Project Title :EPCC OF FLOW LINES &
TRUNK LINES (2018-2021)
1
MSK PCH
4/28/2018
www.msk-group.org
SAKIR ALMOROUJ k. For General Contracts
4/28/2018MSK-PCH-CONTRACT 2
34/28/2018Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
1.Introduction
FLOW LINES AND TRUNK LINES Project (the “Project”) and Related System Project is carried out by
MSK as EPC contractor for PetroChina International Iraq FZE according to letter of award dated on 27
Dec 2017. The project in handled in Halfaya Oil Field located 35 km southeast of Amarah city, Missan
Governorate, southern part of the Republic of Iraq. MSK activities are performed based on signed
service agreement with PetroChina for the period of four years until 2021.
Project Location; The Halfaya Oil Field is situated in the Missan governorate of Iraq, 35 km southeast of
Amarah city
Client; PetroChina International Iraq FZE Iraq Branch
Contractor; SAKIR ALMOUROJ K. FOR GENERAL CONTRACTS LTD (MSK)
Project name; EPCC OF FLOW LINES & TRUNK LINES (2018-2021)
Project number; PRID-3680 HFY-CONF&C0869-089301
Service order number; SO01
Project Activities;
A. Engineering
B. Procurement
C. Construction
D. Testing
E. Commissioning
44/28/2018
1.1 HFY OIL FIELD MAP
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
4/28/2018 5
1.2 Reference
a) PCH and HALFAYA oilfield specifications and
requirements
b) Design Bases
c) 0893 ITB Final PDF files
d) The Project documents
e) Overall Layout
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
64/28/2018
2.1 SCOPE OF WORK FOR (SO01)
a) The flowlines shall be of carbon steel API 5L-PSL2- BNS/X52NS
b) The flowline shall be buried together in common trench where they have the same
route, the minimum cover of pipeline is 1200 mm (top of pipe)
c) The estimated lengths of the flowlines will base on Location Plan of the respective
well at the relevant Site
2.Understanding the Scope of Work for the project.
The Scope of work to be performed be Contractor is only for ENGINEERING AND
CONSTRUCTION OF FLOWLINES AND TRUNKLINES 2018-2021).This project consist of the
followings as per section 4.0 from contract:
1. Flow lines and trunk lines
2. Civil works
3. Anticorrosion protection.
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
2.2 Scope & Quantities;
No. Description Details Unit Quantity
1 Pipeline 6" with 3PE/3PP/FBE Coating m 29500
8" with 3PE/3PP/FBE Coating m 32200
2 Road Crossing (Excavation method) 6" pipeline road crossing m 700
8" pipeline road crossing m 750
3 Road Crossing (Jacking method) 6" pipeline road crossing m 700
8" pipeline road crossing m 750
4 Road Crossing (Reserved Culvert) 6" pipeline road crossing m 700
8" pipeline road crossing m 750
5 River/Channel Crossing (with excavation) 6" Pipeline River/Channel Crossing m 200
8" Pipeline River/Channel Crossing m 80
6 River/Channel/Road Crossing (HDD) 6" Pipeline River/Channel/Road Crossing m 450
8" Pipeline River/Channel/Road Crossing m 200
7 Underground pipeline/cable crossing Pipeline crossing each 39
Cable crossing each 20
8 Anchor block m³ 20
9 Drying and Nitrogen filling 6" pipeline m 900
8" pipeline m 300
84/28/2018
2.3 Overall Layout
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
94/28/2018
3.Battery Limit
PAD WELL FLOWLINE NEW TL TIE-IN & CPF EXPANSIONM091
JK091D1
JK091D2
JK091D3
M0853D1
JK0853D1
JK0853D2
M0853D2
M0397D1
M0397D2
M0397D3
M0397D4
M0888D2
M0888
M0888D1
M0107D1
M0107D2
M0478D1
M0478D2
M0478D3
M0478D4
M0224D1
M0224D2
K0224H1
M064D1
M064D2
JK064
HF119 M119D2
HF005 JK005D1
HF064
MSK
PRID-3680
SO01
CONTRCATOR & PRIDWELLPADS &TIE-IN TIE-IN & OGM EXPANSION
HF091
(Old
HF082)
HF0853
(Old
HF085)
HF0397
(Old
HF039)
HF0888
(Old
HF080)
*HF0107
HF0478
(Old
HF040)
*HF0224
(Old
HF0236)
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
104/28/2018
4. Project Organization Chart
4.1 Project Management Organization
MSK-PRID-3680-Project Manager
Construction Manager
HSE Manager
QC Manager
Commissioning Supervisor
Planner Engineering Coordinator
Inspection Supervisor
Document Control Center (DCC)
Security Supervisor
Accountent
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
114/28/2018
4. Project Organization Chart
4.2 Project Engineering Subcontractor ORG.Chart
124/28/2018
4. Project Organization Chart
4.3 Project Procurement ORG.Chart
HOME OFFICE ON SITE
HOME OFFICE ON SITE
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
134/28/2018
4. Project Organization Chart
4.4 Project Construction ORG.Chart Construction Manager
Civil EngineerPiping
Engineer
Instruent Engineer
Quality Engineer
Testing Supervisor
Workshop Supervisor
Equipment Supervisor
Surveyors
HSE Supervisor
Coating Supervisor
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
144/28/2018
4. Project Organization Chart
4.5 Project QA/QC ORG.Chart
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
154/28/2018
5-Project Milstones.
Service Order effective date:Mar 20nd 2018
Mobilization: 21-Apr-18
Engineering: 20-Mar-18
Construction-6’’ Pipeline & 8’’ Pipeline: 12-May-18
Commissioning and Demobilization: 28-Oct-18
Project Milstones.(Start Date)
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
164/28/2018
6. Overall Project Execution Schedule for SO 01 – Level 3 (Start Date & Finish Date)
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
174/28/2018
6. 1 Engineering Execution Schedule – Level 3 (Start Date & Finish Date)
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
184/28/2018
7. Site Mobilization Plan (Man Power, Tools & Tackles, Camp, Machinery etc.)
7. 6 HISTOGRAM
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
0
50
100
150
200
250
300
1 2 3 4 5 6 7 8 9 10
Project Week
Chart Title
Indirect Manpower Direct Manpower Equipment
194/28/2018
8. Project Execution activities
8.1. TOPOGRAPHIC SURVEY
8.2 ENGINEERING
8.3 PROCUREMENT
8.4 CONSTRUCTION
8.5 COMMISIONING
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
204/28/2018
8. Project Execution activities
8.4.1 TYPICAL DRAWING FOR PIPELINES CROSSING
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
21
224/28/2018
8. Project Execution activities
8.4.2 A Typical Drawing Right of Way and Working Strip Dimensions
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
23
244/28/2018
9.Project Control System
The elements of project control system shall include:
• Work Breakdown Structure (WBS) for the project
• Project Execution Schedule
• Progress Measurement/Monitoring System
• Progress ‘S’ Curve
• Manpower Histograms
Project Title :EPCC OF FLOW LINES & TRUNK LINES (2018-2021) – SO01 -PRID-3680 HFY-CONF&C0869-089301
254/28/2018