mrp 1 deepak 12mt07ind009
TRANSCRIPT
Material Requirement
Planning (MRP1)
DEEPAK KU. KUSHWAHA
MTCH-IND, 12MT07IND009
1
Contributors to MRP• Joseph Orlicky(1964)
• Oliver Wight(1983)
• MRP started in the late 1960s. The technique was applied first to mobile and airplane industry. As the technique became well known, many large and small businesses adopted MRP method in order to increase their productivity and decrease the production cost.
INTRODUCTION
• The main function of material requirements planning is to guarantee material availability, that is, it is used to procure or produce the required quantities on time both for internal purposes and for sales and distribution.
• This process involves
- monitoring of stocks,
- automatic creation of procurement proposals for
purchasing and production.
• In doing so, MRP tries to strike the best balance possible between
- optimizing the service level and
-minimizing costs and capital lockup.
MRP is
• Production Planning System
• Computerized Inventory Control
• Management Information System
• Manufacturing Control System
MRP software- Tuppus, Eci M1, E2 shop system
4
MRP system Gives answer
• What items are required?
• How many are required?
• When are they required?
5
Objectives• Materials and products are available for
production and delivery to customers.
• Maintain the lowest possible level of inventory.
• Plan manufacturing activities, delivery schedules and purchasing activities.
6
When to use MRP?
It is useful for…..
• Independent Demand vs Dependent Demand
• Lumpy demand
• Lead time( order lead time, manufacturing lead time )
• Common use items
7
8
PRODUCTIONPLANNING
PRODUCTIONPLANNING
CAPACITY
WORK FORCE
PRODUCTION
INVENTORY
INTERNAL
EXTERNAL
EXTERNALCAPACITY
COMPETITIONRAW MATERIAL
SUPPLYDEMAND
ECONOMICCONDITIONS
Production Planning Environment
Overview of the MRP System
Product Structure
File
Master Production Schedule
Inventory Master File
Material Requirements
Planning
Manufacturing Orders
Purchase Orders
Various Reports
10
MRP Inputs
• Master Production Schedule
• Product Structure File
• Inventory Master File
11
Master Production Schedule
• A master schedule is the result of disaggregation of an aggregate plan.
• A master schedule show the quantity & timing of specific end item for a time horizon.
• Schedule of Finished Products• Represents Production, not Demand• Combination of Customer Orders and Demand
Forecasts• What Needs to be Produced
12
Product Structure File
• It shows diagrammatically the component required
to assemble it,their no,& the sequence of assembly.
Bill of Material(BOM)
Documentation of product structure.
13
10
Bicycle(1)Level 0
Handle Bars (1)Level -1
Frame Assembly (1)Level-1
Wheels (2)Level -2
Frame (1)Level-2
Product Structure Tree
Product structure & BOM
15
Bicycle(1)
Level 0
Handle Bars (1)Level -1
Frame Assembly (1)Level-1
Wheels (2)Level -2
Frame (1)
Level-2
Item no. Level product Lead time part code Quantity1 level 0 bicycle P/N 1000 102 level 1 handle bar 1wk P/N 1002 103 level 1 frame ass. 1wk P/N 1023 104 level 2 wheel 2wk P/N 1045 205 level 2 frame 2wk P/N 1034 10
Inventory Master FileA database of information contain• Raw material & purchased component.
• In process inventory
• Finished product
• Lot Sizes
• Safety Stock
• Lead Time
• Past-Usage Figures16
MRP Outputs
• Planned order report1. Time for order(Lead time)
2. Helps in preparing founds.
• Order release report1. Order size*, release date.
2. Purchase order taking care of lead time.
• Order change report1. Changing demand ,order,leadtime.
17
Order size in MRP
Lot for lot method
EOQ methd
Least total cost method
Least unit cost method
18
MRP PROCESS
19
Terms Defined
• Item – name or number for the item being scheduled
• Low-Level Code – the lowest level of the item on the product structure file
• Lot Size – order multiples of quantity• Lead Time – the time from when an order is
placed to when it is received• PD – Past Due Time Bucket, orders behind
schedule
20
Terms Defined
• Gross Requirements – demand for an item by time period
• Scheduled Receipts – material already ordered• Projected on Hand – expected ending inventory• Net Requirements – number of items to be
provided and when• Planned Order Receipts – net requirements
adjusted for lot size• Planned Order Releases – planned order receipts
offset for lead times
21
MRP formatItem: A Low-Level Code: 1
Lot Size: 25 Lead Time: 1PD 1 2 3 4 5
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
22
MRP PROCESS
23
Master production schedule for item APeriod(w) 1 2 3 4 5 6 7 8gross requirement 450 600
MRP report for item BA LT=1WeekPeriod in weeks 1 2 3 4 5 6 7 8Gross requirement 450 600Schedule receiptsProject on hand 100 100 100 100Net requirement 350 600Planned order recepits 350 600Planned order release 350 600
• GROSS REQUIREMENT OF COMPONENT B=2*350=700
• GROSS REQUIREMENT OF COMPONENT C=1*350=350
24
A(1)
LT=1
B (2)
LT=1
C(1)
LT-1
Product structure file
25
Master production schedule for item APeriod(w) 1 2 3 4 5 6 7 8gross requirement 450 600
MRP report for item BA ,LT=1WeekPeriod in weeks 1 2 3 4 5 6 7 8Gross requirement 450 600Schedule receiptsProject on hand 100 100 100 100Net requirement 350 600Planned order recepits 350 600Planned order release 350 600
MRP report for item BB,LT=1weekPeriod in weeks 1 2 3 4 5 6 7 8Gross requirement 700 1200Schedule receiptsProject on handNet requirement 700 1200Planned order recepits 700 1200Planned order release 700 1200
MRP report for item BC,LT=2weekPeriod in weeks 1 2 3 4 5 6 7 8Gross requirement 350 600Schedule receiptsProject on handNet requirement 350 600Planned order recepits 350 600Planned order release 350 600
What can MRP do?
• Reduce Inventory Levels• Reduce Component
Shortages• Improve Shipping
Performance• Improve Customer
Service• Improve Productivity• Simplified and Accurate
Scheduling
• Reduce Purchasing Cost• Improve Production
Schedules• Reduce Manufacturing
Cost• Reduce Lead Times• Less Scrap and Rework• Higher Production
Quality
26
Limitation of MRP
• No account of capacity(deal with MRP=II)
• Data sensitive
• Lead time
27
28
Case study
PAL MOHAN ELECTRONIX PVT. LIMITED , DELHI produces a line of electric meters installed in residential buildings by electric utility companies to measure power consumption. Meters used on single-family homes are of two basic types for different voltage and amperage ranges. In addition to complete meters, some parts and subassemblies are sold separately for repair or for changeovers to a different voltage or power load. Forecasting demand
•The problem for the MRP system is to determine a production schedule that would identify each item, the period it is needed, and the appropriate quantities.
•This schedule is then checked for feasibility, and the schedule is modified if necessary.
29
Structure of the study
Section 1. Master Production ScheduleSection 2. Bill of Materials (Product Structure) FileSection 3. Inventory Records (Item Master) FileSection 4. Running the MRP ProgramSection 5. Obtainability control
30
Section 1. Master Production Schedule
Forecasting demand
31
Section 2. Bill of Materials (Product Structure) File.
32
Section 3. Inventory Records (Item Master) File
33
Section 4 . Running the MRP Program
34
Section 5-Obtainability Control
• ROUGH-CUT CAPACITY PLANNING(MRP-2)
• PREPARE REPORT
•It should have to be asked after applying the MRP that whether the MRP schedule was feasible or not. If it is not so, then the new revised MPS has to be applied with MRP packages
Refernce
• Cad/Cam-Mikell P. Groover
• Automation & production,CIM-Mikell P. Groover
• wikipedia.org/wiki/Material requirements planning
35
Query session
Thank You
36