CONTRACT WITH THE CONTRACTOR.6. NOT TO INTERFERE WITH THE PROGRESS OF THE WORK AND NOT TO ISSUE ORDERS

    FOR EXTRA WORKS.

    7. TO SUPPLY ALL NECESSARY PLANS DRAWINGS INSTRUCTION IN TIME THROUGH THEAGENCY OF HIS ARCHITECT WITHIN A REASONABLE TIME

    8. TO MAKE NECESSARY PAYMENTS AS CERTIFIED BY ARCHITECT FROM TIME TO TIMEAND NOT TO INTERFERE WITH ISSUE OF CERTIFICATES IN THE CASE OF HICKMAN &

    CO VS ROBERTS (1913) AC229 WHERE THE EMPLOYER INSTRUCTED THE ARCHITECTNOT TO ISSUE A CERTIFICATE UNTIL HE HAD RECEIVED THE CONTRACTOR S ACCOUNT

    FOR EXTRA THE ARCHITECT WROTE TO THE CONTRACTOR

    HAD YOU BETTER NOT CALL TO SEE MY CLIENTS, BECAUSE IN FACE OF THEIR

    INSTRUCTIONS TO ME I CANNOT ISSUE A CERTIFICATE WHATEVER MY OWN PRIVATE

    OPINION IN THE MATTER.

  • 7/28/2019 MQS 312

    14/25

    14

    FIDIC CONDITIONS OF CONTRACTS FOR CONSTRUCTIONSHOWEVER, IF AND TO THE EXTENT THAT THE EMPLOYERS FAILURE WAS CAUSED BY

    ANY ERROR OR DELAY BY THE CONTRACTOR, INCLUDING AN ERROR IN, OR DELAY IN THE

    SUBMISSION OF, ANY OF THE CONTRACTORS DOCUMENTS, THE CONTRACTOR SHALL NOT BE

    ENTITLED TO SUCH EXTENSION OFTIME,COST OR PROFIT THE EMPLOYER SHALL PROVIDE, ATTHE REQUEST OF THE CONTRACTOR, SUCH REASONABLE ASSISTANCE AS TO ALLOW

    THE CONTRACTOR TO OBTAIN PROPERLY:

    (A) COPIESOF THE LAWS OFTHE COUNTRYWHICHARE RELEVANTTO THE CONTRACTBUT

    ARE NOT READILY AVAILABLE, AND

    (B)ANY PERMITS, LICENSES OR APPROVALS REQUIRED BY THE LAWS OF THE COUNTRY:

    (I) WHICH THE CONTRACTOR IS REQUIRED TO OBTAIN UNDERSUB-CLAUSE 1.13COMPLIANCE

    WITH LAWS

    (II) FOR THEDELIVERY OF GOODS, INCLUDING CLEARANCE THROUGH CUSTOMS, AND

    (III) FOR THE EXPORT OF CONTRACTORS EQUIPMENT WHEN IT IS REMOVED FROM THE SITEANY DELEGATION OR REVOCATION SHALL NOT TAKE EFFECT UNTIL THE ENGINEER HAS

    RECEIVED PRIOR NOTICE SIGNED BY THE CONTRACTORS REPRESENTATIVE, NAMING THE

    PERSON AND SPECIFYING THE POWERS, FUNCTIONS AND AUTHORITY BEING DELEGATED OR

    REVOKED.THE CONTRACTORS REPRESENTATIVE SHALL BE FLUENT IN THE LANGUAGE FOR

    COMMUNICATIONS DEFINED IN SUB-CLAUSE 1.4LAW AND LANGUAGE IF THE CONTRACTORS

    REPRESENTATIVES DELEGATES ARE NOT FLUENT IN THE SAID LANGUAGE , THE CONTRACTOR

    SHALL MAKE COMPETENT INTERPRETERS AVAILABLE DURING ALL WORKING HOURS IN A

    NUMBER DEEMED SUFFICIENT BY THE ENGINEER.

    SUBCONTRACTORS

    THE CONTRACTOR SHALL NOT SUBCONTRACT THE WHOLE OFTHE WORKS.THE CONTRACTOR

    SHALL BE RESPONSIBLE FOR THE ACTS OR DEFAULTS OF ANY SUB CONTRACTOR, HIS AGENTS

    OR EMPLOYEES, AS IF THEY WERE THE ACTS OR DEFAULTS OF THE CONTRACTOR.UNLESS

    OTHERWISE STATED INTHE PARTICULARCONDITIONS:

    THE CONTRACTOR SHALL NOT BE REQUIRED TO OBTAIN CONSENT TO SUPPLIERS SOLELY OF

    MATERIALS, OR TO A SUBCONTRACT FOR WHICH THE SUBCONTRACTOR IS NAMED IN THE

    CONTRACT THE PRIOR CONSENT OF THE ENGINEER SHALL BE OBTAINED TO OTHER PROPOSED

    SUBCONTRACTORS;

    THE CONTRACTOR SHALL GIVE THE ENGINEER NOT LESS THAN 28 DAYS

    NOTICE OF THE INTENDED DATE OF THE COMMENCEMENT OF EACH SUBCONTRACTORS WORK,

    AND OF THE COMMENCEMENT OF SUCH WORK ON THE SITE; AND EACH SUBCONTRACT SHALL

    INCLUDE PROVISIONS WHICH WOULD ENTITLE THE EMPLOYER TO REQUIRE THE SUBCONTRACT

    TO BE ASSIGNED TO THE EMPLOYER UNDERSUB-CLAUSE 4.5[ASSIGNMENT OF BENEFIT OF

  • 7/28/2019 MQS 312

    15/25

    15

    SUBCONTRACT ](IF OR WHEN APPLICABLE) OR IN THE EVENT OF TERMINATION UNDERSUB-

    CLAUSE 15.2

    ASSIGNMENT OF BENEFIT OF SUBCONTRACT IF A SUBCONTRACTORS OBLIGATIONS EXTEND

    BEYOND THE EXPIRY DATE OF THE RELEVANT DEFECTSNOTIFICATION PERIOD AND THE

    ENGINEER, PRIOR TO THIS DATE, INSTRUCTSTHE CONTRACTORTOASSIGNTHE BENEFITOF

    SUCHOBLIGATIONS TO THE EMPLOYER, THEN THE CONTRACTOR SHALL DO SO. UNLESS

    OTHERWISE STATED IN THE ASSIGNMENT, THE CONTRACTORSHALL HAVENO

    LIABILITYTOTHE EMPLOYERFORTHE WORK CARRIED OUT BY THE SUBCONTRACTOR AFTER

    THE ASSIGNMENT TAKES EFFECT.

    CO-OPERATION

    THE CONTRACTOR SHALL, AS SPECIFIED IN THE CONTRACT OR AS INSTRUCTED BY THE

    ENGINEER, ALLOW APPROPRIATE OPPORTUNITIES FOR CARRYING OUTWORK TO:(A) THE EMPLOYERS PERSONNEL,

    (B) ANY OTHER CONTRACTORS EMPLOYED BY THE EMPLOYER, AND

    (C) THE PERSONNEL OFANY LEGALLY CONSTITUTED PUBLIC AUTHORITIES, WHO MAY BE

    EMPLOYED IN THE EXECUTION ON OR NEAR THE SITE OF ANY WORK NOT INCLUDED IN THE

    CONTRACT.

    ANY SUCH INSTRUCTION SHALL CONSTITUTE A VARIATION IF AND TO THE EXTENT THAT IT

    CAUSES THE CONTRACTOR TO SUFFER DELAYS AND/OR TO INCURUNFORESEEABLE COST.

    SERVICES FOR THESE PERSONNEL AND OTHER CONTRACTORS MAY INCLUDE THE USE OF

    CONTRACTORS EQUIPMENT,TEMPORARY WORKS OR ACCESS ARRANGEMENTS WHICH ARE

    THE RESPONSIBILITY OF THE CONTRACTORIF, UNDER THE CONTRACT, THE EMPLOYER IS

    REQUIRED TO GIVE TO THE CONTRACTOR POSSESSION OF ANY FOUNDATION, STRUCTURE,

    PLANT OR MEANS OF ACCESS IN ACCORDANCE WITH CONTRACTORS DOCUMENTS, THE

    CONTRACTOR SHALL SUBMIT SUCH DOCUMENTS TO THE ENGINEER IN THE TIME ANDMANNER

    STATED IN THE SPECIFICATION.

    SETTING OUT

    THE CONTRACTOR SHALL SET OUT THE WORKS IN RELATION TO ORIGINAL POINTS, LINES AND

    LEVELS OF REFERENCE SPECIFIED IN THE CONTRACT OR NOTIFIED BY THE ENGINEER.THECONTRACTOR SHALL BE RESPONSIBLE FOR THE CORRECT POSITIONING OF ALL PARTS OF

    THEWORKS, ANDSHALLRECTIFYANYERRORINTHEPOSITIONS, LEVELS, DIMENSIONS OR

    ALIGNMENT OF THE WORKS THE EMPLOYER SHALL BE RESPONSIBLE FOR ANY ERRORS IN

    THESE SPECIFIED OR NOTIFIED ITEMS OF REFERENCE, BUT THE CONTRACTOR SHALL USE

    REASONABLE EFFORTS TO VERIFY THEIR ACCURACY BEFORE THEY AREUSED.

  • 7/28/2019 MQS 312

    16/25

    16

    THE POWERS OF COURTS UNDER ARBITRATION AND

    CONCILIATION ACT,1996

    AN ACT TO CONSOLIDATE AND AMEND THE LAW RELATING TO DOMESTIC ARBITRATION,

    INTERNATIONAL COMMERCIAL ARBITRATION AND ENFORCEMENT OF FOREIGN ARBITRAL

    AWARDS AS ALSO TO DEFINE THE LAW RELATING TO CONCILIATION AND FOR MATTERS

    CONNECTED THEREWITH OR INCIDENTAL THERETO.WHEREAS THE UNITEDNATIONS

    COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL) HAS ADOPTED THE UNCITRAL

    MODEL LAW ON INTERNATIONAL COMMERCIAL ARBITRATION IN 1985:ANDWHEREAS

    THE GENERAL ASSEMBLYOF THE UNITED NATIONS HASRECOMMENDED THATALL COUNTRIES

    GIVE DUE CONSIDERATION TO THE SAID MODEL LAW, IN VIEW OF THE DESIRABILITY OF

    UNIFORMITY OF THE LAW OF ARBITRAL PROCEDURES AND THE SPECIFIC NEEDS OF

    INTERNATIONAL COMMERCIAL ARBITRATION PRACTICE;ANDWHEREAS THE UNCITRAL

    HAS ADOPTED THE UNCITRALCONCILIATION RULES IN 1980;ANDWHEREAS THEGENERAL ASSEMBLY OF THE UNITEDNATIONS HAS RECOMMENDED THE USE OF THE SAID

    RULES IN CASES WHERE A DISPUTE ARISES IN THE CONTEXT OF INTERNATIONAL COMMERCIAL

    RELATIONS AND THE PARTIES SEEK AN AMICABLE SETTLEMENT OF THAT DISPUTE BY RECOURSE

    TO CONCILIATION;ANDWHEREAS THE SAID MODEL LAW AND RULES MAKE SIGNIFICANT

    CONTRIBUTION TO THE ESTABLISHMENT OF A UNIFIED LEGAL FRAMEWORK FOR THE FAIR AND

    EFFICIENT SETTLEMENT OF DISPUTES ARISING IN INTERNATIONAL COMMERCIAL RELATIONS;

    ANDWHEREAS IT IS EXPEDIENT TO MAKE LAW RESPECTING ARBITRATION AND

    CONCILIATION, TAKING INTO ACCOUNT THE AFORESAID MODEL LAW AND RULES;

    BE IT ENACTED BY PARLIAMENT IN THE FORTY-SEVENTH YEAR OF THE REPUBLIC OF INDIA AS

    FOLLOWS:-PRELIMINARY1.SHORT TITLE, EXTENT AND COMMENCEMENT.-

    (1)THIS ACT MAY BE CALLED THE ARBITRATION AND CONCILIATION ACT,1996.

    (2)IT EXTENDS TO THE WHOLE OF INDIA:PROVIDED THAT PARTS,I,III AND IV SHALL EXTEND

    TO THE STATE OF JAMMU AND KASHMIR ONLY IN SO FAR AS THEY RELATE TO INTERNATIONAL

    COMMERCIAL ARBITRATION OR, AS THE CASE MAY BE, INTERNATIONAL COMMERCIAL

    CONCILIATION.EXPLANATION.-IN THIS SUB-SECTION, THE EXPRESSION "INTERNATIONAL

    COMMERCIAL CONCILIATION "SHALL HAVE THE SAME MEANING AS THE EXPRESSION

    "INTERNATIONAL COMMERCIAL ARBITRATION" IN CLAUSE (F) OF SUB-SECTION (1) OF SECTION

    2, SUBJECT TO THE MODIFICATION THAT FOR THE WORD" ARBITRATION" OCCURRING THEREIN,

    THE WORD "CONCILIATION" SHALL BE SUBSTITUTED.

    (3)IT SHALL COME INTO FORCE ON SUCH DATE AS THE CENTRAL GOVERNMENT MAY, BY

    NOTIFICATION IN THE OFFICIAL GAZETTE, APPOINT.

    (1)IN THIS PART, UNLESS THE CONTEXT OTHERWISE REQUIRES,-

  • 7/28/2019 MQS 312

    17/25

    17

    A) "ARBITRATION" MEANS ANY ARBITRATION WHETHER OR NOT ADMINISTERED BY

    PERMANENT ARBITRAL INSTITUTION;

    B) "ARBITRATION AGREEMENT" MEANS AN AGREEMENT REFERRED TOIN SECTION 7;

    C) "ARBITRAL AWARD" INCLUDESAN INTERIMAWARD;

    D) "ARBITRAL TRIBUNAL" MEANS ASOLE ARBITRATOR OR A PANEL OF ARBITRATORS;

    E)"COURT" MEANS THE PRINCIPAL CIVIL COURT OF ORIGINAL JURISDICTION IN A DISTRICT,

    AND INCLUDES THE HIGH COURT IN EXERCISE OF ITS ORDINARY ORIGINAL CIVIL JURISDICTION,

    HAVINGJURISDICTION TO DECIDE THE QUESTIONS FORMING THE SUBJECT-MATTER OF THE

    ARBITRATION IF THE SAME HAD BEEN THE SUBJECT-MATTER OF A SUIT, BUT DOES NOT INCLUDE

    ANY CIVIL COURT OF A GRADE INFERIOR TO SUCH PRINCIPAL CIVIL COURT, ORANY COURT OF

    SMALL CAUSES;

    F)"INTERNATIONAL COMMERCIAL ARBITRATION" MEANS AN ARBITRATION RELATING TO

    DISPUTES ARISING OUT OF LEGAL RELATIONSHIPS, WHETHER CONTRACTUAL OR NOT,

    CONSIDERED AS COMMERCIAL UNDER THE LAW IN FORCE IN INDIAAND WHERE AT LEAST ONE

    OFTHE PARTIES IS-

    1) AN INDIVIDUAL WHO IS A NATIONAL OF, OR HABITUALLY RESIDENT IN, ANY COUNTRY

    OTHER THAN INDIA; OR

    2) A BODY CORPORATE WHICH ISINCORPORATED IN ANY COUNTRY OTHERTHAN INDIA; OR

    3) A COMPANY OR AN ASSOCIATION OR A BODY OF INDIVIDUALS WHOSE CENTRAL

    MANAGEMENT AND CONTROL IS EXERCISED IN ANY COUNTRY OTHER THAN INDIA; OR4) THE GOVERNMENTOF A FOREIGN COUNTRY;

    (G)"LEGAL REPRESENTATIVE" MEANS A PERSON WHO IN LAW REPRESENTS THE ESTATE OF A

    DECEASED PERSON, AND INCLUDES ANY PERSON WHO INTERMEDDLES WITH THE ESTATE OF THE

    DECEASED, AND, WHERE A PARTY ACTS IN A REPRESENTATIVE CHARACTER, THE PERSON ON

    WHOM THE ESTATE DEVOLVES ON THE DEATH OF THE PARTY SO ACTING ;

    (H)"PARTY" MEANS A PARTY TO ANARBITRATION AGREEMENT.

    (2)THIS PART SHALL APPLY WHERE THEPLACE OF ARBITRATION IS IN INDIA.

    (3)THIS PART SHALL NOT AFFECT ANY OTHER LAW FOR THE TIME BEING IN FORCE BY VIRTUE

    OF WHICH CERTAIN DISPUTES MAY NOT BE SUBMITTED TO ARBITRATION .

    (4)THIS PART EXCEPT SUB-SECTION (1) OF SECTION 40, SECTIONS 41 AND 43 SHALL APPLY TO

    EVERY ARBITRATION UNDER ANY OTHER ENACTMENT FOR THE TIME BEING IN FORCE, AS IF THE

    ARBITRATION WERE PURSUANT TO AN ARBITRATION AGREEMENT AND AS IF THAT OTHER

  • 7/28/2019 MQS 312

    18/25

    18

    ENACTMENT WERE AN ARBITRATION AGREEMENT, EXCEPT IN SO FAR AS THE PROVISION OF THIS

    PART ARE INCONSISTENT WITH THAT OTHER ENACTMENT OR WITH ANY RULES MADE THERE

    UNDER;

    (5)SUBJECT TO THE PROVISIONS OF SUB-SECTION

    EXTENT OF JUDICIAL INTERVENTION.-NOTWITHSTANDING ANYTHING CONTAINED IN ANY OTHER LAWFOR THE TIME BEING IN FORCE,

    IN MATTERS GOVERNED BY THIS PART, NO JUDICIAL AUTHORITY SHALL INTERVENE EXCEPT

    WHERE SO PROVIDED IN THIS PART.

    ADMINISTRATIVE ASSISTANCE(1)IN ORDER TO FACILITATE THE CONDUCT OF THE ARBITRAL PROCEEDINGS, THE PARTIES, OR

    THE ARBITRAL TRIBUNAL WITH THE CONSENT OF THE PARTIES, MAY ARRANGE FOR

    ADMINISTRATIVE ASSISTANCE BY A SUITABLE INSTITUTION OR PERSON

    A DECISION BY THEARBITRAL TRIBUNAL THAT THECONTRACT IS NULL AND VOID SHALL NOT

    JURE THE INVALIDITY OF THEARBITRATION CLAUSE.

    (2)A PLEA THAT THE ARBITRAL TRIBUNAL DOES NOT HAVE JURISDICTION SHALL BE RAISED

    NOT LATER THAN THE SUBMISSION OF THE STATEMENT OF DEFENCE; HOWEVER, A PARTY

    SHALL NOT BE PRECLUDED FROM RAISING SUCH A PLEA MERELY BECAUSE THAT HE HAS

    APPOINTED , OR PARTICIPATED IN THE APPOINTMENT OF, AN ARBITRATOR.

    (3)A PLEA THAT THE ARBITRAL TRIBUNAL IS EXCEEDING THE SCOPE OF ITS AUTHORITY SHALL

    HE RAISED AS SOON AS THE MATTER ALLEGED TO BE BEYOND THE SCOPE OF ITS AUTHORITY IS

    RAISED DURING THE ARBITRAL PROCEEDINGS .

    (4)THE ARBITRAL TRIBUNAL MAY, IN EITHER OF THE CASES REFERRED TO IN SUB-SECTION (2)

    OR SUB-SECTION (3), ADMIT A LATER PLEA IF IT CONSIDERS THE DELAY JUSTIFIED.

    (5)THE ARBITRAL TRIBUNAL SHALL DECIDE ON A PLEA REFERRED TO IN SUB-SECTION (2) OR

    SUB-SECTION(3) AND, WHERE THE ARBITRAL TRIBUNAL TAKES A DECISION REJECTING THE

    PLEA, CONTINUE WITH THE ARBITRAL PROCEEDINGS AND MAKE AN ARBITRAL AWARD

    .(6)A PARTY AGGRIEVED BY SUCH AN ARBITRAL AWARD MAY MAKE AN APPLICATION FOR

    SETTING AS SUCH AN ARBITRAL AWARD IN ACCORDANCE WITHSECTION 34.

    17.INTERIM MEASURES ORDERED BY ARBITRAL TRIBUNAL

    .-(1)UNLESS OTHERWISE AGREED BY THE PARTIES , THE ARBITRAL TRIBUNAL MAY, AT THE

    REQUEST OF A PARTY, ORDER A PARTY TO TAKE ANY INTERIM MEASURE OF PROTECTION AS THE

  • 7/28/2019 MQS 312

    19/25

    19

    ARBITRAL TRIBUNAL MAY CONSIDER NECESSARY IN RESPECT OF THE SUBJECT MATTER OF THE

    DISPUTE.(2) THE ARBITRAL TRIBUNAL MAY REQUIRE APARTY TO PROVIDE APPROPRIATE

    SECURITYIN CONNECTION WITH A MEASURE ORDERED UNDER SUB-SECTION (1).

    CONDUCT

    OF ARBITRAL PROCEEDINGS

    18.EQUAL TREATMENT OF PARTIESTHE PARTIES SHALL BE TREATED WITH EQUALITY AND EACH PARTY SHALL BE GIVEN A FULL

    OPPORTUNITY TOPRESENT HIS CASE19.DETERMINATION OF RULES OF PROCEDURE.-

    (1)THE ARBITRAL TRIBUNAL SHALL NOT BE BOUND BY THE CODE OF CIVIL PROCEDURE,1908

    OR THE INDIAN EVIDENCE ACT,1872.

    (2)SUBJECT TO THIS PART, THE PARTIES ARE FREE TO AGREE ON THE PROCEDURE TO BE

    FOLLOWED BY THE ARBITRAL TRIBUNALIN CONDUCTINGITS PROCEEDINGS.

    (3) FAILING ANY AGREEMENT REFERRED TO IN SUB-SECTION (2), THE ARBITRAL TRIBUNAL

    MAY, SUBJECT TO THIS PART, CONDUCT THE PROCEEDINGS IN THE MANNER IT

    CONSIDERSAPPROPRIATE.(4) THE POWEROF THEARBITRAL TRIBUNAL UNDERSUB-SECTION (3) INCLUDES THEPOWER

    TO DETERMINE THE ADMISSIBILITY , RELEVANCE, MATERIALITY ANDWEIGHT OF ANY

    EVIDENCE.

    PLACE OF ARBITRATION(1) THE PARTIES ARE FREETO AGREE ONTHE PLACE OFARBITRATION.

    (2)FAILING ANY AGREEMENT REFERRED TO IN SUB-SECTION (1), THE PLACE OF ARBITRATION

    SHALL BE DETERMINED BY THE ARBITRAL TRIBUNAL HAVING REGARD TO THE CIRCUMSTANCES

    OF THE CASE, INCLUDING THE CONVENIENCE OF THE PARTIES.

    (3)NOTWITHSTANDING SUB-SECTION (1) OR SUB-SECTION (2), THE ARBITRAL TRIBUNAL MAY,

    UNLESS OTHERWISE AGREED BY THE PARTIES, MEET AT ANY PLACE IT CONSIDERS APPROPRIATE

    FOR CONSULTATION AMONG ITS MEMBERS, FOR HEARING WINNERS, EXPERTS OR THE PARTIES,

    OR FOR INSPECTION OF DOCUMENTS, GOODS OR OTHER PROPERTY.

    COMMENCEMENT OF ARBITRAL PROCEEDINGS

    UNLESS OTHERWISE AGREED BY THE PARTIES, THE ARBITRAL PROCEEDINGS, IN RESPECT OF A

    PARTICULAR DISPUTE COMMENCE ON THE DATE ON WHICH A REQUEST FOR THAT DISPUTE

    TOBE REFERRED TO ARBITRATION IS RECEIVEDBY THE RESPONDENT.

  • 7/28/2019 MQS 312

    20/25

    20

    LANGUAGE(1)THE PARTIES ARE FREE TO AGREE UPON THE LANGUAGE OR LANGUAGES TO IS USED IN THE

    ARBITRAL PROCEEDINGS.

    (2) FAILING ANYAGREEMENT REFERRED TOIN SUB-SECTION (1), THE ARBITRALTRIBUNAL

    SHALL DETERMINE THE LANGUAGE OR LANGUAGES TO BE USED IN THE ARBITRALPROCEEDINGS .

    (3)THE AGREEMENT OR DETERMINATION, UNLESS OTHERWISE SPECIFIED, SHALL APPLY TO

    ANY WRITTEN STATEMENT BY A PARTY, ANY HEARING AND ANY ARBITRAL AWARD, DECISION

    OR OTHER COMMUNICATION BY THE ARBITRAL TRIBUNAL .(4)THE ARBITRAL TRIBUNAL MAY

    ORDER THAT ANY DOCUMENTARY EVIDENCE SHALL BE ACCOMPANIED BY A TRANSLATION INTO

    THE LANGUAGES AGREED UPON BY THE PARTIES OR DETERMINED BY THE ARBITRAL TRIBUNAL.

    STATEMENTS OF CLAIM AND DEFENCE(1)WITHIN THE PERIOD OF TIME AGREED UPON BY THE PARTIES OR DETERMINED BY THE

    ARBITRAL TRIBUNAL, THE CLAIMANT SHALL STATE THE FACTS SUPPORTING HIS CLAIM , THE

    POINTS AT ISSUE AND THE RELIEF OR REMEDY SOUGHT, AND THE RESPONDENT SHALL STATE

    HIS DEFENCE IN RESPECT OF THESE PARTICULARS, UNLESS THE PARTIES HAVE OTHERWISE

    AGREED AS TO ELEMENTS OF THOSE STATEMENTS.

    (2)THE PARTIES MAY SUBMIT WITH THEIR STATEMENTS ALL DOCUMENTS THEY CONSIDER TO

    BE RELEVANT OR MAY ADD A REFERENCE TO THE DOCUMENTS OR OTHER EVIDENCE THEY WILL

    SUBMIT.

    (3) UNLESS OTHERWISE AGREED BY THE PARTIES, EITHER PARTY MAY AMEND OR SUPPLEMENT

    HIS CLAIM OR DEFENCE DURING THE COURSE OF THE ARBITRAL PROCEEDINGS , UNLESS THE

    ARBITRAL TRIBUNAL CONSIDERS IT INAPPROPRIATE TO ALLOW THE AMENDMENT OR

    SUPPLEMENT HAVING REGARD TO THE DELAY IN MAKING IT.

    HEARINGS AND WRITTEN PROCEEDINGS(1)UNLESS OTHERWISE AGREED BY THE PARTIES , THE ARBITRAL TRIBUNAL SHALL DECIDE

    WHETHER TO HOLD ORAL HEARINGS FOR THE PRESENTATION OF EVIDENCE OR FOR ORAL

    ARGUMENT, OR WHETHER THE PROCEEDINGS SHALL BE CONDUCTED ON THE BASIS OFDOCUMENTS AN OTHER MATERIALS;PROVIDED THAT THE ARBITRAL TRIBUNAL SHALL HOLD

    HEARINGS, AT AN APPROPRIATE STAGE OF THE PROCEEDINGS, ON A REQUEST BY A PARTY,

    UNLESS THE PARTIES HAVE AGREED THAT NO ORAL HEARING SHALL BE HELD.

    (2) THE PARTIESSHALL BEGIVEN SUFFICIENTADVANCE NOTICE OFANY HEARING ANDOF ANY

    MEETING OF THE ARBITRAL TRIBUNAL FOR THE PURPOSES OF INSPECTION OF DOCUMENTS ,

    GOODS OR OTHER PROPERTY.

  • 7/28/2019 MQS 312

    21/25

    21

    (3)ALL STATEMENTS, DOCUMENTS OR OTHER INFORMATION SUPPLIED TO, OR APPLICATIONS

    MADE TO, THE ARBITRAL TRIBUNAL BY ONE PARTY SHALL BE COMMUNICATED TO THE O THER

    PARTY, AND ANY EXPERT REPORT OR EVIDENTIARY DOCUMENT ON WHICH THE ARBITRAL

    TRIBUNAL MAY RELY IN MAKING ITS DECISION SHALL BE COMMUNICATED TO THE PARTIES.

    DEFAULT OF A PARTY.-UNLESS OTHERWISE AGREED BY THE PARTIES, WHERE, WITHOUT SHOWING SUFFICIENT

    CAUSE,----A. THE CLAIMANT FAILS TO COMMUNICATE HIS STATEMENT OF CLAIM IN

    ACCORDANCE WITH SUB-SECTION (1) OF SECTION 23, THE ARBITRAL TRIBUNAL SHALL

    TERMINATE THE PROCEEDINGS; B. THE RESPONDENT FAILS TO COMMUNICATE HIS STATEMENT

    OF DEFENCE IN ACCORDANCE WITH SUB-SECTION (1) OF SECTION 23, THE ARBITRAL TRIBUNAL

    SHALL CONTINUE THE PROCEEDINGS WITHOUT TREATING THAT FAILURE IN ITSELF AS AN

    ADMISSION OF THE ALLEGATIONS BY THE CLAIMANT. C. A PARTY FAILS TO APPEAR AT AN ORAL

    HEARING OR TO PRODUCE DOCUMENTARY EVIDENCE, THE ARBITRAL TRIBUNAL MAY CONTINUE

    THE PROCEEDINGS AND MAKE THE ARBITRAL AWARD ON THE EVIDENCE BEFORE IT.

    EXPERT APPOINTED BY ARBITRAL TRIBUNAL(1)UNLESS OTHERWISE AGREED BY THEPARTIES, THE ARBITRAL TRIBUNAL MAY---(A)

    APPOINT ONE OR MORE EXPERTS TO REPORT TO IT ON SPECIFIC ISSUES TO BE DETERMINED BY

    THEARBITRAL TRIBUNAL, AND(B) REQUIRE A PARTYTO GIVETHE EXPERTANY

    RELEVANTINFORMATION ORTO PRODUCE, ORTO PROVIDE ACCESS TO, ANY RELEVANT

    DOCUMENTS, GOODS OR OTHER PROPERTY FOR HIS INSPECTION.

    (2)UNLESS OTHERWISE AGREED BY THE PARTIES , IF A PARTY SO REQUESTS OR IF THE

    ARBITRAL TRIBUNAL CONSIDERS IT NECESSARY, THE EXPERT SHALL, AFTER DELIVERY OF HIS

    WRITTEN OR ORAL REPORT, PARTICIPATE ON AN ORAL HEARING WHERE THE PARTIES HAVE THE

    OPPORTUNITY TO PUT QUESTIONS TO HIM AND TO PRESENT EXPERT WITNESSES IN ORDER TO

    TESTIFY ON THE POINTS AT ISSUE.

    (3)UNLESS OTHERWISE AGREED BY THE PARTIES , THE EXPERT SHALL, ON THE REQUEST OF A

    PARTY, MAKE AVAILABLE TO THAT PARTY FOR EXAMINATION ALL DOCUMENTS , GOODS OR

    OTHER PROPERTY IN THE POSSESSION OF THE EXPERT WITHWHICH HE WAS PROVIDED IN ORDER

    TO PREPARE HISREPORT.

  • 7/28/2019 MQS 312

    22/25

    22

    COURT ASSISTANCE IN TAKING EVIDENCE(1)THE ARBITRAL TRIBUNAL, OR A PARTY WITH THE APPROVAL OF THE ARBITRAL TRIBUNAL ,

    MAY APPLY TO THE COURT FOR ASSISTANCE IN TAKING EVIDENCE.(2)THE APPLICATION SHALL

    SPECIFY---

    -(A) THE NAMES AND ADDRESSESOF THEPARTIES AND THE ARBITRATORS.(B) THE GENERAL NATURE OFTHE CLAIM AND THE RELIEF SOUGHT;

    (C) THE EVIDENCE TO THE OBTAINED, INPARTICULAR,----

    I. THENAMEANDADDRESSOFANYPERSONTOBEHEARDAS WITNESS OREXPERTWITNESS

    AND A STATEMENT OF THE SUBJECT-MATTER OF THE TESTIMONY

    REQUIRED;II. THEDESCRIPTIONOFANDOCUMENTTOBEPRODUCEDORPROPERTYTO

    BEINSPECTED.

    (3)THE COURT MAY, WITHINITS COMPETENCE ANDACCORDING TO ITSRULES ONTAKING

    EVIDENCE, EXECUTE THE REQUEST OR ORDERING THAT THE EVIDENCE BE PROVIDED DIRECTLY

    TO THE ARBITRAL TRIBUNAL.

    (4)THE COURT MAY, WHILE MAKING OR ORDER UNDER SUB-SECTION (3), ISSUE THE SAME

    PROCESSES TO WITNESSES AS IT MAY ISSUE IN SUITS TRIED BEFORE IT

    MAKING OF ARBITRAL AWARDAND TERMINATION OF PROCEEDINGSRULES APPLICABLE TO SUBSTANCE OF DISPUTE.-

    (1)WHERE THE PLACE OF ARBITRATION ISSITUATE IN INDIA,-----

    (A) IN ANARBITRATION OTHERTHAN ANINTERNATIONAL COMMERCIALARBITRATION,

    THEARBITRAL TRIBUNAL SHALL DECIDE THE DISPUTE SUBMITTED TO ARBITRATION INACCORDANCE WITH THE SUBSTANTIVE LAW FOR THE TIME BEING IN FORCE IN INDIA;

    (B) IN INTERNATIONALCOMMERCIAL ARBITRATION,----

    I. THEARBITRALTRIBUNALSHALLDECIDEDTHEDISPUTEINACCORDANCEWITHTHERULESO

    FLAWDESIGNATED BY THE PARTIES AS APPLICABLE TO THE SUBSTANCE OF THE DISPUTE

    (II) ANYDESIGNATIONBYTHEPARTIESOFTHE LAW ORLEGALSYSTEM OFAGIVENCOUNTRY

    SHALL BE CONSTRUED, UNLESS OTHERWISE EXPRESSED, AS DIRECTLY REFERRING TO THE

    SUBSTANTIVE LAW OF THAT COUNTRY AND NOT TO ITS CONFLICT OF LAWS RULES

    (III) FAILINGANYDESIGNATIONOFTHELAWUNDERCLAUSE (A) BYTHEPARTIES, THEARBIT

    RALTRIBUNAL SHALL APPLY THE RULES OF LAW IT CONSIDERS TO BE APPROPRIATE GIVEN ALL

    THE CIRCUMSTANCES SURROUNDING THE DISPUTE.

    (2)THE ARBITRAL TRIBUNAL SHALL DECIDE EX AEQUO ETBONO OR AS AMIABLE COMPOSITE

    URONLY IF THE PARTIES HAVE EXPRESSLY AUTHORISED IT TO DO SO.

  • 7/28/2019 MQS 312

    23/25

    23

    (3)IN ALL CASES, THE ARBITRAL TRIBUNAL SHALL DECIDE IN ACCORDANCE WITH THE TERMS

    OF THE CONTRACT AND SHALL TAKE INTO ACCOUNT THE USAGES OF THE TRADE APPLICABLE

    TO THE TRANSACTION.

    DECISION MAKING BY PANEL OF ARBITRATORS(1)UNLESS OTHERWISE AGREED BY THE PARTIES, IN ARBITRAL PROCEEDINGS WITH MORE

    THAN ONE ARBITRATOR, ANY DECISION OF THE ARBITRAL TRIBUNAL SHALL BE MADE BY A

    MAJORITY OF ALL ITS MEMBERS.

    (2)NOTWITHSTANDING SUB-SECTION (1), IF AUTHORISED BY THE PARTIES OR ALL THE

    MEMBERS OF THE ARBITRAL TRIBUNAL, QUESTIONS OF PROCEDURE MAY BE DECIDED BY THE

    PRESIDING ARBITRATOR.

    SETTLEMENT.-1)IT IS NOT INCOMPATIBLE WITH AN ARBITRATION AGREEMENT FOR AN ARBITRAL TRIBUNAL

    TO ENCOURAGE SETTLEMENT OF THE DISPUTE AND, WITH THE AGREEMENT OF THE PARTIES,

    THE ARBITRAL TRIBUNAL MAY USE MEDIATION, CONCILIATION OR OTHER PROCEDURES AT ANY

    TIME DURING THE ARBITRAL PROCEEDINGS TO ENCOURAGE SETTLEMENT.

    2) IF, DURING ARBITRAL PROCEEDINGS, THE PARTIES SETTLE THE DISPUTE, THE ARBITRAL

    TRIBUNAL SHALL TERMINATE THE PROCEEDINGS AND, IF REQUESTED BY THE PARTIES AND NOT

    OBJECTED TO BY THE ARBITRAL TRIBUNAL, RECORD THE SETTLEMENT IN THE FORM OF AN

    ARBITRAL AWARD ON AGREED TERMS.

    3) AN ARBITRAL AWARD ON AGREED TERMS SHALL BE MADE IN ACCORDANCE WITH SECTION31 AND SHALL STATE THAT IT IS AN ARBITRAL AWARD .4) AN ARBITRAL AWARD ONAGREED

    TERMS SHALL HAVETHE SAME STATUS AND EFFECT AS ANY OTHER ARBITRAL AWARD ON THE

    SUBSTANCE OF THE DISPUTE.

    FORM AND CONTENTS OF ARBITRAL AWARD(1)AN ARBITRAL AWARD SHALL BE MADE IN WRITING AND SHALL BE SIGNED BY THE

    MEMBERS OF THE ARBITRAL TRIBUNAL.

    (2)FOR THE PURPOSES OF SUB-SECTION (1), IN ARBITRAL PROCEEDINGS WITH MORE THAN ONE

    ARBITRATOR, THE SIGNATURES OF THE MAJORITY OF ALL THE MEMBERS OF THE ARBITRAL

    TRIBUNAL SHALL BE SUFFICIENT SO LONG AS THE REASON FOR ANY OMITTED SIGNATURE IS

    STATED.

    (3)THE ARBITRAL AWARD SHALL STATE THE REASONSUPON WHICH IT IS BASED, UNLESS------

    (A) THE PARTIES HAVE AGREEDTHAT NO REASONSARE TO BEGIVEN, OR(B) THE AWARD IS

    ANARBITRAL AWARD ON AGREEDTERMS UNDER SECTION 30.

  • 7/28/2019 MQS 312

    24/25

    24

    (4)THE ARBITRAL AWARD SHALL STATE ITS DATE AND THE PLACE OF ARBITRATION AS

    DETERMINED IN ACCORDANCE WITH SECTION 20 AND THE AWARD SHALL BE DEEMED TO HAVE

    BEEN MADE AT THAT PLACE.

    (5)AFTER THE ARBITRAL AWARD IS MADE, ASIGNED COPY SHALL BE DELIVERED TO

    EACHPARTY.

    (6)THE ARBITRAL TRIBUNAL MAY, AT ANY TIME DURING THE ARBITRAL PROCEEDINGS , MAKE

    AN INTERIM ARBITRAL AWARD ON ANY MATTER WITH RESPECT TO WHICH IT MAY MAKE A

    FINAL ARBITRAL AWARD.

    (7)(A)UNLESS OTHERWISE AGREED BY THE PARTIES , WHERE AND IN SO FAR AS AN ARBITRAL

    AWARD IS FOR THE PAYMENT OF MONEY, THE ARBITRAL TRIBUNAL MAY INCLUDE IN THE SUM

    FOR WHICH THE AWARD IS MADE INTEREST , AT SUCH RATE AS IT DEEMS REASONABLE, ON THE

    WHOLE OR ANY PART OF THE MONEY, FOR THE WHOLE OR ANY PART OF THE PERIOD BETWEEN

    THE DATE ON WHICH THE CAUSE OF ACTION AROSE AND THE DATE ONWHICH THE AWARD IS

    MADE.

    (B)A SUM DIRECTED TO BE PAID BY AN ARBITRAL AWARD SHALL , UNLESS THE AWARD OTHERWISE DIRECTS, CARRY INTEREST AT THE RATE OF EIGHTEEN PER CENTUM PER ANNUM FROM

    THE DATE OF THE AWARD TO THE DATE OF PAYMENT.

    (8)UNLESS OTHERWISE AGREED BY THE PARTIES ,----

    (A) THE COSTS OFAN ARBITRATION SHALL BEFIXED BY THEARBITRAL TRIBUNAL;

    (B) THE ARBITRAL TRIBUNALSHALL SPECIFY---

    I. THEPARTYENTITLEDTOCOSTS,

    II. THEPARTYWHOSHALLPAYTHECOSTS,

    III. THEAMOUNTOFCOSTSORMETHODOFDETERMININGTHATAMOUNT, ANDIV. THEMANNE

    RINWHICHTHECOSTSSHALLBEPAID.EXPLANATION.---

    FOR THE PURPOSE OF CLAUSE (A),"COSTS" MEANS REASONABLE COSTS RELATING TO---

    (I) THE FEES AND EXPENSES OFTHE ARBITRATORS AND WITNESSES,

    (II) LEGAL FEES AND EXPENSES,

    (III) ANY ADMINISTRATION FEES OF THE INSTITUTION SUPERVISING THE ARBITRATION, AND

    (IV) ANY OTHER EXPENSES INCURRED IN CONNECTION WITH THE ARBITRAL PROCEEDINGS AND

    THE ARBITRAL AWARD.

  • 7/28/2019 MQS 312

    25/25

    25

    BIBLIOGRAPHY

    PROFESSIONAL PRACTICEBYDR.ROSHANNAMAVATI

    VALUATIONENGINEERINGBYM.CHAKRABORTY

    ESTIMATING ANDCOSTINGINCIVILENGINEERINGBYB.N.DUTTA

    LAWSOFSURVEYORBYNICMARPUBLICATIONS