1 Constructing Construction Statistics Available through SSAS * * * Author: John Stires October 10, 2008

Upload: pencarver

Post on 09-Jul-2015

273 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: MS BI SSAS Project Portfolio

1

Constructing Construction Statistics

Available through SSAS

* * *

Author: John Stires

October 10, 2008

Page 2: MS BI SSAS Project Portfolio

2

Table of Contents

I. Overview ................................................................................................................................................ 3

II. Component Parts .................................................................................................................................. 3

A. Creating the Cube ............................................................................................................................. 3

1. Setting up the Data Source Connection to the Database. ................................................................ 3

2. Build the cube ................................................................................................................................. 3

3. Created Dimensions ........................................................................................................................ 3

B. MDX Querie ...................................................................................................................................... 5

1. Job Summaries ................................................................................................................................ 5

2. Overhead Summaries ...................................................................................................................... 6

1. Materials Summaries ...................................................................................................................... 7

2. Labor Summaries ............................................................................................................................ 7

C. Key Performance Indicators ( KPIs)............................................................................................... 8

1. % Open Receivables ....................................................................................................................... 8

2. Increase in the Number of Jobs ....................................................................................................... 8

3. Percent Overhead ............................................................................................................................ 8

4. Percent Profit. ................................................................................................................................. 9

5. Increase in Percent of Overhead by Category. ................................................................................ 9

Appendix A - All Works DS Data Source View ..................................................................................... 11

Appendix B - All Works Cube Design View .......................................................................................... 12

Appendix C MDX Job Master Queries .................................................................................................. 13

Appendix D MDX Overhead Queries .................................................................................................... 25

Appendix E MDX Materials Queries ..................................................................................................... 28

Appendix F MDX Labor Queries ........................................................................................................... 32

Appendix G KPIs (Key Performance Indicators .................................................................................. 37

Page 3: MS BI SSAS Project Portfolio

3

I. Overview

This project creates the Cubes and Dimensions necessary to generate MDX Queries and Key

Performance Indicators (KPIs) for a simulated Construction company. The focus of the data for

this project is on data for labor, materials, overhead, and summarized job information. The data

was loaded from a zipped database and a cube and its associated dimension and hierarchies. The

Data Source and Data Source Views were defined. Once this was done, the cube was created and

then dimensions were created in order to organize the data in such a way as to enable the MDX

queries and KPIs to perform their functions efficiently.

The net result was a collection of MDX queries and KPIs showing critical business information in

a way that it can be quickly analyzed.

II. Component Parts

There were three main component parts to this project:

Creating the cube

Creating the MDX Queries

Creating the KPIs

A. Creating the Cube In creating the cube a data base was supplied containing all of the necessary data to carry this

project forward. The database name was SSASStudentProject.

1. Setting up the Data Source Connection to the Database. a) The connection was set to the SSASStudentProject database located in the folder:

C:\SetFocusBIProjects\StudentVersion\SSASStudentProject\SSASStudentProject\bi

n

b) A Data Source View was set up to design the chart showing the data relationships and

establishing the Fact Tables (Measures) and the Dimensions. This chart can be viewed in

Appendix A.

2. Build the cube once the database connect had been established and the Data

Source View created, the Cube, AllWorks Cube was created. As this was

accomplished, a basic chart was created showing the relationships of the data

within the cube. The wizard was used to create the cube and then the individual

elements were adjusted as necessary for producing the desired queries and KPIs.

This Cube Design chart can be seen in Appendix B.

3. Created Dimensions

a) Measures Fact Tables.

(1) Job Labor Facts

(a) Hoursworked

(b) Job Labor Facts

(c) Total Labor

(2) Job Material Facts

(a) Job Material Facts Count

(b) Purchase Amount

(3) Job Overhead Summary Facts

(a) Job Overhead Summary Facts Count

Page 4: MS BI SSAS Project Portfolio

4

(b) Weekly Over Head

(4) Job Summary Facts

(a) Additional Labor Profit

(b) Amount Received

(c) Hours Worked

(d) Invoice Amount

(e) Job Summary Facts Count

(f) Total Labor Cost

(g) Total Labor Profit

(h) Total Material Cost

(i) Total Material Profit

(j) Total Overhead

b) Dimensions

(1) All Works Calendar

(a) Qtr

(b) Weekend Date

(c) Year

(d) Calendar (Hierachy)

(i) Year

(ii) Qtr

(iii)Weekend Date

(2) Client Groupings

(a) Client Groupings

(b) Grouping Name

(3) Clients

(a) Clients.Account No

(b) Clients.Client Image

(c) Clients.Client Name

(d) Clients.Clients

(e) Clients.Project Manager

(f) Clients.Hierarchy

(i) Clients

(4) Clients – County PK

(a) Clients – County PK.Coutny

(b) Clients – County PK.County Name

(5) County

(a) County.County

(b) County.County Name

(6) Division

(a) Division

(b) Division Name

(7) Employees

(a) Cell Phone

(b) Employee Flag

(c) Employees

(d) First Name

Page 5: MS BI SSAS Project Portfolio

5

(e) Full Name

(f) Last name

(8) Job Master

(a) Additional Overhead Pct

(b) Client Job

(c) Description

(d) Job Closed

(e) Job Closed Date

(f) Job master

(g) Material Markup Pct

(9) Job Master – Client PK

(a) Job Master – Client PK.Account No

(b) Job Master – Client PK.Client Image

(c) Job Master – Client PK.Client Name

(d) Job Master – Client PK.Clients

(e) Job Master – Client PK.Project manger

(f) Job Master – Client PK.Hierarchy (Hierarchy)

(i) Job Master – Client PK.Clients

(10) Job Master – Client PK – County PK

(a) Job Master – Client PK – County PK.County

(b) Job Master – Client PK – County PK.County Name

(11) Material Types

(a) Description

(b) Material Types

(12) Overhead

(a) Description

(b) Overhead

c) Hierarchies

Two dimensions had hierarchies.

(1) All Works Calendar

Three hierarchies were created for the calendar based on:

(a) Year

(b) Qtr

(c) Weekend Date

(2) Clients

A single hierarchy based on the Client ID.

(3) Job Master – Client PK

A single hierarchy based on Job Master – Client PK.Clients

B. MDX Queries The MDX queries are grouped in to several categories. They will be presented in those

groupings. An example of the display of each can be found in the appendixes as indicated in

the description for each query.

1. Job Summaries

Screen prints for this group can be found in Appendix C. a) JobSummary01.mdx

Retrieve total labor costs by Client

Page 6: MS BI SSAS Project Portfolio

6

b) JobSummary02.mdx

Retrieves total labor costs by Client, and filters out any NULL values

c) JobSummary03.mdx

Retrieve total labor costs by County

d) JobSummary04.mdx

Retrieve total labor costs by Division

e) JobSummary05.mdx

Retrieve total labor costs by Client Account grouping

f) JobSummary06.mdx

By client, retrieve total labor cost, total material cost, and total overhead.

g) JobSummary07.mdx

Do the same (retrieve 3 measures) and add a 4th measure, a calculated measure, that adds

all three costs.

h) JobSummary08.mdx

Retrieve and calculate the total costs, the total profit, and total profit %, for each

individual job. The three re calculated as follows:

Total costs = total labor cost +

total material cost +

total overhead cost

Total profit = labor profit +

material profit +

additional labor overhead profit

Total profit % = (total profit / (total cost + total profit))*100

i) JobSummary09.mdx

By client, retrieves and calculate the total costs, the total profit, and total profit %, for

each individual job. The three re calculated as follows:

Total costs = total labor cost +

total material cost +

total overhead cost

Total profit = labor profit +

material profit +

additional labor overhead profit

Total profit % = (total profit / (total cost + total profit) )*100

j) JobSummary10.mdx

By client, displays a count of Jobs.

k) JobSummary11.mdx

Retrieve all Clients with a Total Labor cost to date greater than 5,000, and the word 'INC'

appears in the client name

l) JobSummary12.mdx

List the jobs that make up the top 30% of total invoice amount.

2. Overhead Summaries a) JobOverHead01.mdx

Shows Overhead by Overhead Category for Q3 and Q4 2005 (hint, use the FY Qtr as a

dimension).

Page 7: MS BI SSAS Project Portfolio

7

b) JobOverHead02.mdx

Shows Overhead by Overhead Category for Q3 and Q4 2005, and also show the % of

change between the two.

c) JobOverHead03.mdx

Shows Overhead by Overhead Category for all of 2005, order by Overhead Dollar

amount descending.

1. Materials Summaries a) The result set should have 1 column for the purchase amounts for Fuel, Materials, and

petty Cash.

b) JobOverMaterials02.mdx

Shows Material purchase amounts for 2005, broken out by Material Purchase type and

client.

c) JobOverMaterials03.mdx

Shows a list of total client material purchases for 2005, in descending purchase amount

order. The result set should show at the top which client required the most materials.

d) JobOverMaterials04.mdx

Shows jobs in order of purchase amount and then show the breakdown in each job of

material type (for instance, Job A, total purchase amount, amount for fuel, amount for

materials, amount for petty cash, etc.). The general order should be by total purchase

amount, so that the top of the result set shows the jobs that required the highest purchase

amounts.

2. Labor Summaries a) JobOverLabor01.mdx

Lists Hours Worked and Total Labor for each employee for 2005, along with the labor

rate (Total labor / Hours worked).

b) JobOverLabor02.mdx

Lists Hours Worked and Total Labor for each employee for 2005, along with the labor

rate (Total labor / Hours worked). The listing will sort the employees by labor rate

descending, to see the employees with the highest labor rate at the top.

c) JobOverLabor03.mdx

For 2005, show Total Hours worked, total labor dollars, and total labor rate for

contractors (employee flag is false) and employees (employee flag is true).

d) JobOverLabor04.mdx

For 2005, this shows the job and the top three employees who worked the most hours.

Show the jobs in job order, and within the job show the employees in hours worked

order.

e) JobOverLabor04.mdx

Shows All employees for 2005 Q4, and four periods ago, for total hours worked in the

Quarter.

Page 8: MS BI SSAS Project Portfolio

8

C. Key Performance Indicators ( KPIs)

Five KPIs were created using the Allworks Cube and its associated dimensions.

They are briefly described below. Where possible, when a division provides that

possibility for the potential of a “divde by zero” condition, checks are made and steps

taken to avoid output errors. If the denominator turn out to be a zero, the out is

converted to 100%.

1. % Open Receivables This KPI shows, by client, the persent of receivable that are outstanding. The staus

display displays the values and status by client. See Appendix G to see a screen print of

this KPI. a) Measures and Dimensions

(1) Measures

(a) Invoice Amount

(b) Amount Received

b) Dimension N/A

(1) Basic formula Open Receivables = Invoice Amount / Amount Received

c) Status Indicator is the Traffic Light. The status values are:

(1) Good = 0 to 10%

(2) Warning = >10% to 20%

(3) Bad = > 20%

2. Increase in the Number of Jobs This KPI displays the change in the number of jobs by client for the time period of the 2

nd

quarter of 2006 from the previous quarter. a) Measures and Dimensions

(1) Measures

(a) Job Summary Facts Count

(2) Dimension(s)

(a) All Works Calendar

b) Basic formula

Change in number of Jobs = Job Summary Facts Count of the current quarter

- Job Summary Facts Count of the previous quarter

c) Filter

There is a filter in the Excel spreadsheet to select for the 2nd quarter of 2006.

d) Status Indicator is the Traffic Light. The status values are:

(a) Good = Greater than 0

(b) Okay = 0 - No Change on the job count

(c) Bad = > less than 0 (jobs lost)

3. Percent Overhead This KPI displays the percent of overhead by job for all jobs. a) Measures and Dimensions

Page 9: MS BI SSAS Project Portfolio

9

(1) Measures

A calculated member is used for the sum of the Measures for Total Cost.

(a) Total Overhead

(b) Total Material

(c) Total Labor Cost

(2) Dimension(s)

N/A

b) Basic formula

Percent Overhead = Total Overhead / Total Cost

(1) Status Indicator is the Traffic Light.. The status values are:

(a) Good = 0 to 10%

(b) Warning = Greater than 10% to 15%

(c) Bad = Greater than 15%

4. Percent Profit This KPI displays the percent of profit for all clients.. a) Measures and Dimensions

(1) Measures

A calculated member is used for the sum of the Measures for Total Cost.

(a) Total Overhead

(b) Total Material

(c) Total Labor Cost

(2) Dimension(s)

N/A

b) Basic formula

Percent Overhead = Total Overhead / Total Cost

(1) Status Indicator is the Traffic Light.. The status values are:

(a) Good = 0 to 10%

(b) Warning = Greater than 10% to 15%

(c) Bad = Greater than 15%

5. Increase in Percent of Overhead by Category This KPI displays the change in the persent of Overheadt for the time period of the 2

nd

quarter of 2006 from the previous quarter. a) Measures and Dimensions

(1) Measures

(a) [Job Overhead Summary Facts].[Weekly Over Head]

(2) Dimension(s)

(a) All Works Calendar

(3) Basic formula

For clarity and ease of reading a calculated member was created to represent the

Weekly Overhead for the previous quarter.

Change in Percent Overhead = (Weekly Overhead for the current quarter

- Weekly Overhead for the previous quarter)

- / Weekly Overhead for the previous quarter

b) Filter

There is a filter in the Excel spreadsheet to select for the 2nd quarter of 2006.

Page 10: MS BI SSAS Project Portfolio

10

c) Status Indicator is the Traffic Light. The status values are:

(a) Good = Less than 10%

(b) Okay = 10% - 15%

(c) Bad = > Greater than 15%

Page 11: MS BI SSAS Project Portfolio

11

Appendix A - All Works DS Data Source View

Page 12: MS BI SSAS Project Portfolio

12

Appendix B - All Works Cube Design View

Page 13: MS BI SSAS Project Portfolio

13

Appendix C MDX Job Master Queries

1-1 Total Labor Costs by Client

Page 14: MS BI SSAS Project Portfolio

14

1-2 Labor Costs by Client with filtering out the Nulls

Page 15: MS BI SSAS Project Portfolio

15

1-3 Total Labor Costs by County

Page 16: MS BI SSAS Project Portfolio

16

1-4 Total Labor Costs by Division

Page 17: MS BI SSAS Project Portfolio

17

1-5 Total LaborCosts by Client Account Grouping

Page 18: MS BI SSAS Project Portfolio

18

1-6 Labor, Material, and Overhead Costs by Client

Page 19: MS BI SSAS Project Portfolio

19

1-7 Labor, Material, and Overhead Costs and then Total Costs by Client

Page 20: MS BI SSAS Project Portfolio

20

1-8 Total Costs, Profit and Percent Profit by Job

Page 21: MS BI SSAS Project Portfolio

21

1-9 Total Costs, Profit and Percent Profit by Client

Page 22: MS BI SSAS Project Portfolio

22

1-10 Job Counts by Client

Page 23: MS BI SSAS Project Portfolio

23

1-11 Clients with Greater than $5,000 and “INC” in Their Name

Page 24: MS BI SSAS Project Portfolio

24

1-12 Top 30% Jobs by Invoice Amount

Page 25: MS BI SSAS Project Portfolio

25

Appendix D MDX Overhead Queries

2-1 Overhead by Category for the Last Two Quarters of 2005

Page 26: MS BI SSAS Project Portfolio

26

2-2 Overhead by Category and the Percent Change for the Last Two Quarters of 2005

Page 27: MS BI SSAS Project Portfolio

27

2-3 Overhead by Category for 2005 - Highest to Lowest

Page 28: MS BI SSAS Project Portfolio

28

Appendix E MDX Materials Queries

3-1 Material Purchases for Fuel, Materials, Petty Cash and Total

Page 29: MS BI SSAS Project Portfolio

29

3-2 Purchase Amounts by Material Type and by Client

Page 30: MS BI SSAS Project Portfolio

30

3-3 Total Material Purchases By Material Type by Client Starting with the

Client with the Highest Total Purchase Amount First

Page 31: MS BI SSAS Project Portfolio

31

3-4 Material Costs Ordered for Each Job

Page 32: MS BI SSAS Project Portfolio

32

Appendix F MDX Labor Queries

4-1 Labor Hours Worked, Total Cost and the Labor Rate for 2005

Page 33: MS BI SSAS Project Portfolio

33

4-2 Labor Hours Worked, Total Cost and the Labor Rate, Highest to Lowest

by Rate for 2005

Page 34: MS BI SSAS Project Portfolio

34

4-3 Total Labor Hours Worked and Labor Costs by Employees and Contractors for 2005

Page 35: MS BI SSAS Project Portfolio

35

4-4 Jobs with the Most Labor Hours and the Top Three Employees within Each Job

Page 36: MS BI SSAS Project Portfolio

36

4-5 Total hours Worked for Q4 2005 and the Quarter One year Prior

Page 37: MS BI SSAS Project Portfolio

37

Appendix G KPIs (Key Performance Indicators

KPI-1 Percent Open Receivables By Client

Page 38: MS BI SSAS Project Portfolio

38

KPI-2 Change in the Number of Jobs by Client

Page 39: MS BI SSAS Project Portfolio

39

KPI-3 Percent overhead by Job

Page 40: MS BI SSAS Project Portfolio

40

KPI-4 Percent Change in Profit by Client

Page 41: MS BI SSAS Project Portfolio

41

KPI-5

Page 42: MS BI SSAS Project Portfolio

42