MS-P-017 REV.03
METHOD STATEMENT
FOR
TIE-IN OF OILY WATER LINE
CONTRACT No. JI-194
SAUDI ARAMCO OIL COMPANY
KARAN UTILITY AND COGENERATION PROJECT
Khursaniyah, Saudi Arabia
Page 1 of 5
Signature
03 30 Dec. 2010Print Name
A.J. Rogero N.A. Pacleb R.A. Dimatatac P. Ranzenbacher Rev. DATE Prepared By
MMGChecked By
MMGApproved By
MMGApproved By
PSAL
![Page 2: Ms Tie in of Oily Water Rev03](https://reader036.vdocument.in/reader036/viewer/2022082623/54651404b4af9f583f8b4d97/html5/thumbnails/2.jpg)
MS-P-017 REV.03
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCES
3.0 SAFETY
4.0 WORK SEQUENCE
5.0 LIST OF EQUIPMENT
6.0 MAN POWER
7.0 MATERIAL
8.0 ATTACHMENTS
Page 2 of 5
![Page 3: Ms Tie in of Oily Water Rev03](https://reader036.vdocument.in/reader036/viewer/2022082623/54651404b4af9f583f8b4d97/html5/thumbnails/3.jpg)
MS-P-017 REV.03
1.0 SCOPE
The scope and purpose of this document is to describe the execution
methodology of Tie in work to be carried out during to the existing oily water
line.
2.0 REFERENCES
2.1 Construction Safety Manual
2.2 SAES-L-350: Construction of Plant Piping
2.3 SAES-L-109: Selection of Flange, Stud Bolts and Gaskets
2.4 SAES-A-114: Excavation and Backfill
2.5 GI-2.100: Work Permits
2.6 GI-2.102: Safety Precautions for Pressure Testing
2.7 GI-2.711: Fire and Safety Watch
2.8 SAES-S-020 Industrial Drainage & Sewers
2.9 SAES-S-070 Installation of Utility Piping System
2.1001-SAMSS-034 RTR (Fiberglass) Pressure Pipe Fittings
3.0 SAFETY
3.1 Obtained work permit for all associated works in restricted area at the
plant operations
3.2 All personnel shall wear personal protective equipment and working fire
retardant coverall clothing used as necessary
3.3 Provide dry chemical fire extinguisher, pressurized fire hose and fire watch
near the tie-in location
3.4 Conduct tool box meeting related to work activities. Safety officer shall
conduct the tool box meeting.
3.5 All equipment shall be inspected and ensure it is good working condition.
3.6 All equipment operators must have their valid license/certification
4.0 WORK SEQUENCE
4.1 Prefabricate and complete the Tie In spool in accordance with
Page 3 of 5
![Page 4: Ms Tie in of Oily Water Rev03](https://reader036.vdocument.in/reader036/viewer/2022082623/54651404b4af9f583f8b4d97/html5/thumbnails/4.jpg)
MS-P-017 REV.03 01-SAMSS- 034 stated in section 7.0 Materials and Fabrication.
4.2 Provide safe work access platform at Tie in location if necessary
4.3 Mark correctly and legibly the cutting location on existing piping
4.4 Provide adequate habitat for safe work inside the plant.
4.5 Coordinate to Aramco where to isolate the System of Existing Oily Water line pipe.
4.6 Carry out checking the existing pipe at cut, the desired length at its location.
4.7 AOC to carry out necessary Gas Test and Issue Gas Test certificate
4.8 Issue hot/cold work Permit
4.9 Carry out frequent gas test in the work vicinity
4.10 Cut the Tie In location as marked and remove pipe spool
4.11 Clean open end of piping and arrange combined internal inspection
4.12 Fit-up and Laminate New Tie In Spool in accordance with
01-SAMSS-034 stated in section 7.0 Materials and Fabrication.
4.13 Provide permanent support as per design or temporary support as
required.
4.14 Insulating Gasket/kits (PIKOTEK) shall be for flanged joints of dissimilar
metals. PIKOTEK insulating gaskets shall not be used above 200C line
design condition.
4.15 By using the PIKOTEK gaskets, the pressure rating of the flanged joints
may be increased subject to review and approval by the Chairman of
Piping Standards Committee in consulting Services Department
4.16 The PIKOTEK gaskets are with Teflon sealed, glass reinforced epoxy
laminated to 316 stainless steel core. For low pressure services, the
stainless steel laminate is not required.
4.17 Gravity sewers shall be tested from manhole to manhole, or manhole to
sump inlet. The upstream manhole may be tested at the same time.
The first test will be for spool (2) and will be as Gravity Test
The second test will be carry out the service test on the tie-in joints
Page 4 of 5
![Page 5: Ms Tie in of Oily Water Rev03](https://reader036.vdocument.in/reader036/viewer/2022082623/54651404b4af9f583f8b4d97/html5/thumbnails/5.jpg)
MS-P-017 REV.03
during start up and then proceed with the final backfill.
5.0 LIST OF EQUIPMENT:
Shaver 1 No
Tools for lamination joint As required
Cutting set 1 No
Mobile crane 20 Tones
Hand Tools As required
Heating blanket
Laminating materials
6.0 Man Power
Supervisor 1
Certified RTR Pipe Fitter/laminator 2
Helper 2
Crane Operator 1
Rigger 1
Fire Watch 1
7.0 Material
Pre Gravity Tested Tie In spool as per AFC drawing
Permanent Pipe support as required.
8.0 Attachments
Job Safety Analysis
P&ID Drawing no: RA-768933 sht.01/02
---------------------------------------------------END---------------------------------
Page 5 of 5