MS Activities during TS#3 Courtesy of JC, Kajetan, Arek, Jacek, Yan, Richard and Pierre

Upload: haracha

Post on 12-Jan-2016

27 views

Category:

Documents


0 download

DESCRIPTION

MS Activities during TS#3. Courtesy of JC, Kajetan , Arek , Jacek , Yan, Richard and Pierre. Warm Magnet Interlocks. Final validation test of SPS spares for main magnet interlocks Installation of several dosimeters for radiation profile in SPS tunnel (in prospect of future WIC installation) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MS Activities during TS#3

MS Activities during TS#3

Courtesy of JC, Kajetan, Arek, Jacek, Yan, Richard and Pierre

Page 2: MS Activities during TS#3

Warm Magnet Interlocks• Final validation test of SPS spares for main magnet interlocks• Installation of several dosimeters for radiation profile in SPS tunnel (in

prospect of future WIC installation)• Confirmation of cabling layout and patch location for SPS renovation

project with EN/EL

Page 3: MS Activities during TS#3

Software upgrades for MPESection Description Risk of doing the

changeRisk to

OP (0-5)Affected systems/functionality

Risk Mitigation Risk of not doing it Responsible

How to do testing

When

MS New version of PMA server + GUI (new SMP IPOC, Beam Power Loss, Fill Statistics module)

Minor risk that refactored Fill Statistics module will not work correctly anymore.

1 PMA server, PM Database

Usual extensive testing of new module in DEV server. 'Dry-dumps' after deployment.

Discrepancy of information between PLAYBACK and ONLINE server for Fill Statistics, missing new functionality of new modules if not deployed.

R.Gorbonosov, J.Suchowski, A.Gorzawski, M.Zerlauth

Usual extensive testing of new module in DEV server. 'Dry-dumps' after deployment.

Dependent of the Logging API release, so asap after this one

MS New version of cern.pm.data to add a feature to retrieve the SessionConfirmationInfo from a SessionInfoData, and to store the analysis flags of session handles.

None 1 PMA server, newly stored PM data

Test with development servers before deployment in production. Possible rollback

Missing information from Session Data

JC Garnier, R Gorbonosov

Testing with the pm-playback-gui and pm-online-gui in dev

MS PCInterlock to take into account Collision beam process split

Minor defects possible as coverage not optimal yet

2 LHC SIS Maskable interlock No management of splitted collision beam process

K. Fuchsberger

Validation with operators

MS New SMP GUI PRO release to follow the changes made to the HW (expert functionality)

Operation should not be affected as the change is made to an expert functionality.

0 SMP GUI application need to be rebooted

roll-back not synchronized with the SMP hardware, new functionality not provided to experts.

M. Audrain

Validation of the expert functionality change during the TS

Page 4: MS Activities during TS#3

NEW PM MODULES• New PM analysis modules and

Viewers for SMP and Beam Power Loss analysis

Page 5: MS Activities during TS#3

PcInterlock upgrade• Refactoring and GUI improvements• Possibility to split collision beam process (independent for IR1/2/5 and IR8)